The text below shall be used with the FIDIC Conditions of Contract for Plant and Design Build for Electrical
and Engineering Works, Designed by the Contractor, First Edition 1999 (FIDIC Yellow Book)
Employer’s name and 1.1.2.2 & 1.3 Ministry of Water Resources and Irrigation,
address Mechanical and Electrical Department,
Eng. Ahmed Hasballah
Central Directorate of Designs and
Specifications MED, MWRI Head Quarter,
Second Floor
Ministries District , New Administrative Capital,
Cairo
Cairo 11517,Egypt
Tel: +20 (0) 222090690
Email: [email protected]
Time for access to the Site 2.1 14 days after signing the Contract
Normal working hours 6.5 8 hours working day from Saturday to Thursday
(start and closing time to be agreed with the
Contractor)
Delay damages for the Works 8.7 & 14.15(b) 0.1 % of the final Contract Price per day, in the
currencies and proportions in which the
Contract Price is payable.
Currencies and proportions 14.2 The advance payment shall be paid in the
currency or currencies and proportions in which
the Accepted Contract Amount is payable, i.e.
100 % in Euro
Start repayment of Advance 14.2 (a) When payments reach 10 % of the Accepted
payment Contract Amount less Provisional Sums
If Sub-Clause 14.5 applies: 14.5(b) The following Plant and Materials for payment,
when shipped in route to the Site: N/A.
Plant and Materials
14.5(c) The following Plant and Materials for payment,
when delivered to the Site - refer to the Price
Schedule .
Appointment (if not agreed) 20.3 Cairo Regional Centre for International
to be made by Commercial Arbitration (CRCICA)
Signed:
Duly authorised to sign the proposal for and on behalf The Arab Contractors (Osman
of: Ahmed Osman & Co)
Date: 26/2/2025