2. Method Statement for Field Test

This document outlines the method statement for field test soil investigation for the Salak Unit 7 Development Project, detailing the objectives, scope of work, execution plan, and safety measures. It includes information on geotechnical drilling, testing procedures, equipment, quality control, and project staffing. The document emphasizes the importance of safety and compliance with regulations throughout the investigation process.

Uploaded by

yusufnuradi95
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

2. Method Statement for Field Test

This document outlines the method statement for field test soil investigation for the Salak Unit 7 Development Project, detailing the objectives, scope of work, execution plan, and safety measures. It includes information on geotechnical drilling, testing procedures, equipment, quality control, and project staffing. The document emphasizes the importance of safety and compliance with regulations throughout the investigation process.

Uploaded by

yusufnuradi95
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

CONTRACTOR: JO-TR DOC NO..

METHOD STATEMENT FOR


FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 1 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

METHOD STATEMENT FOR


FIELD TEST

Status Code Eng. (OWNER) Dept. Date

Comment status code:


1: Approved
2: Approved With Comments
3: Rejected
4. Not Reviewed

Rev. Date Description Prepared Checked Approved

00 05-Dec-2024 IFI – ISSUE FOR INFORMATION JO-TR

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 2 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

Table of Contents
1 INTRODUCTION .......................................................................................................................................4
2 GENERAL ...................................................................................................................................................4
2.1 SCOPE OF WORK ............................................................................................................................4
2.2 EXECUTION PLAN ...........................................................................................................................5
2.2.1 Material and Field Equipment ..................................................................................................5
2.2.2 Quality Control (QC)/ Quality Assurance (QA) ......................................................................6
2.2.3 Project Staffing ...........................................................................................................................6
2.2.4 Safety ...........................................................................................................................................8
2.2.5 Last Minute Risk Assessment (LMRA) ...................................................................................9
2.2.6 Hazard Identification for Total Safety (HITS) ...................................................................... 11
3 GEOTECHNICAL DRILLING ................................................................................................................ 12
3.1 PREPARATION .............................................................................................................................. 12
3.2 DRILLING......................................................................................................................................... 13
3.3 STANDARD PENETRATION TEST (SPT) ................................................................................. 14
3.4 UNDISTRUBED SAMPLING......................................................................................................... 15
3.5 GROUND WATER LEVEL OBSERVATION .............................................................................. 17
3.6 BORING LOG .................................................................................................................................. 17
4 CONE PENETRATION TESTS (CPTU) ............................................................................................. 18
4.1 PIEZOCONE PENETRATION TEST (CPTU) ............................................................................ 18
4.2 DISSIPATION TEST ...................................................................................................................... 18
5 TEST PIT OPERATION ......................................................................................................................... 18
6 ENGINEERING ANALYSIS AND REPORTING ................................................................................ 19
6.1 DAILY REPORT .............................................................................................................................. 19
6.2 PRELIMINARY REPORT .............................................................................................................. 19
6.3 FINAL REPORT .............................................................................................................................. 19

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 3 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

REVISION SHEET DESCRIPTION

No PAGE SUBJECT DESCRIPTION OF CHANGE REV

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 4 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

1 INTRODUCTION
The primary objective of Geotechnical Investigation is to determine, within practicable
limits of time, but without sacrificing the main purpose, the stratigraphy and physical
properties of the soil under-laying the site, particularly the strength and deformation
characteristics of the soil strata, so that a desirable and satisfactory lay-out of the
proposed structure and economical foundation may be designed.
In addition, information regarding the technical properties of soil and ground water should
be determined to provide data for evaluating any possible hazardous corrosion that may
attack foundation piling. SUBCONTRACTOR has many experiences in executing the
geotechnical investigation for Power Plant in Indonesia.

