MS Quarters
MS Quarters
SUB DATA
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and
conveyance of all materials to site and all labour charges for mixing,
laying and curing etc complete for bed blocks for 10 cum
Supplying and erecting centering shuttering including necessary supports for plane
surface in foundation and basement and in all floors for R C C column footing
column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc
using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild
steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country
wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and
supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre
complete complying with standard specifications and as directed by departmental
officers including conveyance of all materials to site and proper centering etc complete.
Sub Data I
Cost of MS sheets & angles for each set
Weight of MS sheet B.G 10 Gauge size 90x60cm x 3.175 mm
3.175 x 7850/1000 = 24.924 kg/m2
24.924 Kg/m2 x 0.54 m2 = 13.46 Kg.
Weight of MS angle size 25 x 25 x 3 mm
3.6 x 1.1 Kg/m = 4.00 Kg
13.46 kgs Cost of MS sheet 43.50 /kg 585.51
4 kgs Cost of MS angle 43.50 /kg 174.00
17.46 kgs Cutting,bending,welding,etc 30.30 /kg 529.04
1288.55
Sub Data 2
Cost of MS sheets and angles and CW joists and casurina props - 10 Sqm
Rate per one operation for MS sheet & angle 24482.45 /40 612.06
Rate per one operation for strutting 4751.08 /5 950.22
Colour washing two coats using approved colour pigments including cost
and conveyance of all materials to site and all labour charges etc complete
28.20
RATE @Rs 28.20 /Sqm
Priming coat for new iron with ready mixed primer of approved quality 10Sqm
1.33 kg Red Oxide 148.40 kg 197.37
0.70 No Painter-I class 436.00 /each 305.20
sundries including brushes, soaps.putty etc 0.00
502.57
RATE @RS 50.26 /Sqm
Painting two coats over new iron works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
80.20
RATE @Rs 80.20 /Kg
Highways Department
Schedule of Rates for the year 2017-2018
Rates in
S.No. Description Unit
Rupees
FUEL RATES
Bituminous work Labour Diesel (Local Rate) Litre 56.07
1 Bitumen sprayer Man Day 447.00 Furnace Oil Litre 32.01
2 Bitumen raker Man Day 466.00 Kerosene Litre 50.45
3 Heat master operator Day 466.00
4 Mini Hot Mix plant Operator Day 466.00 BITUMEN
5 Gunnuting plant Operator Day 390.00 Bitumen packed MT ###
6 Gunnuting gun Operator Day 424.00 Emulsion MT ###
7 Road Mazdoor Grade I Day 385.00
8 Road Mazdoor Grade II Day 345.00
9 Road Mazdoor Grade III Day 345.00
10 Head Mazdoor Day 397.00
11 Mazdoor (Skilled) 0.00
12 Mazdoor (Unskilled) 0.00
3 Mini Hot Mix Plant Day 1674.00 Mixall 6/10 t capacity 1526.05
Bitumen boiler oil fired1000
Bitumen Boiler with fuel Day litre capacity fitted with spray
4 set 160.00
6 Bitumen Boiler without fuel Day 202.00 Bitumen Sprayer per day 107.00
Coimbatore
Sl.No. Description Unit
Circle
VI Other Materials
1 Cement Mt 5260.00
2 Sand one cum 176.40
3 Sand for filling one cum 176.40
4 Rough stone one cum 413.00 358.00 For Revetment works
RATES FOR CONVEYANCE OF MATERIAL BY ROAD IN PLAINS FOR THE YEAR 2017-18.
2 Incidental charges
6 An Adhoc extra for 17.60 19.35 28.15 23.70 31.60 39.60 0.00
RATES FOR CONVEYANCE OF MATERIAL BY ROAD IN HILLS FOR THE YEAR 2017-18.
Broken Mangalo
Br. Jelly, Country
Stone re Tiles
Wood Bricks Chamber
Sl.No. Distance in Kilometre Sand (1000No Bitumen
work (1000 bricks
Gravel s,)
(one m3) Nos,)
(one m3)
1 2 3 4 5 6 7 8
1 Co- efficient 1.10 1.60 1.35 1.80 2.25 0.00
2 Incidental charges
Starting Ending
Scheme :
Year :
KM 0.000 1.400
Working Metal
From To Bitumen Gravel Sand
milage 63-22.4 13.2-6.7
0.00 13.80 13.80 1.40 5.20 76.20
or or or or
KM 0.00 - 0.00 Hills 0.00 0.00 0.00 0.00 0.00
Plain 0.00 0.00 0.00 0.00 0.00
Total 0.00 0.00 0.00 0.00 0.00
0.00 13.80 13.80 1.40 5.20 76.20
or or or or
KM 0.00 - 0.00 Hills 0.00 0.00 0.00 0.00 0.00
Plain 0.00 0.00 0.00 0.00 0.00
Total 0.00 0.00 0.00 0.00 0.00
0.00 13.80 13.80 1.40 5.20 76.20
or or or or
KM 0.00 - 0.00 Hills 0.00 0.00 0.00 0.00 0.00
Plain 0.00 0.00 0.00 0.00 0.00
Total 0.00 0.00 0.00 0.00 0.00
0.00 13.80 13.80 1.40 5.20 76.20
or or or or
KM 0.00 - 0.00 Hills 0.00 0.00 0.00 0.00 0.00
Plain 0.00 0.00 0.00 0.00 0.00
Total 0.00 0.00 0.00 0.00 0.00
0.20 13.60 13.60 1.20 5.00 76.00
or or or or
KM 1.00 - 1.40 Hills 0.00 0.00 0.00 0.00 0.00
Plain 14.00 14.00 1.00 5.00 76.00
Total 14.00 14.00 1.00 5.00 76.00
0.50 12.90 12.90 0.50 4.30 75.30
or or or or or
KM 0.00 - 1.00 Hills 0.00 0.00 0.00 0.00 0.00
Plain 13.00 13.00 1.00 4.00 75.00
Total 13.00 13.00 1.00 4.00 75.00
Metal Metal
Name of work Strengthening the road from
Name of Quarry
Bitumen : At P.U.Store,Chennimalai
Emulsion : At P.U.Store,Chennimalai
Sand : Karur
I BASIC COST OF 75MM TO 22.40 MM METAL ( WBM Grade II ) BASIC COST OF 63 MM TO 11.20 MM METAL ( WBM Grade III )
1 0.050 M3 75 mm IRC Metal 451.00 22.55 0.025 M3 63 mm IRC Metal 584.00 14.60
2 0.450 M 3
63 mm IRC Metal 584.00 262.80 0.200 M 3
53 mm IRC Metal 710.00 142.00
3 0.425 M3 53 mm IRC Metal 710.00 301.75 0.725 M3 45 mm IRC Metal 953.00 690.93
4 0.050 M3 45 mm IRC Metal 953.00 47.65 0.025 M3 22.40 mm IRC Metal 1334.00 33.35
5 0.025 M 3
22.40 mm IRC Metal 1334.00 33.35 0.025 M 3
11.20 mm IRC Metal 840.00 21.00
Total 668.10 Total 901.88
unE may,
KM 0.00 - 1.00 vao day coi
Nature of co con nho
REACH
Convey 20%
route for nay ngon Convey Stacking
Name of quarry Kind of metal Distance in KM
lam ance (Plain)
ance
Charges
Extra Total
conveyance (Hills) (Labour)
metalled or http://thucai
Plains Hills unmetalled thoi.xlphp.n
et
WBM Gr II metal 13 0 668.10 118.05 0.00 3.15 0.00 789.30
Km 22/2 of Erode Chennimalai road
--do-- WBM Gr III metal 13 0 901.88 118.05 0.00 3.15 0.00 1023.08
--do-- 45mm IRC metal 13 0 953.00 118.05 0.00 3.15 0.00 1074.20
1.00
--do-- 13.2mm IRC metal 13 0 1237.00 118.05 0.00 3.15 0.00 1358.20
--do-- 11.2mm IRC metal 13 0 840.00 118.05 0.00 3.15 0.00 961.20
--do-- 6.7mm IRC metal 13 0 623.00 118.05 0.00 3.15 0.00 744.20
-
Karur Sand for filling 75 0 176.40 539.95 0.00 3.05 0.00 719.40
0.00
--do-- WBM Gr III metal 14 0 901.88 126.10 0.00 3.15 0.00 1031.13
--do-- 45mm IRC metal 14 0 953.00 126.10 0.00 3.15 0.00 1082.25
1.40
--do-- 13.2mm IRC metal 14 0 1237.00 126.10 0.00 3.15 0.00 1366.25
--do-- 11.2mm IRC metal 14 0 840.00 126.10 0.00 3.15 0.00 969.25
--do-- 6.7mm IRC metal 14 0 623.00 126.10 0.00 3.15 0.00 752.25
-
Karur Sand for filling 76 0 176.40 546.44 0.00 3.05 0.00 725.89
1.00
--do-- WBM Gr III metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 45mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- 13.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 11.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 6.7mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
-
Karur Sand for filling 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- WBM Gr III metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 45mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- 13.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 11.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 6.7mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
-
Karur Sand for filling 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- WBM Gr III metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 45mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- 13.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 11.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 6.7mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
-
Karur Sand for filling 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- WBM Gr III metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 45mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
--do-- 13.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 11.2mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
--do-- 6.7mm IRC metal 0 0 0.00 0.00 0.00 0.00 0.00 0.00
-
Karur Sand for filling 0 0 0.00 0.00 0.00 0.00 0.00 0.00
0.00
Spreading Gravel and consolidation with power roller rolling excluding cost
of Gravel
(i) Hire charges for Machineries
Water sprinkler including fuel charges 1159.00
