Energy Sim Customized Loads -Samuelson IBPS
Energy Sim Customized Loads -Samuelson IBPS
Permanent link
http://nrs.harvard.edu/urn-3:HUL.InstRepos:29663437
Terms of Use
This article was downloaded from Harvard University’s DASH repository, WARNING: No
applicable access license found.
Accessibility
Accepted at Proceedings of (Building Simulation) the International Building Performance Simulation
Association International Conference, Glasgow, Scotland, July 2009. Awarded Arup Engineering Best-
Paper Prize for Simulation in the Design Process
RMSE
6
2
i1 measured
DISCUSSION
Known and Suspected Shortcomings
While simulated and measured energy loads were
reasonably close for the Gund Hall model, the
authors do not rule out that hidden “lucky” mistakes
may be cancelling out each other. Some of the known
shortcomings of the model are:
The building’s HVAC system was simplified,
therefore, the VAV system with steam reheats was
not modelled, meaning simultaneous heating and
cooling would be underestimated.
It is suspected that the building systems cannot
Figure 6: Electricity - Measured vs. Simulations actually meet the peak cooling loads. Therefore,
the modelled cooling system, with its unlimited
Heating and Cooling capacity, exceeds the actual utility load in July.
The monthly metered and simulated heating and In addition, manual heating setbacks during the
cooling loads are shown in Figures 7 and 8. The extended holiday and exam periods in late
students found abnormalities in the metered chilled
December and January were likely underestimated
water data from 2007/2008, so data from the previous
by the students in the model.
school-year are shown here.
Finally, the chilled water meter was suspected of
From these graphs, one can see that the use of custom
malfunctioning and was replaced a few weeks prior
versus default settings, including HVAC operating
to this writing. Therefore, the authors are unsure of
schedules, again improved the simulation results,
the accuracy of the measured data shown in Fig. 8.
although the impact is not as consistent throughout
Weather Files
the year as with electricity. This is due in part to
variables cancelling out each other. For example, the Given the significant influence of weather conditions
default occupancy, plug-load and lighting loads on building performance, it is essential to use reliable
resulted in a 17% over estimation in annual heating climate data for energy modelling. Given that each
load, but then the addition of the default air handling of the three weather files tested produced similarly
unit schedule resulted in a 9% under-estimation. accurate simulation results, any of the three would
have been acceptable for this project. This is not
surprising given that all three files were collected
within a relatively small radius of several kilometres.
The different files had some significant discrepancies
in local wind conditions, but since the energy use of
Gund Hall is not very susceptible to wind, these
differences have little impact on the building’s
simulated energy use. The positive news for a
designer is that using a prepared climate file – by far
the easiest solution from a simulation standpoint –
does not seem to compromise significantly the
simulation accuracy. The caveat is that the climate
file must of course be representative of the particular
Figure 7: Heating – Measured vs. Simulations
building site.
In the absence of an already prepared local climate
file, the options for a design team are either to build a
climate file from scratch using local data from one or
several local sources (EPW1) or to collect one’s own
data (EPW2). Surprisingly, the latter option turned
out to be the more attractive one: The total cost for
the Gund Hall weather station is under $2500, the
equipment can be built up and run standalone at even
the remotest locations, and the measurements are
very close to the measured data from the MIT and
UMASS weather stations. During several months of
operation, the data logger produced a very reliable,
Figure 8: Cooling – Measured vs. Simulation synchronized data series that could be converted into
EPW format with little effort.
This finding strongly suggests that design teams
operating in locations for which climate data is not
available should collect their own weather data over largest error margin given that walk-through
at least several months in order to develop a more observations and occupant questionnaires lead to
accurate knowledge of the local climatic conditions different results. However, some occupancy analysis
of their building site. It should be noted, however, seems unavoidable for the creation of an accurate
that weather data might be of limited use if collected model of an existing building, especially when the
in an atypical year. plug-loads are so closely linked to occupancy. The
Conversely, the approach used for EPW1, combining number of site visits conducted in this experiment
multiple incomplete weather files, is not advised as it may be impractical for most project budgets, but
generated by far the most amount of work. certainly multiple site visits, and off-hours site visits,
Compiling data from several sources turned out to be as recommended by others (Waltz, 2000) seem
extremely time consuming and required a lot of necessary.
manual ‘cut and paste’ since data time steps were not It is interesting to note that the occupants consistently
always synchronized or constant and some time over-estimated the time spent at their desks, or
periods were missing altogether. perhaps the 22% of occupants who responded to the
Occupancy and Other Custom Inputs questionnaire tended to be an unrepresentative
sample. Waltz also reported that occupants tend to
Given the results shown in Figure 6, it seems that the
overestimate the amount of time they are spending at
detailed analysis of the building’s internal loads was
their workplace (Waltz, 2000). Therefore, although
worthwhile. The simulation with default occupancy,
more time-consuming for the researchers, walk-
plug-load, and lighting settings predicted an annual
through observations seemed to be a good
electrical consumption that was 18% lower than
supplement to, or replacement for, questionnaires.
