Misa 2
Misa 2
SOP OF OPERATION
SOP for Bus/ Transmission line / ICT/Reactor/Bay Shutdown
Name of Substation : 220/132kV Dimapur Substation Region : NER
S Particular Details
2. Type of Shutdown
(Tick please) OCC D-3 Basis Emergency Post OCC
(Tick please)
CHECKED PPE (Steel rope, Clamps,
PP Rope, helmets, safety belts etc.)
8. Sequence of
Isolation (CB &
Isolator) By 1. 20452 Open/ ⃝ Close
RTAMC (Tick
please) 2 20489L Open/ ⃝ Close
appropriate
time of gap
between two
operations to
be ensured.
12. Names of
additional/external 1. D. Nakhro, JE
POWERGRID engineer’s
supervision to be
mentioned.
Yes No
Signature of CGM(AM)
B. DETAIL WORK PROCEDURE
2. LA IR TESTING
Testing Procedure
C. TESTING EQUIPMENT
.
D. RESOURCE PLANNING
Availabilty of
Activity Activity Work Team Lead Safety Heavy
No Description Incharge Working Team Detail T&P Gear Consumable Vechicles
GD Tripping Cable
Removal after CB 1. D. Nakhro
Himanshu
1. Abhishek (JE)
Compartment Agarwal (Ch.
Kumar
towards ICT side Manager)
(Engr.) 2. Anupal Millik
(Fitter) Availabl Not
1 e Available Available Applicable
1. D. Nakhro
1. Abhishek (JE)
Himanshu
Testing of LA Kumar
Agarwal (Ch.
(Engr.) 2. Anupal Millik
Manager)
(Fitter) Availabl Not
2 e Available Available Applicable
1 Working in Wrong Bay/ICT/Panel Barrication will be done for the working area
2 Falling of Working Personnel from Height Helmet, Fall Arrestor and Harness Belt will b
3 Falling of T&P from Height Proper Tying will be doe using Nylon Rope