MS_01 Surveying Works
MS_01 Surveying Works
STATEMENT
BASE GENERAL CONTRACTING L.L.C.
CLIENT : Ministry of Energy and Infrastructure
PROJECT NO : 83/2024
REVISION CONTROL
Doc. No: BGC-MS-01 Rev 00 Page 1 of 10 Method Statement For Surveying Works and Setting Out
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
7.0 PROCEDURE
Doc. No: BGC-MS-01 Rev 00 Page 2 of 10 Method Statement For Surveying Works and Setting Out
2.0 SCOPE
This document shall be applicable for:
1. Traversing from GPS to GPS, marking of proposed Centre Line and establishment of
TBM/BM as per given survey data and their periodic checking as per requirement.
2. Recording of OGL/NGL (Original Ground Level / Natural Ground Level) on grid points at specified
intervals
3.0 REFERENCES
a) IFC drawings
b) Shop Drawing Approvals
c) Request For Information
d) No Objection Certificates
4.1 ABBREVIATIONS
4.2 DEFINITIONS
Doc. No: BGC-MS-01 Rev 00 Page 3 of 10 Method Statement For Surveying Works and Setting Out
Doc. No: BGC-MS-01 Rev 00 Page 4 of 10 Method Statement For Surveying Works and Setting Out
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
a) Organizing tools and equipment required to the work site.
b) Assigning work crew.
c) Sequence of activities to be carried out for the work as per this work procedure.
d) Stage Inspection & Surveillance.
e) Ensure all safety Regulations are followed as applicable.
f) Contract specific requirements for excavations, if any specified shall be identified and the requirements of
such specification shall prevail in addition to the non-conflicting requirements of this procedure.
g) Ensure & study the approved drawings & statements before starting the activity.
h) Communicate all HSE requirements to the entire working crew and ensure that they understand.
i) Thoroughly familiar with all MODES/RAY contract and general HSE requirements and understand it to
maintain a healthy and safe environment for employees and contract staff.
Doc. No: BGC-MS-01 Rev 00 Page 5 of 10 Method Statement For Surveying Works and Setting Out
5.6 Surveyor
Doc. No: BGC-MS-01 Rev 00 Page 6 of 10 Method Statement For Surveying Works and Setting Out
a) Ensure all P & M Equipment being used for the activity are in good working condition.
b) Ensure P & M Operators are qualified & authorized to operate the relevant equipment.
c) Ensure the work area shall be barricaded.
d) The toolbox talk shall be carried out before starting the work.
e) Ensure all necessary PPEs are worn by workers involved in the work.
Doc. No: BGC-MS-01 Rev 00 Page 7 of 10 Method Statement For Surveying Works and Setting Out
a) Total station
b) Auto level / leveling staff
c) Measuring tape
d) Ancillary items such as but not limited to paint, pegs, lime powder, etc.
7.0 PROCEDURE
7.1 General
The following documents as a minimum shall be readily available for ready reference at work site.
Client specifications
Approved Method statement
Issued for Construction drawing &
Approved Shop Drawing
No Objection Certificates
The foregoing procedure for the Surveying Works will serve as a guide by the Surveyor together with the
SE and QA/QC Inspector along the course of their work to achieve an acceptable quality of workmanship
and attaining the optimum results with less time and effort:
a) Establishing primary control points.
b.1.1 Setting Out of working points shall be conveniently located for easy access and as to avoid
Doc. No: BGC-MS-01 Rev 00 Page 8 of 10 Method Statement For Surveying Works and Setting Out
A rough grading will be run through the proposed roadway leaving a 200mm clearance above
subgrade level manned by a surveyor to avoid overcutting beyond the design subgrade level. After
Rough Grading the following sequence of work shall be observed:
d) Establishing benchmarks
Staking shall be established basing the approved roadway layout and following its intended design cross-
sections and profiles.
e.1.1 The surveyor shall locate the Municipality Bench Mark at the nearest location to the project
site, this BM shall be ensured to be correct and updated.
e.1.2 Coordinates shall be fed to the Total Station from the approved Working Coordinates Plan.
e.1.3 The surveyor shall start and position his instrument at the Benchmark (BM) and feed to the
instrument the known BM’s coordinate and elevation.
e.1.4 The surveyor can now conveniently locate and establish the control points for future
references.
e.1.5 After establishing the control points, the surveyor may now start to run the required
surveying works such as Staking and Grading, Road Stationing, Road Center Line Setting
Out and Line Marking.
f) Recording of OGL
f.1.1 After fixing of proposed Centre line and benchmarks for recording of natural ground levels
(NGL) the grid points will be marked with the measuring tape etc. The staff reading will
be recorded on marked grid points. All staff readings (BS, IS & FS) will be recorded in
level book and levels will be reduced in reference with the respective Temporary
Benchmarks (TBMs). NGL/OGL recording will be carried out jointly.
g) Rectification of Works
Doc. No: BGC-MS-01 Rev 00 Page 9 of 10 Method Statement For Surveying Works and Setting Out
h) As-built Survey
h.1.1 As-Built Survey will be conducted as soon as substantial work has been completed.
h.1.2 Results of the As-built Survey will then be correlated with the proposed or planned
coordinates noting any variance or if results is within acceptable limits i.e. coordinates
deviation from plan to actual.
h.1.3 If results is beyond acceptable limits, necessary corrective action shall be made to address
the concern. All Subsequent work maybe stop as per instruction by the Engineer until
corrective actions has been rectified.
h.1.4 Results of the Survey shall be kept, tagged, and properly bounded in binder folder.
The Equipment Accuracy for Survey Equipment will be maintained as per Project Specifications.
Doc. No: BGC-MS-01 Rev 00 Page 10 of 10 Method Statement For Surveying Works and Setting Out