This document outlines the method statement for the installation of a fall arrest system on cat ladders at the Tuwaiq Forging Plant in Jubail. It details the scope of work, safety procedures, and installation steps, emphasizing compliance with health and safety regulations. The document also includes requirements for personal protective equipment and inspection protocols to ensure safe and effective installation.

Uploaded by

haiderparrai00
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

Method Statement for the KEE LINE Works (1)

This document outlines the method statement for the installation of a fall arrest system on cat ladders at the Tuwaiq Forging Plant in Jubail. It details the scope of work, safety procedures, and installation steps, emphasizing compliance with health and safety regulations. The document also includes requirements for personal protective equipment and inspection protocols to ensure safe and effective installation.

Uploaded by

haiderparrai00
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Document No : KS-MS-AFS-001

METHOD STATEMENT FOR Revision No : 00


Date : 13/11/2024
INSTALLATION OF FALL
Page No : 1 of 6
ARREST SYSTEM ON CAT
LADDERS
METHOD STATEMENT FOR KEE LINE INSTALLATION ON METAL ROOFS

Site Name: TUWAIQ FORGING PLANT, JUBAIL Date: 13/11/2024

Location/Area: RAS AL KHAIR INDUTRIAL AREA

SCOPE OF WORK (Purpose/Project description)

Scope of work for the following RAMS is to elaborate the procedure of the Fall Arrest system installation with their
component and testing procedure on cat ladder of the Tuwaiq Forging plant facility .

PROCEDURE / METHOD TO BE EMPLOYED

All works carried out will be in accordance with site Health & Safety regulations and Kee Safety Company Policies.

1. All operatives will attend all Fanar steel induction and Kee Safety specific inductions with a Method Statement and
Risk Assessment briefing prior to commencing works on-site. All operatives will sign Method Statement / Risk
Assessment.
2. Before work starts the Kee Safety installation manager Amjad islam will carry out a Dynamic Risk Assessment (DRA)
of the work area. The DRA is an internal Kee Safety Document the operatives must complete in conjunction with
this method statement and attached risk assessment. It will allow changes to site conditions to be documented
daily and the RAMS(risk assessment method statement) to be reviewed if and when required. All Major Safety
concerns, hazards and or unsafe acts in the work area will be reported to the site HSE and Kee Safety operation
manager immediately. All work will stop until the safety precautions are in place and the area is safe for everyone.

3. Access and egress will be via ladders . in case of any medical emergency, Kee safety will follow main contractor
protocols.
4. For installation, operatives will need to have correct PPE which includes Safety Helmet (Vertex Best), suitable,
Glasses, Gloves, Hi-Viz Vest and Steel toe safety shoes.
Document No : KS-MS-AFS-001
METHOD STATEMENT FOR Revision No : 00
Date : 13/11/2024
INSTALLATION OF FALL
Page No : 2 of 6
ARREST SYSTEM ON CAT
LADDERS
5. Additional requirement, operatives will also have PFPE (personal fall protection equipment) full body harness, 2m
twin leg lanyard. Each operative will only require the use of their PFPE if working within 3 meters of an exposed
edge including Roof Skylights.
6. Once worker on roof, installation head will explain the all potential hazard to the workers with their control
measures, remove any possible slip and trip hazard in work location.
Approved shop drawing should be kept with supervisor and orientation of the life line should be decided with client prior
execution, in standard generic method vertical lifeline is installed in center of rungs ,so while climbing , the travellor will
remain Infront of chest. works will be followed as per below installation Guide step by step

