Scaffolding procedure

The document outlines the proper sequence for erecting scaffolding, emphasizing base preparation, leveling, and securing connections. It includes specific guidelines for using materials and ensuring safety measures, such as barricading the area and inspecting components. Additionally, it features a detailed layout plan for scaffolding in a project setting, including color coding and project specifications.

Uploaded by

kifayat khan
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Scaffolding procedure

The document outlines the proper sequence for erecting scaffolding, emphasizing base preparation, leveling, and securing connections. It includes specific guidelines for using materials and ensuring safety measures, such as barricading the area and inspecting components. Additionally, it features a detailed layout plan for scaffolding in a project setting, including color coding and project specifications.

Uploaded by

kifayat khan
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 191

Proper Scaffold Erection Sequence

Base preparation and setup


x Area is barricaded & proper signage is installed
x Ground is firm, stable, level, free of debris
x Scaffolding components have been inspected & counted
x Use steel base plates, adjustable screw jacks, or castors for mobile towers
x Use mudsills when erecting on soil
x Use screw jacks to level the base
x Never stack wood, bricks, or concrete blocks to level the scaffold

Attachment  - Proper Erection Sequence


xCheck ledgers for level
xAdjust screw jacks to level
xInstall first lift transoms & check for proper fit
xCheck level of transoms & adjust screw jacks
xSquare the base lift.
xInsure all connections are properly secured.

xConnect first lift standards to base standards


xInspect connection for proper fit
xMake sure connections are fully engaged
xInstall base level working planks to assist with installation of next level
xAlways fully plank working levels
xWith base level working planks installed, begin installation of next level
transoms & ledgers
Provide the standard color
coding for scaff tag as per
the project requirement.
Project approved template
must be used.
KEY PLAN:

NORTH

10 11 12 13 14 15 16 17 18
QIBLA PART 1 PART 2

PART 3 PART 4

PART 5 PART 6

LEGEND:

DEMISE LINE

EXISTING WALLS
TOP VIEW
EXISTING WALLS

AZ
STRUCTURE

SCAFFOLDING

ACOUSTIC WALL
BA

LIFT

LIFT

FRONT VIEW SIDE VIEW

SCAFFOLDING DETAILS
1 NTS
BB

VOID SCREEN 1 A=168M²


SC-01 71 SEATS+2H 00 ISSUED FOR APPROVAL 26-MAY-2024 SA

REV. DESCRIPTION DATE REV. BY

DUMB WAITER EMPLOYER:

VOID

BC
ENGINEER:

SCAFFOLDING

SUPERVISION CONSULTANT:
FOYER
1M01

FIRE EXIT
BD

1050 MAIN CONTRACTOR:


SCREEN 2 A=204M²
SC-02 88 SEATS+2H

SCREEN 3 A=180M²
SCREEN 4 A=126M²
SC-03 66 SEATS+2H
SC-04 54 SEATS+2H

SUB-CONTRACTOR:
45

BE

PROJECT TITLE AND LOCATION:

VOID
FIRE EXIT SCREEN 5 A=151M²
SC-05 56 SEATS+2H
AMC CINEMAS
EXIT 10 CINEMAS-RIYADH,KSA

ISSUE STATUS
+201mm

SHOP DRAWING
BF DRAWING TITLE:

FIRST FLOOR MEZZANINE


(SCAFFOLDING LAYOUT)

DATE ISSUED: 02 JUNE 2024 SCALE: AS SHOWN PAPER SIZE : A1


1st FLOOR_MEZZANINE (SCAFFOLDING LAYOUT) DRAWN BY: MIRZA CHECKED BY: ENG.EMAD
1 1 : 100 PROJECT NO: DRAWING NO: REV:

