0% found this document useful (0 votes)
6 views

Chapter 6

Chapter 06 discusses construction surveying, which involves staking out reference points for new structures and verifying their locations during construction. It covers horizontal and vertical control methods, positioning techniques, and specific setting out procedures for buildings, culverts, and bridges. The chapter emphasizes the importance of accuracy and efficiency in the surveying process to minimize costs and ensure compliance with design specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

Chapter 6

Chapter 06 discusses construction surveying, which involves staking out reference points for new structures and verifying their locations during construction. It covers horizontal and vertical control methods, positioning techniques, and specific setting out procedures for buildings, culverts, and bridges. The chapter emphasizes the importance of accuracy and efficiency in the surveying process to minimize costs and ensure compliance with design specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

Chapter: 06 Construction Survey

6.1 Introduction

Construction surveying or building surveying (otherwise known as "staking", "stake-out", "lay-


out", "setting-out" or "BS") is to stake out reference points and markers that will guide the
construction of new structures such as roads or buildings as per plan or map.

Elements of Construction Survey:

 Survey existing conditions of the future work site, including topography, existing buildings
and infrastructure, and underground infrastructure whenever possible (for example,
measuring invert elevations and diameters of sewers at manholes);
 Stake out lot corners, stake limit of work and stake location of construction trailer (clear of
all excavation and construction)
 Stake out reference points and markers that will guide the construction of new structures
 Verify the location of structures during construction;
 Provide horizontal control on multiple floors.
 Conduct an As-Built survey: a survey conducted at the end of the construction project to
verify that the work authorized was completed to the specifications set on plans.

6.2 Horizontal and Vertical Control

Horizontal Control

Setting out is about working from the whole to the part. Secondary points (Established from the
primary control points) are used to the site to enable fast location of design points. Primary
control points should be far enough away from building activity to avoid damage. Primary
control points should be set in concrete.

Reference grids

 Survey grid- usually based on original traverse.


- Known as Easting and Northing
- Control points are original points.
 Site grid - Specified by designer
- Usually coincides with survey grids.
 Structural grids- Use to ensure building accuracy ( particularly of the verticals)

Vertical Control

Points of horizontal control are often used for levels (vertical control) as well. One of these is
usually made the Master Bench Marks, while others becomes Temporary Bench Marks(TBMs).
TBMs can be established in existing structures, or could be steel bars set in concrete. Accuracy

Er. Mukesh kafle Page 1


must be appropriate to the type of construction. Bench marks should be checked regularly. The
elevation of any station / points is the vertical control. It is established by leveling process.

6.3 Positioning of a structure

The new structure must be correct in all three dimensions both relatively and absolutely.
i) correct level, size, plan and position.
ii) Once setting out begins it must proceed swiftly with little delay so that costs can be
minimised.

Techniques used to achieve these aims are based on three general principles.

a) Horizontal control points must be established within or near the design area.
b) Vertical control (bench marks) must be within or near the design area.
c) Accurate positioning techniques must be adopted to establish design points from horizontal
and vertical control.

Positioning of any structure can be done by

Basic Tasks

i) Setting Out of a point


ii) Setting Out of a line
iii) Prolongation of a line
iv) Setting Out of Angles
v) Setting out of lines disturbed by obstacles.

The most commonly used methods are


a) Orthogonal co-ordinates (Offsets)
b) Polar co-ordinates.
c) Intersections (Angle of Intersection 30o <<150o)
d) Linear Intersections (ties)

For Vertical Control the basic tasks are:

i) Transfer of height
ii) Setting out a horizontal line.
iii) Setting out a gradient line.
iv) Setting out a contour line.

The methods used are


a) Ordinary levelling
b) Projected heights (e.g. in Mining Surveying)
c) Trig Heighten

Er. Mukesh kafle Page 2


6.4 Setting out of Building, Culvert and Bridge

Setting out a Building:

Fig.1: Example plan to be set out on the ground


1. From the plan (fig 1), the Centre line of the walls are calculated. Then the Centre lines of the
rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are a, b,
c, d, e, f and g which are marked by pegs with nails on top.
2. The setting of the corner point is checked according to diagonals ac, bd, cf and eg.

3. During excavation, the Centre points a, b, c, d, e, f, g may be removed. Therefore the Centre
lines are extended and the Centre points are marked about 2m away from the outer edge of
excavation.

Thus the points A1, A2, B1, B2 and likewise, are marked outside the trench. Centre line are
shown clearly by stretching thread or rope. The Centre points fixed 2m away from the excavation
are marked with sit out pegs.

4. From the plan details, the width of excavation to be done is also marked by thread with pegs at
appropriate positions.

5. The excavation width is then marked by lime or by with furrow with spade.

Er. Mukesh kafle Page 3


6. If the plan is much too complicated and follows a zigzag pattern, then the Centre pegs are kept
at suitable positions according to site conditions.

Setting out a culvert:


A culvert is set out by locating the corners of the abutments and wing walls at the foundation by
means of their co-ordinates with reference to the Centre lines of a road and a stream (nalla)
crossed. The Centre lines of road and stream which cross each other are taken as axes of co-
ordinates, thief origin being at the Centre of the culvert.

