Plan Risk Management
Plan Risk Management
Management
1
Risk Management
Risk in project management, unlike the common definition of the word, can be both
negative (threats) and positive (opportunities). The objective of Project Risk
Management is to decrease the likelihood and impact of negative events, while
increasing the likelihood and impact of positive ones
The Process of Planning for Risk
Perform Perform
Identify Plan Risk
Qualitative Quantitative
Risks Risk Analysis Responses
Risk Analysis
1. Identify Risks
Identify Risks is the process of
determining individual risks as well as
sources of overall project risk, and
documenting their characteristics .
All project personnel should be
encouraged to identify potential risks
Information gathering techniques
Brainstorming Delphi Technique*
MUST mitigate
P
r
o
b Write
a Contingency
b Plan
i
l
i
t
y
Identified
No contingent plan
LIKELIHOOD
4 -4 -8 -12 -16 -20 20 16 12 8 4 4
3 -3 -6 -9 -12 -15 15 12 9 6 3 3
2 -2 -4 -6 -8 -10 10 8 6 4 2 2
1 -1 -2 -3 -4 -5 5 4 3 2 1 1
-1 -2 -3 -4 -5 5 4 3 2 1
THREATS OPPORTUNITIES
(NEGATIVE IMPACT) (POSITIVE IMPACT)
Example 1: The following are four risks with probabilities and impact for a small construction
project. Determine the EMV for each risk and the project contingency reserve:
Solution
Contingency Reserve
Decision tree analysis
A Decision Tree : is a common use of EMV analysis
Example 2: determine the best decision to take for the following decision tree assumptions. Assume 5 years of
return on investment
0.6
Increased shopper traffic
(+$100,000)/month
Flagship store in new mall
Chance Node
(-$1,000,000)
Stronger competition
(-$50,000) )/month
0.4
New store or renovation? Decision Node
0.8 Initial business surge
(+$50,000) )/month
Renovate existing store Chance Node
(-$250,000)
Dwindling shopper traffic
(-$100,000) )/month
0.2
Solution
Assumed 5 years of return on investment
0.6
Increased shopper traffic 100000*5*12 – 1000000
(+$100,000)/month = + 5,000,000
Flagship store in new mall
Chance Node
(-$1,000,000)
Stronger competition
-50000*5*12 – 1000000
EMV of Node 1= 0.6* 5m + (-4m*0.4) (-$50,000) )/month = - 4,000,000
= + 1,400,000 0.4
New store or renovation? Decision Node
0.8 Initial business surge 50000*5*12 – 250000
EMV of Decision Node =
(+$50,000) )/month = + 2,750,000
+ 1,400,000
Renovate existing store
Chance Node
(-$250,000)
Dwindling shopper traffic -100000*5*12 – 250000
EMV of Node 2= 0.8* 2.75m + (-6.25m*0.2) = - 6,250,000
(-$100,000) )/month
= + 950,000 0.2
Example 3: You are planning modifications to a product line. Below is a complete assessment
of risks on the project:
• Determine:
• EMV for each risk
• Project Contingency reserve
Solution
Example 4: A construction project will have an Base cost of $1,250,000. There is a 10 percent
chance that the costs will increase by 10 percent. There is a 20 percent chance that the building
foundation will win the “Foundation of the Year” award and its $50,000 prize. There is a 5
percent chance that an accident will add $125,000 to the cost.
Calculate the following:
a. calculate the contingency reserve
b. What is the expected value of the project?
c. What is the best case scenario and its value?
d. What is the worst case scenario and its value?
Solution
Base cost = - $1,250,000
Avoid – eliminate the task or the threat, or isolate the project objectives from the threat
Accept – proceed anyway in spite of the risk, maybe with a fallback contingency reserve
Share – work with a third party who is best placed to tip the odds in favor Positive
risks
Enhance – increase the likelihood or impact of the opportunity, or both
Accept – make the most of an opportunity if it comes along, but not proactively
Thank you for you Attention