CHAPTER 5
CHAPTER 5
5.1Introduction
In medium span Pre-engineered Industrial building span range is kept between20m-30m. The
available profiles of slope for medium span industrial building are1:3, 1:6, 1:10 & 1:12.
10.54 m
6m
20 m
6m
20 m
Fig.5.2 (a)Elevation
6.67 m
6.67 m
6.67 m
6.67 m
60 m
6.67 m
6.67 m
6.67 m
6.67 m
6.67 m
Wind Load
According to Clause 5.3 of IS: 875(Part3)
Vz = Vb K1 K2 K3
I. 1) Roof
Referring to Table 6 of IS: 875(Part3)
Here h = 6m; w= 20m
Roof Angle18.43o
60 m
20 m
Building Plan
TGPCET/CIVIL/2019-20 60
0.53N 0.40N
I. Walls
Referring to Table 4 of IS: 875(Part3)
h/w=6/20=0.3<1/2
l/w=60/20=3.0<4
TGPCET/CIVIL/2019-20 61
0.70N 0.25N
0.60N
0.70
N
0.5 N 0.5N
0.10N
Wind Load
Maximum Wind Load per metre on each Purlin= (0.7+0.2) x1.01x1.5
= 1.39 kN/m (↑)
Since the Slope is very small, all the forces are assumed to act vertically w.r.t. Purlin section
Load Combination1- Dead Load + Imposed Load
Total Load per meter on Each Purlin = 0.16+ 0.87 =1.03 kN/m (↓)
Load Combination2- Dead Load + Wind Load
Total Load per meter on Each Purlin = 0.16 – 1.39=1.23 kN/m (↑)
[https://archinect.com/forum/thread/149971695/primary-vs-secondary-structure]
Fig.5.8
Property of the Z-section selected is as shown below:
TABLE 5.1
Area Thickness Weight/ Ixx Iyy Zxx Zyy
metre
8.37sq.cm 2.55mm 6.57Kg/m 439cm4 58.8cm4 46.21cm3 10.01cm3
4.8t=4.8x2.55=12.24mm<18.3mm (O.K)
Calculation of effective design width of compressive element as per clauseno.5.2.2.1 of IS: 801-
1975
¿ ( wt )
lim ¿=
1435
√f
=41.4 ¿
Where f = 0.75 x 1600 = 1200 kg/cm2
2
L S xc
; Where L = Unbraced Length of the member = 2.23m (considering sag rods at spacing
d I yc
2.23m)
Iyc = Moment of inertia of the compression portion of a section about the gravity axis of the
entire section parallel to the web
2
L S xc 2232 x 46.21
= =4113.81
d I yc 19 x 29.4
2
0.18 π E C b
=1030
fy
2
0.9 π E C b
=5150
fy
Where E= 2 x 106 kg/cm2
fy = 3450 kg/cm2
( )
2 2
2 fy L x S xc
Hence F b= f y −
3 2.7 π E C b d x I yc
2
2
2 3450 2
F b= x 3450− 2 2
x 4113.81=1381.26 kg/cm
3 2.7 π x 2. x 10 x 1
2
F b=138.12 N /mm
Referring to Clause no. 6.1 of IS: 801-1975
F (Basic design stress) = 0.6Fy = 0.6x3450 =2070kg/cm2
F = 207 N/mm2
Hence, F b=138.12 N /mm2 is the governing value
Since here Wind load condition is critical,
Fb perm = 1.33 x 1238.12 = 183.7Mpa
6
M 4.25 x 10
Fb = =
Z xx 46.21 x 103
act
Fv = 67.51N/mm2
Actual Shear stress for Dead Load + Wind Load = 1.93 kN/m
3
1.23 x 10 x 6.67 2
Actual Shear stress= =17.98 N /mm
178.9 x 2.55
= 17.98Mpa< 67.51 x1.33
= 17.98Mpa< 89.78 Mpa
36560000 36560000
F bw = =
()
2
h ( 70.15 )2
t
Fbw= 7429.3 kg/cm2
Fbw= 742.93 N/mm2
√(f bw
2 2
/F bw ) + ( f v /F v ) ≤1.0
W1 = 1.39 kN/m
W2 = 0.16 kN/m.
