I. MES for Installation of PVC Conduiting Accessories

Uploaded by

mohamedyasarm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 16

MES Ref No.

: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev : 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 1 of 16

METHOD STATEMENT
METHOD STATEMENT TITLE

FOR
INSTALLATION OF
PVC CONDUITS AND ACCESSORIES

Rev Date Document Status Prepared By Reviewed by Approved by

00 28 Aug 2023 Submitted for Approval [QA/AC Engineer] [QA/QC Manager] [Project Director]
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 2 of 16

CONTENT

1. INTRODUCTION........................................................................................................................................5
2. SCOPE OF WORK:.....................................................................................................................................5
3. DEFINITIONS & ABBREVATIONS:........................................................................................................5
4. REFERENCES:............................................................................................................................................6
5. ROLE AND RESPONSIBILITIES:.............................................................................................................6
6. WORKING ACCESS:............................................................................................................................11
7. LIGHTING:..............................................................................................................................................11
i. Safety Lighting:..........................................................................................................................................11
ii. Task Lighting:.............................................................................................................................................11
8. PLANT & EQUIPMENT:.......................................................................................................................11
i. General:.......................................................................................................................................................11
iii. Personal Protective Equipment:..............................................................................................................12
iv. Power:.....................................................................................................................................................12
v. Working Platforms:....................................................................................................................................12
9. MATERIALS:.............................................................................................................................................12
10. SEQUENCE / METHOD OF WORK:.........................................................................................................13
11. PROGRAMME..............................................................................................................................................14
12. RISKS & CONTROLS:...........................................................................................................................14
i. Hazards / Risks.........................................................................................................................................14
ii. Control Measures / Permits.....................................................................................................................14
iii. 3rd party Protection..............................................................................................................................14
13. TECHNICAL INFORMATION.............................................................................................................14
14. EMERGENCY ARRANGEMENTS..........................................................................................................14
i. General........................................................................................................................................................14
ii. Fire Precautions..........................................................................................................................................15
iii. Communication...........................................................................................................................................15
15. TRAINING.................................................................................................................................................15
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 3 of 16

16. SUPERVISION..........................................................................................................................................15
17. WORKING HOURS................................................................................................................................15
18. HOUSEKEEPING......................................................................................................................................15
19. OTHER INFORMATION..........................................................................................................................16
20. ATTACHMENTS.......................................................................................................................................16

CONTRACTOR AUTHORIZED SIGNATORY

P.P
Praveen Mani Darrel Fletcher Tyron Holgate
QAQC MANAGER HSE MANAGER PROJECT MANAGER
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev : 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 4 of 16

1. INTRODUCTION

The Purpose of this Method statement is to define the typical sequence of works for installation of PVC conduits and
accessories. This Method Statement Provides the controlled sequence and methodology that will be implemented
for installation of PVC conduits, accessories, and related associated works.

2. SCOPE OF WORK:

2.1 The scope of this method statement includes sequence of works in supply, installation of PVC conduits and
accessories as required in Wynn Marjan Island- Ras Al Khaimah.

2.2 This procedure is to be read in conjunction with relevant ITP and check lists outlining the responsibility and
quality verification to be carried out by the various parties.

3. DEFINITIONS & ABBREVATIONS:

Client Wynn Marjan Island


Engineer Dewan
Main Contractor ALEC Engineering and Contracting L.L.C
Contractor ALEMCO Electro-Mechanical Contracting L.L.C
PD ALEC Project Director
DPD ALEC Deputy Project Director
PM ALEMCO Project Manager
APM ALEMCO Asst Project Manager
CM ALEMCO Construction Manager
QCM ALEC QA/QC Manager
DM ALEMCO Design Manager
SM ALEMCO Section Manager
QCE ALEMCO Quality Control Engineer
CRM ALEC Safety Manager
LS ALEC Surveyor
MEP ALEC MEP Coordinator
LM ALEC Logistic Manager
ITP ALEMCO Inspection and Test Plan
MSS ALEMCO Method Statement Submittal
QCP ALEMCO Quality Control Plan
TS Technical submittal Request
NCR Non-Conformance Report
ITL Independent Testing Laboratory
SD ALEMCO Shop Drawing
CD Contract Drawing Issued for Construction
CL Check List
RA Risk Assessment
MS Material Submittal
MRS Material Reference Schedule
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 5 of 16

