The document outlines the installation and associated costs for tubewells as part of the Punjab Rural Sustainable Water Supply & Sanitation Project in Khushab. It includes detailed descriptions of various tasks, materials, and their respective quantities and rates, totaling an estimated cost of Rs. 23,588,633.82. The project aims to enhance water supply and sanitation in rural areas through comprehensive tubewell installations.

Uploaded by

Aamir Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views

1.1

The document outlines the installation and associated costs for tubewells as part of the Punjab Rural Sustainable Water Supply & Sanitation Project in Khushab. It includes detailed descriptions of various tasks, materials, and their respective quantities and rates, totaling an estimated cost of Rs. 23,588,633.82. The project aims to enhance water supply and sanitation in rural areas through comprehensive tubewell installations.

Uploaded by

Aamir Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

PUNJAB RURAL SUSTAINABLE WATER SUPPLY & SANITATION PROJECT

PILOT PHASE, CLUSTER NORTH


ADHI SARGAL,CH.29,CH-49 & CH-53 VILLAGE TEHSIL NOORPUR THAL,DISTRICT KHUSHAB
Bill No. 1.1: TUBEWELL INSTALLATIONS

Sr.
Ref Description Unit Quantity Unit Rate (Rs) Amount (Rs)
No.
1 23/05 Direct rotary/ reverse rotary drilling of bore for
tubewells in all types of soil except shingle, gravel
and rock.
a) From ground level to 250 ft (75 m).
i) 15" to 18" (375 to 450 mm) i/d Per Rft 1,550.00 789.40 1,223,570.00
2 23/7 Providing strong substantially built box of deodar
wood 4'x2.25'x9" (1200x750x225 mm) with locking
arrangement for preserving soil samples from bore Job 5.00 43,826.67 219,133.35
3 23/8 Furnishing sample of water from borehole per set P.Set of 2
of two bottles. bottles 50.00 224.40 11,220.00
4 N/S Taking Soil samples after every 10' depth or from
each Strata change, testing and submission of
complete results of strata analysis each 160.00 54.82 8,771.20
5 N/S Geophysical logging of bore (self potential resistivity
Both short normal and Gama) complete in all
respect. P/Job 5.00 98,668.80 493,344.00
6 23/13 Providing and installing Fiber glass Reinforced
Polypropelene (FRP) strainer of specified wall
thickness having's lot size of 0.9mm to 1.10mm in
tubewell borehole i/c the cost of male/female
coupling with Nylone Strip, studs complete in all
respect as approved and directed by the Engineer
Incharge
vi) 10" inch dia (6.35 mm thickness) Per Rft 220.00 3,532.39 777,125.80
7 23/13 a Providing and installing, Fiber glass Reinforced
Polypropetene (FRP) bail plug of specified wall
thickness having slot size of 0.9 mm to 1.10 mm in
tubewell bore hole i/c the cost of male/female
coupling with Nylone Strip, studs complete in all
respect as approved and directed by the Engineer
Incharge
vi) 10" inch dia (6.35 mm thickness)
Per Rft 50.00 3,412.75 170,637.50
8 23/13 a Providing and installing, Fiber glass blind pipe in
tubewell bore hole socketed, special socket etc,
including jointing complete in all respect as
approved and directed by Engineer.
vi) 10" inch dia (6.35 mm thickness)
Per Rft 1,280.00 3,412.75 4,368,320.00
9 23/19 Shrouding with graded pea gravel 3/8" to 1/8" (10 to
3 mm), around tubewell in bore hole. Per Cft 2,118.00 163.60 346,504.80

10 6/5 Cement concrete plain including placing,


compacting, finishing and curing complete
(including screening and washing of stone
aggregate):

f Ratio 1: 2: 4 100Cft 1.00 45,427.02 45,427.02


PUNJAB RURAL SUSTAINABLE WATER SUPPLY & SANITATION PROJECT
PILOT PHASE, CLUSTER NORTH
ADHI SARGAL,CH.29,CH-49 & CH-53 VILLAGE TEHSIL NOORPUR THAL,DISTRICT KHUSHAB
Bill No. 1.1: TUBEWELL INSTALLATIONS

Sr.
Ref Description Unit Quantity Unit Rate (Rs) Amount (Rs)
No.
11 23/16 Providing and installing P.V.C. blind pipe, B.S.S.
Class `B', in tubewell bore hole, including sockets
and solvents and jointing with strainer, etc.
complete.
a 3" i/d (75 mm) Per Rft 200.00 374.58 74,916.00
12 23/18(ii Testing and developing of tubewell of size 6" (150
) mm) i/d and above continuously. above 1.5 cs.
Discharge Hr. 360.00 2,972.03 1,069,930.80
13 N/S Chemical, Physical and Arsenic Analysis of water
from approved Water Testing Lab. Each 5.00 8,989.82 44,949.10

14 N/S Providing / fixing M.S Centralizer. Each 20.00 2,368.05 47,361.00

15 N/S Supply and erection of roof suspension hook, 16


mm (5/8") dia rod with 75x40x3 mm (3"x1½"x1/8")
M.S. steel channel, with clamp, bolts and nuts, etc.,
including fixing with cement concrete 1:3:6. Each 5.00 2,368.05 11,840.25
Pump
16 N/S i) Supply, install, testing and commissioning of
submersible pump set 0.25 cfs capacity, 80 ft.
pumping setting depth, Having heads of 200
feets, 6 stages, 2 poles submersible motor, Motor
Control Unit consisting of MCCB, Over/Under
voltage relay, Phase reversal relay, volt meter,
Ampere meter, indicating lights for all above relays,
on/Off Push Buttons, All contained in a lockable
Cabinet complete in all respect.