Fuel charges / day 3.25 litres 56.07 / litre 8 lit 1457.82
2616.82
Daily out turn 1000 cum
Hire charges for per cum 2.62
(ii) Power roller 8-10 ton capacity
Hire charges for per day 828.00
Fuel charges / day 20 litres 56.07 per litre 1121.40
1949.40
Daily out turn 425 cum
Hire charges for per cum 4.59
(iii) Labour charges for spreading 100cum of gravel
Mazdoor class I 2 Nos. 385.00 770.00
Labour charges per Cum 7.70
Total hire charges and Labour charges per Cum (i)+(ii)+(iii) 14.91
Providing WBM Grade II & Grade III 75mm thick Hire charges and labour
charges for WBM Gr.II & III
Hire charges for Machinery
Water srinkler
Hire charges excluding fuel charges/day 1159.00
Fuel charges / day 3.50 litres 56.07 8 1569.96
Total hire charges / day 2728.96
Daily out turn 450 Sq.m of 75mm thick
Hire charges per 10Sq.m 2728.96 /450x10 60.64
Power roller
Hire charges excluding fuel charges/day 828.00
Fuel charges / day 2.5 litres 56.07 / litre 8 1121.40
Total hire charges / day 1949.40
Daily out turn 450 Sq.m of 75mm thick
Hire charges per 10Sq.m 1949.40 /450x10 43.32
Total hire charges for Machinery / 10M2 60.64 + 43.32 103.96
Labour charges (for spreading 10sq.m 75mm thick)
1.08x3/16 Nos Mazdoor I class 385.00 77.96
1.08x1/4 Nos Mazdoor II class 345.00 93.15
1.08x1/3 Nos Mazdoor III class 345.00 124.20
a) Forming edge bunds L.S. 1.50
b) Maintaining berms for traffic barricading, providing danger lig L.S. 1.50
c) Watering and keeping the surface moist for 15days L.S. 1.50
d) Rent for tools including baskets, sherpining, pick axes L.S. 1.50
e) Sundries such as rope, waterpots L.S. 1.50
Labour charges per 10 Sq.m 302.81
Hire charges for Machinery and Labour charges
10 Sq.m of 75mm tk (i)+(ii) 103.96 + 302.81 406.77
(ii) Hire charges for Bitumen Sprayer per 10 sqm L.S. 15.00
Labour charges for laying 1.00 m3 of Bituminous material 154.42 / 0.625 247.07
Total hire charges and Labour charges (i)+(ii) Rate per Sq.m 193.99
Forming embankment with earth work excavation from borrow pits and
compaction by power roller 100 % Compaction
Forming embankment with earth work excavation from borrow pits and
compaction by power roller 97% Compaction
Hire charges and labour charges for earthwork compaction
Hire charges for Machinery
(i) Water srinkler
Hire charges excluding fuel charges/day 1159.00
Fuel charges / day 3.25 litres 56.07 / litre 8 1457.82
Total hire charges / day 2616.82
Daily out turn 1000 cum
Hire charges per cum 2.62
(ii) Power roller
Hire charges excluding fuel charges/day 828.00
Fuel charges / day 2.5 litres 56.07 / litre 8 1121.40
Total hire charges / day 1949.40
Daily out turn 500 cum
Hire charges per cum 3.90
Total hire charges for Machinery (i)+(ii) 2.62 + 3.90 6.52
Rs 3.05 /Sq.m
Add 20% Extra for Labour in hilly areas 0.00
3.05 /Sq.m
Earth work excavation in all classes of soils except hard rock requiring blasting
depositing on bank with initial lead of 10M and lift of 2M including all labour charges
2
and incidental charges such as shoring, strutting, providing coffer dams, bailing out of
water as per 20A
Rs 65.10 /Cu.m
Add 20% Extra for Labour in hilly areas 0.00
65.10 /Cu.m
Earth work excavation in all classes of soils except hard rock requiring blasting
depositing on bank with initial lead of 10M and lift of 2M including all labour charges
2a
and incidental charges such as shoring, strutting, providing coffer dams, bailing out of
water as per 20B
Rs 61.10 /Cu.m
Add 20% Extra for Labour in hilly areas 0.00
61.10 /Cu.m
Providing and laying including cost and conveyance of gravel from approved sources to
work site including labour for spreading, watering and compacting by power roller to
3 achieve the required Proctor density at 100% compaction at Optimum moisture content
and hire fuel charges for powerroller, watersprinkler and all other incidental charges
such as traffic barricading and providing dangerlights etc. comp for base-course and
side berms.
-for Km 0.00 1.00 -for Km 1.00
DATA
1.16 cum Cost of Gravel 223.61 /cum 259.39 233.00
1.00 cum Labour Charges 14.91 /cum 14.91 14.91
Add 20% Extra for Labour in hilly areas 0.00
274.30
Rate per CUM: Rs 274.30 Rs
Providing and laying 75mm compacted thick WBM Grade II using 1 cum of 75mm to
22.4mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm
compacted thick (the blindage material shall have PI value less than 6%) including cost
and conveyance of all materials from approved quarry to work site and stacking to
departmental gauge for pre-measurement as directed by the departmental officers
4 including labour for spreading metal and gravel hand packing to camber and grade
lines blinding with required quantity of gravel, forming edge bunds, watering with all
leads for good water slurrying, rolling and consolidation by power roller and finishing as
per MOST 404 (III revision) including hire and fuel charges for power roller and water
sprinkler and all other tools and plants employed therefor and all incidental charges
etc., complete for BOTTOM LAYER
-for Km 0.00 1.00 -for Km 1.00
DATA
1.00 cum 75-22.40mm IRC metal 789.30 /cum 789.30 797.35
0.24 cum gravel 223.61 /cum 53.67 233.00
10.00 sqm Hire and fuel charges 103.96 /10sqm 103.96 103.96
10.00 sqm Labour charges 302.81 /10sqm 302.81 302.81
Add 20% Extra for Labour in hilly areas 0.00
1249.74
1249.74 /0.75 ### /0.75
Rate per CUM: Rs 1666.32 Rs
Providing and laying 75mm compacted thick WBM Grade III using 1 cum of 63mm to
11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm
compacted thick (the blindage material shall have PI value less than 6%) including cost
and conveyance of all materials from approved quarry to work site and stacking to
departmental gauge for pre-measurement as directed by the departmental officers
5 including labour for spreading metal and gravel hand packing to camber and grade
lines blinding with required quantity of gravel, forming edge bunds, watering with all
leads for good water slurrying, rolling and consolidation by power roller and finishing as
per MOST 404 (III revision) including hire and fuel charges for power roller and water
sprinkler and all other tools and plants employed therefor and all incidental charges
etc., complete for TOP LAYER
-for Km 0.00 1.00 -for Km 1.00
DATA
1.00 cum 63-11.20mm IRC metal 1023.08 /cum 1023.08 1031.13
0.24 cum gravel 223.61 /cum 53.67 233.00
10.00 sqm Hire and fuel charges 103.96 /10sqm 103.96 103.96
10.00 sqm Labour charges 302.81 /10sqm 302.81 302.81
Add 20% Extra for Labour in hilly areas 0.00
1483.52
1483.52 /0.75 ### /0.75
Rate per CUM: Rs 1978.03 Rs
17 Advance patch work for making up the undulation in the existing B.T
surface to an average thickness of of 50mm using 45mm IRC size HBG metal
Advance patch work for making up the undulation in the existing B.T
surface to an average thickness of of 50mm using 45mm IRC size HBG metal
18 Advance patch work for making up the undulation in the existing B.T
surface to an average thickness of of 25mm using 13.20mm IRC size HBG
metal
For Km 0.00 1.00 For Km 1.00
Advance patch work for making up the undulation in the existing B.T
surface to an average thickness of of 25mm using 13.20mm IRC size HBG
metal
For Km 0.00 0.00 For Km 0.00
Advance patch work for making up the undulation in the existing B.T
surface to an average thickness of of 25mm using 13.20mm IRC size HBG
metal
For Km 0.00 0.00 For Km 0.00
Applying tack coat over BT surface (not treated with primer) using 3Kg of bituminous
emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied
departmentally at section stores and cost of which will be recovered at the rates as per
special conditions appended herewith including conveyance of bituminous emulsion to
actual work spot handling charges including labour charges for brushing, cleaning and
7
preparing the surface for laying the tack coat and labour and machinery charges for
applying the required quantity of bituminous emulsion including hire, fuel and running
charges for all tools and plants employed for the work including all other incidental
charges such as barricading and providing danger lights, flags etc., complete as per
standard specification.