IR Inspection Request
PSSP Project safety security plan
TC Tower crane
MC Mobile crane
MIM Manufacturer instruction manual

4. REFERENCES:
1. Project Quality Plan (PQP)
2. Project Safety & Security Plan (PSSP)
3. Reference Spec.
4. Site Establishment / Logistic Plan.
5. Method statement for Lifting Operations (Submitted Separately)
6. Other references (Shop drawings, design calculations, RFI etc.)
7. Local Authority regulations

5. ROLE AND RESPONSIBILITIES:

Construction Manager:

The construction manager will be responsible for following activities:


• Ensure high standard of quality workmanship on site
• Ensure total Human Resource Management on site
• Contract improvement actions
• Safeguard and promote ALEC’s interests when dealing with subcontractors and suppliers:
• Ensure contract programme deadlines are met and exceeded where possible:
• Materials and storage management:
• Site Administration

Quality Manager:

The quality manager will be responsible for following activities:


• Plan, Organize and Manage the QA QC team for the implementation of project quality management
system.
• Develop and implement the Project Quality Plan.
• Develop and implement Internal and External Audit schedule and conduct /organize audits as per the
schedule.
• Coordinate with third party laboratories for initial testing activities and material testing. Verify the test
reports for the compliance to specification and submit to consultant.
• Develop and establish a comprehensive schedule of all planned material submittals based on the
project schedule.
• Review and ensure the detailed material submittal schedule from subcontractor is in compliance with
project schedule.
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 6 of 16

• Coordinate with team, subcontractors, and Consultants - to ensure the progress of material submittals
is as per schedule.
• Establish and Implement the Material and work Inspection procedure for the project. Monitor
inspection status, analysis status reports and trend analysis, implement corrective actions for the
variations from plan.
• Ensure the non-conforming materials are tagged and removed from site and provide the rejected
material inspection report to commercial and procurement for corrective actions.
• Organize/Manage offsite inspections in coordination with team, Consultant, and subcontractor
/supplier / manufacturer.
• Review subcontractor’s prequalification to verify the capability/compliance to project requirements
and provide recommendation.
• Establish and Implement procedures for monitoring and controlling subcontractor’s quality of work
including site surveillance, recording the deficiencies and continuous follow up with construction tea
for closing the recorded deficiencies.
• Close Site Instructions/non-conformance reports from consultant and conduct the review of the Site
instruction/corrective action to verify the scope for a potential claim.
• Coordinate with subcontractor, team, and consultant for implementing the corrective actions and
closing the site instruction /NCR.
• Coordinate with subcontractors for the timely submission of material submittals, test reports and O &
M manual for the project.
• Prepare the closeout documentation requirements for the project and manage the
Preparation / compilation and submission of project closeout documents to consultant.
• Coordinate with consultant, and subcontractor for testing and commissioning inspections.
• Establish and implement the procedures for snagging /de-snagging at project site. Coordinate with
Consultant and subcontractor to complete the snagging and de-snagging inspections as per project
schedule.
• Provide accurate progress updates of material submittals to planning department weekly and monthly.
• Provide accurate status of material inspections to planning department weekly.
• Present weekly material submittal status, weekly look ahead, status of site instructions to
management and implement the actions decided for any variations from plan.
• Report to commercial department regarding the poor performance of subcontractor in quality or any
other concerns, which needs to be taken contractually.
• Organize trainings on special systems/new procedures introduced in the project.
• Lead, motivate, Train, and develop QA QC team.

Design Manager:

The design manager will be responsible for following activities:


• Understand the conditions of the contract with the client.
• Liaise with client to determine factors affecting planning of the MEP Services, such as budget, purpose
and function.
• Prepare detailed drawings and submit these for approval by relevant planning authorities.
• Ensure all MEP works is carried out to the specific requirements of the client.
• Coordinate with other professionals, such as contractors, architects, Engineers, and planners, to
ensure that work is completed to the highest standards and that the highest quality product is
delivered to the client.
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 7 of 16

• Oversee all the tasks of the design team and to provide motivation and support for the team.
• Review and detail shop drawings for construction plans.
• Render design ideas in form of paste-ups or drawings.
• Use computer-aided drafting (CAD) and related software to produce construction documents.
• Maintain an awareness of developments in the field of architecture so that up-to-date and accurate
advice can be given to clients.
• Coordinate with the local authorities where necessary.