2 GENERAL
2.1 SCOPE OF WORK
The main scopes of work for geotechnical study are on land drilling include borehole
quantity, depth borehole, and SPT interval.
The work to be performed and setting up of field test locations by surveyor at given
coordinates. If find any obstacles, should be informed and discussed with main contractor
to move location or further instructions. Consists of furnishing all labor, equipment &
materials, licenses, and technical services; and any supervision in performing any and all
work required for:
 Drilling, sampling and testing of exploration
 Sealing, boxing, storing and transporting of samples
 Cleaning up site and demobilizing
 Positioning and leveling for drilling location
 Preparing complete soil boring logs and recording field operations on a daily basis
while the work is being performed
 Preparing and submitting to the Client a performed drilling plan, boring locations,
boring logs, and boring reports required by specifications
Sampling and testing in overburden include the following:
please add the total depth.
 Standard Penetration Test, with interval 1.5 m
 Undisturbed soil sampling, with thin-walled tube sampling at each different layer for
cohesive soil, or every interval 5.0m depth each borehole.
 Pocket Penetrometer (on clayey soil in test of disturbed and undisturbed sample)
 Groundwater Observation during drilling
 Permeability Test

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 5 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

2.2 EXECUTION PLAN


2.2.1 Material and Field Equipment
We will maintain our own equipment for soil investigation, laboratory testing and office
furnishing including materials, parts, tools, and supplies to meet the requirements for the
work. All equipment will be capable of securing satisfactory samples of the required
diameters at the required drilling depths.
All accessories for drilling, sampling, and testing such as casing, drill rods, drill bits,
piping, pumps, meters, gauges and other materials or supplies necessary for the work,
will be furnished.
The equipment will be in satisfactory operating condition and capable of performing the
work set forth herein safety, quality, and efficiency. The equipment will be subjected to
any possible inspection by the Client at all times and, if deemed unsatisfactory, will be
removed from the work site and replaced by other satisfactory equipment.
If we are appointed to carry out this assignment, to meet the Contract schedule we will
mobilize the drilling rigs which consist of the rotary-type TOHO Standard Drill, Sanchin
Bean Royal and SC-45 speed pumping unit, and other related accessories. This drilling
equipment is capable of penetrating 80 meter deep.

List of Equipment
No Item Quantity
1 Drilling Machine (500 kg) 1 set
2 Water Pump (50 kg and 75 kg) 2 set
3 Drilling Bit 5 set

List of Tools
No Item Quantity
1 Stang Rod 4 set
2 Casing 2 set
3 Hammer 4
4 Wrench 6
5 Chainsaw 2
6 Screwdriver 2
7 Waterpass 1
8 Bentonite 3
9 Water tank 2

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 6 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

2.2.2 Quality Control (QC)/ Quality Assurance (QA)


To meet expectations of the Client, a QC /QA procedure will be fully integrated into our
services. Our Safety & QC/QA Manager will set up appropriate QC/QA Procedures and
practices to facilitate quality control during performing the services. The QC/QA will be
equally applied to the services. To ensure this quality control, we have proposed that an
integrated QC/QA program will be implemented from the earliest possible stage of the
project.

2.2.3 Project Staffing


For successfully executing the field and laboratory works, we will employ qualified
personnel. The formation of the personnel is arranged to achieve maximum efficiency in
executing the works.
The functions, tasks and responsibilities of each personnel are the following:

a. Field Team Leader (Field)


He is a Geotechnical Engineer who is familiar with geotechnical investigation,
surveying and laboratory works. The job descriptions are:
 To coordinate preliminary site survey, and approach local authority including permit
arrangement at the Client
 To coordinate the execution of all works in the field as well as in the laboratory
 To check, examine and complete all draft records prepared by Drilling Master and
CPT operator
 To make continuous counseling and discussion required with the engineer from the
Client
 To prepare daily progress reports, and work programs
 To attend regular weekly meeting with the Client Representative

b. Drilling Master (Field)


Drilling Master should be experienced personnel in operating drilling rig apparatus on
various soil types. The job descriptions are:
 To perform borings, SPT testing, continuous coring, taking undisturbed samples,
performing field vane shear test, measuring water level, preparing core-box, and
others

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 7 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

 To assist the supervisors in furnishing draft records of drilling results and another
field testing

c. Laboratory Technician (Office)


