05-Design-Deliverables
05-Design-Deliverables
SCHEMATIC PHASE DESIGN DEV. PHASE CONST. DOC. PHASE CONST. DOC. PHASE
(SEE NOTE 1) (SEE NOTE 2 & 3 FOR 90% &
100% REQUIREMENTS)
GENERAL DESCRIPTION
1. Building Code Review & Describe means of 1. Documentation on drawings as 1. Documentation on drawings as
1. Scope of Work Narrative
code compliance required by building codes required by building codes
2. Preliminary drawings to include outline
2. List of applicable building codes on specifications, fire protection/life safety plan, site 2. Contract Documents (see note 5, 2. Final Contract Documents (see note
drawing title sheet plan, floor plan(s), elevations, typical wall section(s), sheet 16) 5, sheet 16)
and building section(s) (see note 5, sheet 16)
3. Review and Update Project
3. Equipment Lists 3. Updated Project Schedule 3. Updated Project Schedule
Program document
4. Schematic Drawings to include Site
Plan, Floor Plan(s), and Exterior
4. Engineering Systems Analysis 4. Estimate of Cost 4. Estimate of Cost
Elevation(s) as a minimum (see Note 5,
Sheet 16)
5. Identification of construction phasing 5. Updated construction phasing plan,
5. Preliminary Energy Use & Conservation
5. Engineering Systems Description plan, including temporary requirements including temporary requirements during
Analysis
during each phase each phase
6. Energy Use & Conservation
6. Track & Estimate changes in scope of work 6. Minutes of Meetings 6. Minutes of Meetings
Analysis
7. Annotated comments of services “B”
7. Project Schedule 7. Updated Project Schedule 7. Annotated comments of 60% review
review
8. Review Drawings to Governing 8. Annotated comments of 90% review
8. Estimate of Cost 8. Estimate of Cost
Agencies, as required. for 100% submittal
9. Submit complete set of drawings
(electronically via SharePoint web link) to 9. Annotated comments of 100% review
9. Minutes of Meetings 9. Minutes of Meetings
the City of Tuscaloosa Fire & Rescue with bid document submittal
Service. Reference Note #9 for procedure.
10. Review drawings to governing 10. Review Drawings to Governing
10. Annotated comments of services “A” review
agencies, as required Agencies, as required.
11. Submit pdf drawings (electronically)
11. Review drawings to governing agencies, as to the Tuscaloosa Water & Sewer Dept –
required Linear Assets Division, reference Note #9
for procedure.
12. Submit Final complete set of drawings
(electronically via SharePoint web link) to
the City of Tuscaloosa Fire & Rescue
Service. Reference Note #9 for procedure.
SPECIFICATIONS
1. System & material narrative 1. Outline specification with same section 1. Complete specification including draft 1. Final specification including front end
description numbering as final front end documents documents (see note 6, sheet 16)
Note: Site survey and soil tests
Note: All construction testing will be provided by Note: All construction testing will be Note: All construction testing will be
indicating all existing conditions will be
Owner provided by Owner provided by Owner
provided by Owner
SERVICES (A) 10% SERVICES (B) 30% SERVICES (C) 60% SERVICES (C) 90%
SCHEMATIC PHASE DESIGN DEV. PHASE CONST. DOC. PHASE CONST. DOC. PHASE
(SEE NOTE 1) (SEE NOTE 2 & 3 FOR 90% &
100% REQUIREMENTS)
SITE
1. Existing conditions 1. General dimensions & elevations 1. Extent of construction area and work 1. Extent of construction area and work
2. Demolition identified 2. Site demolition plan 2. Site demolition plan 2. Site demolition plan
3. Traffic plan if existing roads/walks are 3. Traffic plan if existing roads/walks are
3. Building outline(s) 3. Parking plan & elevations
impacted impacted
4. Site entrance 4. Site drainage 4. Site development and phasing plans 4. Site development and phasing plans
5. Roads & driveways 5. Lighting plan 5. Construction site access 5. Construction site access
6. Parking locations 6. Concept details of fixtures & equipment 6. Staging area 6. Staging area
7. Soil erosion control plan for both 7. Soil erosion control plan for both
7. Loading dock location 7. Utility plans, elevations & details
construction and occupancy periods construction and occupancy periods
8. Plan to address existing hazardous materials, if
8. Waste collection locations 8. Construction signage 8. Construction signage
applicable
9. Walkway locations 9. Dewatering plan 9. Pipe sizes 9. Pipe sizes
10. Stairway locations 10. Site demolition plans 10. Connection details 10. Connection details
11. Protection requirements for 11. Protection requirements for
11. Future expansion 11. Soil retention work, if needed
construction, plantings that remain construction, plantings that remain
12. Utility requirements
13. Site utilities
14. Clearly show “Build-to” line (Refer
to UA Campus Design Guide portion of
UA Campus Master Plan)
LANDSCAPING
1. Existing conditions 1. Planting plan 1. Existing tree protection 1. Existing tree protection
2. Soil preparation & planting 2. Soil preparation & planting
2. Irrigation plan
specifications specifications
3. Planting legend 3. Guying diagrams 3. Guying diagrams
4. Irrigation legend 4. Piping diagrams 4. Piping diagrams
5. Pipe sizes 5. Pipe sizes
6. Landscape details 6. Landscape details
SERVICES (A) 10% SERVICES (B) 30% SERVICES (C) 60% SERVICES (C) 90%
SCHEMATIC PHASE DESIGN DEV. PHASE CONST. DOC. PHASE CONST. DOC. PHASE
(SEE NOTE 1) (SEE NOTE 2 & 3 FOR 90% &
100% REQUIREMENTS)
STRUCTURAL
1. Structural scheme 1. Foundation plan 1. Definition of control joints 1. Definition of control joints
2. Written description 2. Typical floor framing plan 2. Beam, column, & slab schedules 2. Beam, column, & slab schedules
3. Mechanical & electrical concrete 3. Mechanical & electrical concrete
3. Framing plan(s) at unique features
pads pads
4. Main member sizing 4. Foundation details 4. Foundation details
5. Structural sections 5. Structural details 5. Structural details
6. Structural notes 6. Structural notes
7. Final calculations, if requested