CRM Advisor / Safety Manager:

The CRM Manager will be responsible for the following activities:


• Will train construction personnel in safe work practices on the job site.
• Will prepare report as required by the Project Leader.
• Will monitor, inspect, and report on unusual and/or serious accidents which may occur on the job sit.
• Will submit written evaluation and recommendations direct to the Project Leader.
• Will be based on site and manage the SAFETY performance of all project team personnel and
operative.
• Will assist the managers in overseeing SAFETY related activities that are associated with any of ALEC
Sub-Contractor personnel, who are working on the project.
• Will coordinate and supervise safety advisors and site clinic.
• Will assist to prepare ‘lifting operations’ plan, ‘Fire and emergency’ plan and coordinate for its
implementation.
• Will ensure that method statement/risk assessment is carried out.
• Will ensure that ‘Emergency Evacuation’ training is carried out. Monitor for drill compliance and
recommend areas of improvement.
• Will ensure that workplace monitoring is implemented and carried out by the allocated managers.

Site Manager / Section Manager:

The Site Manager will be responsible for following activities:


• Will implement engineering systems, documentation, and controls by compliance with Healthy Safety
Environmental and Industry standards, including Temporary works.
• Will go through the project scope of work such as drawings, specification, Quality Plans, project
program
• Will check engineering drawings and specification to identify and resolve design conflicts
• Will prepare method statements, ITP’s, and risk assessments in accordance with ALEC Quality Systems
as and when required
• Will ensure all technical information is available when required for delivery of design or construction
• Will raise and process NCR immediately
• Will provide effective supervision and guidance to less experienced engineering staff
• Will actively manage safety and quality on site ensuring side wide compliance and not just their area of
operation.

Logistic Manager:
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 8 of 16

The logistic manager will be responsible for following activities:


 All aspects of the logistics supply chain
 Plan site set-up to move labour, plant, and materials around site efficiently (e.g., hoarding, gates, site
accommodation, cranes, hoists, security, temporary services, material delivery and waste management
strategy, catering).
 Plan internal and external logistics routes through the project phases
 Pre-plan the usage of key assets to meet the needs of program.
 Responsible for all traffic management internally and externally and road network cleanliness.
 Produce daily, weekly, and long-term movements plans.
 Control materials in and out of site.
 Organize resources to enable contract deadlines to be achieved.
 Ensuring the project safety policies are followed.
 Development and optimisation of site logistic solutions to meet the needs of the project.
 To manage the movement of people, good and equipment at the construction site.
 Define and organise all site signage.
 Coordination with construction team for logistic activities in support of the construction program.

Site Engineer:

The site engineer will be responsible for following activities:


• Will go through the project scope of work such as drawings, specification, Quality Plans, project
program.
• Will supervise site mobilization and demobilization for each activity under his / her control
• Will formulate work breakdown structure and document Sub-Contractor package including estimates
of man hours and cost.
• Will oversee and administer Forman’s daily report to ensure direct labour efficiency.
• Will ensure periodic reports are transmitted to Project Leader.
• Will track and report material delivery.
• Will ensure SAFETY requirements are maintained.
• Will co-ordinate with Sub-Contractor to ensure interface problem are avoided and maximum Quality
work achieved.
• Will prepare and control inspection requests, ITPs, method statements, risk assessment, check sheets
and any other quality requirements in conjunction with the project quality representative.
• Will ensure that the requirements of the ALEC Quality Procedures and followed and adhered to it
• Will raise and process NCR.
• Will help create a site culture of best practice regarding safety, housekeeping, workmanship, and
waste management.
• Will assist supervisors and managers to allocate correct resource to activities and to review and report
on the same.
• Will create an open site culture where operative and foreman can raise concerns and discuss matters
with the mangers and administer result.
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 9 of 16

QA/QC Engineer:

The QA/QC Engineer will be responsible for the following activities:


• Review the ITPs for each activity along with method statement from, ALEC direct works and sub-
contractors works, to verify the compliance to Project requirements. Ensure the subcontractors are
adhering to their ITP and inspections are raised accordingly.
• Conduct day to day site surveillance, identify, record, and communicate the deficiencies to team to
avoid reoccurrence
• Conduct work inspections in co-ordination with subcontractor, ALEC team and consultant to verify the
compliance to drawings and specifications, Ensure the records are maintained
• Coordinate and Conduct Material inspections with subcontractors and Consultant to verify the
compliance to the specifications. Ensure all rejected materials from internal and consultant inspections
are tagged and removed from the site.
• Conduct subcontractor/supplier factory/fabrication yard inspections as per QA QC Manager Instruction
to verify the compliance with project requirements and communicate the observations to project
team.
• Coordinate with subcontractor, ALEC Team and Consultant and ensure all the inspections are
conducted as per approved ITP and ensure the records are maintained
• Coordinate with subcontractor, third-party laboratories, and consultants for various field tests as per
approved ITP and ensure the test reports/records are submitted/maintained
• Conduct internal verification/inspections for the implementation of corrective and preventive actions
for the site NCRs and deficiencies identified by the QA QC Team. Verify the effectiveness of corrective
and preventive actions.
• Analyse the status of QA QC activities, prepare the trends including submittals, inspections, tests,
deficiencies identified & NCRs and communicate to QA QC Manager/Project team
• Conduct snagging – De-snagging inspections coordinating with subcontractors, ALEC execution Team
and Consultants.
• Lead and guide the inspection team to achieve the project Goals.

Site Surveyor:

The Site Surveyor will be responsible for the following activities:


• Topographic and as built survey on site
• Compute the area and volume for cut and fill
• To setting out points of foundations, columns, beam lines, etc. before casting
• To setting out the base plates, points for block works and slab edges.
• To prepare sketches and written reports following the surveying of an area
• To prepare contour plans and compile data from survey findings
• Solve practical problems and deal with the variables in situations where limited standardisation exists
• To input and prepare coordinates using Auto Cad
• To check the dimensions on drawings and ensure this reflects what is built on site
• Update drawings to ensure any changes during construction are accounted for
• To calculate distances, angles, area, and volume on site using surveying methods
• To manage the surveying equipment, monitoring accuracy and ensuring it is calibrated
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 10 of 16

• To assist the ALEC related businesses and Sub Contractors in location of points and updating of
drawings
• Cooperate with the façade team in marking the accurate
• Observe the displacement of structure for deflection
• Take the as built for all construction items after casting concrete

Responsible persons for each stage of work are marked against each phase of work in work sequence section.

6. WORKING ACCESS:

The access / egress for the construction vehicles for the installation of activities shall be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all
activities.
All Access routes through the site to be properly maintained to minimize interference with adjoining roads.
Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during
operations. Flagman will be provided at critical locations.

7. LIGHTING:

i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.

ii. Task Lighting:


Task lighting shall be provided in addition to the safety lighting to undertake the task with the proper level of
lighting to meet acceptable safety and quality of workmanship standards.

8. PLANT & EQUIPMENT:

i. General:
 Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools and
equipment shall be checked visually prior to use.
 Only authorized applicator approved and trained by the manufacturer to install manufacturer's
products.
 All Operators shall be trained and certified by the 3rd party where required.
 No defective plant and equipment shall be allowed to use on site.

ii. Plant & Equipment Schedule:

SL No Description of Plant, Equipment & Tools


1 Hand Tools

2 Hacksaw Blade
3 Pulling spring and Bender

4 Measuring tape
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 11 of 16

5 Spirit level

6 Electrical Tool Kit

7 Steel Wire

8 Gloves, Eye Protection

iii. Personal Protective Equipment:


(Refer Attachment-1 for Risk Assessment)
All operatives involved in the activity shall be provided with Job specific Personal Protective equipment
which are and but not limited as mentioned below.
 Polycarbonate Safety Helmet
 Safety boots with steel toe
 Coverall with high visibility strips
 Hand Gloves
 Full body Harness
 Ear Plugs
 Eye protection / Goggles

iv. Power:
The electric supply used on site for power tools shall be 110/230 volts as per voltage rating of the
equipment. Higher voltage power shall be provided to site welfare areas if necessity arises.

v. Working Platforms:
 The working platforms for the task shall be firm and stable.
 The elevated working platforms for the activity (if used) shall be provided by means of cup lock
scaffold system.
 The scaffolds for the activity shall be built by competitive scaffolders trained by third party.
 The built scaffolds shall be inspected and signed off by a third party trained inspectors / supervisors.
 Were necessary access shall be provided by means of scaffold.
 The working platforms shall be used as only platforms for working and shall not be used for loading
heavy material or equipment on to it.