-for Km 0.00 1.00 -for Km 1.00
Providing and laying open graded premix carpet of 20mm compacted thick using
0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm
IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet
including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC
size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and
conveyance of chips and stacking them to departmental gauge for pre-measurements
including cost of bitumen which will be supplied by the department at departmental
10 section stores and its cost will be recovered as per special condition appended
including heating the bitumen and metal mixing the materials in mini hot mix plant for
premix carpet including spreading the same and finishing and compacting the same by
power rolling to the specified lines and grades including all labour charges application
of bitumen for seal coat over the premix carpet and spreading the seal coat and power
roller rolling separately as per MOST specification 509 and 513 (III revision) including
all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN
capacity and all other tools and plants employed therefor etc.com.
-for Km 0.00 1.00 -for Km 1.00
0.18 Cum 13.2mm IRC metal 1358.20 /cum 244.48 1366.25
0.09 Cum 11.2 mm IRC metal 961.20 /cum 86.51 969.25
0.09 Cum 6.7 mm IRC metal 744.20 /cum 66.98 752.25
24.40 Kgs Bitumen 60/70 ### /Mt 863.76 35400.00
10.00 Sqm Hire & fuel charges for P. 198.73 /10sqm 198.73
10.00 Sqm Hire & fuel charges for S 33.83 /10sqm 33.83
617.56
10.00 Sqm Labour charges for P.C 288.75 /10sqm 288.75
10.00 Sqm Labour charges for S.C 96.25 /10sqm 96.25
Add 20% Extra for Labour in hilly areas 0.00
1879.29
Rate per sqm Rs 187.93 Rs
Providing and laying open graded premix carpet of 20mm compacted thick using
0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm
IRC HBG machine crushed chips with 13.432Kg of bitumen and 1.168 Kg of
Plastic waste for 10 Sqm. of premix carpet including laying of seal coat 'A' over the
premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with
9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking
them to departmental gauge for pre-measurements including cost of bitumen which will
be supplied by the department at departmental section stores and its cost will be
10
recovered as per special condition appended including heating the bitumen and metal
mixing the materials in mini hot mix plant for premix carpet including spreading the
same and finishing and compacting the same by power rolling to the specified lines and
grades including all labour charges application of bitumen for seal coat over the premix
carpet and spreading the seal coat and power roller rolling separately as per MOST
specification 509 and 513 (III revision) including all labour charges hire and fuel charges
for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants
employed therefor etc.com.
-for Km 0.00 1.00 -for Km 1.00
0.18 Cum 13.2mm IRC metal 1358.20 /cum 244.48 1366.25
0.09 Cum 11.2 mm IRC metal 961.20 /cum 86.51 969.25
0.09 Cum 6.7 mm IRC metal 744.20 /cum 66.98 752.25
23.23 Kgs Bitumen 60/70 ### /Mt 822.41 35400.00
1.168 Kgs Plastic waste ### /Mt 35.04 30000.00
10.00 Sqm Hire & fuel charges for P. 198.73 /10sqm 198.73
10.00 Sqm Hire & fuel charges for S 33.83 /10sqm 33.83
617.56
10.00 Sqm Labour charges for P.C 288.75 /10sqm 288.75
10.00 Sqm Labour charges for S.C 96.25 /10sqm 96.25
Add 20% Extra for Labour in hilly areas 0.00
1872.98
Rate per sqm Rs 187.30 Rs
g blasting
labour charges
ms, bailing out of
g blasting
labour charges
ms, bailing out of
pproved sources to
y power roller to
m moisture content
idental charges
ase-course and
1.40
270.28
14.91
0.00
285.19
285.19
0.00
0.00
14.91
0.00
14.91
14.91
um of 75mm to
qm. of 75mm
6%) including cost
nd stacking to
mental officers
ber and grade
watering with all
er and finishing as
roller and water
dental charges
1.40
797.35
55.92
103.96
302.81
0.00
1260.04
1680.05
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
um of 63mm to
Sqm. of 75mm
6%) including cost
nd stacking to
mental officers
ber and grade
watering with all
er and finishing as
roller and water
dental charges
1.40
1031.13
55.92
103.96
302.81
0.00
1493.82
1991.76
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0
0
0
0.00
0.00
0.00
1.40
1082.25
1557.60
247.07
0.00
2886.92
2886.92
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.40
1366.25
1557.60
247.07
0.00
3170.92
3170.92
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4Kg of bituminous
ill be supplied
at the rates as per
inous emulsion to
ing, cleaning and
ery charges for
, fuel and running
her incidental
omplete as per
1.40
137.20
215.00
0.00
15.00
367.20
36.72
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Kg of bituminous
ill be supplied
at the rates as per
inous emulsion to
ing, cleaning and
ery charges for
, fuel and running
her incidental
omplete as per
1.40
102.90
73.00
0.00
15.00
190.90
19.09
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
d thick using
cum of 11.20mm
. of premix carpet
m of 6.70mm IRC
. including cost and
e-measurements
t departmental
appended
i hot mix plant for
acting the same by
arges application
al coat and power
vision) including
r roller 80-100KN
1.40
245.93
87.23
67.7
863.76
617.56
0.00
1882.18
188.22
0.00
0
0
0
0
0.00
0.00
0.00
0.00
0.00
0
0
0
0
0.00
0.00
0.00
0.00
d thick using
cum of 11.20mm
168 Kg of
coat 'A' over the
hed chips with
ps and stacking
bitumen which will
s cost will be
tumen and metal
g spreading the
specified lines and
at over the premix
y as per MOST
re and fuel charges
tools and plants
1.40
245.93
87.23
67.7
822.41
35.04
617.56
0.00
1875.87
187.59
0.00
0.00
0.00
0
0
35.04
0.00
0.00
35.04
3.50
0.00
0
0
0
0
35.04
0.00
0.00
35.04
3.50
LEAD STATEMENT ( Kms)
Plain 0 104 21 1 1 3 0 3 3 1
HILLS 21 21 21 21 21 21 0 21 21 0
From 1.06.2017
xxx PWD Rates Schedule of Rates for the year 2017-2018 xxx Highways sh. rates
xxx Collector's appd rates xxx Local Rates
2 Carpenter II class 488.00 DRD Rate 1.7.2015 1 Hard rock blasting & Stack 432.00
3 Fitter I class 474.00 474.00 1 Cement 5260.00 2 Wedging hard rock 867.00
4 Fitter II class440.00 440.00 2 Shell lime 1285.00 3 Medium rock blasting 221.00
5 Floor polisher 420.00 3 Lime stone 947.00 4 Drilling holes 50mm 195.00
6 Mason I class for BW 545.00 4 Grinding mortor 154.00 5 Drilling holes 40 mm 139.00 163.00 45mm Dia
7 Mason II class for B 488.00 5 Cement Mixing mort 63.30 84.00 Mixing mortor by Machine
Gr. Addl.
