Weekely Work Program from 04.04.2025 to 10.04.2025

The document outlines the weekly work program for Abir Infrastructure Private Limited for the Barrage Complex of the Rammam - III Hydro Electric Project from April 4 to April 10, 2025. Key tasks include the installation of a security gate, construction of a civil office shed, and various concreting and excavation activities at different work locations. Additional remarks indicate ongoing wiring and planned blasting for excavation work.

Uploaded by

krishnacivil6785
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views1 page

Weekely Work Program from 04.04.2025 to 10.04.2025

The document outlines the weekly work program for Abir Infrastructure Private Limited for the Barrage Complex of the Rammam - III Hydro Electric Project from April 4 to April 10, 2025. Key tasks include the installation of a security gate, construction of a civil office shed, and various concreting and excavation activities at different work locations. Additional remarks indicate ongoing wiring and planned blasting for excavation work.

Uploaded by

krishnacivil6785
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Abir Infrastructure Private Limited

Name of Work: Balance Civil and HM Works of Barrage Complex including Part HRT Package for Rammam - III
Hydro Electric Project (3x40 MW) - Package-2

Weekly Work Program

Period from 04.04.2025 to 10.04.2025

SN Work Description Scheduled Dates Remarks (If any)


Work Location: Adit-02, Restoration Work

1 Installation of Security Gate at Adit02 Portal 05.04.2025

2 Civil Office Shed Construction 04.04.2025 to 07.04.2025 Wiring in progress

3 Magzine House Plastering with Mud 04.04.2025

4 Batching Plant Foundation 04.04.2025 to 07.04.2025

5 Complete Setup of Porta Cabin/Shifting of NTPC container near 04.04.2025 to 07.04.2025 Wiring in progress
Adit02, Entry point
6 Excavation at RD 641.8 by Drilling and Blasting Method, 07.04.2025 to 10.04.2025 Total three Blast should be
planned (1.2*4=4.8 mtr.) for Adit-
02, Class-V)
Work Location: Adit-01

1 2nd Gantry concreting of B-HRT-02 04.04.2025 Total Progress will be 21 mtr. of


Lining.
2 Preparation of 2nd Gantry concreting for B-HRT-01

3 Preparation of 3rd Gantry concreting for B-HRT-02 05.04.2025

4 2nd Gantry concreting of B-HRT-01

5 3rd Gantry concreting for B-HRT-02 06.04.2025

6 Preparation of 3rd Gantry concreting of B-HRT-01

7 Preparation of 4th Gantry concreting for B-HRT-02 07.04.2025

8 3rd Gantry concreting of B-HRT-01

9 4th Gantry concreting for B-HRT-02 08.04.2025

10 Preparation of 4th Gantry concreting for B-HRT-01

11 Preparation of 5th Gantry concreting for B-HRT-02 09.04.2025

12 4th Gantry concreting for B-HRT-01

13 5th Gantry concreting for B-HRT-02 10.04.2025

14 Preparation of 5th Gantry concreting for B-HRT-01

15 Desilting Chamber-02/Downstream: Gantry cleaning and repairing of 04.04.2025 to 10.04.2025


the existing gantry.

16 Desilting Chamber-01/Upstream: Preparation of the transition portion


for shuttering reinforcement and concrete work.

17 Dewatering at HRT 04.04.2025 to 10.04.2025 Total Progress will be 72 no. of


Contact Grouting.
18 Contact Grouting at Intake Tunnel-01

19 Miscellenious Work 04.04.2025 to 10.04.2025

Setup of Batching Plant in Progress


Set Up of Stone Crusher