9. MATERIALS:

SL No. Material Description


1 PVC Conduits & Accessories
2 PVC solvent

The above listed materials/items to be in line with the approved material submittal and shop drawings in
compliance with Project requirements industry standards, code, regulation of the local authority & regulations
bodies.
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 12 of 16

10. SEQUENCE / METHOD OF WORK:

Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document

10.1 PRELIMINARY ACTIVITIES: PD/DPD/ PROJECT


 Submit material submission for all materials related to the task for Engineer PE/QCM/ Design
approval and obtain approval. HSEM guidelines
 As per approved material submittal and shop drawing and obtain approval from
the relevant project authorities and local regulatory body if applicable.
 Method statement, inspection & test plan and Risk Assessment to be submitted
for Engineer approval and obtain approval. Authorities (as applicable)
 Implement the risk mitigation actions as per the approved risk assessment and
ensure that the risk is as low as reasonably practicable.

10.2 PRE-CONSTRUCTION ACTIVITIES:


 Delivery notes to be obtained for materials delivered to site and stored in the
designated areas as per manufacturer recommendations.
 Submit MIR for delivered materials on site.
 Ensure that all materials are approved prior to using the material on site.
Project
 Ensure that method statement, ITP and shop drawing approved prior to starting
Stores In- Design
any activity on site.
charge/QC guidelines
 Adequate lighting to be provided in the work areas to execute the task.
M/HSEM /
 All risk hazards on operations have been identified and precautions are taken.
DO/MIR/R
 Ensure that all necessary personnel, plant, equipment, and services are required
A
for the work is in place.
 Implement employee induction procedure and toolbox talks for ongoing risk
assessment and identification of hazards.
 Ensure RFI is raised and approved for technical clarification and modification
as/if required.
 Ensure the work area is clear and safe for working.

10.3 CONSTRUCTION ACTIVITIES:


Prior Works : For PVC Conduits and Accessories Installation

 Ensure that the work area is ready and safe to start the installation of electrical
conduits.
 Prior to start the installation Refer the approved shop drawings related to the
area of installation and ensure that required material is available at site as per
approved material submittals.
Project
Installation Of PVC conduits in Slab Design
 Mark the location of the back box or pull boxes & place Polystyrene secured with PM/PE/ guidelines
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 13 of 16

Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document

masking tape on these locations. SE/QCM/ /


 Install the PVC conduits utilizing the steel reinforcements as support by using HSEM MSS/ITP/
necessary binding wires. RA/PTW/
 The concealed conduits of slab or any concrete structure should be securely ASD
fastened with binding wires to reinforcement rods or shuttering to withstand
concrete & screed pour.
 The jointing of PVC conduits shall be done with suitable coupler and solvent
cement or PVC glue. The PVC conduit shall be bonded tightly to the back boxes /
pull box with suitable adapters.
 Approved connectors / adopters will be used for connections to back box/ pull
boxes.
 Expansion couplers and fittings of approved type shall be provided wherever the
conduits passes through the expansion joints of the building.
 All bends of PVC conduit will be made by using correct size of bending spring.
Ensure the radius of any conduit bend shall not be less than four times the
outside diameter of the conduit to satisfy the easy cabling/ wire pulling
requirements.
 To facilitate easy cabling / wiring sufficient pull boxes or junction box will be
provided in all conduiting. At least one pull box shall be provided on every two
90o bends.
 In longitudinal straight runs the pull boxes / junction box will be provided in
every 30 meters
 Close bunch of PVC conduits in slab shall be avoided to maximum possible
extent.
 Sufficient gap shall be provided between conduit at cross-over location.
 Ensure all open ends of the conduit are capped / plugged properly before
concrete pouring. Also ensure caps are provided for unused knockout holes
where blanks have been removed.
 After completion of conduiting installation for any portion the area will be
cleaned properly by removing all surplus material, construction debris or scrap
material etc. to leave the area in clean and tidy condition prior to pouring
concrete.