8 Mazdoor I class 341.00 Concrete Vibrators Lift Gharges Floor Floor
12 Plumber I class 474.00 1 CW scantling < 4m 37500.00 1 Concrete 64.40 129.10 2.4 Scrapping the old pl
13 Plumber II class 440.00 2 CW scantling over 4m(raft)39500.00 2 Brk/stone masny 43.20 86.70
14 Stone Cutter I class 419.00 3 CW planks 43000.00 d Earth work 278.00 110mm PVC pipe (6
15 Stone Cutter II class 387.00 4 CW reepers-50x25 37.80 1 Ordinary soil 20b 40.80 185.20 110mm PVC pipe (4
16 Wodder 353.00 5 CW reepers-50x12 27.30 2 Gravelly soil SS 20 A 65.10 79.30 110mm PVC Shoe (p
17 Mazdoor I cl. For roa 385.00 6 Palmyrah rafter 54.00 3 Gravelly soil SS 20 b 61.10 98.90 110mm PVC Bend (p
18 Mason I class(stone 545.00 7 Casu. poles 13-15 36.10 4 SDR 91.00 92.50 110mm PVC Elbow (
19 Mason II class(stone 488.00 8 Casu. poles 10-13 27.50 5 MR & DMR 159.70 79.30 110mm PVC Ventco
II Rates of Material 9 Casu. poles 8-10 21.00 6 EW addl. Lead 10mts 7.55 9.30 PVC water Tank / Ltr
a Bricks and Tile product 10 Casu. poles 5-8 18.00 7 EW addl. Lift 1mts 6.00 20.30 110mm GI clamp
1 Country bricks ( 2 3/4" ) 5205.00 11 Silver oak Scandlin 17000 8 Refilling ( Sand ) 18.80
4 Pressed Tiles.(20x20) 11390.00 e Metal and Iron w 11 Stacking metal /m3 3.15
5 --do-- (23x23) 16140.00 1 Steel rods 39800.00 12 Stacking gravel /m3 3.05
6 Mang. Tiles class AA 10840.00 2 MS plate kg 43.50 13 Stacking sand /m3 3.05
8 Mosaic (Grey)20x20x2cm 8320.00 4 Binding wir Mt 46200.00 1 600 to 900mm dia 45.35
10 Country bricks ( 2 1/4" ) 4095.00 6 Iron works ( 28.00 30.30 /kg 3 up to 300 mm dia 17.75
f RCC Hume PipesNP2 & coller n Labour wrought put up Door/W 67/sqft Paver Block 80mm
NP3 900mm dia pipe 4480 1 900 mm dia 2.5m 3290 220 1 Frames/cum ### 125.00 Door fixing
2 750 mm dia 2.5m 2690 210 2 Shutters/sqm 843.00 157.00 Window fixing
b Stone and Road materials 3 600 mm dia 2.5m 2390 190 V Miscellaneous (Local Rates) 3366 European colour
4 450 mm dia 2.5m 2290 180 1 Rural sanitay pan 153.00 2978 European
1 Roughstone (masonry) 413.00 III Rates of works 1600 100 2 Indian water closet White ### 1488 colour
2 Roughstone ( revet ) 358.00 a Clearing the site 3 Wash basin 550x400 mm ### 2165 colour
3 Bond stones 567.00 1 Lighjungle 3.35 4 Enamel Paint lit Iron 247.40 259.10 Wood
4 Stoneslab 4275.00
(3 face 1 ln) ab 1.2 m 2 Scrub jungle 3.05 5 Wood primer paint 159.85
5 Km stone1.65 x 0.45 407.00 3 Heavy jungle 4.45 6 Red oxide primer for Iron 148.40 147 Distember Primer
6 Hm stone 0.75 x0.2 204.00 b Dismanling 7 Cement paint 54.15 147 Exterior Emulsion pr
8 Cut stone roughly d 4060.00 1 Brick/stone in clay 37.50 9 Distember OBD kg 80.00 92.40 Acrylic Distember
ISS Metal 2 Brick/stone in lime 115.00 10 White / Clr cement (kg) 25.80 29.80 Colour Cement
9 20mm metal 1300.00 4 Lime concrete 177.00 12 Crude oil kg 15.00 9.35 Cotton Waste
10 12mm metal 1206.00 5 Cement concrete 242.00 13 Glass tiles 0.15x0.15 10.50 12.40 Design
11 10mm metal 888.00 6 RCC 3670.00 14 --do-- 0.30x0.20x6 33.25 11.15 0.1X0.2 Design
12 6mm metal 601.00 7 Chipping concrete 20.10 /m2 15 Ceramic tiles 0.20x0.20 24.30 17.70 Plain
13 Gravel 183.00 8 Pres.tiles & WC 22.90 /m2 16 --do-- 0.305x0.30 Design 55.30 39.60 Plain
14 Well gravel 150.00 9 Clean removalCemen 4.40 /m2 17 --do-- 0.400x0.400 64.00 700.00 600x600x8 Vitrified
15 Sand for mortor 176.40 IV Electrification 2.40 Scrappin 18 Hollow block 16"x4"x8" 10.00 595.00 prepolished concret
16 Sand for filling 176.40 19 Hollow block 16"x6"x8" 14.00 38.80 PVC adhesive solutio
17 Clay for puddle & masonry 35.50 20 Hollow block 16"x8"x8" 17.00 12.80 Spun Yarn
18 Cuddapah slab 50mm 426.00 1 Light & Fan Pt(21) 456.80 /pt 21 Water proofing compound 43.20 18.50 Shellac 100gm
19 Cuddapah slab 38/40 411.00 2 Plug point SI 34 340.05 /pt VI Steel Doors & Ventilators 0 3.65 Thread ball /each
20 Cuddapah slab 20/30 378.00 3 16 amp DPICSI 136 358.55 /pt 1 Two leaf 'W' 0.90x1.20m 3275 /each 6.40
21 Granite slab sqm 1850.00 4 Meter board SI120 127.80 /pt 2 Steel Gate 1.20x1.80 0.00 /each 4.90
5 GI serv. Pip SI 67 200.25 /m 3 Single leaf 'D' 0.90x2.00m 3300 /each 129.00
IRC Metal 6 Serv.main SI 62 25.10 /m 4 Two leaf 'D' 1.10x2.10m 4650 /each ###
1 45 mm metal 953.00 7 Arial Fuse SI 124 99.90 /pt 5 Two leaf 'W' 0.90x1.20m 3275 /each
2 25 mm metal 919.00 8 4x40W tube SI 83 371.15 /no 6 Zinc door 0.75x1.80m 1400 /each 271.00
3 11.2 mm metal 840.00 9 Ceiling.Fan SI 106 ### /no 7 Ventilator 0.90x0.45m 900 /each 9.35
4 6 mm metal 623.00 10 BH Fitting SI 80 307.85 /no 8 TV Shutter 0.90x0.75 0.00 /each 125.00
11 40W bulb SI 77 77.20 /no 9 PD shop count 0.45x0.60 0.00 /each 157.00
Conveyance of Material by road in PLAINS for the year 2017 - 18
Lime
Rough stone, Brick I & II
stone, M.Tiles(1000),
Cement Steel Metal, sand, Country class,
Sl.No. Distance in brick jelly, pressed
1 M.T 1.00MT gravel,surki, bricks III class Chamber
woodwork tiles(2000)
earth (1Cum) bricks
(1Cum)
1 2 3 4 5 6 7 8 9
1 Chennai IOC & BPC to 20 Block Head Rs 2.80 / Km / Mt 2 HCL to Erode dt 20 blocks 1500 / / Mt
3 Coimbatore IOC to 20 Block Head qrs. Rs 550 / / Mt 4 CBE / BPC to 20 blocks 550 / / Mt
CONVEYANCE TABLE
KM 0-10 KM 10-20 KM 20-40 KM 40-80 KM above 80
KM I.C KM rate amt KM rate amt KM rate amt KM rate amt KM rate amt
I Buildings
1 Cement 0 0.00 0 5.87 0.00 0 5.02 0.00 0 4.32 0.00 0 3.73 0.00 0 3.40 0.00
2 Rough stone 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
3 Bond stone 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
4 40mm iss m 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
5 20mm iss m 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
6 10-12mm me 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
7 6-10mm met 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
8 sand for mor 104 0.00 10 9.39 ### 10 8.05 80.50 20 6.92 138.40 40 6.49 ### 24 5.45 130.80
9 sand for filli 104 0.00 10 9.39 ### 10 8.05 80.50 20 6.92 138.40 40 6.49 ### 24 5.45 130.80
10 steel 0 0.00 0 5.87 0.00 0 5.02 0.00 0 4.32 0.00 0 3.73 0.00 0 3.40 0.00
11 country bric 1 0.00 1 7.93 7.93 0 6.79 0.00 0 5.84 0.00 0 5.02 0.00 0 4.60 0.00
12 brick jelly 1 0.00 1 6.46 6.46 0 5.53 0.00 0 4.76 0.00 0 4.11 0.00 0 3.75 0.00
13 shell lime 0 0.00 0 6.46 0.00 0 5.53 0.00 0 4.76 0.00 0 4.11 0.00 0 3.75 0.00
14 Lime stone 3 0.00 3 6.46 ### 0 5.53 0.00 0 4.76 0.00 0 4.11 0.00 0 3.75 0.00
15 pressed tiles 3 0.00 3 ### ### 0 9.05 0.00 0 7.78 0.00 0 6.70 0.00 0 6.13 0.00
16 CW planks 3 0.00 3 6.46 ### 0 5.53 0.00 0 4.76 0.00 0 4.11 0.00 0 3.75 0.00
17 CW scantling 3 0.00 3 6.46 ### 0 5.53 0.00 0 4.76 0.00 0 4.11 0.00 0 3.75 0.00
18 Gravel 1 0.00 1 9.39 9.39 0 8.05 0.00 0 6.92 0.00 0 6.49 0.00 0 5.45 0.00
19 cutstone rou 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
20 25mm IRC m 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
21 11.2mm IRC 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
22 6mm IRC me 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
23 45mm IRC m 21 0.00 10 9.39 ### 10 8.05 80.50 1 6.92 6.92 0 6.49 0.00 0 5.45 0.00
Lime
stone, Rough stone, Brick I & II
brick jelly, Metal, sand, M.Tiles(1000), class,
Cement Steel woodwork gravel,surki, Country pressed Chamber
Sl.No. Distance in 1 M.T 1.00MT (1Cum) earth (1Cum) bricks tiles(2000) bricks
1 2 3 4 5 6 7 8 9
NAME OF WORK: Repairs and Improvements the M.S quarters at Anthiyur BDO office
compound H/o. Anthiyur
COST OF MATERIALS AT SITE
loading
Sl.No name of materials lead in KM cost conveyance unloadin total
g
1 Cement 0 5260.00 0.00 0.00 5260.00
2 sand for mortar 104 176.40 703.20 0.00 879.60
3 sand for filling 104 176.40 703.20 0.00 879.60
4 Rough stone 21 413.00 181.32 0.00 594.32
5 Bond stone 21 567.00 181.32 0.00 748.32
6 40mm iss metal 21 934.00 181.32 0.00 1115.32
7 20mm iss metal 21 1300.00 181.32 0.00 1481.32
8 10-12mm metal 21 1047.00 181.32 0.00 1228.32
9 steel 0 39800.00 0.00 0.00 39800.00
10 country bricks ( 23/4") 1 5205.00 7.93 0.00 5212.93
11 country bricks ( 21/4") 1 4095.00 7.93 0.00 4102.93
12 brick jelly 20 mm 1 718.00 6.46 0.00 724.46
13 shell lime 0 1285.00 0.00 0.00 1285.00
14 Lime stone 3 947.00 19.38 0.00 966.38
15 pressed tiles 3 16140.00 15.86 0.00 16155.86
16 Country wood planks 3 43000.00 19.38 0.00 43019.38
17 Silver Oak scantlings 3 17000.00 19.38 0.00 17019.38
18 6-10mm metal 21 744.50 181.32 0.00 925.82
19 25 mm metal 21 919.00 181.32 0.00 1100.32
20 12 mm metal 21 840.00 181.32 0.00 1021.32
21 6 mm metal 21 623.00 181.32 0.00 804.32
22 Rough stone for revetme 21 358.00 181.32 0.00 539.32
23 Cutstone roughly dresse 21 4060.00 181.32 0.00 4241.32