Work Procedure for vertical Lifeline on Ladders

Step Equipment Action/Task PPE Required

Material Delivery to site (Life line and its accessories ) and shifting the Hi Viz, Helmet,
Vertical material to work location in manually. Following steps will elaborate the Steel toe cap
1.1
Lifeline installation procedure. boots, gloves and
Safety Glasses ,
Installation of ladder extension plate at upper end of ladder with Clamps Hi Viz, Helmet,
Extended Bar and bolts as per shop drawing, ladder extension bar will be extended Steel toe cap
and steel above the ladder as per shop drawing. Worker should stand on ladder boots, gloves,
1.2
rope landing/ roof and remain hooked with ladder site structure . Safety Glasses
installation Upon installation of steel bar, rope with factory swaged fixed the and harness PFPE
structure, rope will be drop to ground for further works
Hi Viz, Helmet,
Steel toe cap
Installation of intermediate main rope guide at middle span with U-clamps
boots, gloves and
Intermediate fixed to rungs of ladder as per shop drawing. Worker will be hooked with
1.3 Safety Glasses,
support double lanyards with rungs while fixing intermediate support. Rope and
PFPE harness
grab system as well could be used to fix the intermediate Guide post.
with double
lanyard
End post at Installation of the bottom anchor plate with tensioner at bottom rungs Hi Viz, Helmet,
lower end with U-clamps fixings. Worker will stand ground- no required any harness Steel toe cap
1.4
with boots, gloves and
tensioner Safety Glasses
Once the top , intermediate and bottom supports are installed and cable Hi Viz, Helmet,
Tensioner will run through end post and through tensioner. pull manually the steel Steel toe cap
1.5
assembly rope by adding stopper assembly in tensioner. Later by tightening boots, gloves and
tensioner rod desired tension of rope will be attained required tension. Safety Glasses
Document No : KS-MS-AFS-001
METHOD STATEMENT FOR Revision No : 00
Date : 13/11/2024
INSTALLATION OF FALL
Page No : 3 of 6
ARREST SYSTEM ON CAT
LADDERS

Step Equipment Action/Task PPE Required

Hi Viz, Helmet,
Steel toe cap
Vertical Additional cable will be cut by steel scissor and cut part will be covered by boots, gloves and
1.6
lifeline plastic cover. Safety Glasses,
safety harness and
rope with grab

Hi Viz, Helmet,
Steel toe cap
boots, gloves and
Vertical Attached the F-5A guided type fall arrester with shock absorber to vertical Safety Glasses,
1.7
lifeline life line and hook with harness while move up, system is ready to use. Full Body
Harness with F5A
guided Type fall
arrestor
Document No : KS-MS-AFS-001
METHOD STATEMENT FOR Revision No : 00
Date : 13/11/2024
INSTALLATION OF FALL
Page No : 4 of 6
ARREST SYSTEM ON CAT
LADDERS
Below snap is showing the buildup detail of the vertical life at ladders.

Extended Bar at Roof Level or Landing


level , explained in 1.2 section

Intermediate support will install if


span increase above 15 m and if less
than 20m , rope guide will be
installed. Explained in section 1.3

End post with tensioner fixed at


ground or at landing level where
continuity of the cat ladder
changed.Explained in Section-1.4
VERTICAL LIFELINE COMPONENTS
LL-150
LIFELINE WIRE ROPE

RP-300 LS
LADDER EXTENSION

*ONLY APPLICABLE FOR LADDRE ABOVE 10M HEIGHT

F-5A
GUIDED TYPE FALL
ARRESTER
WITH ENERGY
ABSORBER

S.N. BUILDING QTY LADDER HEIGHT, H


LADDER HEIGHT, H

1 SLAG DISPOSAL AREA & BUILDING 1 10.2 m


FC-30 V
MAIN ROPE GUIDE 2 WATER TREATMENT PLANT 1 12.2 m
3 FIRE FIGHTING PUMP BUILDING 1 8.3 m
4 COMPRESSED AIR PLANT 1 11.9 m
5 SECURITY SUPPORT BUILDING (GATE-02) 1 6.2 m
6 NON-DESTRUCTIVE TESTING SHOP 2 10.4 m
7 PATTERN SHOP NORMAL 2 10.4 m
8 TEMPORARY WASTE STORAGE 2 9.6 m
9 EAF CABINS NORMAL 1 8.7 m
LADDER RUNG

TOTAL QTY 12
0 ISSUED FOR APPROVAL VN MZ MZ 29-04-2024
REV NO. REVISION DESCRIPTION CREATED BY CHECKED BY APP. BY REV. DATE
RS-40 S TENSIONER+ JUBAIL, KSA. Road #150, Beside Saudi Kayan, Industrial Area-2 "This drawing and the information contained
RP-300 BS BOTTOM ANCHOR TEL# +966-920006111 FAX# +966-11-4945461 herein are sole property of Alfanar Steel Structure
PLATE+ no reproduction in full or part shall
be obtained without written consent of its owner"

