Chapter 3 - Setting Out Survey (2) (2)
Chapter 3 - Setting Out Survey (2) (2)
(CEng 2092)
LOGO
Contents
Contour Lines
Topographic Mapping
Applications in CEng
2
Definition
3
The aims of setting out
6
Horizontal control techniques
7
Vertical control techniques
9
Curve
10
Setting out of horizontal curves
11
Curve Setting out
Horizontal Curve
Circular Curve
Compound Curve
Reverse Curve
Transition Curve
Vertical Curve
Parabolic curve
12
Simple circular and Compound
13
Reverse Curve and Transition curve
14
Vertical Curves
15
Horizontal Curves
The principal
consideration in
the design of a
curve is the
selection of the
length of the radius
or the degree of
curvature
This selection is
based on such
considerations as
the design speed of
the highway and
the sight distance
as limited by
headlights or
obstructions
16
Elements of Horizontal Curves
I – Point of intersection
T1 – Point of
commencement
T2 – Point of tangency
E – External distance
T1T2 – Length of the
curve
T1I = IT2 = tangent
length
AI – Back Tangent
BI – Forward Tangent
T1T2 – Chord length
- Deflection angle
R – Radius of the curve
- Angle of intersection
M – Mid-ordinate
17
Formula to calculate the various elements of a circular
curve for use in design and setting out
18
Setting out of circular curves
19
Offset from tangent
20
Setting out using one theodolite and tape
21
Setting out using two theodolite
22
Setting out using Coordinates
Refer Schofield p – 352-353
23
Setting out with inaccessible intersection point
24
Example
25
Solution
26
The offset from long chord is calculated as:
27
Offset from tangent
28
Point Chainage Chord Length Tangential Deflection Angle set on 1’’
(m) angle (‘) Angle (‘)
0(T1) 54 + 21.22 - 0.0 0.0
1 55 + 00 8.78 30.184 30.184 0030’11’’
2 56 + 00 30 103.134 133.318 0213’19’’
3 57 + 00 30 103.134 236.452 0356’27’’
4 58 + 00 30 103.134 339.586 0539’35’
5 59 + 00 30 103.134 442.720 0722’43’’
6 60 + 00 30 103.134 546.104 0906’06’’
7 61 + 00 30 103.134 648.988 1048’59’’
8 62 + 00 30 103.134 752.122 1232’07’’
9 63 + 00 30 103.134 855.256 1415’15’’
10 64 + 00 30 103.134 958.839 1558’50’’
11 65 + 00 30 103.134 1061.524 1741’31’’
12(T2) 65 + 22.83 22.83 78.485 1140.009 1900’01’’
29
Transition curves
30
Shift, S
31
32
Setting out of transition curve
33
34
Example
39
Setting out data for circular curve
40
Setting out data for 2nd Transition
curve
41
Vertical Curve
42
Vertical curve formula
43
Derivation of vertical curve equation
44
Example
A
C
1/200
(p = -0.5%) 1/300
q = (+0.33%)
B
30.36
Chainage 2000
45
Solution
47
Building Setting Out
48
Bridge Setting out
49
CONTROLLING VERTICALITY
Using a plumb-bob
Using a theodolite
Plan
Section
50
Underground Survey
52
Underground Survey - Mechanical
53
Underground survey - GYRO-THEODOLITE
54
LOGO