24 Gravel (Well) 1 150.00 9.39 0.00 159.39
Gravel (Gritty) 1 183.00 9.39 0.00 192.39
SUB DATA
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and
conveyance of all materials to site and all labour charges for mixing,
laying and curing etc complete for 10 cum.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and
conveyance of all materials to site and all labour charges for mixing,
laying and curing etc complete for bed blocks for 10 cum
Brick work in cement mortar 1:5 mix using country bricks 83/4"x43/8"x23/4"
and conveyance of all materials to site and all labour charges etc complete -10 cum
4590 nos Country bricks 8 3/4" x 4 3/8" x2 3/4" 5212.93 /1000nos 23927.35
2.50 cum Cement mortar 1:5 2457.78 /cum 6144.45
3.50 nos Mason I class 545.00 /each 1907.50
10.60 nos Mason II class 488.00 /each 5172.80
7.10 nos Mazdoor I class 341.00 /each 2421.10
21.20 nos Mazdoor II class 308.00 /each 6529.60
0.00
46102.80
RATE @RS 4610.28 /cum
Collection and supply of sand and filling in to the basement including cost and
conveyance to the siteand all labour charges for filling
as per standard speecifications
898.40
RATE @RS 898.40 /cum
Refilling the basement with excavated earth other than sand complying the
Standard specification
RATE @RS 21.40 /cum
Supplying and erecting centering shuttering including necessary supports for plane
surface in foundation and basement and in all floors for R C C column footing
column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc
using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild
steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country
wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and
supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre
complete complying with standard specifications and as directed by departmental
officers including conveyance of all materials to site and proper centering etc complete.
Sub Data I
Cost of MS sheets & angles for each set
PAGE59
Weight of MS sheet B.G 10 Gauge size 90x60cm x 3.175 mm
3.175 x 7850/1000 = 24.924 kg/m2
24.924 Kg/m2 x 0.54 m2 = 13.46 Kg.
PAGE60
Weight of MS angle size 25 x 25 x 3 mm
3.6 x 1.1 Kg/m = 4.00 Kg
13.46 kgs Cost of MS sheet 43.50 /kg 585.51
4 kgs Cost of MS angle 43.50 /kg 174.00
17.46 kgs Cutting,bending,welding,etc 0.00
24.49
784.00
Sub Data 2
Cost of MS sheets and angles and CW joists and casurina props - 10 Sqm
Rate per one operation for MS sheet & angle 14896.00 /40 372.40
Rate per one operation for strutting 4751.08 /5 950.22
Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mm
ISS metal to 25mm thick including cost and conveyance of all materials to site
and all labour charges for mixing, laying, curing etc complete for 10 cum
Ellispattern Ist sort -20mm thick including cost and conveyance of all
materials to site and all labour charges etc complete
Dadooing of walls with colour glazed tiles of size 300x200x6 mm of best quality
including cost and conveyance of all materials to site and all labour charges etc
complete.
Paving the Floor with scratch proof ceromic tiles of size 305x305x6mm including
cost and conveyance of all materials to site and all labour charges etc complete
112 Nos Design Ceromic tiles all colo305x305x6 55.30 /each 6193.60
0.21 cum Cement mortar 1:3 mix 3467.70 /cum 728.22
1.20 nos Mason I class 545.00 /each 654.00
1.00 no Mason II class 488.00 /each 488.00
1.00 no Mazdoor I class 341.00 /each 341.00
PAGE63
1.00 no Mazdoor II class 308.00 /each 308.00
0.50 no Stone cutter I class 419.00 /each 209.50
PAGE64
0.50 Kg Cotton waste 9.35 /Kg 4.68
3.0 Kg Colour cement 29.80 /Kg 89.40
Sundries LS 0.00
9016.40
RATE @RS 901.64 /Sqm
Paving the Floor with scratch proof ceromic tiles of size 400x400x7mm including
cost and conveyance of all materials to site and all labour charges etc complete
White washing two coats using shell lime including cost and conveyance of
all materials to site and all labour charges etc comoplete for 100 Sqm
Colour washing two coats using approved colour pigments including cost
and conveyance of all materials to site and all labour charges etc complete
28.20
RATE @Rs 28.20 /Sqm
0.98 ltr Water based primer liquid 159.85 Ltr 156.65 156.65
LS Cost of putty 0
Priming coat on new wood work with ready mixed primer of approved quality-10 Sqm
Painting two coats over new iron works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
Painting two coats over new wood works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
Painting two coats over old iron works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
Painting two coats over old wood works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
Pointing with cement mortar 1:3 to full depth of tiles using crudeoil 10% by
weight of cement including cost and conveyance of all materials to site
and all labour charges etc complete for 10 Sqm
Brick jelly lime concrete using 20mm brick jelly with slacked lime in the ratio
of 32:12.5 including cost and conveyance of all materials to site and all labour
charges for mixing , laying ,and finishing etc complete for 10 cum
Weathering course with brick jelly lime concrete using 20mm brick jelly with
pure slacked lime over R.C.C. roof slab in the proportion of 32:12.5 and
finshed with one course of pressed tiles of size 23x23x2cm with cement
mortar 1:3 mix and pointed with the same oiled mortar including cost and
conveyance of all materials to site and all labour charges etc complete for 10 Sqm
Honey comb brick work with class III country bricks including cost and conveyance
of all materials to site and all labour charges etc complete
Supplying and Fixing inposition of best quality make White glazed wash
basin of size 550x 400mm - 1 No.
Supplying and fixing P.V.C rainwater down fall pipe of 110mm dia
with necessary shoes, bends,& clamps etc.,
DATA
Earth work excavation and depositing on bank with in initial lead of 10 m
and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,
earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Rate / cum 61.10
Add 100% extra for narrow foundation 61.10
122.20
Add for 20% on labour 24.44
146.64 /cum
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and
conveyance of all materials to site and all labour charges for mixing,
laying and curing etc complete for 10 cum.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and
conveyance of all materials to site and all labour charges for mixing,
laying and curing etc complete for bed blocks for 10 cum
Cement concrete 1:3:6 mix using 20mm ISS metal including cost and
conveyance of all materials to site and all labour charges for mixing,
laying and curing etc complete for bed blocks for 10 cum
Brick work in cement mortar 1:5 mix using country bricks 83/4"x43/8"x23/4"
and conveyance of all materials to site and all labour charges etc complete -10 cum
4590 nos Country bricks 8 3/4" x4 3/8" x2 3/4" 5514.83 /1000nos 25313.07
2.50 cum Cement mortar 1:5 2764.55 /cum 6911.38
3.50 nos Mason I class 545.00 /each 1907.50
10.60 nos Mason II class 488.00 /each 5172.80
7.10 nos Mazdoor I class 341.00 /each 2421.10
21.20 nos Mazdoor II class 308.00 /each 6529.60
Add for 20% on labour 3206.20
0.00
51461.65
RATE @RS 5146.17 /cum
Collection and supply of sand and filling in to the basement including cost and
conveyance to the siteand all labour charges for filling
as per standard speecifications
Collection and supply of gritty gravel from appd quarry including cost and
conveyance of all materials to site including all labour charges for filling
etc.complete,
Collection and supply of Well gravel from appd quarry including cost and
conveyance of all materials to site including all labour charges for filling
etc.complete,
Refilling the basement with excavated earth other than sand complying the
Standard specification
RATE @RS 21.40 /cum
Add for 20% on labour 4.28
25.68 /cum
Supplying and erecting centering shuttering including necessary supports for plane
surface in foundation and basement and in all floors for R C C column footing
column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc
using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild
steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country
wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and
supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre
complete complying with standard specifications and as directed by departmental
officers including conveyance of all materials to site and proper centering etc complete.