0000 L(0)01M 00
KEY PLAN:
13 14 15 16 17 18 19 20
NORTH

QIBLA

AW

STAIR 3

STAIR REI 120 FIRE EXIT


SCREEN 9 A=273M²
SC-09 92 SEATS+2H

SCREEN 11-IMAX A=743M²


SC-11 198 SEATS+4H
LEGEND:
AX
SCREEN 8 A=248M²
SC-08 98 SEATS +3H

SCAFFOLDING
TOP VIEW

AY

EXIT CORRIDOR
2M01
STAIR 4

ACOUSTIC WALL
STAIR REI 120 NOTE:THE STAIRCASE
FIRE EXIT FROM LEVEL +10.00m TO
LEVEL +14.42m WILL BE
DONE BY TENANT
AZ

EMER. EXIT
SCREEN 11-IMAX-ELITE
SCE-11 46 VIP SEATS+1H

SCREEN 10 A=133M²
SC-10 47 SEATS+2H
SCREEN 7 A=168M²
SC-07 62 SEATS +2H
IMAX ENTRANCE
2M02
REMOVE
FRONT VIEW SIDE VIEW

UP 1

BA SCAFFOLDING DETAILS
FREEZER CHILLER
LIFT
1 NTS
2M04 2M05

SCREEN 6 A=116M² GUEST


SC-06 45 SEATS+2H SERVICE

LIFT

SCREEN 12 PRIME A=476M²


SC-12 124 SEATS+2H 00 ISSUED FOR APPROVAL 28-MAY-2024 SA
ELITE KITCHEN
REV. DESCRIPTION DATE REV. BY

SCREEN 12-PRIME-ELITE
2M06

22 SEATS+1H
BB EMPLOYER:
ELITE-SCREEN 6 A=132M²
SCE-06
28 SEATS+2H
COMMON AREA

SCE-12
2M11

POT/DISH WASH
DUMB WAITER
2M03 ENGINEER:
RECEIVING
DEBOX AREA STORE
2M07 2M17

57 BC

SUPERVISION CONSULTANT:

BAR

ELITE-SCREEN 1 A=159M²
SCE-01 36 SEATS+2H
MAIN CONTRACTOR:
BD

12
13

FEMALE
DIASABLE WC
2M12

EXIT CORRIDOR
SUB-CONTRACTOR:

2M10
ELITE-SCREEN 2 A=157M²
SCE-02 36 SEATS+2H

BE ELITE MALE
TOILET
CLEANER ELITE-SCREEN 5 A=134M²
2M08
2M15 SCE-05 28 SEATS+2H

ELITE FEMALE
TOILET
2M16
PROJECT TITLE AND LOCATION:

shaft
AMC CINEMAS
FIRE EXIT ELITE-SCREEN 3 A=163M² ELITE-SCREEN 4 A=165M² FIRE EXIT EXIT 10 CINEMAS-RIYADH,KSA
STAIR 1 SCE-03 36 SEATS+2H SCE-04 36 SEATS+2H STAIR 2
ELECTRICAL LIFT / SERVICE
ROOM STAIR REI 120 03-F-025 STAIR REI 120
2M09
ISSUE STATUS
BF
SHOP DRAWING

DRAWING TITLE:

SECOND FLOOR MEZZANINE


(SCAFFOLDING LAYOUT)

SECOND FLOOR MEZZANINE (SCAFFOLDING LAYOUT) DATE ISSUED: 02 JUNE 2024 SCALE: AS SHOWN PAPER SIZE : A1

1 1 : 125
DRAWN BY: MIRZA CHECKED BY: ENG.EMAD

PROJECT NO: DRAWING NO: REV:

0000 L(0)02SM 00
CUP-LOCK SYSTEM'

m0
FFL+ 3.645

Tube 1.00 m

Tube 1.00 m
0m 0.1
e 1.0 ebu
Tu b T

FFL+ 2.965

FFL+ 2.285
Tube 1.00 m

Tube 1.00 m
Tu b
e 1.0
0m 0m
e 1.0
Tub
FFL+ 1.605

Plan of Access FFL+ 1.095


TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 3.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 3.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 3.00 M WOODEN PLANK
m0
FFL+ 3.645
Tube 1.00 m

Tube 1.00 m
0 m 0.1
e 1.0 ebu
Tu b T
3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK

3.00 M WOODEN PLANK


TRANSOM - 1.25 m TRANSOM - 1.25 m

FFL+ 2.965

TRANSOM - 1.25 m TRANSOM - 1.25 m

TRANSOM - 1.25 m TRANSOM - 1.25 m FFL+ 2.285


2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK

2.00 M WOODEN PLANK


Tube 1.00 m

Tube 1.00 m
Tu b
e 1.0
0m 0m
e 1.0
Tub
FFL+ 1.605
TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m

TRANSOM - 1.25 m
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK

Plan of Planks FFL+ 1.095


1440-0A
hand rail ledger

LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M mid rail ledger

LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M working station
STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M

Cuplock Standard 3.00 m

.00 m
ER 3
Spigot

LADD
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M

TR

TR
M

M
spigot spigot spigot spigot spigot spigot spigot spigot spigot spigot

00
0
6.

6.
BE

BE
TU

TU
G

NG
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
Steel Ladder 3.00 m
IN

I
AC

AC
BR

BR
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M

Cuplock Standard 3.00 m


STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M
.00 m
hand rail ledger

ER 3
LADD
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M mid rail ledger

LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M working station
spigot spigot spigot spigot spigot spigot spigot spigot spigot spigot

LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
TR

TR
M

M
00

00
6.