Laboratory Technician should be experienced personnel who is familiar with laboratory
equipment. The job description should include, but not limited to:
 Performing laboratory testing for disturbed and undisturbed samples taken from
boring and test pit
 Evaluating test results and then submitting them to the Chief Laboratory person for
data processing

d. Data Processing (Office)


Data processing personnel should be experienced personnel and computer literate
who is familiar with any software used for processing the laboratory data. The job
description should include, but not limited to:
 Performing data processing for laboratory test data in accordance with standard
format for presenting laboratory test result

e. Geotechnical Engineer (Office)


Geotechnical Engineer should be a Civil Engineer with over 15 years of experiences
in analyzing geotechnical data, and familiar with using geotechnical software and
geotechnical report preparation and certified as Professional Geotechnical Engineer
(G-1) by Indonesian Society for Geotechnical Engineers. The job description should
include, but no limited to:
 Checking and evaluating the field test results, and reviewing the laboratory test
results
 Preparing engineering analysis based on field and laboratory test results
 Preparing recommendation of the foundation, slope stability, excavation, site filling,
dynamic soil properties, road construction and others
 Preparing final report and others

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 8 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

f. Safety & QC/QA Manager (Office)


He will be responsible for initiating the safety program, ensuring that project safety
requirements and procedures are being accomplished. He also prepares QC/QA
procedures and ensures that all performed works meet the standard procedures.

g. Safety Representative (Field)


He will be responsible for a continuing survey of the operations, ensuring that any
probable causes of injury or accident are controlled and that operating equipment, tools
and facilities are used, inspected and maintained as required by applicable safety and
health regulations. He will also supervise the fieldwork to meet the quality standards.
List of PPE
No Item Quantity
1 Team Leader 1
2 Driller 2
3 HSE 1

2.2.4 Safety
We fully recognize that safety is essential for the welfare of mind kind and also important
contributor to corporate growth. In order to ensure the safety of all people concerned, we
will comply with the following codes of conduct for safety:
 Recognize that every manager, supervisor and employee have a duty and
responsibility for safety
 Enhance safety consciousness and knowledge through education and training
 Establish safety regulations and comply therewith to eliminate unsafe activities and
procedures
 Assess every situation which presents a possibility of an accident and take all
precautionary measures against such possible accident
 Ensure a hazard free and clean work environment
 Create interest and enthusiasm in safety effort through recognition of safety
performance; every accident is preventable
We will perform the work by paying a lot of attention to safety aspects. We will also take
measures to ensure public safety as well as the safety of employees are fully maintained
and will take all measures required to comply with applicable laws and regulations. We
will make the work permits, gate pass and other permits as the regulation applies. We will
show the permits that we have made which in Attachment 1.

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 9 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

List of PPE
No Item Quantity
1 Hand Gloves For all personnel
2 Safety Shoes For all personnel
3 Safety Helm For all personnel
4 Safety Glasses For all personnel
5 First Aid Bag For all personnel

2.2.5 Last Minute Risk Assessment (LMRA)


1 Apakah Penerbit Izin (PI) mendiskusikan bahaya dan Kontrol dengan Ya Tidak
Pemegang ada
Izin (PH)?
2 Apakah Pemegang Izin memperingatkan pihak lain yang dapat terdampak Ya Tidak
oleh ada
pekerjaan anda?
3 Apakah ada konflik pekerjaan yang berdampak pada anda? Ya Tidak
ada
4 Apakah kelompok kerja mengetahui alarm darurat dan tindakan yang Ya Tidak
diperlukan ada
apabila muncul alarm atau kecelakaan?
5 Apakah kelompok kerja tahu rute penyelamatan diri yang paling efektif dan Ya Tidak
lokasi ada
titik kumpul terdekat?
6 Apakah kelompok kerja tahu lokasi membilas mata terdekat, shower darurat, Ya Tidak
peralatan pertolongan pertama, dan perangkat AED? ada

Apakah ada bahaya tambahan yang harus dikontrol? Jika bahaya teridentifikasi
adalah perubahan material terhadap izin, hubungi Permit Issuer!

