1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
7.0 PROCEDURE
Doc. No: BGC-MS-005 Rev 00 Page 2 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
1.0 PURPOSE
The purpose of this document is to provide the guidelines for subbase work by satisfying all the
relevant specifications and requirements.
2.0 SCOPE
This document shall be applicable for subbase work under the project- 83/2024 for Maintenance of
Federal Road Assets (Design & Built) - Group 2.
3.0 REFERENCES
4.1 ABBREVIATIONS
4.2 DEFINITIONS
Doc. No: BGC-MS-005 Rev 00 Page 3 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
5.0 ROLES & RESPONSIBILITIES
Doc. No: BGC-MS-005 Rev 00 Page 4 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
c) Responsible for managing all interfaces with Client and Project Manager.
d) Responsible for actual progress of the work against planned program.
e) Obtain subcontractors Procedures / Plans / Method Statements, where applicable and coordinate approval of
the same.
f) Coordinate with the Procurement Unit in carrying out procurement activities for the project through Project
manager.
g) Liaise with Site Engineers to ensure timely completion of civil activities pertaining to the project
h) Analyze deviations, change of contract scope or delays, if required, and reschedule to meet target dates in
coordination with the Project Manager.
i) Appropriate actions shall be taken on all NCRs and Audit Non-Conformances raised in the Project.
j) Ensure through the QA/QC Engineer that all Corrective & Preventive Actions taken in the Project are
Effective.
k) Identify Training needs and Coordinate with appropriate function for fulfilling the Training Requirements.
l) Reports to the Project Manager.
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
a) Organizing tools and equipment required to the work site.
b) Assigning work crew.
c) Sequence of activities to be carried out for the work as per this work procedure.
d) Stage Inspection & Surveillance.
e) Ensure all safety Regulations are followed as applicable.
f) Contract specific requirements for excavations, if any specified shall be identified and the requirements of
such specification shall prevail in addition to the non-conflicting requirements of this procedure.
g) Ensure & study the approved drawings & statements before starting the activity.
h) Communicate all HSE requirements to the entire working crew and ensure that they understand.
i) Thoroughly familiar with all MODES/RAY contract and general HSE requirements and understand it to
maintain a healthy and safe environment for employees and contract staff.
5.4 NOC Officer
Doc. No: BGC-MS-005 Rev 00 Page 5 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
e) Support in resolving authority approval and permit interface issues as necessary together with the wider
project team, develop systems to ensure that permits are current and valid for the activity being undertaken.
f) Advising and informing appropriate staff and department of document and plan submittal requirements
5.6 Surveyor
Doc. No: BGC-MS-005 Rev 00 Page 6 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
d) Coordinate with approved Third party laboratory for Material testing as per Client specifications and
International standards.
e) Ensure all incoming site materials are as per approved Material submittal.
f) Review and Maintain records of all material test reports as per client requirement.
a) Ensure all P & M Equipment being used for the activity are in good working condition.
b) Ensure P & M Operators are qualified & authorized to operate the relevant equipment.
c) Ensure the work area shall be barricaded.
d) The toolbox talk shall be carried out before starting the work.
e) Ensure all necessary PPEs are worn by workers involved in the work.
f) Work shall be carried out in the daytime and if authorized, night work is permitted.
g) All sub-contractor men, material, machinery details to be collected and checked against insurance.
h) No work shall be allowed if temperature is more than 50 degree Celsius / high wind / more than 80%
humidity / inclement weather due to rain, lighting storm, fog or dark condition.
Doc. No: BGC-MS-005 Rev 00 Page 7 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
6.2 Materials, Tools, Equipment and Machineries
a) Tipper
b) Trailer
c) Loader/Bobcat
d) Tandem Power-driven Roller
e) Pneumatic Tired Roller
f) Vibrating Roller
g) Plate compactor
h) Grader
i) Water tanker
j) Shovel
k) Six-wheel
l) 3-Ton Pick up
m) Total station
n) Auto level / leveling staff
o) Measuring tape
p) Temporary Signs
q) Safety Barriers
r) Safety Traffic Cones
7.0 PROCEDURE
7.1 General
The following documents as a minimum shall be readily available for ready reference at work site.
Client specifications
Approved Method statement
Issued for Construction drawing &
Approved Material approval sheet
Doc. No: BGC-MS-005 Rev 00 Page 8 of 9 Method Statement for Subbase Work
Date of issue: BASE GENERAL CONTRACTING LLC
c) Compaction of the subbase layer shall be carried out using vibrating roller to achieve dry density as per
specification.
d) Alignment, level and surface regularity will be checked in accordance to the Technical Specification.
e) The final surface of granular subbase layer shall be regulated and trimmed by back pusher to the required
level and cross fall within the specified vertical tolerances. Compaction work shall be done using roller
compactor.
f) Field Density Test (FDT) or California Bearing Ratio Test on the subgrade shall be carried out according
to the specifications.