Sub Data I
Cost of MS sheets & angles for each set
Weight of MS sheet B.G 10 Gauge size 90x60cm x 3.175 mm
3.175 x 7850/1000 = 24.924 kg/m2
24.924 Kg/m2 x 0.54 m2 = 13.46 Kg.
Weight of MS angle size 25 x 25 x 3 mm
3.6 x 1.1 Kg/m = 4.00 Kg
13.46 kgs Cost of MS sheet 43.50 /kg 585.51
4.00 kgs Cost of MS angle 43.50 /kg 174.00
kgs Cutting,bending,welding,etc /kg 0.00
24.49
784.00
Sub Data 2
Cost of MS sheets and angles and CW joists and casurina props - 10 Sqm
Rate per one operation for MS sheet & angle 14896.00 /40 372.40
Rate per one operation for strutting 4779.77 /5 955.95
856.39
6545.61 -856.39 = 5689.22
Damp proof course in cement mortor CM1:3 - 20mm thick with water proofing
compound at 5% by wt of cement
0.21 cum cement mortar 1:3 mix 3817.95 /cum 801.77
1.10 nos Mason I class 545.00 /each 599.50
1.10 nos Mason II class 488.00 /each 536.80
2.20 nos Mazdoor I class 341.00 /each 750.20
1.10 nos Mazdoor II class 308.00 /each 338.80
Add for 20% on labour 445.06
5.00 kg Crude oil 15.00 / kg 75.00
0.00
3547.13
RATE @RS 354.71 /Sqm
Damp proof course in cement mortor CM1:3 - 12mm thick with water proofing
compound at 2 % by wt of cement
Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mm
ISS metal to 25mm thick including cost and conveyance of all materials to site
and all labour charges for mixing, laying, curing etc complete for 10 cum
Dadooing of walls with colour glazed tiles of size 300x200x6 mm of best quality
including cost and conveyance of all materials to site and all labour charges etc
complete.
Paving the Floor with scratch proof ceromic tiles of size 305x305x6mm including
cost and conveyance of all materials to site and all labour charges etc complete
112 Nos Design colour Ceromic tiles 305x305x6 55.30 /each 6193.60
0.21 cum Cement mortar 1:3 mix 3817.95 /cum 801.77
1.20 nos Mason I class 545.00 /each 654.00
1.00 no Mason II class 488.00 /each 488.00
1.00 no Mazdoor I class 341.00 /each 341.00
1.00 no Mazdoor II class 308.00 /each 308.00
0.50 no Stone cutter I class 419.00 /each 209.50
Add for 20% on labour 400.10
0.50 Kg Cotton waste 9.35 /Kg 4.68
3.0 Kg Colour cement 29.80 /Kg 89.40
Sundries LS 0.00
9490.05
RATE @RS 949.01 /Sqm
Paving the Floor with scratch proof ceromic tiles of size 400x400x7mm including
cost and conveyance of all materials to site and all labour charges etc complete
Supplying & fixing of Granite slab of 20mm thick with nosing, cutting and bedding
laidover in CM 1 : 2 20mm thick - 10 Sqm
Pointing with cement mortor 1:3 cuddapah slab & paving stone to full depth - 10 Sqm
Flooring with cuddapah slabs 50mm thick over a bed of concrete 100mm
thick and pointed with cement mortar 1:3 -10 Sqm
10.50 Sqm Cuddapah slabs (50mm thick) 426.00 Sqm 4473.00
0.12 cum cement mortar1:3 3817.95 cum 458.15
1.00 cum Cement Concrete 1:6:12 3706.01 cum 3706.01
10.00 Sqm Pointing with CM 1:3 158.63 cum 1586.30
1.10 No Mason I class 545.00 cum 599.50
2.10 No Mason IIclass 488.00 /each 1024.80
2.20 No Mazdoor I Class 341.00 /each 750.20
1.10 No Mazdoor II class 308.00 /each 338.80
Add for 20% on labour 542.66
sundries 0.00
13479.42
RATE @RS 1347.94 /Sqm
White washing two coats using shell lime including cost and conveyance of
all materials to site and all labour charges etc comoplete for 100 Sqm
0.07 cum cost of shell lime 1285.00 /cum 89.95
1.60 nos Mason II class 488.00 /each 780.80
0.50 nos Mazdoor I class 341.00 /each 170.50
2.70 nos Mazdoor II class 308.00 /each 831.60
PAGE83
Add for 20% on labour 356.58
0.00
2229.43
RATE @RS 22.29 /Sqm
Colour washing two coats using approved colour pigments including cost
and conveyance of all materials to site and all labour charges etc complete
Priming coat for new iron with ready mixed primer of approved quality 10Sqm
1.33 kg Red Oxide 148.40 kg 197.37
0.70 No Painter-I class 436.00 /each 305.20
Add for 20% on labour 61.04
sundries including brushes, soaps.putty etc 0.00
563.61
RATE @RS 56.36 /Sqm
Priming coat on new wood work with ready mixed primer of approved quality-10 Sqm
Painting two coats over old iron works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
Painting two coats over old wood works using ready mixed enamel paint
including cost and conveyance of paint and all labour charges etc complete
PAGE85
Pointing with cement mortar 1:3 flush pointing for brickwork including cost
and conveyance of all materialsand all labour charges etc complete for 10 Sqm
Brick jelly lime concrete using 40mm brick jelly with slacked lime in the ratio
of 32:12.5 including cost and conveyance of all materials to site and all labour
charges for mixing , laying ,and finishing etc complete for 10 cum
Brick jelly lime concrete using 20mm brick jelly with slacked lime in the ratio
of 32:12.5 including cost and conveyance of all materials to site and all labour
charges for mixing , laying ,and finishing etc complete for 10 cum
Weathering course with brick jelly lime concrete using 20mm brick jelly with
pure slacked lime over R.C.C. roof slab in the proportion of 32:12.5 and
finshed with one course of pressed tiles of size 23x23x2cm with cement
mortar 1:3 mix and pointed with the same oiled mortar including cost and
conveyance of all materials to site and all labour charges etc complete for 10 Sqm
Honey comb brick work with class III country bricks including cost and conveyance
of all materials to site and all labour charges etc complete
0.64 x1000Nos Country bricks 5514.83 /1000Nos 3529.49
0.70 cum cement mortar 1:3 mix 3817.95 /cum 2672.57
3.20 nos Mason I class 545.00 /each 1744.00
6.50 nos Mason II class 488.00 /each 3172.00
2.20 nos Mazdoor I class 341.00 /each 750.20
PAGE87
5.40 nos Mazdoor II class 308.00 /each 1663.20
Add for 20% on labour 1465.88
0.00
14997.34
RATE @RS 1499.73 /Sqm
Dry Brick work using country bricks 83/4"x41/4"x23/4" including cost and
conveyance of all materials to site and all labour charges etc complete
4.59 x1000nos Country bricks 5514.83 /1000nos 25313.07
3.50 nos Mason I class 545.00 /each 1907.50
7.20 nos Mason II class 488.00 /each 3513.60
7.10 nos Mazdoor I class 341.00 /each 2421.10
14.10 nos Mazdoor II class 308.00 /each 4342.80
Add for 20% on labour 2437.00
0.00
39935.07
RATE @RS 3993.51 /cum
Dry Brick work using country bricks 83/4"x41/4"x21/4" including cost and
conveyance of all materials to site and all labour charges etc complete
6.01 x1000nos Country bricks 4404.83 /1000nos 26473.03
3.50 nos Mason I class 545.00 /each 1907.50
7.20 nos Mason II class 488.00 /each 3513.60
7.10 nos Mazdoor I class 341.00 /each 2421.10
14.10 nos Mazdoor II class 308.00 /each 4342.80
Add for 20% on labour 2437.00
0.00
41095.03
RATE @RS 4109.50 /cum
Gravel backing for revetments including cost and
conveyance and all labour charges etc complete - 10 cum.