Langkah-langkah control /
No Bahaya
perbaikan

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 10 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

Sebutkan Aturan Penyelamatan jiwa (Live Saving Rules) yang berlaku

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 11 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

2.2.6 Hazard Identification for Total Safety (HITS)


Tanggal / Jam :
Lokasi :
Perusahaan :
Departemen :
Nama Permit Holder :
Nama Pembicara :

Topik / Materi :

No Nama Nomor ID Posisi Tanda Tangan


1 1 2

3 3 4

5 5 6

7 7 8

9 9 10

10

11 11 12

12

13 13 14

14

15 15 16

16

17 17 18

18

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 12 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

conduct underground facilities check, to ensure there is no underground cable or pipe in


3 GEOTECHNICAL DRILLING
the survey location. The underground cable checking using cable locator witnessed by
Client and conduction manual excavation 1-1.5m to ensure there is no underground
3.1 PREPARATION cable.

 Wear PPE (Personal Equipment) consisting of gloves, coverall (with reflector), safety
helmet, safety glasses, safety shoes, ear Plug and full body hardness.
 Check the drilling machine and the completeness of the equipment used before the
drilling work is carried out. Ensure there is no tree cutting works without Client's approval,
 Make a flat drilling machine working yard of + 8 x 6 m2, at the location of the drilling
point to be carried out.
 Make trenches and small ponds for the circulation of drilling water and install safety
line surrounding the trenches.
 Move the drilling machine (with weight around 500 Kg) to the working court (at the
location of the drill point to be carried out). We will show the method that we have made
which in Attachment 2.
 Place the water pump (with weight around 50 Kg to 75 Kg) at the location of the water
intake plan that will be used for drilling and connect water pipes to the drilling site.
 Assemble the tripod along with pulleys / pulleys in the work court, lift the tripod at the
meeting of the 3 ends of the tripod pole manually as high as 1 meter and prop it up
with a drum.
 Install the holder to put the handlebar drill in the right location so that the drilling
process can take place safely and efficiently.
 Install the rope/mine on the pulley to make it easier to install the sling on the pulley
after the tripod is standing.
 Hook the toe of a tripod that is in line with the drilling machine using an alternating
prepare connected to the drilling machine.
containment to
ensure there is
 Start the machine, pull the alternating so that the toe of the tripod in line with the drilling
no spill from machine shifts towards the drilling machine and the tripod in the center is raised.
machinery.
 If the height of the tripod and position are right, strengthen the position of the 3 feet of
the tripod pole by installing iron or wooden pegs and strengthen the tripod pole by
installing a reinforcing iron rod using a ladder.
 Move the drilling machine forward until the rod hole at the head of the drilling machine
is just above the drilling point to be carried out.
 Strengthen the position of the drilling machine by installing the armature and
tying/hooking the machine mount to the armature.
 Install the slings and hooks on the pulleys, using the mines that have been installed to
pull the slings into the pulleys.

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 13 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

 Make sure the position of the rod hole at the head of the drilling machine is in line with
the pulley.
 Check the horizontal position of the drilling machine with a waterpass, if it is still tilted
with wood on the drilling machine holder

3.2 DRILLING
Drillings are made to determine the true nature, arrangement, thickness, and texture of
various soil strata as they exist in the ground. Every effort should be made to locate and
record the datum elevation at which any change in stratification occurs. Truly
representative samples of the soil comprising each stratum as it exists in the ground
including its natural moisture content must be obtained. Prior to commencement of drilling
location and drilling depth will be submitted to the Client for confirmation and approval.
The final position and elevation will be provided for each bore hole locations.
Continuous disturbed sample for lithologic soil description will be taken by utilizing single
tube core barrel and utilizing double or triple core barrels on any rock condition
encountered.
Steel casing will be driven as required to maintain an open hole for field testing and
sampling operations. The casing will be advanced to a depth greater than the depth at
which field testing of sampling is to be undertaken. Drilling without flushing water for the
purpose of obtaining better core recovery will be admitted in soft materials such as clayey
soil. Drilling rigs will be operated in such a speed and with such water pressure to ensure
perfect core recovery in whatever kind of soil strata is being drilled.

