6_7_merged
6_7_merged
The amount of time a task can be delayed without delaying the end date of
the project.
The difference between either the Late and Early Start or the Late and Early
Finish.
2 Days 12 Days 5 Days
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
(0) (0) (0) Finish
Start
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16 (0)
Float = (0)
D E F
3 9 9 16 16 19
10 1 4
C D E
6 7 9 8 4 6 3
A B F G H J K
11
Figure H
C D E
6 7 9 8 4 6 3
A B F G H J K
11
Figure H
10- Using figure H, a new task R with a duration of five is added to this
project. Task R has a predecessor of task A and a successor of task B.
How long will the project now take?
A. 49
B. 48
C. 38
D. 52
10 1 4
C D E
6 7 9 8 4 6 3
A B F G H J K
11
Figure H
12- Based on the network diagram in figure H, the resource working on task
G is replaced with another resource with 50% of the productivity of the
previous resource. How long will this project take?
A. 44
B. 51
C. 52
D. 36
Exercise:
You have a project with the following tasks:
Task 1 can start immediately and has an estimated duration of four.
Task 2 can start after Task 1 is completed and has an estimated
duration of eight.
Task 3 can start after Task 2 is completed and has an estimated
duration of five.
Task 4 can start after Task 1 is completed and has an estimated
duration of eight.
Task 5 has an estimated duration of three and must take place
concurrently with Task 3. It can start after Tasks 4 and 2. What is
the duration of the critical path of this project?
A. 15
B. 18
C. 17
D. 12
Answer: A
C. Activity I A D G
D. Activity C
2 1 9
Start B F I End
6 2 1
C E H
Answer: C
3. Lag means:
A. The amount of time an activity can be delayed
without delaying the project finish date.
B. The amount of time an activity can be delayed
without delaying the early start date of its
successor.
C. Waiting time.
D. The product of a forward and backward pass.
Answer: C
Answer: A
5. Which of the following is CORECT?
A. The critical path helps prove how long the
project will take.
B. There can be only one critical path.
C. The network diagram will change every
time the end date changes.
D. A project can never have negative float.
Answer: A
Answer: C
7. The float of an activity is determined by:
A. Performing a Monte Carlo analysis.
B. Determining the waiting time between activities.
C. Determining lag.
D. Determining the amount of time the activity can
be delayed before it delays the critical path.
Answer: D
Answer: C
9. An activity has an early stat (ES) of days 3, a late
start (LS) of days 13, an early finish (EF) of day 9,
and a late finish (LF) of day 19.
The activity:
A. Is on the critical path.
B. Has a lag.
C. Is progressing well.
D. Is not on the critical path.
Answer: D
Answer: C
Questions & Answers
1) You are a project manager working on a project that
requires 100 widgets to be built in five weeks. You
have just begun week three, with an overall budget of
US $10,000. To date you have spent US $2,000 with
40 widgets successfully built. What does the cost
variance tell you in this circumstance?
A. Over budget
B. On budget
C. Under budget
D. Not having enough information provided
Exercise: Accounting Standards
A. Project A
B. Project B
C. Project C
D. Project D
1) One common way to compute estimate at
completion (EAC) is to take the budget at
completion (BAC) and:
A. Divide by SPI.
B. Multiply by SPI.
C. Multiply by CPI.
D. Divide by CPI.
Answer: D
Answer: C
3) If earned value (EV) = 350, actual cost (AC) =
400, planned value (PV) = 325, what is cost
variance (CV)?
A. 50
B. -75
C. 400
D. -50
Answer: D
Answer: D
5) Which of the following is an example of a
parametric estimate?
A. Dollars per module
B. Learning bend
C. Bottom-up
D. CPM
Answer: A
Answer: A
7) Project setup costs are an example of:
A. Variable costs.
B. Fixed costs.
C. Overhead costs.
D. Opportunity costs.
Answer: B
Answer: A
9) The difference between the cost baseline and
the cost budget can be BEST described as:
A. The Contingency reserve.
B. The Management reserve.
C. The project cost estimate.
D. The cost account.
Answer: A
Answer: C