Method Statement for Installation and Testing of Earthing and Lightning Protection System R01
Method Statement for Installation and Testing of Earthing and Lightning Protection System R01
METHOD STATEMENT
METHOD STATEMENT
00 01-08-2023 Submittal for Approval QA/QC Engineer QA/QC Manager Project Director
01 12-09-2023 Submittal for Approval QA/QC Engineer Project Director Project Director
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 2 of 21
CONTENT
1. INTRODUCTION........................................................................................................................................5
2. SCOPE OF WORK:.....................................................................................................................................5
3. DEFINITIONS & ABBREVATIONS:........................................................................................................5
4. REFERENCES:............................................................................................................................................6
5. ROLE AND RESPONSIBILITIES:.............................................................................................................6
6. WORKING ACCESS:............................................................................................................................11
7. LIGHTING:..............................................................................................................................................11
i. Safety Lighting:..........................................................................................................................................11
ii. Task Lighting:.............................................................................................................................................11
8. PLANT & EQUIPMENT:.......................................................................................................................11
i. General:.......................................................................................................................................................11
iii. Personal Protective Equipment:..............................................................................................................12
iv. Power:.....................................................................................................................................................12
v. Working Platforms:....................................................................................................................................12
9. MATERIALS & DRAWING Ref.:.............................................................................................................12
10. SEQUENCE / METHOD OF WORK:.........................................................................................................13
11. PROGRAMME..............................................................................................................................................14
12. RISKS & CONTROLS:...........................................................................................................................14
i. Hazards / Risks.........................................................................................................................................14
ii. Control Measures / Permits.....................................................................................................................14
iii. 3rd party Protection..............................................................................................................................14
13. TECHNICAL INFORMATION.............................................................................................................14
14. EMERGENCY ARRANGEMENTS..........................................................................................................14
i. General........................................................................................................................................................14
ii. Fire Precautions..........................................................................................................................................15
iii. Communication...........................................................................................................................................15
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 3 of 21
15. TRAINING.................................................................................................................................................15
16. SUPERVISION..........................................................................................................................................15
17. WORKING HOURS................................................................................................................................15
18. HOUSEKEEPING......................................................................................................................................15
19. OTHER INFORMATION..........................................................................................................................16
20. ATTACHMENTS.......................................................................................................................................16
1. INTRODUCTION
The Purpose of this Method statement is to define the typical sequence of works for the installation of earthing
lightning protection system. This Method Statement Provides the Controlled Sequence and methodology that will be
used for installation of earthing and lightning protection system and related associated works.
2. SCOPE OF WORK:
2.1 Scope of this method statement includes sequence of works in supply, installation, testing, and
commissioning of complete earthing and lightning protection system as per project design guidelines for the
project Wynn Marjan Island- Ras Al Khaimah and it consists of terminal networks, thermos weld joints,
exothermic welding, Arc welding, earth continuity conductors, connection to structural reinforcement and
all related accessories including bonding and terminations.
2.2 This procedure is to be read in conjunction with relevant ITP and check lists outlining the responsibility and
quality verification to be carried out by the various parties.
MS Material Submittal
MRS Material Reference Schedule
IR Inspection Request
PSSP Project safety security plan
TC Tower crane
MC Mobile crane
MIM Manufacturer instruction manual
4. REFERENCES:
1. Project Quality Plan (PQP)
2. Project Safety & Security Plan (PSSP)
3. Reference Spec.
4. Site Establishment / Logistic Plan.
5. Method statement for Lifting Operations (Submitted Separately)
6. Other references (Shop drawings, design calculations, RFI etc.)
7. Local Authority regulations
Construction Manager:
Quality Manager:
• Coordinate with team, subcontractors, and Consultants - to ensure the progress of material submittals
is as per schedule.
• Establish and Implement the Material and work Inspection procedure for the project. Monitor
inspection status, analysis status reports and trend analysis, implement corrective actions for the
variations from plan.
• Ensure the non-conforming materials are tagged and removed from site and provide the rejected
material inspection report to commercial and procurement for corrective actions.
• Organize/Manage offsite inspections in coordination with team, Consultant, and subcontractor
/supplier / manufacturer.
• Review subcontractor’s prequalification to verify the capability/compliance to project requirements
and provide recommendation.