6.
BE

BE
TU

TU
G

NG
IN

I
AC

AC
BR

BR
Cuplock Standard 3.00 m
STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M

STANDARD 3.0M
m
.00
ER 3
LADD
Base Jack 60 cm
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M

Elevation of Access

POST
500mm.
STANDARD

TOE BOARD CLAMP TOE BOARD


500 MM.

(min 100mm HIGH)


O.C. SPACING
TYPICAL
500mm.

Ф 35°-55°
WOODEN PLANK
300mm.
max.

400 MM.
300mm.

O.C. SPACING
PUTLOG COUPLER
max.

500 MM.
max.
500mm.

TOE BOARD Ф 35°-55°


SCAFFOLD BOARD

TRANSOM / LEDGER
WORKING PLATFORM
DETAIL OF CUPLOCK
BRC CLAMP
200mm.
Minimum

Station Work DETAIL 3D. Timber DETAIL TYP. BRACING DETAIL SPIGOT CONNECTION DETAIL BASE JACK DETAIL
CUP-LOCK SYSTEM'

LEDGER 1.25M

LEDGER 1.25M
3 BOARDS WIDE

STANDARD 3.0M

STANDARD 3.0M
SWIVEL GUARDRAILS
LEDGER 1.25M

LADDER 3.50 M
500mm.

1150
900
500mm.

Ф 35°-55°
300mm.
max.
300mm.
max.

ACCESS LADDER SPECIFICATION : ARAMCO SSH


500mm.

Ф 35°-55° ACCESS STEEL LADDER CONFORMING


TO EN-131-1 1993 / BS 2037-1990
SIDERAIL RECTANGULAR TUBE = 25.4 X 50.8mm X 2.0mm Thk.
RUNGS CIRCULAR TUBE = OD 32.0mm X 2mm Thk.
DISTANCE BETWEEN SIDE RAILS = 360mm c/c
RUNG SPACING = 300mm

200mm.
LEDGER 1.25M
Minimum

°
75
spigot spigot

LADDER
TYP. BRACING DETAIL OPENING DETAIL LEDGER 1.25M

LEDGER 1.25M

STANDARD 3.0M

STANDARD 3.0M
500 MM.

LADDER 3.50 M
O.C. SPACING
TYPICAL

STANDARD

WOODEN PLANK

DETAIL OF CUPLOCK PUTLOG COUPLER

TOE BOARD

TRANSOM / LEDGER
BRC CLAMP

LEDGER 1.25M
SPIGOT CONNECTION DETAIL
Station Work DETAIL
LEDGER 1.25M
spigot spigot

POST
LEDGER 1.25M

TOE BOARD CLAMP TOE BOARD


(min 100mm HIGH)
400 MM.

O.C. SPACING
500 MM.
max.

STANDARD 3.0M

STANDARD 3.0M
LADDER 3.50 M
SCAFFOLD BOARD
WORKING PLATFORM

BASE JACK DETAIL

3D. Timber DETAIL

LEDGER 1.25M

Side View of Access


Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

Risk Assessment for Cinema Scaffolding


Project: - Exit 10– Al Hamra Development Project, Riyadh (Warmshell)

Signature

HSSE Engineer- Al-Ramsat HSSE Manager- Al-Ramsat HSSE Manager Shapoorji


Designation Project Director
Contracting Company Contracting Company Pallonji Meddle East L.L.C

00 10-Jun-2024 Kifayat Ullah Dr. Abdul Khader Danny Eastes Christos Grammatikopoulos

Rev. Date Prepared by Approved by Reviewed by Approved by

Page 1 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

Risk Assessment Committee


RA Preparation Members - Consultant approval to be
obtain for HSE staff prior to
mobilization.

Danny Eastes HSSE Manager -SPML


Ayman Attia Elbagouri Project Manager-RCC
Abdul khater HSSE Manager-RCC
Kifayat Ullah HSSE Engineer-RCC
Khaled Reda Site Engineer-RCC
Abdul Aziz Tramboo Projects Coordinator-RCC

Responsible Implementation Members -


Concern Site Engineer: Khaled Reda
Concern Site HSSE Engineer: Kifayat Ullah
Concern Site Foreman:

