7
7
A. Over budget
B. On budget
C. Under budget
D. Not having enough information provided
Exercise: Accounting Standards
A. Project A
B. Project B
C. Project C
D. Project D
1) One common way to compute estimate at
completion (EAC) is to take the budget at
completion (BAC) and:
A. Divide by SPI.
B. Multiply by SPI.
C. Multiply by CPI.
D. Divide by CPI.
Answer: D
Answer: C
3) If earned value (EV) = 350, actual cost (AC) =
400, planned value (PV) = 325, what is cost
variance (CV)?
A. 50
B. -75
C. 400
D. -50
Answer: D
Answer: D
5) Which of the following is an example of a
parametric estimate?
A. Dollars per module
B. Learning bend
C. Bottom-up
D. CPM
Answer: A
Answer: A
7) Project setup costs are an example of:
A. Variable costs.
B. Fixed costs.
C. Overhead costs.
D. Opportunity costs.
Answer: B
Answer: A
9) The difference between the cost baseline and
the cost budget can be BEST described as:
A. The Contingency reserve.
B. The Management reserve.
C. The project cost estimate.
D. The cost account.
Answer: A
Answer: C