Drilling work

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 14 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

Core samples taken from each bore hole will be placed in wooden box, each of which has
5 grooves with 1 m of length to contain the drill core. The shallowest core will be placed
in the top left corner; cores from SPT will also be placed in the core boxes at the correct
relative depth. The core samples of moist soft rock will be wrapped air-tightly with
transparent vinyl sheet before being placed in the core box. Depth will be indicated on
the core box by permanent markers at the beginning and end of each drill run. Rigid core
spacer will be used to indicate missing length. The project name, location, bore hole
number and depth of coring contained in each core box will be clearly indicated at the
core box. The core will be protected from direct heat and sunlight. At the end of each
day’s work, core boxes will be stored securely from any interference and protected from
the weather.

Wooden box for sample


Prior to examination of the core, our supervisor will take photographs of the cores. The
time between commencement of preparation and the examination of the prepared and
photographed cores will be minimized to prevent loss of moisture from the core samples.
The cores will be examined and described on site by our experienced Geologist in
accordance with Unified Soil Classification System (ASTM D-2487).

3.3 STANDARD PENETRATION TEST (SPT)


Standard Penetration Test will be performed in accordance with ASTM D-1586. For
accuracy we assumed that this test will be conducted at every change of strata and within
a continuous stratum. The sampler will be driven with a guided hammer or ram into
undisturbed soil below the bottom of the boring after the boring has been cleaned to
remove all loose and foreign materials. The sampling spoon will be 2 inches OD split
barrel sampler with an inside diameter of 1 3/8 inches. The inside of the split barrel will
be flushed with the inside of the drive shoe.

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 15 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

SPT Split Spoon SPT Apparatus

The hammer used to drive sampler have weight of 63.5 kg and will fall freely through a
height of 75 cm. The number of blows required to drive the sampler every 15 cm for a
total depth of 45 cm will be observed and recorded. The record will clearly show the
number of blows for every 15 cm of penetration. In hard materials requiring more than 50
blows/15 cm of penetration, the blows for smaller amount of penetration may be observed
and recorded with special note of the amount of penetration actually obtained.

Immediately upon removal from the hole, the sample will be carefully disassembled and
the soil classified. The samples will be wrapped in a transparent vinyl sheet and then
placed in the core box.

3.4 UNDISTRUBED SAMPLING


In fine grained or cohesive soils, undisturbed sample will be recorded for laboratory
testing purposes and will be performed in accordance with ASTM D-1587. For accuracy
of data, we assumed that undisturbed samples will be taken at every 3-meter interval.
Undisturbed soil samples are to be recorded by means of a thin-walled Shelby tube
having 70 mm inside diameter and 80 cm length. Shelby tubes will be seamless steel,
properly cleaned and polished on the inside. The sampler will be pushed with hydraulic
pressure fed continuously by boring machine not by driving to minimize disturbance of
the undisturbed sample.

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 16 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

Thin-walled Shelby tube


The sampler with its contained soil sample should remain in place for about 5 minutes.
The drill rod will then be rotated for two complete revolutions or until the soil immediately
below the sample has sheared. The tube containing the sample will later be carefully
removed from the boring and detached from the driving head.
Bottom end of each sample will be cleaned and tested with Pocket Penetrometer and
Hand Vane Shear.

Pocket penetrometer Hand Vane Shear

Hand Vane Shear test is most useful in determining the in-place shear strength of soft
clays, and unsuitable for stiff and hard clays and for clays containing gravel pieces. A
vane tester consists of a pair of thin steel blades connected to a vertical shaft. The tester
is pushed into the bottom samples and a torque is applied on the shaft. This test will be
performed in accordance with ASTM D-2573.
The soil sample in the tube will be carefully squared at each end, not less than ½ inch
back of the ends of the tube, and both end spaces will be completely filled with hot sealing
wax.

