The document outlines a Bill of Quantities for a construction project, detailing various categories such as Earthworks, Concrete Works, Rebars, Formworks, Masonry Works, Steel Works, Roofing, and Plumbing. Each category lists item descriptions, units, quantities, unit costs, and total amounts, culminating in a grand total of 484,229.11. Additionally, it provides a cost per square meter and emphasizes the need for a labor-to-materials ratio exceeding 30%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

SAMPLE-BOQ

The document outlines a Bill of Quantities for a construction project, detailing various categories such as Earthworks, Concrete Works, Rebars, Formworks, Masonry Works, Steel Works, Roofing, and Plumbing. Each category lists item descriptions, units, quantities, unit costs, and total amounts, culminating in a grand total of 484,229.11. Additionally, it provides a cost per square meter and emphasizes the need for a labor-to-materials ratio exceeding 30%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Name SAMPLE ONLY

Location PRICES MAY VARY


Owner Civil Traveler
Subject BILL OF QUANTITIES
Date Start
Duration
Admin Pricing (Baseline)
Materials Labor and Equipment
Item No. Item Description Unit Quantity
TOTAL COST
Unit Cost Total Amount Unit Cost Total Amount
A. EARTHWORKS
1 Excavation cu.m. 10.784 0.00 0.00 850.00 9,166.40 9,166.40
2 Backfill/Compaction cu.m. 6.71 0.00 0.00 250.00 1,677.50 1,677.50
3 Haul Out cu.m. 6.77 0.00 0.00 250.00 1,692.50 1,692.50
4 Gravel Bedding cu.m. 4.662 1,550.00 7,226.10 250.00 1,165.50 8,391.60
B. CONCRETE WORKS
1 Footing cu.m. 1.26 4,500.00 5,670.00 600.00 756.00 6,426.00
2 Column/Pedestal cu.m. 0.76125 4,500.00 3,425.63 600.00 456.75 3,882.38
3 Wall Footing cu.m. 1.344 4,500.00 6,048.00 600.00 806.40 6,854.40
4 Slab on Grade cu.m. 4.725 4,500.00 21,262.50 600.00 2,835.00 24,097.50
5 Catch Basin cu.m. 0.1512 4,500.00 680.40 600.00 90.72 771.12
C. REBARS
1 Footing kg 106.54 30.00 3,196.20 18.00 1,917.72 5,113.92
2 Column/Pedestal kg 94.70 30.00 2,841.00 18.00 1,704.60 4,545.60
3 Wall Footing kg 97.10 30.00 0.00 18.00 1,747.80 1,747.80
4 Slab on Grade kg 66.53 30.00 0.00 18.00 1,197.54 1,197.54
5 Catch Basin kg 29.57 30.00 0.00 18.00 532.26 532.26
6 Concrete Pads kg 38.84 30.00 0.00 18.00 699.12 699.12
D. FORMWORKS/SCAFFHOLDING
1 Footing sq.m. 4.8 500.00 2,400.00 400.00 1,920.00 4,320.00
2 Column/Pedestal sq.m. 12.8 500.00 6,400.00 400.00 5,120.00 11,520.00
3 Wall Footing sq.m. 6.4 500.00 3,200.00 400.00 2,560.00 5,760.00
4 Slab on Grade sq.m. 4.4 500.00 2,200.00 400.00 1,760.00 3,960.00
5 Catch Basin sq.m. 5.76 500.00 2,880.00 400.00 2,304.00 5,184.00
E. MASONRY WORKS
1 4" CHB sq.m. 29.2 350.00 10,220.00 120.00 3,504.00 13,724.00
2 Plastering sq.m. 58.4 180.00 10,512.00 120.00 7,008.00 17,520.00
3 CHB Rebars kg 29.568 30.00 0.00 18.00 532.22 532.22
F. STEEL WORKS
1 2" x 2" x 3/16" x 6m Angle Bar kg 1162.31 42.00 48,816.87 19.00 22,083.82 70,900.69
2 C Purlins LC-100x50x1.5 x 6m kg 304.92 300.00 91,476.00 100.00 30,492.00 121,968.00
3 Plain Round
12mm.Ø CROSS Sagrod
BRACING w/ 16mm. STD. kg 11.39 35.00 398.65 19.00 216.41 615.06
4 TURNBUCKLE
SC1-4"Ø STEEL COLUMN kg 35.6 35.00 1,246.00 19.00 676.40 1,922.40
5 STRUCTURAL STEEL PIPE SCHEDULE 40 (6m) kg 192.84 35.00 6,749.40 19.00 3,663.96 10,413.36
6 200x200x8mm. THICK BASEPLATE kg 15.06 35.00 527.10 200.00 3,012.00 3,539.10
7 12mm.Ø ANCHOR BOLTS pcs 24 from scrap 0.00 19.00 456.00 456.00
8 Steel Framing: Doors and Windows sq.m. 20 60.00 1,200.00 850.00 17,000.00 18,200.00
G. ROOFING
1 Long Span Rib Type G.I. Sheet (4'x8') l.m. 48.8 464.74 22,679.31 350.00 17,080.00 39,759.31
2 Ridge Roll (8') l.m. 9.6 261.48 2,510.21 350.00 3,360.00 5,870.21
3 Fascia Cover (8') l.m. 19.2 351.64 6,751.49 350.00 6,720.00 13,471.49
4 Flashing (8') l.m. 19.2 261.48 5,020.42 350.00 6,720.00 11,740.42
5 Stainless Steel Box Gutter 0.60mmx1.22mx2.44m l.m. 19.2 752.46 14,447.21 350.00 6,720.00 21,167.21
H. PLUMBING
1 3" dia. PVC Downspout Pipes l.m. 14 200.00 2,800.00 175.00 2,450.00 5,250.00
2 3" dia. PVC 90-degree elbow pcs 4 200.00 800.00 110.00 440.00 1,240.00
3 300mm.Ø RCPC 1.0 meter long for Drainage Line pcs 16 1,000.00 16,000.00 150.00 2,400.00 18,400.00
TOTAL 309,584.48 174,644.63 484,229.11
TOTAL FLOOR AREA sq.m. 32
COST PER SQ.M. 9,674.52 5,457.64 15,132.16

ratio between labor/mats should be more than 30%

new 0.5641259052 #DIV/0!


old 0.3151125402