1_Current Generation
1_Current Generation
CURRENT GENERATION
DC , AC , PWM
Direct Current
V
o
l
+
t
a Pulse Width Modulation
g
e _ Time
50% Duty Cycle
Steady Dc Voltage
V
o
l
+
t
a
g
e _ Time
10% Duty Cycle
Alternating Current 90% Duty Cycle
V
o
l
+
t
a
g
e _ Time
CURRENT GENERATION
If we place a conductor in a variable magnetic field a current is
induced proportional to the force of the magnetic field.
If we move the conductor parallel to the lines of the magnetic field
we will not produce voltage.
S N
CURRENT GENERATION
We need 3 things:
Magnetic field N
Conductor
+
Movement -
S
CURRENT GENERATION
Rotor
Magnetic field
N
Stator S
Coil
Wave generation
V
S o
N l
t
Time
S
N
N
S
a
N g
S e
Sine wave
+
V Peak
o Voltage RMS
l (0.707 Peak value)
t
a Time
g
e
-
Amplitude
Cycle
Three phase generation
N V
o
l
t Time
a
S g
e
Four pole rotor
V
N o 2 pole rotor
l sine wave
N
S t
a Time
g
S e
4 pole rotor
sine wave
T4
T7
T10
T11
T8
T12
T5
T9
T6
T3 T2
WYE Series connection
High Voltage Low Amps
T1
Coil
115,5V
T4 Phase Line
T7 + 231V x 3 400V
T0 Coil
115,5V
T10
T11
T12 T8
T5
T9
T6
T3
T2
WYE Parallel connection
Low Voltage High Amps
T1
T4
T1
T7
T6 T10
T4
T11
T12
T3 T8
T6 T5
T9
T5
T2
T3 T2
WYE Parallel connection
Low Voltage High Amps
T1
T7
Coil &
T0 Line
Phase x 3 200V
115,5V
T10 T4
T6
T11
T3 T12 T5
T8
T9
T2
DELTA series connection
12 1
Coil
115,5V
9 Phase
4 = Line Voltage
6 7 + 231V
Coil
115,5V
3 10
11 8 5 2
DELTA parallel connection
12 7
1
6
Coil & Phase = Line Voltage
115,5V
9 10
3 4
5 2
11 8
Wire system
Single
voltage
4 Wires
T1 T2
T0
T1 T2 T0 T3
T3
Wire system
T2
Dual voltage
10 Wires
T3
T1
T0
Wire system
Dual voltage
12 Wires
LAB 1 : Phase recognition and
connection
GENERATOR NAMEPLATE
CATERPILLAR
GENERATOR SET
SALES MODEL 3508
RATING
GENERATOR DATA
3 PHASE 12 WIRE
XXX WYE DELTA
CONNECTION XXX SERIES PARALLEL
GENERATOR 400 VOLTS 1443 AMPS
EXCITATION 39 VOLTS 7.3 AMPS
693 FRAME 1500 REV/MIN
ENCLOSURE TYPE
YEAR
CAT DIESEL RATING DEFINITIONS:
Emergency Standby Power (ESP)
Output available with varying load for the duration of an emergency outage. Average power
output is 70% of the standby power rating. Typical operation is 50 hours per year with
maximum expected usage of 200 hours per year.
Standby Power
Output available with varying load for the duration of the interruption of the normal source
power. Average power output is 70%. Typical operation is 200 hours per year, with
maximum expected usage of 500 hours per year.
Prime Power
Output available with varying load for an unlimited time. Average power output is 70% of
the prime power rating. Overload operation cannot exceed 25 hours per year.
Continuous Power
Output available without varying load for an unlimited time.
Average power output is 70 - 100% of the continuous
power rating. Typical peak demand is 100% of continuous
rated ekW for 100% of operating hours.
INSULATION TEST
4C4213
For a preventive maintenance schedule, use the following guidelines:
• Generators used for seasonal operation should be tested and inspected prior
to being put back in service.
•If the generator is installed in an enclosed building with low humidity and
minimal temperature variations, test the insulation annually.
2) Visually inspect for moisture. If moisture exists, do not megger. Dry unit
first. Refer to SEHS9124 (Cleaning & drying) for drying procedure.
11) Set voltage to 500 volts for generators that are 600 volts or less.
Set voltage to 1000 volts for generators that are more than 600 volts.
A) Apply voltage.
D) Record temperature.
E) Record humidity.
F) Remove voltage.
Insulation test
The insulation condition must be evaluated based on the 60 seconds
resistance readings compare to the readings taken on previous dates
under similar conditions. A 60 second resistance reading with a 50%
reduction from previous reading indicates that the insulation may have
absorbed too much moisture.
30 s 60 s
30 s 60 s
Normal reading:
Clean & dry the windings:
The resistance after 60
The resistance after 60 seconds
seconds is greater or equal to
is lower than the resistance after
the resistance after 30
30 seconds.
seconds.
LAB 2 : Insulation Test