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 17 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

Undisturbed soil sample will be clearly, accurately and permanently marked to show the
number of bore hole, the depth from which the sample was taken, top and bottom of the
sample and many other information which may be helpful in determining sub-surface
condition.
All undisturbed samples will be protected in every possible way to avoid disturbance of
the samples during transportation. All samples will be protected from excessive heat and
carefully packed to prevent damage during storage or transportation.

3.5 GROUND WATER LEVEL OBSERVATION


Water levels in all holes will be taken and recorded
in the daily field records and logs at the following
period:
 Before the drilling commenced in the morning
 After the drilling finished in the evening
 When a hole has been completed

Deepmeter
3.6 BORING LOG
A field boring log will be prepared as boring progresses for each of the boring and
information in the boring log will include, but not be limited to, the following:
 Name of Contractor, driller and supervisor
 Name of supervising engineer
 Identification of project
 Date and weather condition when borehole was drilled
include coordinates?
 Number and location of borehole
 Elevation of surface with respect to reference datum, water depth and state of tide, as
applicable
 Depth of different strata and to each sample
 Depth of groundwater and any contributing factors
 Type of sample
 Descriptions of each soil sample and soil stratum according to the Unified Soil
Classification System

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 18 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

 Results of all pocket penetrometer and shear vane tests


 Descriptions of all equipment used in performing the investigation and pertinent data
regarding obtaining of samples and field tests such as weight of hammer fall used, size
and type of samples, standard penetration blow counts on sample, and others.

4 CONE PENETRATION TESTS (CPTU)


4.1 PIEZOCONE PENETRATION TEST (CPTU)
This test will be performed according to ASTM D—3441. Cone penetration tests (CPT)
were carried out using a 10 ton capacity piezocone and penetrometer. The cone tip has a
60° point angle with a projected area of 10cm2 and a friction sleeve area of 150 cm2. The
pore pressure filter is located at the cone shoulder or commonly known as u2 cones. The
cone was connected to a series of steel rod and advanced hydraulically at a speed of
2cm/sec into the subsoil. The cone is designed with an equal-end area friction sleeve and
a tip-end area ratio of 0.81. The cone was used to take measurements of cone bearing,
sleeve friction, inclination, and dynamic pore water pressure at 1cm intervals.

4.2 DISSIPATION TEST


Multiple dissipation tests were carried out during cone penetration test with a piezocone.
During the test penetration is temporarily stopped while the pore pressure is being
monitored continuously. The change in pore pressure as a function of time is a measure
for the permeability of the layer in which the piezocone is stopped. The dissipation test
data is then used to predict the coefficient of permeability and coefficient of consolidation
in horizontal direction for estimating settlement time rates. The dissipation tests were
performed at multiple depths where the layers are expected clay.
Before starting a dissipation test it is determined first when the test is considered to be
completed. For this project the dissipation test is continued until equilibrium is reached or
50% of the initial excess pore water pressure, t50, has dissipated.

5 TEST PIT OPERATION


 Make trenches and small ponds for the circulation of drilling water and install
safety line surrounding the trenches.
 Test Pit activity is carried out will be digging manually
 Excavation is carried out in accordance with instructions, as well as dimensions
and the correct depth
 The dimension of pit sized 1.0 x 1.0 x 2.0 meter

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 19 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

 The excavation must always be monitored by a work leader or geologist, it is


not allowed to dig by alone
 Provide stairs to meet the safety requirements
 Take undisturbed sample using mold or keep the disturbed soil sample using
sack
 Identify soil layers on the four walls of the excavation using pocket penetrometer
 If the test pit work is completed, the pit must be fill in again and compacted
properly
 Density testing per ASTM D1556 or ASTM D2922 shall be performed on the
undisturbed soils at depths of 0.0, 0.5, 1.0, 1.5, and 2.0m depths, and bulk
samples representative of the soil layer(s) shall be taken for laboratory chemical
and earthwork tests including California Bearing Ratio (CBR) testing as per
ASTM D1883.