Installation Of PVC conduits & Accessories in wall


 In vertical wall the conduit shall run vertically from back boxes. Horizontal runs
shall be avoided on walls.
 Ensure the recessed position of outlets boxes is accurate to allow for surface
finish thickness.
 Conduits chased into wall should be recessed sufficiently to permit a minimum
thickness of 15mm for plaster cover. For conduits runs to be embedded in
concrete a minimum 25mm cover will be provided.
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 14 of 16

Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document

Verification & House Keeping

 After removal of concrete shuttering all the conduits shall be checked for project
blockage (wherever possible) shall be cleaned & plugged/ covered and protected Design
from any potential damage which might happen due to latter activities. guidelines
 All Boxes which are installed in wall must be protected from debris by sealing it /
with manufacturer recommended covers. MSS/ITP/
ASD
Quality Control PM/PE/
SE/QCM
1. All inspections will be performed by quality team in accordance with method
statements, reviewed and approved by the Supervision Consultant.
2. The internal self-inspection shall be carried out as per the Hold, witness points as
identified in the inspection test plan for the installation PVC conduits and
accessories (for electrical services).
3. instructed by the Commissioning Manager. Site Management and QAQC
personnel should monitor the installation to ensure it is done according to the
approved drawings.
Site Supervision personnel must ensure that the work fully complies with the norms
laid down as per specification in all respects.

11. PROGRAMME

As per the site construction programme.

12. RISKS & CONTROLS:

i. Hazards / Risks

Please refer Attachment-1 for the Risk Assessment

ii. Control Measures / Permits

Please refer Attachment-1 for the Risk Assessment

iii. 3rd party Protection

Please refer Attachment-1 for the Risk Assessment


MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 15 of 16

13. TECHNICAL INFORMATION

In addition to the requirements indicated in work will be in accordance with recommendations and
requirements of the following standards, codes and bodies. The current editions of publications being those
applicable:

14. EMERGENCY ARRANGEMENTS

i. General

 The Site HSE department shall be responsible to arrange and coordinate with site execution teams in
arranging Day & Night emergency procedures.
 In case of any emergency the CRM will be informed about the emergency
 Emergency assembly point shall be allotted and communicated to all the operatives in involved in the job.
 Ensure clear access to the emergency assembly area with signage’s in place.
 No construction activity shall block the access leading to the emergency assembly point. In case of any
deviation the access has to divert and the same shall be communicated to all the operatives on site.

ii. Fire Precautions

 Fire extinguishers shall be put in place in each working zone and a clear access shall be provided to the
location.
 All the operatives shall be trained for fire precautions on site.
 A fire warden is appointed and trained from each team of operatives.

iii. Communication
The communication on site shall be through mobile provided by the contractor or by two-way wireless radio
systems.

15. TRAINING

 Necessary safety or operational training shall be provided to the operatives involved in the activities.

16. SUPERVISION

 Adequate supervision shall be provided for the executing each activity.


 Project QAQC Engineers shall monitor the workmanship and quality of the works.

17. WORKING HOURS

Site working hours as below:


 Day shift - 7:00am to 6:00pm (Break 12:00 pm to 01:00 pm)
 Night shift - 6:00pm to 5:00am (Break 11:00 pm to 12:00 am)
 Summer working hours as below:
 Day shift - 2:00am to 12:30pm
 Night shift - 3:30pm to 2:00am
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 16 of 16

 Authority regulations for the working hours will be followed.

18. HOUSEKEEPING

 The work areas shall be clean and tidy.


 No debris from construction activities is allowed to accumulate in the work area.
 Work areas shall be cleaned on daily basis at the end of the shift or on completion of the activity.
 Sufficient Waste collection bins shall be provided at each working zone.
 Waste segregation area (where recyclable / landfill materials are segregated, usually as Steel, Wood,
Plastic, Concrete and Debris) shall be established to control the waste generated on site due to
construction.

19. OTHER INFORMATION

NA

20. ATTACHMENTS

1. Risk Assessment
2. Inspection Test Plan
3. Inspection checklist