Pump efficiency should not be less than 65% with


efficiency IE-2 Submersible Pump coupled with re- wind-able
water cooled Submersible ( 3 Phase, 3x400 Volts, 50Hz, 2
Pole), Enclosure Class IP 68, Insulation Class F, Voltage
Tolerance +/- 10%., Cable Termination Kit, MS Flanged
Riser MS Pipe 80ft, Sluice Valve, Non-Return Valve, Air
Release Valve, MS Nipple, MS Bend, Bore cover plate, No. 2.00 2,193,405.00 4,386,810.00
Installation clamp, Gasket, Nut bolts, Drop Cable-3 core 40
Meters, Motor Cooling Jacket, Electrodes & Electrode cable
(60Meter) and DOL Motor Control Unit with Dry running
relay, Magnetic Contactor, Circuit Breaker, EOCR, EVR,
Ampere Meter, Volt Meter, Volt Selector Switch,
Ampere Selector Switch, Current Transformer etc.
PUNJAB RURAL SUSTAINABLE WATER SUPPLY & SANITATION PROJECT
PILOT PHASE, CLUSTER NORTH
ADHI SARGAL,CH.29,CH-49 & CH-53 VILLAGE TEHSIL NOORPUR THAL,DISTRICT KHUSHAB
Bill No. 1.1: TUBEWELL INSTALLATIONS

Sr.
Ref Description Unit Quantity Unit Rate (Rs) Amount (Rs)
No.

i) Supply, install, testing and commissioning of


submersible pump set 0.25 cfs capacity, 80 ft.
pumping setting depth, Having heads of 280 feets, 6
stages, 2 poles submersible motor, Motor Control Unit
consisting of MCCB, Over/Under voltage relay, Phase
reversal relay, volt meter, Ampere meter, indicating lights
for all above relays, on/Off Push Buttons, All contained in
a lockable Cabinet complete in all respect.
Pump efficiency should not be less than 65% with
efficiency IE-2 Submersible Pump coupled with re- wind-able
17 water cooled Submersible ( 3 Phase, 3x400 Volts, 50Hz, 2 No. 1.00 2,193,405.00 2,193,405.00
Pole), Enclosure Class IP 68, Insulation Class F, Voltage
Tolerance +/- 10%., Cable Termination Kit, MS Flanged
Riser MS Pipe 80ft, Sluice Valve, Non-Return Valve, Air
Release Valve, MS Nipple, MS Bend, Bore cover plate,
Installation clamp, Gasket, Nut bolts, Drop Cable-3 core 40
Meters, Motor Cooling Jacket, Electrodes & Electrode cable
(60Meter) and DOL Motor Control Unit with Dry running
relay, Magnetic Contactor, Circuit Breaker, EOCR, EVR,
Ampere Meter, Volt Meter, Volt Selector Switch,
Ampere Selector Switch, Current Transformer etc.

18 N/S i) Supply, install, testing and commissioning of -


submersible pump set 0.5 cfs capacity, 80 ft.
pumping setting depth, Having heads of 200
feets each, 6 stages, 2 poles submersible motor,
Motor Control Unit consisting of MCCB, Over/Under
voltage relay, Phase reversal relay, volt meter,
Ampere meter, indicating lights for all above relays,
on/Off Push Buttons, All contained in a lockable
Cabinet complete in all respect.
Pump efficiency should not be less than 65% with
efficiency IE-2 Submersible Pump coupled with re-
wind-able water cooled Submersible ( 3 Phase,
3x400 Volts, 50Hz, 2 Pole), Enclosure Class IP 68,
Insulation Class F, Voltage Tolerance +/- 10%.,
Cable Termination Kit, MS Flanged Riser MS Pipe
80 ft, Sluice Valve, Non-Return Valve, Air Release
Valve, MS Nipple, MS Bend, Bore cover plate,
Installation clamp, Gasket, Nut bolts, Drop Cable-3
core 40 Meters, Motor Cooling Jacket, Electrodes &
Electrode cable (60Meter) and DOL Motor Control
Unit with Dry running relay, Magnetic Contactor,
Circuit Breaker, EOCR, EVR, Ampere Meter, Volt
PUNJAB RURAL SUSTAINABLE WATER SUPPLY & SANITATION PROJECT
PILOT PHASE, CLUSTER NORTH
ADHI SARGAL,CH.29,CH-49 & CH-53 VILLAGE TEHSIL NOORPUR THAL,DISTRICT KHUSHAB
Bill No. 1.1: TUBEWELL INSTALLATIONS

Sr.
Ref Description Unit Quantity Unit Rate (Rs) Amount (Rs)
No.
Meter, Volt Selector Switch, Ampere Selector
19 N/S Switch, Current Transformer etc. No. 2.00 3,693,909.00 7,387,818.00
Providing, fixing, commissioning & testing of Hypo
Chlorinator (make Europe/USA or equivalent)
consisting of multifunction dosing pump with a
microcontroller (RX controller) make Europe/USA or
equivalent complying to EU directives 2006/95/EC
and 2004/108/EC, having capacity of 8-10
Liter/hour and maximum pressure of 10 bar, having
standard power supply of 230V A.C ± 10%, 50 Hz
single phase, Insulation protection rating of IP65,
complete with all accessories like injection valve,
suction hose, discharge hose, valves, RX probe,
level switch, dosing tank to be installed with 1

cusecs capacity tubewells complete in all respect. Each 5.00 141,510.00 707,550.00

Total Amount (Rs.) 23,588,633.82