• Establish and Implement procedures for monitoring and controlling subcontractor’s quality of work
including site surveillance, recording the deficiencies and continuous follow up with construction tea
for closing the recorded deficiencies.
• Close Site Instructions/non-conformance reports from consultant and conduct the review of the Site
instruction/corrective action to verify the scope for a potential claim.
• Coordinate with subcontractor, team, and consultant for implementing the corrective actions and
closing the site instruction /NCR.
• Coordinate with subcontractors for the timely submission of material submittals, test reports and O &
M manual for the project.
• Prepare the closeout documentation requirements for the project and manage the
Preparation / compilation and submission of project closeout documents to consultant.
• Coordinate with consultant, and subcontractor for testing and commissioning inspections.
• Establish and implement the procedures for snagging /de-snagging at project site. Coordinate with
Consultant and subcontractor to complete the snagging and de-snagging inspections as per project
schedule.
• Provide accurate progress updates of material submittals to planning department weekly and monthly.
• Provide accurate status of material inspections to planning department weekly.
• Present weekly material submittal status, weekly look ahead, status of site instructions to
management and implement the actions decided for any variations from plan.
• Report to commercial department regarding the poor performance of subcontractor in quality or any
other concerns, which needs to be taken contractually.
• Organize trainings on special systems/new procedures introduced in the project.
• Lead, motivate, Train, and develop QA QC team.
Design Manager:
Logistic Manager:
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 8 of 21
Site Engineer:
QA/QC Engineer:
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 9 of 21
Site Surveyor:
• Take the as built for all construction items after casting concrete
Responsible persons for each stage of work are marked against each phase of work in work sequence section.
6. WORKING ACCESS:
The access / egress for the construction vehicles for the installation of activities shall be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all
activities.
All Access routes through the site to be properly maintained to minimize interference with adjoining roads.
Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during
operations. Flagman will be provided at critical locations.
7. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.
i. General:
Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools and
equipment shall be checked visually prior to use.
Only authorized applicator approved and trained by the manufacturer to install manufacturer's
products.
All Operators shall be trained and certified by the 3rd party where required.
No defective plant and equipment shall be allowed to use on site.
3 Hammer
4 Hacksaw Blade
5 Set of Spanner
6 Measuring tape
7 Earth Tester
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 11 of 21
9 Denso Tape
11 Powdered metal
iv. Power:
The electric supply used on site for power tools shall be 110/230 volts as per voltage rating of the
equipment. Higher voltage power shall be provided to site welfare areas if necessity arises.
v. Working Platforms:
The working platforms for the task shall be firm and stable.
The elevated working platforms for the activity (if used) shall be provided by means of cup lock
scaffold system.
The scaffolds for the activity shall be built by competitive scaffolders trained by third party.
The built scaffolds shall be inspected and signed off by a third party trained inspectors / supervisors.
Were necessary access shall be provided by means of scaffold.
The working platforms shall be used as only platforms for working and shall not be used for loading
heavy material or equipment on to it.
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
Submit material submission for all materials related to the task for Engineer
approval and obtain approval. PD/DPD/ PROJECT
As per approved material submittal and IFC drawings/specifications PE/QCM/ APPROVAL
prepare/submit shop drawings. HSEM
Submit MIR for the delivered materials on site.
Method statement, inspection & test plan, cand Risk Assessment to be
submitted for Engineer approval and obtain approval.
Identify, Quantity & Ensure all risk managed in this method statement & residual
risk are acceptable.
Implement the risk mitigation actions as per the approved risk assessment and
ensure that the risk is as low as reasonably practicable. Project
Stores In- guidelines/
10.2 PRE - CONSTRUCTION ACTIVITIES: Charge/QC DO/MIR/R
M/HSEM A
Ensure all required document and material approvals have been obtained.
The materials received at site shall be verified as per the approved Material
Submittal, inspected, and stored in the designated area as per manufacturer
recommendation.
Submit MIR for delivered materials on site.
Ensure that all materials are approved prior to using the material on site.
Ensure that method statement, ITP and shop drawing approved prior to starting
any activity on site.
Adequate lighting to be provided in the work areas to execute the task.
All risk hazards on operations to be identified and precautions implemented.
Ensure that all necessary personnel, plant, equipment, and services are required.
for the works is in place.
Implement employee induction procedure and toolbox talks for ongoing risk
assessment and identification of hazards.