The co-ordinates of different points are found from the foundation plan and indicated in the
tabular form.

In fig. 14.5, PQ and RS are centre lines of road and the stream respectively passing through the
centre O of the culvert and co-ordinates for the points, 1, 2, 3 etc are x1 y1, x2y2, x3 y3. etc.
Procedure:
(i) Derive a peg at 0 and set up a theodo lite over it. Fix points A, B, C, D etc. on line POQ by
arrows. The cord passing through the eyes of the arrows will define the line PQ.

(ii) Set out the line RS at right angles to PQ and fix the points EFGH, IJKI, etc by arrows.

Er. Mukesh kafle Page 4


(iii) Stretch the cords along lines PQ and Rs. Set off the distances OA, OB, OC etc on PQ and
OE, OF, OI, OJ etc. on RS and fix arrows at all these points.

(iv) Set out comer 1 by measuring co-ordinates x1 and y1 from A and F respectively with the help
of two tapes and marks it with a peg.
(v) Similarly, fix other points by their co-ordinates and drive pegs at each point.

(vi) Pass a cord around the periphery of abutment and wing wails as 1, 2, 3, 4, 5, 6, 7, 8 and mark
the outline of the foundation with lime and by nicking i.e. cutting a narrow trench along this line.

(vii) Similarly fix the corners of other abutment and wing walls and mark the outline of the
foundation.

(viii) Take levels at all pegs and determine depth and quantities of excavation.

(ix) If the wing walls are curved, the points on the curve may be set out by offsets to the chords
1-8, 6-7 and 2-3, 4-5 as indicated in fig. 14.6.

Er. Mukesh kafle Page 5


Setting out a bridge:
The setting out of a culvert is quite simple because there is only one span and the flow of water is
less. Even if the flow of water is more, it can be easily diverted. But in the case of Bridges and
dams, the flow of water cannot be diverted and also the length may be very long. Therefore
setting out is not possible from the centre of the bridge.

The setting out involves the following operations:


1. Preparation of topographic map of the bridge site.

2. Determination of the length of the bridge.

3. Location of piers.

1. Preparation of topographic map:


A topographic survey of the bridge site and approaches to the bridge is required for long and
important bridges.

Tacheometric methods are used for the survey work and contouring and the map must
indicate the following:
(i) The north line

(ii) The name of river and the direction of flow of water,

(iii) The name of the nearest town or village on either side of the bridge.

(iv) The width of the proposed roadway.

(v) The width of existing roadway if any.

(vi) The radius of curvature of the curve at approach road.

(vii) The position and description of Bench Marks and the ground levels on both the banks for a
distance of about 150 m both on upstream as well as downstream sides.

(viii) The normal, lowest and highest levels of water.

(ix) The catchment area.

(x) The maximum velocity and discharge at the bridge site.


Er. Mukesh kafle Page 6
(xi) The detail and results of trial pits and borings etc.

2. Determination of the length of the bridge:


The length of the bridge is required to be measured along the Centre line. If the bridge is short,
the length may be measured directly with a steel tape but that of a large bridge is measured by
method of triangulation.

Let A and B be the two points on opposite banks on the Centre line of the road. Any one of the
following methods may be adopted to find the length of the bridge

(a) First method (Fig. 14.7):

(i) Draw base line AC perpendicular to the Centre line AB.

(ii) Measure the base line AC very precisely as also the angle ACB (θ1) with theodolite by
method of repetition.

Then AB = AC tan θ1

(iii) To check the length AB, set out a line BI) perpendicular to AB at B. Measure BC and the
angle ADB (θ2) as before. Then AB = BD tan θ2.
(iv) If the two distances are almost equal, the mean of the two may be taken as the length of AB,
otherwise the whole operation should be repeated and accurate length should be computed.

Er. Mukesh kafle Page 7


(b) Second method (Fig. 14.8):
(i) Set out the base lines AC and BD along both banks of the river.

(ii) Join CD, BC and AD. Then ABDC is a quadrilateral having BC and AD as their diagonals.

(iii) Measure the base lines AC and BD and the eight angles as shown very accurately.

(iv) Adjust the quadrilateral by approximate method or by method of squares.

(v) Calculate the length AC from the corrected length of BD and the adjusted values of the
angles and compare it with its measured value. If the discrepancy is less than 1 in 5000, the
length of the Centre line AB is accepted.

3. Location of piers:
After measuring the length of the bridge, mark the position of central points of piers along the
Centre line on the plan.

The piers are located by intersection of sights from the ends of the base line by the
following method:
(i) Set up the base lines at A and B perpendicular to AB extending on both upstream and
downstream sides.

Er. Mukesh kafle Page 8


(ii) Set off on each base line and on each side of the center line the distances equal to the center
points 1 and 2 as shown.

Thus the intersection lines 1-1 and 2-2 make angles of 45& with base line on opposite banks and
also with the center line AB.

(iii) Locate the center point P1by simultaneously sighting at the intersection of the two lines 1-1
.Similarly establish P2 at the intersection of the lines 2-2
This method is the fairly accurate and easy but is suitable only when perpendicular base lines
on both sides of the center line of bridge are possible.

Er. Mukesh kafle Page 9

You might also like