( w2 cos 18.43 ) x l2
M yy = =0.2225 kNm
10
TGPCET/CIVIL/2019-20 67
M xx M yy
Maxm fibrestress= + =141.49 Mpa <0.66 f y (ok )
Z xx Z yy
a) Dead Load
Unit weight per meter run of Sheeting @ 0.06 kN/m2 = 0.06 x 1.5 = 0.09 kN/m
Unit weight per meter run for self-weight of Side Girt = 0.07 kN/m
Total Dead Load per meter on each Girt = 0.16 kN/m
b) Wind Load
Maximum Suction Wind Load per meter = (0.5+0.2) x 1.01x1.5=1.06kN/m.
Maximum Pressure Wind Load per meter = (0.7+0.2) x1.01x1.5=1.37kN/m.
Considering the Side Girt as Continuous members with overlap of 285mm on either side for
splicing purpose
2
0.16 x 6.67
M y= Due to Dead Load only
10
My = 0.72kN m
M x= ( 1.37
1.23
x 4.4 ) Due ¿ MaximumWind Load only
Mx = 4.9kN m
Sag rods needs to be placed at 1/3 of Span i.e. 2.23m.
Checking the adequacy of Girt section as per BS: 5950- Part 5
The Section as used for girt is. Lipped “Z” Section (20mmx60mmx180mmx2.0mm thick) @
5.07kg/m
Property of the Z-section selected is as shown below:
TABLE 5.2
Area Thickness Weight/metre Ixx Iyy Zxx Zyy
6.46 2.0 5.07 311 48.5 34.6 8.2
sq.cm mm Kg/m cm4 cm4 cm3 cm3
TGPCET/CIVIL/2019-20 68
60.000
20.000
180.000
180.000
2.000
2.000
Fig.5.9
1) Overall Depth < 100 t
190mm< 100x2.55
190< 255 (O.K)
2) Overall Depth > L/45
190mm > 138.89mm (O.K)
3) Total width of both flanges > L/60
= 60x2 > 6250 /60
=120 > 104.17(O.K)
4) Overall Width of Compression Flange/ Thickness i.e. B/t £ 35
= 60 / 2.55 = 23.52 < 35 (O.K)
5) Width of Lip > B/5
20 > 60 /5
20 > 12 (O.K)
6) Unity check as per BS: 5950 Part-5
Checking for Design expression for “Z” sheeting rails as per Table 13 of BS: 5950 Part-5
Consider Span as Continuous & two rows of Vertical supports at 1/3 of Span.
WwL WdL
+ ≤1.0
2250 Z x 16880 Z y
Where,
Ww = 1.37x6.67 = 9.14kN Wind Load on Girt causing Tension on inside face.
Wd= 0.16x6.67 = 1.067 or 2 kN whichever is greater.
9.14 x 6670 2.6670
+ =0.78+ 0.09=0.87 ≤ 1.0 Hence Safe
2250 x 34.6 16880 x 8.22
TGPCET/CIVIL/2019-20 69
4000 4000
0
6000
4000
20000
X X
180.000
4.000
80.000
C c=
√ 2 π2 E
Fy
=
√
2 π 2 x 2 x 10 6
3450
=107
( wt )
lim ¿=
1435 1435
√f
=
√20
¿
( wt )
lim ¿=321∨w=321 x 4=1284¿
Q=1.0
Where Q = Effective Design Area / Full or Gross Area.
Steel thickness used is 4mm> 2.29mm.
TGPCET/CIVIL/2019-20 71
KL
=82.95< Cc =107
r
KL
As <C caccording to Clause no. 6.6.1.1. (b) of IS: 801-1975.
rx
( ) ( )
2
KL
r
1− 2
Fy
2 (C c )
Fa =
( ) ( )
3
1
KL KL
5 3 r r
+ x − 3
3 8 Cc 8 (C c)
Fa =
( 1−
( 104.12 )2
2 ( 107 ) )
2
x 3450
3
=947.78
kg
2
=94.78 N /mm
2
5 3 ( 104.12 ) ( 104.12 ) cm
1
+ x − 3
3 8 107 8 ( 107 )
Permissible Axial Compressive under Wind Load = 94.78x1.33 =126.05Mpa.
