mfe module4
mfe module4
DR.BIJESH R
ASSISTANT PROFESSOR
GEC Thrissur
Project
A project is defined as a combination of interrelated activities
which must be executed in a certain order in for its completion
The activities that has definite starting and ending points and
that result in a unique product or service
A project is a one shot, time limited, goal directed, major
undertaking, requiring the commitment of varied skills &
resources.
It also describes project as a combination of human and non
human resources pooled together in a temporary organization to
achieve specific purpose
GECT, DEPARTMENT OF MECHANICAL ENGINEERING 2
Examples of Projects
Hosting a College Annual Function
Plan a Space Shuttle to Mars
Construct a Plant to Manufacture Ball Bearings
Plan for Wedding
Designing and Implement a Computer System
Executing Environmental Clean-up Of a Contaminated Site
Erect a New Lab in the Dept. of Mechanical Engineering
Activity
An activity is a task, or item of work to be done, that consumes time, effort, money or other
resources.
It lies between two events, called the ‘Preceding’ and ‘Succeeding’ ones.
An activity is represented on the network by an arrow with its head indicating the sequence
in which the events are to occur.
2. Dangling
3. Redundancy
Optimistic Time( to):- It is the shortest possible time in which an activity can be completed if
everything going exceptionally well
Most likely Time (t m) :- It is the time in which the activity normally expected to complete under
normal conditions
Pessimistic Time (t p) :- It is the shortest possible time in which an activity can be completed if
everything going wrong
𝑡𝑝 −𝑡𝑜
Standard Deviation, St =
6
𝑡𝑝 −𝑡𝑜 2
Variance = [ ]
6
D− Te
Normal deviation, Z =
𝑆𝑡
GECT, DEPARTMENT OF MECHANICAL ENGINEERING 25
Difference between CPM and PERT
Normal time: It is the minimum time required to achieve the task at normal cost
Crash Cost: It is the cost of completing the activity by employing all possible means
like overtime, additional machinery, and materials.
Crash Time: It is the absolute minimum time associated with the crash costs
Scheduling
Bjesh R
Scheduling
Scheduling
Allocation of work to the facility with specification of time and
sequence in which the work is to be done.
Determines the order upon which machine, which department, at
what time and by which operator.
Objectives of Scheduling
To minimize total time and cost of
production.
To get maximum capacity utilization.
To reduce labor cost by reducing idle time.
For better utilization of materials.
To meet the correct delivery dates
To minimize unbalance of work among
various workstations.
Scheduling
External Factors
Factors not within the control of the
management.
Scheduling
Internal Factors
Availability of man power
Availability of material
Availability of machines
Manufacturing facilities.
Feasibility of economic production runs
Stock of finished product within the enterprise.
Time interval to process finished products from raw materials.
Scheduling
External Factors
Customers demand
Delivery date of customers
Scheduling
Single Machine Scheduling
Product 1
Input
A D B
Output
Product 2
C B A
Scheduling
10
Govt. College of Engg. Kannu r
Scheduling
Output
Product 1
Input
A B
Product 2
C D
Scheduling
Measuring Performance
Makespan.
Job lateness.
Job tardiness.
Scheduling
Makespan:
The total amount of time required to complete a group of jobs.
Measure of efficiency
Scheduling
Job lateness(Lj)
Amount of time by which the completion of time of job differs from its due date.
Shows the job is completed ahead of, on, or behind schedule.
Can be positive, zero or negative.
Lj = Cj – Dj
Cj = Completion time.
Dj = Due date
Scheduling
Job tardiness(Tj)
How long after the due date a job was completed, measures
due date performance.
Measure of lateness.
20
Govt. College of Engg. Kannu r
Scheduling
Critical Ratio
CR =(Due date - Today’s date)/(Total
shop time remaining)
OR
(Time remaining before due date)
/(Remaining processing time )
Scheduling
Problem
Scheduling
Ans:-
Scheduling
FCFS
Scheduling
FCFS_Ans
Scheduling
SPT
Scheduling
SPT_Ans
Scheduling
EDD
Scheduling
EDD_Ans
30
Govt. College of Engg. Kannu r
Scheduling
CR
Scheduling
CR_Ans
Scheduling
Slack
Scheduling
Slack_Ans
Scheduling
Summary