TYPICAL LADDER ELEVATION DRAWING TITLE LIFE LINE ON NORMAL LADDER

Scale NTS KEE SAFETY LLC PROJECT FORGING SHOP MODELED BY VN


Dubai Investment Park, Near Green Community
P.O Box 18448 Dubai, United Arab Emirates - UAE MODELED BY INS ISSUED DRAWN BY VN
Tel. No.: (+971) 4 - 8859066 REVIEWED BY MZ
CONTRACT NO SCALE NTS
www.keesafety.ae
© 2019 Kee Safety LLC. All rights reserved. DRAWING No KSF-STS-0001 REVISION No. 0
A1 APPROVED BY MZ
Document No : KS-MS-AFS-001
METHOD STATEMENT FOR Revision No : 00
Date : 13/11/2024
INSTALLATION OF FALL
Page No : 5 of 6
ARREST SYSTEM ON CAT
LADDERS

HEALTH & SAFETY REQUIREMENTS

• All works shall be performed in accordance with the Kee safety HSE Manual and Main Contractor Health and
Safety Requirements.
• Exclusion zones below the workplace at Ground level shall be cordon off with hard barricades.
• Site Engineer/Supervisor will ensure that appropriate PPE or Personal Protective Equipment is worn by site
personnel at all times complying with Dussan PPE Procedure.
• Prior to commencement of any activity, all operatives will be given in a general Site Safety Induction by the
HSE Personnel, the Site Engineer/Supervisors including HSE Personnel will also conduct Tool Box Talk and
Method Statement briefings to the personnel involved in operation.
• PPE is mandatory for all workers and staff personnel consist of safety boots/shoes, safety helmet, cotton
gloves, Hi-visibility jacket/vest and goggles. Full body harness is required and 100% tie off has to be maintained
for those working at heights above 1.8 meters. Lanyard with shock absorber will be used if working at height
above 6 meters. All used lifting equipment will have valid third-party certificates.
• Where required handrail or for edge protection will be provided and if it’s not practicable, safety harness at
different locations where applicable will be used by the operatives attach or fixed on the anchor points. 100%
tie off policy has to be complied while working at height. All work at height activities has to be complied in
accordance with the RSG Work at height procedure.
• In the event of accident or incident, immediately notify the HSE/Project Manager or HSE Personnel at site.
• In case of fire/emergency, immediately evacuate from the work area and go to designated Site Assembly
Point.

QHSE DOCUMENTS AND RECORDS

a. Risk Assessment (RA)

In reference to the Method Statement, all health & safety hazards and environmental impacts associated
with the site activities will be evaluated as to the level of threat they pose in a uniform and quantitative
manner. Consequently, controls can be applied in a hierarchical way commensurate with the level of
hazard, affording the best use of resources to protect people, equipment & materials and the
environment. The procedure shall be applied to all site activities and processes with regards to the
possibility of potential harm to any person having access to the workplace, the environment or damage
to equipment & materials.
Document No : KS-MS-AFS-001
METHOD STATEMENT FOR Revision No : 00
Date : 13/11/2024
INSTALLATION OF FALL
Page No : 6 of 6
ARREST SYSTEM ON CAT
LADDERS
The strategy is to focus on primary Hazards. RA should then provide the majority of information needed
for all routine work activities to be conducted on site, in a safe and environmentally responsible manner.

b. Inspection & Test Plan (ITP)

The ITP shall set out in matrix format the sequence of inspection steps, the governing Document
(approved shop drawings, specification, standard, etc.), the standard to be achieved, the persons
witnessing and the supporting documents to be produced.

c. Work Inspection Request (WIR)

Upon completion of each section of work, Site QAQC Engineer/Inspector and Site Engineer/Supervisor
will carry out an inspection of the work according to the Inspection & Test Plan (ITP). Completed
checklist sheets will be submitted to the Engineer/Consultant for approval.
When all the installation works under the contract are completed or where phased hand over is
required and when the relevant phase is complete, the Project Manager/Site Engineer shall request the
company QAQC Engineer/Inspector to carry out preliminary inspection of the finished works to ensure
that all elements are ready for inspection by the Engineer/ Consultant.
RECORDS
Following records shall be maintained.
• Work Inspection request

• MIR and ITP