Method Statement of Installation of Rebars for Slabs
Method Statement of Installation of Rebars for Slabs
Suntrust Amadea
(Substructure)
Installation of
Reinforcement Steel Bars
for Slabs
1. TITLE
2. SCOPE OF WORK
2.1 General Description
2.3 Materials
2.3.1 List of materials:
Grade 60 Steel Bars
#16 G.I. Wires
2.3.2 Procurement, Storage and Handling Material
a. The reinforcement shall be ordered & procured from the approved cut & bend
sub-contractor / supplier with all necessary documentation as required.
b. On receipt of the material on site the reinforcement shall be checked against
the documentation to ensure compliance. Once the delivery order and mill certificate
have been stamped. Approved and accepted the material shall be stacked in the storage
yards / lay down area.
c. The storage yards shall be set up to ensure that the quality of the
reinforcement does not fall below acceptable limits before it’s placement at site. To
ensure this:
d. Keep material off the ground by supporting by timber / concrete pad at all
times.
e. Keep material covered whenever possible.
f. Handle and stack material to prevent deformation.
2.4 Site Planning and Preparation
2.4.1 Daily Preparation
a. Always check and verify the actual site condition prior to activities.
b. Verify manpower, status and condition of materials tools & equipment necessary
during execution.
c. Check with representative from Main Contractor, all materials for use are in
compliance with the approved specifications and the activities are guided by approved
method statement.
d. Check all workers daily before reporting to site and inspect wearing complete
Personal Protective Equipment.
f. Prepare daily work permit, Daily Safety Task Instruction (DSTI) sheet and conduct
daily Tool Box Meeting with the workers in order to prevent an unwanted incident.
h. Coordinate with the associated parties if there are any concerns related to the
work location.
i. Check daily all the tools and equipment to be use on working to prevent any
unwanted accidents during implementation.
j. Every work place must ensure proper housekeeping before leaving the activity
area, all tools are on proper place and secure the materials from deterioration or damaged.
k. Implement the ZERO ACCIDENT PROGRAM protocol every time on site.
l. Due to the work shall be held at the Construction Area, scheduling as well as the
time of start and finish shall be dictated by the Contractor.
m. All workers shall have preapproval and permits to enter to the Construction Area.
The passes should be worn at all times and/or readily available to present whenever demanded by
proper authorities.
n. All incoming materials at the site location shall be screened and should follow the
procedures provided before mobilizing.
o. Supervision must be present at all times in the place of work while commencing
any activity.
b. Before commencement of any work activity, coordinate with the contractor for daily
work permit approval.
c. Check and verify all activities if there shall be implications to associated parties.
Inform immediately the person in charge through a formal letter informing the activities required to be
undertaken.
d. Request for Information must be submitted to the Contractor for coordinating with
other Contract Package Contractors and also to clarify and discrepancies from pan to actual site
condition, solve issues and proper information support.
f. Ensure that all activities are in compliance with the Contractor’s HSE Policy.
The straight bars received at site will be stacked in the steel yard. The steel
reinforcement shall be stacked clear off the ground and covered with polyethylene
sheet to protect from moisture.
As per the construction program and the priority, the cutting and bending of steel
reinforcement for that particular structural element will commence as per the
approved shop drawings and bar bending schedule or BBS.
The cut length will be marked with a steel measuring tape, as shown in the BBS.
The bar will be cut with a shear line cutting machine.
For straight bars, after cutting the required numbers, it will be bundled and tagged
with bar mark number and stack for delivery to site.
For stirrups and cranked bars, the cut bars will be taken to the bending machine and
bend as per dimensions in the BBS. During bending process re-check randomly with
a template for dimensions.
Upon completing the required numbers, bundle and tag the bars with bar mark
number and stack for delivery to site.
b. Fixing of Reinforcement:
c. Site Installation:
Setting out shall be marked by the surveyor prior to proceeding.
Necessary scaffolding shall be provided for binding fixing steel.
Prefabricated steel shall be placed in position as per approved shop drawings of the
related structural member.
Approved 1.6mm dia. Galvanized/black annealed mild steel wire shall be used to tie
reinforcing bar. The ends of the wire shall be bending back away.
Spacer blocks of approved type will be used to maintain the cover.
Support the reinforcing bar by approved spacers appropriately to prevent
displacement during concreting operation. The thickness of cover block shall be as
per approved shop drawings or specifications.
While fixing of steel reinforcing bars, care will be taken to see that proper concrete
cover is available for bottom, top, sides, and edges.
Wherever reinforcements are placed in two or more layers, minimum 25mm spacer
shall be placed between layers. All bars in upper layers must be placed directly
above those in the bottom layers.
All embedment or inserts to MEP shall be placed as per approved shop drawings.
Steel around MEP openings and sleeves shall be provided as per approved shop
drawings.
Necessary dowel bars shall be provided wherever necessary as per approved shop
drawings.
Proper anchorage of bars for slabs shall be provided as per approved shop
drawings and specifications.
All reinforcement must be cleared to ensure that it is free from all oil, dust, and,
deleterious materials.
After the completion of installation of steel reinforcement and MEP inserts inspection
and approval shall be done prior to concrete pouring.
2.5.6 Inspection
a. Project Director
i. Responsible in overall run and progress of the entire project.
ii. Responsible and controls accounting, general affairs and report the
progress of work to the Contractor.
iii. The one responsible on project planning and scheduling. Also, he
will be responsible on all administrative matters including establishing
project organization.
iv. Checks and controls all the documents such as shop drawings,
construction schedules, progress billing statements, submittals, etc.
v. Assigns the Design Manager to overlook overseas logistics, design
and conceptualization and solving issues with regards to materials and shop
drawings.
vi. Assigns the General Manager to establish policies with regards to
personnel recruitment, promote Safety and Health, to check the quality of
works and all administrative matters.
vii. Checks the works of all his staff to provide the necessary work and
accomplishment needed.
viii. The Project Director is ultimately responsible for HS&E Policy
Performance and must champion zero accidents at all staff meetings and in
the field.
b. General Manager
i. Responsible on assisting the Project Director for controlling the work
of the project.
ii. Responsible on project planning and project scheduling. Also he will
be responsible on all administrative matters including establishing project
organization.
iii. Responsible on safety matters and related issues. Also,
responsible in orienting and reminding all his staff safety before reporting
to site and also aware on actual site condition.
c. Project Manager
i. Responsible on checking all shop drawings before submission to the
Contractor. Also responsible in coordinating to the Contractor for the
associated work schedule and activities.
ii. Checks all QA/QC matters and informing the Project Director for
awareness.
iii. Responsible on studying all cost variance and Scope of Works.
iv. Coordinating all Shop Drawings to Contractor for approval before
turnover to Project Engineer.
v. Responsible on all design related activities.
vi. Responsible on checking the material availability to the procurement
department.
vii. Ensuring the field personnel are working to the latest available
information.
d. Site Engineer
i. Assists the Project Director and Design Manager in executing the
activities. Responsible on overlooking the activities on the project and
preparing work progress.
ii. Ensures all activities for implementation is as per approved
drawings. Checks the Method Statement procedures are properly executed.
iii. Responsible on all work safety during execution.
iv. Conducts daily toolbox meeting at site to all workers prior the start
of activities.
v. Coordinate the activities to other trade contractor before
implementing at the site.
e. Design Engineer
i. Responsible on all drawings submittals, as-built plans and updating
all changes occurs during implementation.
ii. Coordinate from time to time to the Contractor’s Design Department
for any changes on the plans.