4060
Actual Axial Compressive Stress= 2
=1.42 Mpa
28.4 x 10
( wt ) lim ¿=
1435 1435
=
√ f √1500
=37¿
Where f = 0.75 x 2000 = 1500 kg/cm2
Unity Check
Referring to Clause no. 6.7.2 Of IS: 801-1975,
fa 1.42
= =0.0112< 0.15
F a 126.05
1
f b 156.138
= =0.56
Fb 275.31
1
fa fb
+ < 1.0
Fa Fb 1 1
fa fb
+ =0.57<1.0 Hence Safe
Fa Fb 1 1
50.000
3.1500
180.000
Fig.5.12
The property of the Lipped C section is as listed below:
TABLE5.4
Area in cm2 11.1
Weight (kg/m) 7.24
Ixx 413cm4
Iyy 28.3cm4
Zxx 45.9cm3
Zyy 7.82cm3
rxx 6.69cm
ryy 1.75cm
Cyy 1.38 cm
Xo 3.66 cm
J 0.38cm4
Cw 1840cm6
[ ] [ ]
2 2 6
1 π EC w 1 π x 2 x 10 x 1840 kg
σ t= 2
GJ+ 2
= 2
795000 x 0.38+ 2
=1521 2
A ro ( KL ) 11.1 x 7.82 ( 223 ) cm
TGPCET/CIVIL/2019-20 74
2
¿ 193.63 N /mm
( ) ( )
2 2
xo 3.66
β=1− =1− =0.78
ro 7.82
1
σ TFO= [
2 β ex t √ 2
( σ +σ )− ( σ ex +σ t ) −4 β σ ex σ t ]
1
σ TFO=
2 x 0.78
[ ( 17766+1521 )− √( 17766+1521 )2−4 x 0.78 x 17766 x 1521 ]=1491 kg /cm2
2
σ TFO=149.1 N /mm
kg kg
σ TFO=1491 2
<0.5 cf y =0.5 x 3450=1725 2
cm cm
F a =0.522 σ TFO
2
F a =0.522 x 1491=778.3
2
kg
F a =1.33 x 778.3=1035.14 2
cm
2
( wt ) lim ¿=
1435 1435
=
√ f √750
=52.4 ¿
( )
2 2
2 fy L x S xc
F b= f y −
3 2.7 π 2 E C b d x I yc
TGPCET/CIVIL/2019-20 75
2
2 3450 2
F b= x 3450− 2 6
x 8968=1300 kg /cm
3 5.4 π x 2. x 10 x 1
F bperm =130 x 1.33=172.9 Mpa
Considering Eave beam as simply supported
( 0.7+0.2 ) x 1.01 x 3.33 x 6.67
Wind Load on Eave beam= =10.09 kN
2
10.09 x 6.67
M x= =8.42 kNm
8
6
8.42 x 10
Actual Bending Stress= 3
=183.45 Mpa
45.9 x 10
Total Compressive Stress = 183.45+52.35= 235.8Mpa< 0.6 x 345 x 1.33 (O.K)
Total Compressive Stress=235.8Mpa< 275.31 Mpa; Hence Safe
5.8 Bracings design
θ=tan−1 ( 6.25
6.25 )
=45 o
58.1 58.1
Force∈Vertical Bracing member= = =125 kN
cos θ cos 45
Using “X” Bracings at both ends Fy = 250 Mpa
3
58.1 x 10 2
Areareqd = =145.64 mm
2 x 0.6 x 250 x 1.33
Using 24 mm Diameter Rod,
2
0.8 xπx 24 2 2
Area provided = =362 mm >145.64 mm Hence Ok
4
TGPCET/CIVIL/2019-20 76
b) Service Load:
Service Load on the Rafter is considered as 0.1 kN/m2
Hence, Loads on rafter as U.D.L = 0.1 x 6.67 = 0.667kN/m(↓)
c) Imposed Load:
As θ<10oLive Load = 0.58kN/m2
Hence, Loads on rafter as U.D.L = 0.58 x 6.67 = 3.87kN/m(↓)
d) Wind Load:
0.2N
0.33N
0.9N
0.05N
0.6N
0.73N
0.45N
0.5N
0.52N 0.52N
0.30N 0.30N
0.92N
0.92N
0.70N 0.70N
114 KN/M
0.85 KN/M
394 KN/M
3) Service Load
0.667 KN/M
3.37 KN/M
3. 03 KN/M
Figure-5.14(d) Wind Load -1
(windward)
Fig 5.14 (d)shows lateral load and vertical point load both acting on it
4.92 KN/M
4.04 KN/M
6) Wind Load-2(Windward)
6.06 KN/M
0.34 KN/M
8) Wind Load-3
TGPCET/CIVIL/2019-20 81
4.72 KN/M
6.19 KN/M
4.72 KN/M
4.72 KN/M
Load Combination
TGPCET/CIVIL/2019-20 82
The STAAD analysis has been carried out considering the following combination of Individual
load cases:
1) D.L + L.L +S.L
2) D.L +W.L1 (windward)
3) D.L + W.L1(leeward)
4) D.L + W.L2(windward)
5) D.L + W.L2(leeward)
6) D.L+W.L3
7) D.L+W.L4
2.99
4.50 Member 5
3.00 Member 4
Member 6
Member 3
5 Member 7
Member 2 4 6
3 8
7
