6.1 Introduction
Survey existing conditions of the future work site, including topography, existing buildings
and infrastructure, and underground infrastructure whenever possible (for example,
measuring invert elevations and diameters of sewers at manholes);
Stake out lot corners, stake limit of work and stake location of construction trailer (clear of
all excavation and construction)
Stake out reference points and markers that will guide the construction of new structures
Verify the location of structures during construction;
Provide horizontal control on multiple floors.
Conduct an As-Built survey: a survey conducted at the end of the construction project to
verify that the work authorized was completed to the specifications set on plans.
Horizontal Control
Setting out is about working from the whole to the part. Secondary points (Established from the
primary control points) are used to the site to enable fast location of design points. Primary
control points should be far enough away from building activity to avoid damage. Primary
control points should be set in concrete.
Reference grids
Vertical Control
Points of horizontal control are often used for levels (vertical control) as well. One of these is
usually made the Master Bench Marks, while others becomes Temporary Bench Marks(TBMs).
TBMs can be established in existing structures, or could be steel bars set in concrete. Accuracy
The new structure must be correct in all three dimensions both relatively and absolutely.
i) correct level, size, plan and position.
ii) Once setting out begins it must proceed swiftly with little delay so that costs can be
minimised.
Techniques used to achieve these aims are based on three general principles.
a) Horizontal control points must be established within or near the design area.
b) Vertical control (bench marks) must be within or near the design area.
c) Accurate positioning techniques must be adopted to establish design points from horizontal
and vertical control.
Basic Tasks
i) Transfer of height
ii) Setting out a horizontal line.
iii) Setting out a gradient line.
iv) Setting out a contour line.
3. During excavation, the Centre points a, b, c, d, e, f, g may be removed. Therefore the Centre
lines are extended and the Centre points are marked about 2m away from the outer edge of
excavation.
Thus the points A1, A2, B1, B2 and likewise, are marked outside the trench. Centre line are
shown clearly by stretching thread or rope. The Centre points fixed 2m away from the excavation
are marked with sit out pegs.
4. From the plan details, the width of excavation to be done is also marked by thread with pegs at
appropriate positions.
5. The excavation width is then marked by lime or by with furrow with spade.
The co-ordinates of different points are found from the foundation plan and indicated in the
tabular form.
In fig. 14.5, PQ and RS are centre lines of road and the stream respectively passing through the
centre O of the culvert and co-ordinates for the points, 1, 2, 3 etc are x1 y1, x2y2, x3 y3. etc.
Procedure:
(i) Derive a peg at 0 and set up a theodo lite over it. Fix points A, B, C, D etc. on line POQ by
arrows. The cord passing through the eyes of the arrows will define the line PQ.
(ii) Set out the line RS at right angles to PQ and fix the points EFGH, IJKI, etc by arrows.
(iv) Set out comer 1 by measuring co-ordinates x1 and y1 from A and F respectively with the help
of two tapes and marks it with a peg.
(v) Similarly, fix other points by their co-ordinates and drive pegs at each point.
(vi) Pass a cord around the periphery of abutment and wing wails as 1, 2, 3, 4, 5, 6, 7, 8 and mark
the outline of the foundation with lime and by nicking i.e. cutting a narrow trench along this line.
(vii) Similarly fix the corners of other abutment and wing walls and mark the outline of the
foundation.
(viii) Take levels at all pegs and determine depth and quantities of excavation.
(ix) If the wing walls are curved, the points on the curve may be set out by offsets to the chords
1-8, 6-7 and 2-3, 4-5 as indicated in fig. 14.6.
3. Location of piers.
Tacheometric methods are used for the survey work and contouring and the map must
indicate the following:
(i) The north line
(iii) The name of the nearest town or village on either side of the bridge.
(vii) The position and description of Bench Marks and the ground levels on both the banks for a
distance of about 150 m both on upstream as well as downstream sides.
Let A and B be the two points on opposite banks on the Centre line of the road. Any one of the
following methods may be adopted to find the length of the bridge
(ii) Measure the base line AC very precisely as also the angle ACB (θ1) with theodolite by
method of repetition.
Then AB = AC tan θ1
(iii) To check the length AB, set out a line BI) perpendicular to AB at B. Measure BC and the
angle ADB (θ2) as before. Then AB = BD tan θ2.
(iv) If the two distances are almost equal, the mean of the two may be taken as the length of AB,
otherwise the whole operation should be repeated and accurate length should be computed.
(ii) Join CD, BC and AD. Then ABDC is a quadrilateral having BC and AD as their diagonals.
(iii) Measure the base lines AC and BD and the eight angles as shown very accurately.
(v) Calculate the length AC from the corrected length of BD and the adjusted values of the
angles and compare it with its measured value. If the discrepancy is less than 1 in 5000, the
length of the Centre line AB is accepted.
3. Location of piers:
After measuring the length of the bridge, mark the position of central points of piers along the
Centre line on the plan.
The piers are located by intersection of sights from the ends of the base line by the
following method:
(i) Set up the base lines at A and B perpendicular to AB extending on both upstream and
downstream sides.
Thus the intersection lines 1-1 and 2-2 make angles of 45& with base line on opposite banks and
also with the center line AB.
(iii) Locate the center point P1by simultaneously sighting at the intersection of the two lines 1-1
.Similarly establish P2 at the intersection of the lines 2-2
This method is the fairly accurate and easy but is suitable only when perpendicular base lines
on both sides of the center line of bridge are possible.