Ensure RFI is raised and approved for technical clarification and modification
as/if required.
Ensure the work area is clear and safe for working. Project
PM/PE/SE/ Specs with
QCM/HSEM Design
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 13 of 21
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
The whole of the earthing and bonding shall be installed and tested in
accordance with the requirements of BS 7430, FEWA/EWE regulations, IEE wiring
regulations and specifications.
The earthing system for the project is considered pile earthing as per the design
drawings.
Installation of earthing system works carried out as per approved shop drawings
and manufacturer recommendation.
Identify the pile rebar used for earthing system as per the drawing and necessary
coordination with structural team.
The cross section of all earthing conductors shall be maintained as per design
drawing and authority requirement.
Earthing network classified into group of piles dedicated for
TX/HT/RMU body (Normal, Emergency and Business critical)
TX Neutral (Normal, Emergency and Business critical)
MDB Earthing (Normal, Emergency and Business critical)
ICT Earthing (Primary Data center and Secondary Data center)
ICT earthing (Telephone rooms)
Bare copper conductor shall be installed embedded in raft concrete to make
earthing network as per approved shop drawing.
The looping between the piles will be done through bare copper conductor and
the connection between rebar to cable shall be done with exothermic welding as
per approved shop drawing and manufacturer recommendation.
The cable from pile cap to earth bar (test point) shall be installed as PVC
insulated cable directly embedded screed and the connection between rebar to
cable will be done with exothermic welding.
The location earth bar test point will be in basement 2 as per the approved shop
drawing.
Continuity of earth connections shall be checked for every link in the network.
On completion of pile earthing, resistance and continuity shall be checked and
ensured to be in limits as per standards. The reports shall be submitted for
approval.
The earthing system shall be efficiently bonded back to all main switchboards by
using approved materials.
Protect all exposed grounding conductors from mechanical damage.
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 14 of 21
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
Installation work shall be carried out as per approved shop drawings and in
compliance with project specification.
Installation of lightning protection and Bonding system to be coordinated with
installation of other building systems and components, including electrical
wiring, supporting structures, metal bodies requiring bonding to lightning
protection system, facades, curtain, and structural pile cabs and building
finishes.
Identify and ensure the pile rebars used for lightning protection as per the
approved shop drawing and necessary coordination required with structural
team for the location of structural piles dedicated for lightning protection
system.
From the identified pile select two resistant rebars as per the approved shop
drawings and these two rebars to be used to connect with 2 dedicated rebar on
structural column as lightning protection system down conductor as shown in
approved shop drawing.
Mark the two rebars used for lightning protection down conductor from pile to
roof.
Ensure the connection between the pile rebar to test point shall be carried out
as per manufacturer recommendation such as
Exothermic welding to be carried out between the rebar and cables
shall be as per approved shop drawing detail / manufacturer
recommendation in pile rebar.
The exothermic welded cables from pile dedicated rebar shall be
connected to the test point @ 1000mm above the FFL as shown in
approved shop drawing.
Looping between the piles to be carried out with rebar welding between the
piles through arc welding.
All earthing connections shall be made after cleaning the surface thoroughly
tightness checks for each connection shall be performed.
Continuity of earth connections shall be checked for every link in the network.
On completion of pile earthing, resistance and continuity shall be checked and
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 15 of 21
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
The Lightning arrestor network consists of copper tape (25x3) installed on the
roof in a mesh. The size of the mesh (5m x 5m) depends on the level of
protection obtained from risk analysis carried out by specialist and approved by
consultant (Level I protection obtained from Risk Analysis as per BSEN62305-II).
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 16 of 21
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
The connection from each down conductor to the copper tape on the parapet is
made as per approved shop drawing.
Fix the proprietary clips and clamps conforming to BSEN50164 to firmly fix the
air termination network of copper tapes on the roof.
The network of approved size tapes shall be installed across the roof area and
interconnected with the down conductors placed at appropriate intervals as per
BSEN62305.
Lightning arrestor shall be installed as per details shown in the approved
drawing.
A visual inspection of the installation shall be conducted in the presence of the
specialist.
All enclosures equipment exposed conductive parts, extraneous conductive
parts, metallic trunking conduits, metallic cable trays and other metals work,
other than any live part, forming protection to or part of the electrical
installation, including apparatus and appliances to be effectively bonded to
earth.
