QS REBARS
QS REBARS
FOOTING (RSB)
Ln= 1.5 – 2(0.075)
= 1.35m
Hook= 2 (9(16))
=0.45
Lt= 1.8
12 pcs. = 1.8m
For 18 footings
12 (18) – 1.8m
2.16 – 1.8 m
COMMERCIAL LENGTH : 6m
6/1.8 = 3.33 = 216/3.33= 64.86=65 pcs
65= 16mm dia. RSB @6m
CONVERT INTO KG
65 x 6= 390 x 3.86 kg/m= 1505.4 kg
III. BEAMS
BEAM 1
MAIN BARS
SPLICING AND BEND
(TOP)
Splicing: 200 x 16 + 160= 480 mm
Bend: 5 x 16 x 2= 160 mm
(BOTTOM)
Splicing: 25 x 16 +150= 550 mm
Bend: 5 x 16 x 2= 160 mm
MAIN BARS= 4 - 16 mm dia. RSB
COLUMN= 0.3 x 0.3
Ltop= Span + Splicing + Bend
= 8 + 0.48 + 0.16
= 8.64m = 8.7m
Lbot= Span + Splicing + Bend
= 8 + 0.55 + 0.16
= 8.71 = 8.8m
FOR COMMERCIAL LENGTH (6m)
TL= 8.8(6)= 52.8m
52.8/= 8.8 = 9 pcs
9 x 6= 54 x 1.58= 85.32 kg
@8m (6)
50mm= 6 (0.05) (6)= 1.8m
100mm= 6 (0.1) (6)= 3.6m
Ln= 7.7 – 1.8 – 3.6= 2.3m
Rest= 2.3/0.15= 15.33= 16 pcs
# of stirrups= 6 (6) + 6 (6) +16
= 88 pcs
STIRRUPS
ROOF BEAM
A= 250 – 40(2)= 170mm
B= 300 – 40(2)= 220mm
Ls= 2 (170 + 220) + 20(10)
Ls= 0.98 = 1m
STIRUPPS= 1m
COMMERCIAL LENGTH
6/1= 6 cuts
Tstirrups:
TL= 88 pcs
88/6= 14.67= 15 pcs – 10mm dia. RSB @6m
CONVERT INTO KG (16mm dia.= 0.62 kg)
TL= 88 x 1= 88 x 0.62
= 54.56 kg
TIE WIRES:
NO. OF INTERSECTIONS= 88 X 6= 528
USE 40 cm TIE WIRE
LT= 528 X 40= 21,120 cm
21.12m x 1kg/53m= 0.40kg
BEAM 2
Ltop= span + splicing + bend
= 9.5 + 0.48 + 0.16
Ltop= 10.14 = 10.2m
Lbot= span + splicing + bend
= 9.5 + 0.55 + 0.16
Lbot= 10.21 = 10.3
FOR COMMERCIAL LENGTH (6m)
TL= 10.3m (4) = 41.2m
41.2/6= 6.87 = 7 pcs.
7 x 6= 42 x 1.58= 66.36 kg
@9.5 (4)
50 mm= 6(0.05) (4)= 1.2m
100mm= 6(0.1) (4)= 2.4m
Ln= 9.2 – 1.2 – 2.4 = 5.6m
Rest= 5.4/ 0.15= 36 pcs
#of stirrups= 6(4) + 6(4) + 36 = 84
STIRRUPS: Ls= 1m
COMMERCIAL LENGTH= 6/1= 6 cuts
7 STIRRUPS= 84 pcs
84/6= 14 pcs – 10mm dia. RSB @6m
CONVERT INTO KG: (16 mm dia. = 0.62kg)
TL= 84 x 1 = 84 x 0.62
= 52.08 kg
TIE WIRES:
# OF TIE WIRES= 84 x 4= 336 (use 40 cm tie wire)
Lt= 336 x 40 = 13,440= 13.44 x 1kg/53m = 0.25 kg
IV. SLAB
@TERMINAL
Area= 19m x 24m = 456 sq.m
Number of bars along 19m
19m/6m + 1= 3.17 = 4
Number of bars along 24m
24m/6m + 1 = 5
Lengthwise= 4 bars x 24m = 96m
Widthwise= 5 bars x 19m = 95m
TL= 96m + 95m = 191m
@16 mm dia. Bars
16 sq/162= 1.58 kg/m
Weight of rebars: 191m x 1.58kg/m = 301.78kg
@ WAITING AREA
Lengthwise: 9.5m/6m= 1.58m = 2m
Widthwise: 4.8m/6m= 0.8m = 1m
Total length of rebars along the length:
2 bars x 4.8m= 9.6m
Total length of rebars along the width:
1 bar x 9.5m= 9.5m
Total length= 9.5 + 9.6= 19.1
Total weight of rebar:
19.1m x 1.58kg/m= 30.178 kg
@COMFORT ROOM
Lengthwise: 8.5m/6m= 1.416 = 2 m
Widthwise: 4.8m/6m= 0.8m = 1m
Total length of rebars along the length:
2 bras x 4.8m = 9.6m
Total length of rebars along the width:
1 bar x 8.5m = 8.5m
Total length= 9.6 + 8.5 = 18.1m
Total weight of rebars:
18.1m x 1.58kg/m= 28.598kg
Total weight of all rebars:
301.78kg + 30.178kg + 28.598kg = 360.556 kg