6 ENGINEERING ANALYSIS AND REPORTING


6.1 DAILY REPORT
The daily report will be submitted to the Client’s representative which consist of:
 Daily activity
 Draft of boring logs
 Manpower record
 Program for next day work

6.2 PRELIMINARY REPORT


Soilens to submit Preliminary Report shall be submitted 2 weeks after finished field work
for some areas if required by Contractor.

6.3 FINAL REPORT


The Final report will be submitted according to the attached schedule. The report consists
of:
 A map showing the location of all boreholes and their elevation referenced to the
existing permanent bench mark
 Description on the geology of the area
 A brief discussion of field drilling and sampling procedures and equipment used
 Boring Log graph
 Description of laboratory test performed and test results

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 20 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

 Summary of soil properties obtained from various test required for the site
preparation and foundation design.
If required, we can also provide discussion and recommendations with respect to:
 Recommendation and discussion for site preparation including road and site grading
 Recommendation on foundation types and depths of deep and shallow foundation
 Allowable bearing capacity at various recommended depth for spread foundation.
Allowable bearing capacity indicated as being gross of net values, allowable passive
and active pressure to resist horizontal loads.
 Allowable capacities of deep foundations for downward, uplift and horizontal loads.
Plots of depth versus pile capacity for various pile diameters will be provided. The
effect of group action will also be provided.
 Possibility of harmful sulfate attack on concrete below and advisability of the use
sulfate resistant Portland cement
 And any others topics as required by the Client
Engineering analysis for foundations will be performed based on field and laboratory test
data encountered. Previous soil data will also be reviewed for these analyses. The
engineering analysis will be performed using relevant geo-technical software as follows:
a. PLAXIS
For slope stability analysis, soil deformation, soil settlement, shallow foundation and
bearing capacity, pile group analysis, seepage analysis, sheet pile analysis, stability of
sheet pile and others.
PLAXIS is a finite element package that has been developed specifically for the analysis
of deformation and stability in geotechnical engineering. The simple graphical input
procedures enable a quick generation of complex finite element models, and the enhanced
output facilities provide a detailed presentation of computational results.
The finite element program of PLAXIS is selected because:
 PLAXIS analyzes steady state pore pressures;
 PLAXIS allows for the development of excess pore pressure due to undrained
loading and subsequent dissipation of this excess pore pressure through
consolidation. Deformations coupled with the dissipation of excess pore pressure
are included in the consolidation calculations;
 PLAXIS incorporates large deformation theory in the soil model.
The ability to handle these complexities with a single integrated code is highly
desirable for geotechnical analysis. The results of the analysis will be presented in
chart or graph, or table as required.

CONFIDENTIAL: This document contains the confidential information. It shall not be reproduced, copied, disclosed and/or used for other purposes
without the written permission of STAR ENERGY GEOTHERMAL, JO TIMAS - REKIND
CONTRACTOR: JO-TR DOC NO..
METHOD STATEMENT FOR
FIELD TEST SOIL INVESTIGATION SEG-SK7-CI-GN00-PCD-502

OWNER Sheet Rev.


Page 21 of 21 00
SALAK UNIT 7 DEVELOPMENT
PROJECT Doc Class 1

b. PILE
For analysis of ultimate compressive and uplift (tension), pile capacity. The ultimate pile
capacity is developed based on static capacity. The characteristic side friction versus pile
movement (T-Z) or load transfer curves for cohesive soils is based on the results of model
and full-scale pile load tests, tests reported by Seed and Reese.
End bearing or tip load is assumed to increase with displacement of the pile tip. The tip
movement producing full mobilization of the ultimate end bearing is assumed to be 10 %
of the pile diameter. Values of the ultimate end bearing correspond to those used in the
pile capacity computations. The ultimate tip load corresponds to the unit end bearing values
times the gross end area of the pile.
The results of this analysis will be presented in graph showing the relation of downward
displacement vs compressive load, upward displacement vs tension load at the top of pile
head and base of pile.
And others software for analysis and presentation of Boring log graph results