I. MES for Installation of PVC Conduiting Accessories
I. MES for Installation of PVC Conduiting Accessories
: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev : 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 1 of 16
METHOD STATEMENT
METHOD STATEMENT TITLE
FOR
INSTALLATION OF
PVC CONDUITS AND ACCESSORIES
00 28 Aug 2023 Submitted for Approval [QA/AC Engineer] [QA/QC Manager] [Project Director]
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 2 of 16
CONTENT
1. INTRODUCTION........................................................................................................................................5
2. SCOPE OF WORK:.....................................................................................................................................5
3. DEFINITIONS & ABBREVATIONS:........................................................................................................5
4. REFERENCES:............................................................................................................................................6
5. ROLE AND RESPONSIBILITIES:.............................................................................................................6
6. WORKING ACCESS:............................................................................................................................11
7. LIGHTING:..............................................................................................................................................11
i. Safety Lighting:..........................................................................................................................................11
ii. Task Lighting:.............................................................................................................................................11
8. PLANT & EQUIPMENT:.......................................................................................................................11
i. General:.......................................................................................................................................................11
iii. Personal Protective Equipment:..............................................................................................................12
iv. Power:.....................................................................................................................................................12
v. Working Platforms:....................................................................................................................................12
9. MATERIALS:.............................................................................................................................................12
10. SEQUENCE / METHOD OF WORK:.........................................................................................................13
11. PROGRAMME..............................................................................................................................................14
12. RISKS & CONTROLS:...........................................................................................................................14
i. Hazards / Risks.........................................................................................................................................14
ii. Control Measures / Permits.....................................................................................................................14
iii. 3rd party Protection..............................................................................................................................14
13. TECHNICAL INFORMATION.............................................................................................................14
14. EMERGENCY ARRANGEMENTS..........................................................................................................14
i. General........................................................................................................................................................14
ii. Fire Precautions..........................................................................................................................................15
iii. Communication...........................................................................................................................................15
15. TRAINING.................................................................................................................................................15
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 3 of 16
16. SUPERVISION..........................................................................................................................................15
17. WORKING HOURS................................................................................................................................15
18. HOUSEKEEPING......................................................................................................................................15
19. OTHER INFORMATION..........................................................................................................................16
20. ATTACHMENTS.......................................................................................................................................16
P.P
Praveen Mani Darrel Fletcher Tyron Holgate
QAQC MANAGER HSE MANAGER PROJECT MANAGER
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev : 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 4 of 16
1. INTRODUCTION
The Purpose of this Method statement is to define the typical sequence of works for installation of PVC conduits and
accessories. This Method Statement Provides the controlled sequence and methodology that will be implemented
for installation of PVC conduits, accessories, and related associated works.
2. SCOPE OF WORK:
2.1 The scope of this method statement includes sequence of works in supply, installation of PVC conduits and
accessories as required in Wynn Marjan Island- Ras Al Khaimah.
2.2 This procedure is to be read in conjunction with relevant ITP and check lists outlining the responsibility and
quality verification to be carried out by the various parties.
IR Inspection Request
PSSP Project safety security plan
TC Tower crane
MC Mobile crane
MIM Manufacturer instruction manual
4. REFERENCES:
1. Project Quality Plan (PQP)
2. Project Safety & Security Plan (PSSP)
3. Reference Spec.
4. Site Establishment / Logistic Plan.
5. Method statement for Lifting Operations (Submitted Separately)
6. Other references (Shop drawings, design calculations, RFI etc.)
7. Local Authority regulations
Construction Manager:
Quality Manager:
• Coordinate with team, subcontractors, and Consultants - to ensure the progress of material submittals
is as per schedule.
• Establish and Implement the Material and work Inspection procedure for the project. Monitor
inspection status, analysis status reports and trend analysis, implement corrective actions for the
variations from plan.
• Ensure the non-conforming materials are tagged and removed from site and provide the rejected
material inspection report to commercial and procurement for corrective actions.
• Organize/Manage offsite inspections in coordination with team, Consultant, and subcontractor
/supplier / manufacturer.
• Review subcontractor’s prequalification to verify the capability/compliance to project requirements
and provide recommendation.
• Establish and Implement procedures for monitoring and controlling subcontractor’s quality of work
including site surveillance, recording the deficiencies and continuous follow up with construction tea
for closing the recorded deficiencies.
• Close Site Instructions/non-conformance reports from consultant and conduct the review of the Site
instruction/corrective action to verify the scope for a potential claim.
• Coordinate with subcontractor, team, and consultant for implementing the corrective actions and
closing the site instruction /NCR.
• Coordinate with subcontractors for the timely submission of material submittals, test reports and O &
M manual for the project.
• Prepare the closeout documentation requirements for the project and manage the
Preparation / compilation and submission of project closeout documents to consultant.
• Coordinate with consultant, and subcontractor for testing and commissioning inspections.
• Establish and implement the procedures for snagging /de-snagging at project site. Coordinate with
Consultant and subcontractor to complete the snagging and de-snagging inspections as per project
schedule.
• Provide accurate progress updates of material submittals to planning department weekly and monthly.
• Provide accurate status of material inspections to planning department weekly.
• Present weekly material submittal status, weekly look ahead, status of site instructions to
management and implement the actions decided for any variations from plan.
• Report to commercial department regarding the poor performance of subcontractor in quality or any
other concerns, which needs to be taken contractually.