metered data. The addition of custom lighting inputs
reduced this error to 12%, and custom occupancy and Little effort was invested in documenting window
plug-loads, reduced it further to 0.2%. This finding shade usage; however, the addition or subtraction of
underlines the benefits of carefully surveying a the shading in this simulation resulted in less than a
building during retrofitting projects. 1% change in annual energy consumption. One
should note that this number could be significantly
However, in the design phase of a project, the
larger for spaces with external shading. In Gund
modeller may have no additional information
Hall, the window shading is entirely internal, and it
available. In the Gund Hall project, deviation
exists on less than ½ of the glazing.
between “expected” and actual occupant behaviour
and plug-loads resulted in an additional 11.8% error In retrospect, the students’ detailed modelling
in electricity consumption. Yet an owner faced with strategy resulted in exponentially increasing
a nearly 12% delta between a design-phase energy complexity. Breaking the building into 23 different
simulation and the first year’s utility bills may be activity types resulted in exponentially more
tempted to blame the modeller’s ineptitude. schedules (occupancy, equipment, lighting, and
shading.) In addition, the 100+ model zones made
For buildings like Gund Hall, the analysis
inputs tedious and debugging difficult. Breaking the
methodology used in this project may be beneficial
schedules into short (two-hour) intervals made
but may not be feasible in projects outside of
adding calendar divisions time consuming, since they
academia with limited budgets. Therefore, the
were calculated as a percentage of the original
following discussion aims to pinpoint the most
occupancy. The added difficulty of trouble-shooting
effective analysis tasks employed on Gund Hall.
the model may outweigh the additional accuracy
First, the lighting was easy to document and
acquired through this level of detail. Therefore, the
decreased the error in electricity consumption by 6%
students would reduce the complexity of the model
of annual load, so a lighting analysis, both installed
next time with fewer zones, fewer schedules, and
density and operation schedule, seems advisable on
fewer time steps in the schedules.
every project. Inputting HVAC schedules is
similarly advisable (Waltz, 2000). The custom Energy Simulations for Architecture Students
HVAC schedules were easily obtained from the Following the experience of a semester long-course
facilities manager, and they significantly influenced on building energy simulation, four individual
the heating & cooling loads. modelling exercises and the group project of
Next, the detailed plug-load analysis was more modelling Gund Hall, the students were asked how
challenging. The three watt meters were a good comfortable they now felt with their modelling skills
investment, since they were a quick and easy way to and whether they would use the software again. As
gather accurate information. Given that smart watt novice energy modellers and non-engineers, they
meters that monitor energy use over an extended seemed to be reasonably satisfied with the simulation
period are becoming increasingly more affordable, results from the course project and there was a
using a higher number including watt meters for general expectation that with minor tweaking of the
larger equipment seems advisable. settings, the simulation results could be brought into
even better alignment with the measured data. Most
Finally, the detailed occupancy analysis was the most
students found that the exercise of modelling Gund
challenging piece and probably the one with the
Hall helped them understand the software better but models showing that there certainly remains a need
at the same time they felt that outside of academia, for modelling specialists, especially at the later
this type of benchmarking project would be better design stages.
left to simulation experts. A key lesson learned was that collecting one’s own
The students felt more comfortable using the weather data has become an affordable and easy-to-
software for smaller projects, where there is less implement option for design teams that leads to
room for modelling mistakes, and earlier in the reliable data sets. At the same time, it became
design process, when more basic decisions regarding apparent that this effort is only justifiable if no
programming and massing can be made based on the nearby climate file is available. Given the availability
software. The students also believed that using the of reliable low-cost weather station sets it actually
software to compare design decisions was a useful seems more effective for a design team to collect a
and interesting method for augmenting their building new climate file ‘from scratch’ than to assemble a
science curriculum. file from multiple local sources.