2
Member 1
6.000 Member 8
1 9
The Maximum Designed Axial force, Shear force and Bending moment for the Four members is
as shown below:
TABLE 5.5
TGPCET/CIVIL/2019-20 83
Member no. Axial force (kN) Shear force (kN) Moment (kNm)
1 69.8 (C) 30.6 158.3
2 44.7(C) 50.5 158.3
3 44.6 (T) 32 47.2
4 45 (T) 15 48.5
5 45 (T) 15 48.5
6 44.6 (T) 32 47.2
7 44.7 (C) 50.5 158.3
8 69.8 (C) 30.6 158.3
The Depth of flange, web thickness and flange width are kept constant throughout the
Pre-engineered Lean to portal frame
TABLE 5.6
Member Depth of Depth of Width of Thickness of Thickness of
no. Section at Section flange flange web
Start Node at End Node
1 200 mm 450 mm 200 mm 10 mm 6 mm
2 450 mm 250 mm 200 mm 10 mm 6 mm
3 250 mm 250 mm 200 mm 10 mm 6 mm
4 250 mm 300 mm 200 mm 10 mm 6 mm
5 300 mm 250 mm 200 mm 10 mm 6 mm
6 250 mm 250 mm 200 mm 10 mm 6 mm
7 250 mm 450 mm 200 mm 10 mm 6 mm
8 450 mm 250 mm 200 mm 10 mm 6 mm
Maximum permissible Horizontal Deflection due to Wind Load only for the frame =6000/60 to
6000/ 100= 100 mm to 60mm.
As per MBMA Maximum permissible Vertical Deflection due to Live Load only forthe frame =
span/240 = 20000/ 240 = 82.33 mm.
The frame was checked for horizontal Deflection at nodes “2” &”4” for Wind Loadand was
found Safe.
The frame was also checked for Vertical Deflection at node “3” for Live Load andwas found
safe.
TGPCET/CIVIL/2019-20 86
TABLE 5.7
1 Tapered 6m 0.2687
4 Tapered 3m 0.1276
5 Tapered 3m 0.1276
8 Tapered 6m 0.2687
The Final Weight of Lean to frame including Stiffeners, Splice plates will be1.15 times the total
weight of all members. Therefore Final Weight of the” LEAN TOFRAME” will be 1.15x 1.45 =
1.67 Tonnes.
Connections
Detailed Design of different Connections like Main frame base Plate, Gable end Column base
plate, Splice plate connection, Bolt design etc. are not covered to limit the size of the problem.
Bolt used for the Connections is “HTFG” i.e. High tension friction grip bolts.
TGPCET/CIVIL/2019-20 87
TABLE 5.8
Sr.
Items Section/Size Material
No.
Combined Lipped
6 End wall Column Combined 345 Mpa
C20x80x180x4
14 Foundation Bolt Mainframe 4 no.'s M16 dia 500mm long 250 Mpa
6.67 7.50
8.57
6.67
7.50
8.57
6.67
7.50
6.67 8.57
7.50
6.67
8.57
7.50
6.67
8.57
7.50
6.67
7.50 8.57
6.67
20.00
20.00 20.00
All three cases are solved by changing the slope of the frames. Slopes considered are 1:3, 1:6,
1:10 and 1:12.The total cases solved are twelve by changing the parameters viz. slope and frame
spacing.
TGPCET/CIVIL/2019-20 89
TABLE 5.9
Foundation Bolt
15 2 no.'s M16 dia450mm long 250 Mpa
End wall Column
TGPCET/CIVIL/2019-20 90
TABLE 4.10
Foundation Bolt
15 2 no.'s M16 dia 500mm long 250 Mpa
End wall Column
TGPCET/CIVIL/2019-20 91
TABLE 5.11
Combined Lipped
6 End wall Column 345 Mpa
C25x80x180x4
Foundation Bolt
15 2 no.'s M18dia600mm long 250 Mpa
End wall Column
TGPCET/CIVIL/2019-20 92
7.730
5.000
Elevation
15m
6.25 m
6.25 m
6.25 m
6.25 m
50 m
6.25 m
6.25 m
6.25 m
6.25 m
Plan
Figure-5.17Plan and Elevation of Conventional Industrial Building