• Organize trainings on special systems/new procedures introduced in the project.
• Lead, motivate, Train, and develop QA QC team.
Design Manager:
• Oversee all the tasks of the design team and to provide motivation and support for the team.
• Review and detail shop drawings for construction plans.
• Render design ideas in form of paste-ups or drawings.
• Use computer-aided drafting (CAD) and related software to produce construction documents.
• Maintain an awareness of developments in the field of architecture so that up-to-date and accurate
advice can be given to clients.
• Coordinate with the local authorities where necessary.
Logistic Manager:
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 8 of 16
Site Engineer:
QA/QC Engineer:
Site Surveyor:
• To assist the ALEC related businesses and Sub Contractors in location of points and updating of
drawings
• Cooperate with the façade team in marking the accurate
• Observe the displacement of structure for deflection
• Take the as built for all construction items after casting concrete
Responsible persons for each stage of work are marked against each phase of work in work sequence section.
6. WORKING ACCESS:
The access / egress for the construction vehicles for the installation of activities shall be as per the logistic Plan.
Ensure Proper coordination with all interfacing contractors for Logistics, access prior to commencement of all
activities.
All Access routes through the site to be properly maintained to minimize interference with adjoining roads.
Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during
operations. Flagman will be provided at critical locations.
7. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements (Minimum 50 lux) will be provided.
i. General:
Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools and
equipment shall be checked visually prior to use.
Only authorized applicator approved and trained by the manufacturer to install manufacturer's
products.
All Operators shall be trained and certified by the 3rd party where required.
No defective plant and equipment shall be allowed to use on site.
2 Hacksaw Blade
3 Pulling spring and Bender
4 Measuring tape
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 11 of 16
5 Spirit level
7 Steel Wire
iv. Power:
The electric supply used on site for power tools shall be 110/230 volts as per voltage rating of the
equipment. Higher voltage power shall be provided to site welfare areas if necessity arises.
v. Working Platforms:
The working platforms for the task shall be firm and stable.
The elevated working platforms for the activity (if used) shall be provided by means of cup lock
scaffold system.
The scaffolds for the activity shall be built by competitive scaffolders trained by third party.
The built scaffolds shall be inspected and signed off by a third party trained inspectors / supervisors.
Were necessary access shall be provided by means of scaffold.
The working platforms shall be used as only platforms for working and shall not be used for loading
heavy material or equipment on to it.
9. MATERIALS:
The above listed materials/items to be in line with the approved material submittal and shop drawings in
compliance with Project requirements industry standards, code, regulation of the local authority & regulations
bodies.
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 12 of 16
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
Ensure that the work area is ready and safe to start the installation of electrical
conduits.
Prior to start the installation Refer the approved shop drawings related to the
area of installation and ensure that required material is available at site as per
approved material submittals.
Project
Installation Of PVC conduits in Slab Design
Mark the location of the back box or pull boxes & place Polystyrene secured with PM/PE/ guidelines
MES Ref No.: WAMI-ALM-EL-
PROJECT: WYNN MARJAN ISLAND MES-00002
METHOD STATEMENT FOR INSTALLATION OF Rev: 00
PVC CONDUITS AND ACCESSORIES
Date: 28-Aug-23
Page 13 of 16
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
Reference
Responsible
DESCRIPTION OF SEQUENCE / METHOD OF WORK /Verifying
person
Document
After removal of concrete shuttering all the conduits shall be checked for project
blockage (wherever possible) shall be cleaned & plugged/ covered and protected Design
from any potential damage which might happen due to latter activities. guidelines
All Boxes which are installed in wall must be protected from debris by sealing it /
with manufacturer recommended covers. MSS/ITP/
ASD
Quality Control PM/PE/
SE/QCM
1. All inspections will be performed by quality team in accordance with method
statements, reviewed and approved by the Supervision Consultant.
2. The internal self-inspection shall be carried out as per the Hold, witness points as
identified in the inspection test plan for the installation PVC conduits and
accessories (for electrical services).
3. instructed by the Commissioning Manager. Site Management and QAQC
personnel should monitor the installation to ensure it is done according to the
approved drawings.
Site Supervision personnel must ensure that the work fully complies with the norms
laid down as per specification in all respects.
11. PROGRAMME
i. Hazards / Risks
In addition to the requirements indicated in work will be in accordance with recommendations and
requirements of the following standards, codes and bodies. The current editions of publications being those
applicable:
i. General
The Site HSE department shall be responsible to arrange and coordinate with site execution teams in
arranging Day & Night emergency procedures.
In case of any emergency the CRM will be informed about the emergency
Emergency assembly point shall be allotted and communicated to all the operatives in involved in the job.
Ensure clear access to the emergency assembly area with signage’s in place.
No construction activity shall block the access leading to the emergency assembly point. In case of any
deviation the access has to divert and the same shall be communicated to all the operatives on site.
Fire extinguishers shall be put in place in each working zone and a clear access shall be provided to the
location.
All the operatives shall be trained for fire precautions on site.
A fire warden is appointed and trained from each team of operatives.
iii. Communication
The communication on site shall be through mobile provided by the contractor or by two-way wireless radio
systems.
15. TRAINING
Necessary safety or operational training shall be provided to the operatives involved in the activities.
16. SUPERVISION
18. HOUSEKEEPING
NA
20. ATTACHMENTS
1. Risk Assessment
2. Inspection Test Plan
3. Inspection checklist