DesignBuilder/EnergyPlus was chosen for this course This experiment also attempted to quantify the
because, in comparison to most other building benefit of various building analysis tasks and custom
simulation software, DesignBuilder is a state-of-the- modelling inputs. The results are limited to one
art GUI. However, it still did not meet the building; therefore, the numbers cannot be readily
expectations of architecture students accustomed to extracted to another project, but rather offer insight
using sophisticated CAD and 3D modelling tools. In into the magnitude of the differences one might
particular, in DesignBuilder, the ability to select and expect between a non-standard building and the
organize model objects seemed limiting, and the illusive “typical building.” Collecting reliable
system of templates and attribute inheritance seemed internal load schedules is a very useful exercise for
both inflexible and unintuitive compared to other retrofitting projects. For new design projects, these
software for architects. Conversely, the students simulation assumptions should be carefully reviewed
needed to learn to abstract their models better. The with the building owner. Summing up, the students
students approached the geometries, schedules, and viewed the seminar and the course project as the
construction types with a minute level of detail much beginning rather than the culmination of their
more appropriate for an architectural model than a education in building systems and energy simulation.
building simulation. Nevertheless, in a survey, 10
out of 11 students said they would definitely ACKNOWLEDGEMENTS
recommend using DesignBuilder/EnergyPlus for The authors would like to thank the following
comparing architectural design decisions. 7 students and the teaching assistant for research
seminar GSD-6417 for all of their help with and
CONCLUSION dedication to this project: Diego Ibarra (TA), James
The paper documents the results from modelling a Kallaos, Anthony Kane, Cynthia Kwan, David
large educational building by simulation novices Lewis, Elli Lobach, Jeff Laboskey, Sydney Mainster,
using a state-of-the art graphical user interface. Rohit Manudhane, Natalie Pohlman, and Jennifer
Overall, it was found that over the course of a Sze. We further express our gratitude to the Harvard
semester design students are capable of learning how Graduate School of Design as well as the Real Estate
to set up a model of a larger complex building. As Academic Initiative at Harvard University for
suggest by others, students not only learned about supporting this effort.
energy simulation, but also learned about building
physics in the process (Schmid, 2008 and Batty & REFERENCES
Swann, 1997). Collecting their own weather data and Augenbroe, G. 2002. Trends in Building
carefully surveying the internal loads of a building Simulation, Georgia Institute of Technology,
helped the students to develop sensitivity for the College of Architecture, Atlanta, Georgia USA.
effect of these model inputs on simulation results.
Autodesk. last accessed in February 2009. Ecotect
Based on the students comments the authors believe
2009. http://ecotect.com/products/ecotect
that current state-of-the-art GUIs such as
DesignBuilder allow architectural students to build Batty, W. J., Swann, B. 1997. Integration of
meaningful energy models that can be used for initial Computer Based Modelling and an Inter-
design explorations. Learning how to set up an Disciplinary Based Approach to Building Design
energy model might further help architects to engage in Post-Graduate Education, Department of
in a more informed dialogue with their consultants. Applied Energy, Cranfield University,
At the same time, the students expressed their Bedfordshire, England.
discomfort with working on too complex building DesignBuilder version 1.9.0.003BETA. Last
accessed February 2009.
7 www.designbuildersoftware.com
The dissenting student believed the modelling and data
input process was too arduous to use realistically during the Energy Information Administration, Office of Energy
quickly evolving early design process. Markets and End Use. 2003. Commercial
Buildings Energy Consumption Survey US Department of Energy (US-DOE). last accessed
(CBECS) – Forms EIA-871A,C,&E, February 2009. EnergyPlus Climate File
Washington, D.C. USA. Database.
Google. last accessed in February 2009. SketchUp http://apps1.eere.energy.gov/buildings/energyplu
Pro 7. http://sketchup.google.com/ s/cfm/weather_data.cfm
National Renewable Energy Laboratory (NREL) for U.S. Green Building Council (USGBC). last accesed
the U.S. Department of Energy. last accessed in in February 2009. LEED Rating Systems.
February 2009. OpenStudio Version 1.0.2 Build www.usgbc.org/leed/
37. United States Environmental Protection Agency.
http://apps1.eere.energy.gov/buildings/energyplu 2007. Putting Energy into Profits: Energy Star
s/openstudio.cfm Guide for Restaurants, 3, Washington, D.C.
Schmid A.L. 2008. The Introduction of Building USA.
Simulation into an Architectural Faculty: Voit, P., White, D., & Bummele, A. 2007. Gund Hall
Preliminary Findings, Departamento de – Analysis of Envelope and Thermal Comfort,
Arquitetura e Urbanismo, Universidade Federal Transsolar Inc., New York, New York USA.
do Parana, Curitiba Brazil. Waite, M. 2008. personal communication. Simpson
US Department of Energy (US-DOE). Last accessed Gumpertz & Heger, New York, New York USA.
February 2009. EnergyPlus Version 2.2.0.025. Waltz J.P. 2000. Computerized Building Energy
DLL default version embedded in Simulation Handbook, Fairmont Press, Lilburn,
DesignBuilder, Georgia USA
http://apps1.eere.energy.gov/buildings/energyplu
s/