timeline chart

The document outlines a detailed timeline for a research project, including tasks such as identifying research problems, formulating problem statements, and conducting a pilot study. Key milestones include literature review, ethics committee approval, data collection, and final editing, spanning from November 2024 to June 2026. The project culminates in the submission of research to MUHS and a research viva.

Uploaded by

sports news
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

timeline chart

The document outlines a detailed timeline for a research project, including tasks such as identifying research problems, formulating problem statements, and conducting a pilot study. Key milestones include literature review, ethics committee approval, data collection, and final editing, spanning from November 2024 to June 2026. The project culminates in the submission of research to MUHS and a research viva.

Uploaded by

sports news
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

TASK START DATE END DATE DURATION

IDENTIFYING 25/11/24 25/12/24 30 days


RESEARCH
PROBLEM
FORMULATING 26/12/24 04/01/24 10 days
PROBLEM
STATEMENT,
OBJECTIVES,
HYPOTHESIS
REVIEW OF 05/01/25 30/01/24 26 days
LITERATURE
PREPARATION OF 31/02/25 25/03/25 26 days
SYNOPSIS
SYNOPSIS 12/03/25 30/04/25 35 days
PRESENTATION
ETHICS COMMITTEE 01/05/25 05/05/25 5 days
APPROVAL
SUBMISSION OF 06/05/25 10/05/25 5 days
SYNOPSIS TO
UNIVERSITY
SUBMISSION OF 11/06/25 30/07/25 51 days
CHAPTER 1,2 AND 3
DEVELOP TOOL FOR 01/08/25 15/08/25 15 days
DATA
CONTENT VALIDITY 16/08/25 26/08/25 10 days
REPORT
RELIABILITY OF 27/08/25 04/09/25 9 days
RESEARCH TOOL
CONSULT 05/09/25 09/09/25 4 days
STATISTICAL
EXPERT
OBTAIN 10/09/25 12/09/25 3 DAYS
ADMINISTRATIVE
APPROVAL
CONDUCT PILOT 13/09/25 17/09/25 5DAYS

STUDY
ANALYZE DATA OF 18/09/25 01/10/25 13 DAYS

PILOT STUDY
MODIFY DESIGN IF 02/10/25 05/10/25 4 DAYS

NECESSARY
PILOT STUDY 06/10/25 09/10/25 4 DAYS

REPORT
SUBMISSION
FINAL STUDY DATA 10/10/25 15/11/25 36 DAYS

COLLECTION
SUBMISSION OF 16/11/25 30/11/25 15 DAYS

MASTER SHEET
CHAPTER 4 01/12/25 10/12/25 10 DAYS
CHAPTER 5 11/12/25 20/12/25 10 DAYS
FINAL EDITING OF 21/12/25 15/01/26 26 DAYS

ALL RESEARCH
RESEARCH 20/01/26 21/01/26 1 DAYS

PRESENTATION
ONLINE 22/01/26 31/01/26 10 DAYS

SUBMISSION OF
RESEARCH TO MUHS
RESEARCH VIVA 05/06/26 09/06/26 DAYS
DISSEMINATION OF 10/06/26 20/06/26 10 DAYS

RESEARCH