Drain
Drain
6 Joint sealing
Sealing @30m interval along width 130 6.1 793 rm
Total 793 rm 1,081.45 857,589.85
7 Form work
7.1 Bed side
Long Side wall (Outer) 2 3861.5 2.3 17762.9 m2
Long Side wall (inner) 2 3861.5 2 15446 m2
short wall 387 10.7 0.3 1242.27 m2
Total form work 34451.17 m2 742.43 25,577,582.14
8 Reinforcement
Top Slab Total Length
Top main bars 16Ø@150mm c/c 25742 6.1 157026.2 248140.168 kg
Bottom main bars 16Ø@150mm c/c 25742 6.1 157026.2 248140.168 kg
Distribution bars 10Ø@150mm c/c 80 3861.5 308920 190691.358 kg
Bottom Slab
Top main bars 16Ø@150mm c/c 25742 6.1 157026.2 248140.168 kg
Bottom main bars 16Ø@150mm c/c 25742 6.1 157026.2 248140.168 kg
Distribution bars 10Ø@150mm c/c 80 3861.5 308920 190691.358 kg
Side Wall
Outside and Inside Wall Total Length kg
Vertical bars 16Ø@150mm c/c 154452 2.8 432465.6 683402.43 kg
Distribution bars 10Ø@150mm c/c 108 3861.5 417042 257433.333 kg
Total volume of reinforcement 2314779.15 kg 134.68 311,754,456.01
9 Manhole
Iron plate for covering the manhole 25 25 no. 11,466.24 286,656.00
10 ladder 175 0.19 10 mm dia 0.617 20.515 kg 134.68 2,762.99
Total 753,793,145.59
-
SIDE DRAIN QUANTITY CALCULATIO
708042.290
0.850
Length 758.320 m
Width 7.980 m
longitudinal 758.220
Spacing 200.000 mm
No. of rod 40
Transverse direction 7.880
No. of rod 3791
dia of bar 10.000 mm 0.010
total length (long) 3032.880 m
Total Length (traverse) 39.400 m
Total Length 3072.280 m
Volume of road 0.241 m3
unit weight 7850.000 kg/m3
wt of rod 1893.216
Length Breadth Height
S.N Items Number Quantity Unit Remarks
(m) (m) (m)
1 Earthwork in excavation
Along the drainage alignmnet 1 758.32 0.92 0.7 43268.49 m3
Total 43268.5 m3
3 Stone Solling
Foundation 1 758.32 0.92 0.1 69.76544 m3
Total 69.76544 m3
5 M20 Concreting
5.1 Bed part 1 758.32 0.92 0.15 104.64816 m3
5.2 Top part cover 1 758.32 0.92 0.2 139.53088 m3
5.3 Wall side 2 758.32 0.15 0.45 102.3732 m3
Total 346.55224 m3
7 Form work
7.1 Bed side
Long Side wall (Outer) 2 758.32 0.65 985.816 m2
Long Side wall (inner) 2 758.32 0.45 682.488 m2
top cover 2 758.32 0.2 303.328 m2
Total form work 1971.632 m2
8 Reinforcement
Top cover Slab Total Length
Top main bars 10Ø@150mm c/c 5054 0.82 4144.28 2558.19753 kg
Distribution bars 10Ø@150mm c/c 7 758.32 5308.24 3276.69136 kg
Base Distribution bars 10Ø@150mm c/c
Distribution bars 10Ø@150mm c/c 7 758.32 5308.24 3276.69136 kg
Side Wall
Outside and Inside Wall and bottom Total Length kg
main Vertical bars 10Ø@150mm c/c 5056 1.82 9201.92 5680.19753 kg
Base Distribution bars 10Ø@150mm c/c 8 758.32 6066.56 3744.79012 kg
Total 43268.5 m3
3 Stone Solling
Foundation 1 1890.98 0.92 0.1 173.97016 m3
Total 173.97016 m3
5 M20 Concreting
5.1 Bed part 1 1890.98 0.92 0.15 260.95524 m3
5.2 Top part cover 1 1890.98 0.92 0.2 347.94032 m3
5.3 Wall side 2 1890.98 0.15 1.4 794.2116 m3
Total 1403.10716 m3
7 Form work
7.1 Bed side
Long Side wall (Outer) 2 1890.98 1.6 6051.136 m2
Long Side wall (inner) 2 1890.98 1.4 5294.744 m2
top cover 2 1890.98 0.2 756.392 m2
Total form work 12102.272 m2
8 Reinforcement
Top cover Slab Total Length
Top main bars 10Ø@150mm c/c 12606 0.82 10336.92 6380.81481 kg
Distribution bars 10Ø@150mm c/c 7 1890.98 13236.86 8170.90123 kg
Base Distribution bars 10Ø@150mm c/c
Distribution bars 10Ø@150mm c/c 7 1890.98 13236.86 8170.90123 kg
Side Wall
Outside and Inside Wall and bottom Total Length kg
main Vertical bars 10Ø@150mm c/c 12607 3.72 46898.04 28949.4074 kg
Base Distribution bars 10Ø@150mm c/c 22 1890.98 41601.56 25679.9753 kg