Rough stone dry packing for aprons and revetments including cost and
conveyance and all labour charges etc complete
11.00 cum Rough stone 828.24 /cum 9110.64
3.50 nos Wodders 353.00 /each 1235.50
10.60 nos Mazdoor I class 341.00 /each 3614.60
7.10 nos Mazdoor II class 308.00 /each 2186.80
Add for 20% on labour 1407.38
0.00
17554.92
RATE @RS 1755.49 /Sqm
Precast Hollow Block Masonry with C.m.1:5 mix using hollow in size
of 0,40x0.10mx0.20m for 2.56 Cum
302 nos Hollow Block 10.00 each 3020.00
0.21 cum CM 1:5 2764.55 each 580.56
2.00 nos Mason ii class 488.00 each 976.00
1.00 nos mazdoor I class 341.00 each 341.00
1.00 nos mazdoor ii class 308.00 each 308.00
Add for 20% on labour 325.00
0.00
for 2.56 Cum 5550.56
= 5550.56 /2.56
RATE @RS 2168.19 /cum
Precast Hollow Block Masonry with C.m.1:5 mix using hollow in size
of 0,40x0.20mx0.20m for 2.56 Cum
151 nos Hollow Block 17.00 each 2567.00
0.21 cum CM 1:5 2764.55 each 580.56
2.00 nos Mason ii class 488.00 each 976.00
1.00 nos mazdoor I class 341.00 each 341.00
1.00 nos mazdoor ii class 308.00 each 308.00
Add for 20% on labour 325.00
0.00
for 2.56 Cum 5097.56
= 5097.56 /2.56
Roofing with AC corrugated sheet 6mm thick including cost of " J " bolts
and bitumen washer etc.complete. -10 Sqm
Supplying and Fixing inposition of best quality make White glazed wash
basin of size 550x 400mm - 1 No.
Supplying and fixing P.V.C rainwater down fall pipe of 110mm dia
with necessary shoes, bends,& clamps etc.,
3.00 m 110 mm dia PVC pipe 185.20 /Rm 555.60
1.00 No 110 mm dia PVC shoe 79.30 /each 79.30
1.00 No 110 mm dia PVC Bend 98.90 /each 98.90
1.00 No 100 mm dia GI Clamp 20.30 /each 20.30
1.00 No Fitter I class 474.00 /each 474.00
Add for 20% on labour 94.80
For 3 Rm = 1322.90
RATE @RS 440.97 /Rm
Rates Length of Road
Starting Chainage
Ending Chainage
Kerosene & Oil
Emulsion
Bitumen
Diesel
Hills
Hill Percentage 20 %
I ROADS
II CD WORKS
Materials Plain Hills
2 C.C.1:4:8 4002.27
3 C : C 1: 5: 10 3824.51
4 R . R. MASONARY 1 : 5 4110.10
5 R . R. MASONARY 1 : 4 4244.41
Gravel
Sand
10.00 10.00 1.00 25.00 270557
14.91
5411.14
13508.28
8987.10
………… 0
8543.91
284797
Honeycome Brk
Work 1499.73
15x15x6 1077.90
600x600x8 1029.70
WC 4009.99
EWC 6322.22
Washbasin 2965.36
P.U.G.F = 2017-18
DETAILED CUM ABSTRACT ESTIMATE
Sl. Measurements
Description of Items Nos contents Amount
No Length Breadth Depth
WALL CRACK
Clean removal of cement plaster from wals and clean away from site
1
including labour charges etc complete
Outer wall 1 x 2 2.00 - 0.75 3.00
Outer wall 1 x 2 3.00 - 0.75 4.50
7.50
Wall Plastering with cement mortar 1:5 mix 12 mm thick including all cost
2
and conveyance of materials and labour charges etc complete
7.50
Pointing with Cement mortar 1:3 mix after scapping the jointd for 20 mm
3 depp including all cost and conveyance of materials and labour charges etc.,
complete
20.10
20.10 Sqm @ Rs. 160.22 3220.00
CEILING CRACK
3.36
3.36
Pointing with cement mortar 1:3 to full depth of tiles using crudeoil 10% by
6 weight of cement including cost and conveyance of all materials to site and all
labour charges etc complete
104.20
Finishing the top of roof with one course of pressed tiles of size 23x23x2cm
7 with cement mortar 1:3 mix and pointed with the same oiled mortar including
cost and conveyance of all materials to site and all labour charges etc complete
10.60
10.60 Sqm @ Rs. 799.15 8471.00
Floor finish
Chippingt the flooring of cement concrete and away from site including all
8
labour charges etc., complete.
Verandah ceiling 1 x 1 4.25 1.80 - 7.65
Hall ceiling 1 x 1 4.25 2.70 - 11.48
Bed ceiling 1 x 1 4.00 2.75 - 11.00
Dining ceiing 1 x 1 3.05 2.70 - 8.24
Kitchen ceiling 1 x 1 2.75 2.75 - 7.56
Rear verandah ceiling 1 x 1 3.15 2.60 - 8.19
Grill soffits 1 x 1 1.50 0.20 - 0.30
WD - door soffits 1 x 5 1.05 0.20 - 1.05
WD1 - door soffits 1 x 1 0.90 0.20 - 0.18
Open soffits 1 x 1 0.90 0.25 - 0.23
W.C ceiling 1 x 1 1.05 1.85 - 1.94
Bath ceiling 1 x 1 1.20 1.85 - 2.22
WD2 - door soffits 1 x 2 0.85 0.20 - 0.34
60.38
Paving the Floor with scratch proof ceromic tiles of size 305X305x6mm in
9 C.M. 1:3 mix including cost and conveyance of all materials to site and all labour
charges etc complete
60.38
Wall tiles
Clean removal of cement plaster from wall and away from site including all
10
labour charges etc., complete.
Bath alround upto 7'0" ht 1 x 1 6.10 - 2.10 12.81
WC alround upto 7'0" ht 1 x 1 5.80 - 2.10 12.18
Kitchen wall 1 x 1 5.05 - 1.20 6.06
Deductions:-
Doors - WD2 -1 x 2 0.85 - 2.05 -3.49
27.56
27.56
COLOUR WASHING
White washing the two coats using best quality of shell lime inclusing all cost
12
and conveyance etc complete to site
Ceiling
Verandah ceiling 1 x 1 4.25 1.80 - 7.65
Hall ceiling 1 x 1 4.25 2.70 - 11.48
Bed ceiling 1 x 1 4.00 2.75 - 11.00
Dining ceiing 1 x 1 3.05 2.70 - 8.24
Kitchen ceiling 1 x 1 2.75 2.75 - 7.56
Rear verandah ceiling 1 x 1 3.15 2.60 - 8.19
W.C ceiling 1 x 1 1.05 1.85 - 1.94
Bath ceiling 1 x 1 1.20 1.85 - 2.22
58.28
Deductions:-
Grill Gate -1 x 1 1.50 - 2.05 -3.08
Doors - WD -3 x 2 1.05 - 2.05 -12.92
Doors - WD -1 x 2 1.05 - 2.05 -4.31
Doors - WD1 -1 x 2 0.90 - 2.05 -3.69
Doors - WD2 -1 x 2 0.85 - 2.05 -3.49
Open -1 x 2 0.90 - 2.05 -3.69
Windows - WW -1 x 7 0.90 - 1.35 -8.51
154.36
Exterior emulsion finishing two coats over one coat of primer including all
14
cost and conveyance of materials and labour charges etc., complete
Out side
209.02
DOOR REPLACEMENT
Removal of damaged wooden Door and stocking them on site including all
15
labour charges etc., complete.
5.23
5.23 Sqm @ Rs. 76.20 399.00
Supplying the new steel Door of size 0.85x2.05 m including all cost and
16
conveyance of materials and labour charges etc., complete
3.00
3.00 No @ Rs. 3,195.00 9585.00
Fixing the new steel Door of size 0.85x2.05 m including all cost and conveyance
17
of materials and labour charges etc., complete
5.23
5.23 Sqm @ Rs. 125.00 654.00
Painting two coats over Old Wood work with synthetic enamel paint of
18 approved quality including all cost and conveyance of materials and labour
charges etc., complete
42.23
42.23 Sqm @ Rs. 109.84 4639.00
Painting two coats over Old Iron work with synthetic enamel paint of approved
19 quality including all cost and conveyance of materials and labour charges etc.,
complete
6.15
6.15 Sqm @ Rs. 94.72 583.00
Painting two coats over New Iron work with synthetic enamel paint of approved
20 quality including all cost and conveyance of materials and labour charges etc.,
complete
10.46
10.46 Sqm @ Rs. 102.88 1076.00
Contingencies and PS
27 L.S. 128.00
charges
200000.00
P.U.G.F = 2017-18
Repairs and Improvements the M.S quarters at Anthiyur BDO office compound H/o. Anthiyur
The EOB quarters had been constructed above 40 years. This quarters had been maintained
above 10 years. Now the quarters is in repairable condition. Hence the quarters will be maintain for
the further usage condition. The expenditure will be met with Panchayat Union General Fund during
2017-18. In this basis the estimate has been prepared.