Wherever protection of internal system against over voltages caused by lightning
discharges requires SPD’s (surge protection devices) these shall be conform to
BSEN 62305-part 4
All the main panel boards must have a service entry current surge protection
device of type 1 fitted in, as per the BSEN62305.
10.3.5 Testing
The resistance of each of the earthing systems on its own, to the mass of the
earth will not exceed the following values measured with an approved and
calibrated Earth Reading instrument.
General electrical earthing : less than 1 ohm
Lightning protection earthing : less than or equal to 10 ohms
Instrument clean earth : less than 1 ohm
Stick the auxiliary earth spikes P and C in to ground deeply or use a rebar of
nearby pile and they should have aligned at the interval of 5-10 M from the
rebar under test E. Connect the green lead wire to the rebar under test, the
yellow wire to the auxiliary earth rebar P and red wire to the auxiliary earth
rebar C from terminals E, P and C of the Instrument.
Pile Rebar is used as an earth electrode for both earthing & Lightning protection
system. If the earth resistance Value is not satisfactory, the process of adding
further earth electrodes shall be continued till the expected resistance value of
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 17 of 21
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
less than 1 ohm is achieved or general electrical earthling & 10 ohms for
lightning protection.
Calibrated instruments shall be used for testing of earthing and lightning
protection.
Grounding conductor continuity and all bonding connection shall be tested and
recorded.
All Piles shall be tested by using an earth tester and records shall be maintained
and submitted to the consultant for approval.
Clean all the unwanted construction debris / materials after the installation.
10.3.6.1 PILE REBAR TESTING for Earthing and Lightning protection system
Structural Pile rebar proposed as LPS and Earthing Electrode. The location of the
proposed piles and the test link locations are shown in the approved earthing
and LPS Layout. Earth resistance measurement for the reinforced concrete piles
used as earth electrodes shall be tested & recorded.
Minimum permissible earth resistance value for lightning protection is to <10
ohms for LPS and less than 1 ohm for earthing system.
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
Quality Control
Site Management and QAQC personnel should monitor the installation to ensure
it is done according to the approved drawings.
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 19 of 21
Reference/
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK Verifying
person
Document
Site Supervision personnel must ensure that the work fully complies with the
norms laid down as per specification in all respects.
11. PROGRAMME
i. Hazards / Risks
In addition to the requirements indicated in the guidelines, drawings, schedules, the work will be in accordance with
recommendations and requirements of the following standards, codes and bodies. The current editions of
publications being those applicable:
i. BS EN/IEC 62305 Protection against lightning
ii. BS EN 50164 Lightning Protection Components (LPC)
iii. BS 7671 Requirements for electrical installations, IET Wiring Regulations
iv. BS 7430 Code of practice for protective earthing of electrical installations.
v. BS 2784 and BS 970 BS for earthing material, solid copper rods and accessories.
vi. BS 951: 2009 Clamps for Earthing and bonding.
vii. BS 4444 Guide to electrical earth monitoring and protective conductor proving.
i. General
The Site HSE department shall be responsible to arrange and coordinate with site execution teams in
arranging Day & Night emergency procedures.
In case of any emergency the CRM will be informed about the emergency
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 20 of 21
Emergency assembly point shall be allotted and communicated to all the operatives in involved in the job
Ensure clear access to the emergency assembly area with signage’s in place.
No construction activity shall block the access leading to the emergency assembly point. In case of any
deviation the access has to divert and the same shall be communicated to all the operatives on site.
Fire extinguishers shall be put in place in each working zone and a clear access shall be provided to the
location.
All the operatives shall be trained for fire precautions on site.
A fire warden is appointed and trained from each team of operatives.
iii. Communication
The communication on site shall be through mobile provided by the contractor or by two-way wireless radio
systems.
15. TRAINING
Necessary safety or operational training shall be provided to the operatives involved in the activities.
16. SUPERVISION
18. HOUSEKEEPING
NA
PROJECT: WYNN MARJAN ISLAND MES REF NO: WAMI-ALM-EL-MES-00001
METHOD STATEMENT FOR INSTALLATION AND Rev : 01
TESTING OF EARTHING AND LIGHTNING PROTECTION Date : 12-Sep-23
SYSTEM
Page 21 of 21
20. ATTACHMENTS
1. Risk Assessment
2. ITP
3. Check lists and test report.