1 Wall crack will be plastered in C.M. 1:5 mix - 12 mm thick after removal of exisiting cement plaster.
Ceiling crack will be plastered in C.M. 1:3 mix - 10 mm thick after chipping the exisiting cement
3
plaster.
Roof top new slanding weathering coasr tiles with C.M.1:3 mix mixed with oiled motor and existing
4
tiles will be pointing with C.M.1:3 mix mixed with oiled motor.
Floor finish will be provided with Ceramic floor tiles of size 305x305x6 mm in C.M. 1:3 mix after
5
chipping the flooring concrete.
Bath, W.C and Kitchen wall will be finish with colour glazed tiles of size 300x200x6 mm in C.M. 1:2
6
mix after clean removal of cement plaster.
Ceiling will be painted with white wash two coats, Inner walls will be painted with wo coats of Oil
7 bound distember over a priming coat and Outer walls will be painted with two coats of Exterior
emulsion paint over a priming coat
The New Steel door - 3 Nos will be provided for WC, Bath & Outer way after remooving the
8
dismantled wooden door.
The old wooden doors, Windows, The old iron grill gates and New iron steel doors will be painted
9
with two coats of enamel painting.
10 The Lump sum provision are provided for the following items,
i). Provision for Kitchen slab & sink
ii). Provision for AC sheet roof at Opne terrace area
iii). Provision for Leach pit - 1 No
iii). Povision for Name board
iv). Photography charages and Contingecies and ps charges
The T.N.P.W.D. schedule of rates for the year 2017-18 are adopted for the Erode district. The Total
Estimate cost is Rs. 200000.00 (Rupees Two Lakhs) only and this cost will met with P.U.G.F scheme - 2017-18.
0.00 page -1
P.U.Form no.55-A Voucher No…………...
FINAL CONTRACT CERTIFICATE
Amount of Estimate:- 0.00
Name
of 0
Work:-
Remarks
Executed of Amount
supplied ITEMS
Rate Per
up to since last M.Book No:- /2016-17 since last
up to date
date certificate certificate
1 2 3 4 5 6 7 8
Rs Ps Rs Ps Rs Ps
#REF!
222.00 222.00 0
Rm Rm #REF! Rm #REF! #REF!
As per page
0.00 0.00 0
Rm Rm 0.00 Rm 0.00 0.00
As per page
Pointing with cement mortar 1:3 to full depth of
tiles using crudeoil 10% by weight of cement
including cost and conveyance of all materials
to site and all labour charges etc complete
123.50 123.50
Over roof - Verandah 0.00 Rm 0.00 0.00
Rm Rm
As per page
1.00 1.00
10.6 - No #VALUE! #VALUE!
No No
As per page
C/O #VALUE! #VALUE!
Page - 2
Quantity
Remarks
Executed of Amount
supplied ITEMS Rate Per
up to since last since last
up to date
date certificate certificate
1 2 3 4 5 6 7 8
Rs Ps Rs Ps Rs Ps
Brought Forward #VALUE! #VALUE!
COMPLETION CERTIFICATE
Certified that the work has been completed in accordance with the plan and estimate in a substancial
and satisfactory manner.
Pay Rupees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Station . . . . . . . . . . . . . . .
Date . . . . . . . . . . . . . . .
Received Rupees . . . . . . . . . . . . . . . . . . . . . . . . ( . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . ) only as final payment in settlement of all demands … . .. . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . .
CHAIRMAN
COMMISSIONER
0.00 page -3
P.U.Form no.55-A Voucher No…………...
FINAL CONTRACT CERTIFICATE
Amount of Estimate:- 0.00
Name
of 0
Work:-
Quantity
Remarks
Executed of Amount
supplied ITEMS
Rate Per
up to since last M.Book No:- /2016-17 since last
up to date
date certificate certificate
1 2 3 4 5 6 7 8
Rs Ps Rs Ps Rs Ps
Brought Forward #VALUE! #VALUE!
65.88 65.88
Cum Cum 2.40 Cum 158.11 158.11
As per page
123.50 123.50
Window soffits - WW #REF! Rm #REF! #REF!
Rm Rm
As per page
65.88 65.88
0 2.75 Cum 181.17 181.17
Cum Cum
As per page
As per page
Bill Bill Towards the charges for Photgraphic Bill 0.00 0.00
As per page
C/O #REF! #REF!
Page - 4
Quantity
Remarks
Executed of Amount
supplied ITEMS Rate Per
up to since last since last
up to date
date certificate certificate
1 2 3 4 5 6 7 8
Rs Ps Rs Ps Rs Ps
Brought Forward #REF! #REF!
Pay Rupees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Station . . . . . . . . . . . . . . .
Date . . . . . . . . . . . . . . .
Received Rupees . . . . . . . . . . . . . . . . . . . . . . . . ( . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . ) only as final payment in settlement of all demands … . .. . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . .
Witness . . . . . . . . . . . . . . . . Resolution . . . . . . . . . . . . . . . Dated . . . . . . . . . 200 Payee
...............
CLASSIFICATION Amount
Head of Account Rs. Rs
CHAIRMAN
COMMISSIONER
COMPLETION REPORT SHOWING THE DIFFERENCE BETWEEN THE ORIGINAL ESTIMATE AND BILLS
2
#REF!
5
0
Sqm 0.00 #VALUE! 123.50 0.00 0.00 #VALUE! #VALUE! As per actuals
Over roof - Verandah
Rm Rm
0.84
Plain Cement concrete 1:4:8 mix using 40mm ISS metal including cost and
2 conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
Bed foundation 1 x 1 1.05 0.80 0.15 0.13
0.13
B.W masonry in C.M. 1:5 mix using new good country including cost and conveyance
3 of all materials to site and all labour charges for mixing, laying and curing etc
complete.
Kiskon bed 1 x 1 1.00 0.70 0.85 0.60
1.40
Plastering with cement mortar 1:5 mix to 12 mm thick including cost and
4
conveyance of all materials to site and all labour charges etc complete
Bed all round 1 x 1 3.20 - 1.30 4.16
4.16
4.16
7718.00
Sub Estimate
NAME OF WORK : Construction of Borewell Safety Bed
Estimate amount :Rs: 1759 /-
DETAILED ESTIMATE
S
N Describtion of work No L B D QTY Amount
O
Earth work excavation and depositing on bank with in initial lead of 10 m and initial
1 lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with
small sized boulders and hard gravelly soil as per SS 20B
Bed foundation 1 x 1 0.60 0.60 0.45 0.16
Deduct Bre well -0.25 x 3.14 0.165 0.165 0.45 -0.01
0.15
Plain Cement concrete 1:4:8 mix using 40mm ISS metal including cost and
2 conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
Bed foundation 1 x 1 0.60 0.60 0.10 0.04
0.04
B.W masonry in C.M. 1:5 mix using new good country bricks including cost and
3 conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
Kiskon bed 1 x 1 0.60 0.60 0.80 0.29
0.27
Plastering with cement mortar 1:5 mix to 12 mm thick including cost and
4
conveyance of all materials to site and all labour charges etc complete
Bed all round 1 x 1 2.40 - 0.80 1.92
2.28
1.08
NAME OF WORK : Construction of 2000 litre PVC tank bed with PVC Tank
1.00
Earth work excavation and depositing on bank with in initial lead of 10 m and initial
2 lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with
small sized boulders and hard gravelly soil as per SS 20B
1.73
Plain Cement concrete 1:4:8 mix using 40mm ISS metal including cost and
3 conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
Tank bed foundation 1 x 1 1.70 1.70 0.10 0.29
0.44
RR masonry in C.M. 1:5 mix using new rough stones and bond stones including cost
4 and conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
4.91
Plain Cement concrete 1:2:4 mix using 20mm ISS metal including cost and
5 conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
Over tank bed 1 x 1 1.70 1.70 0.10 0.29
0.29
(OR) 0.29 Cum at Rs 4558.94 / Cum 1322.00
Brick work in cement mortor 1:5 mix using country bricks including cost and
7 conveyance of all materials to site and all labour charges for mixing, laying and
curing etc complete.
Around the the tnak bed 1 x 1 1.70 1.70 0.115 0.33
0.26
Plastering with cement mortar 1:5 mix to 12 mm thick including cost and
8
conveyance of all materials to site and all labour charges etc complete
1.37
Plastering with cement mortar 1:5 mix to 20 mm thick including cost and
9
conveyance of all materials to site and all labour charges etc complete
9.36
Colour washing two coats using shell lime mixed with colour pigments
10 including cost and conveyance of all materials to site and all labour
charges etc complete
Tank bed all round 1 x 1 6.80 - 1.20 8.16
8.16
43083.00