Page 2 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

Risk Matrix

Page 3 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

Risk Risk
Who might be Who is
Steps Activity Hazards Risk Description Ranking Risk Control Measures Ranking
harmed Responsible
L S R L S R
1 Mobilization of tools and Site or road accidents Personnel onDelay in work, loss 3 3 9 • The required documents shall be presented before entering 1 3 3 Logistic
equipment- the site time, personal injury the site that includes personal iqama, driver’s license and Supervisor
Damage or unapproved Strain or sprain valid insurance registration, and 3rd party certificate of the
(Trailer & Forklift, materials injury equipment and its lifting gears and shall be witnessed by Site Engineer
Scaffolding materials - HSE dept.
cup lock) Heavy Materials • Plant, equipment & operators of the must be 3rd party Site Foreman
certificate
Hand tools- Hammers & Wrong or damaged tools, • Maintain 10km/hr. speed limit on site. Procurement
Spanners) • 3rd party certified banksmen will assist the drivers/operators Engineer
Miss use of tools while reversing the vehicles.
• All Scaffold Materials on site shall be the standard and Scaffolding
approved prior to entry on site & Visual inspection shall be inspector.
done by scaffolding inspector.
• Damage materials to be removed from site. HSE Dept.
• All tools must be properly checked (color coded) and tested
prior to operation and be assured of good condition prior
delivery, tools must be included in Subcontractor register.
• Check tools for damage before use Damage tools store in
safe lock room to restrict it usage
• Operatives must be trained when using all tools
2 Access to and from site Slips, trips and falls Worker Visitors Serious personal 3 4 12 • All waste materials to be removed from the work area as 1 4 4 Site Engineer
injury, or other soon as possible – before break times and the end of the shift
unwanted situations by using of pedestrian walk way that shall be segregated Site Foreman
from the main access displaying appropriate signages.
• All trailing cables to be positioned above head height by Workers
using nonconductive hangers.
??? • Ensure all materials are delivered to the site with the aid of
mechanical means when possible.
• All personnel must acquire PTW before commencing of the
activity with approved documents in hand.
3 Site preparation for Un authorized entry People inside Personal injury 3 5 15 • PTW shall be acquired before commencing of work. 1 5 5 Scaffolding
erection of scaffolding exclusion zone. • Tool box and task briefing shall be done prior to start of the inspector
Falling into the excavation Fatality activity.
• The Approved MESRA must be in hand and briefed to the Scaffolders
Falling of material.
Page 4 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

operatives. Site Engineer


Unstable surface/loose • The area must be barricade and exclusion zone shall be set
ruble around with appropriate signages to prevent unauthorized
entry into the area.
Underground services. • Overhead services like electrical lines shall be disconnected
/Overhead services or removed temporarily by competent electricians.
• LOTO procedure shall be followed in this case.
Floor openings edge • All unwanted materials in the exclusion zone shall be
protection removed and shifted to designated areas.
• Housekeeping should be done on regular basis.
Slip trip and fall • Check nearby excavations are barricade and appropriate
signages like danger deep excavation are posted
• Do not place or store scaffolding material at the edge of the
excavation.
• All floor openings and edge protection shall be secured and
ensured by competent person on site.
4 Scaffold Erection Collapse of scaffolding Operatives and Personal injury 4 5 20 • Only trained & 3rdparty component certified scaffolders 1 5 5 Scaffolding
workers inside must be allowed to erect scaffoldings. inspector
Overloading of scaffolding exclusion zone Fatality • Full time scaffolding supervisor to monitor the erection
sequence as per approved method. Scaffolders
Fall hazard Property damage • All workmen working on scaffolding should wear helmet
with chin strip, safety glasses safety shoes and Double Site Engineer
Falling of tools and Lanyard full body harness and must be 100% tie-off
materials • All tools must be secured by appropriate tool lanyards.
• Scaffold shall be inspected by an approved third party to
Unstable surface/loose ensure the compliance on international and local standards
ruble applicable.
Which excavation is effecting
the subjected activity? • Do not use ladders or make shift devices on top of scaffolds
Unsafe access or place planks on guardrails/mid-rails to gain extra height
• Ensure that build-up of debris on working or access
Erection near to the
platforms is removed.
excavations
• Scaffolding supervisor should inspect the workplace to
avoid overloading of materials and instruct regarding of
Bad Weather conditions
overloading.
• Diagonal brace shall be placed by means of adjustable
couplers tightly connected into vertical member.
• Plan brace shall be placed by means of 90° couplers tightly

Page 5 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

connected into vertical chord.


• Scaffolding bracing and anchoring with RC wall should be
executed as per calculation and site conditions.
• Proper access and egress to be provided and ensured while
erecting, dismantling, and modifying any scaffold.
• The lifeline/proper anchorage and full body harness with
double lanyard to be ensured while doing any activity on
scaffold unless it is on green tag.
• Alteration and modifications shall be done only by
competent scaffolders and shall be in inspected by the
scaffold inspector.
• All raising and lowering of materials to be carried out in a
controlled manner i.e. Hand to hand, by light-line and fitting
bags
• Scaffold erections near to the excavations shall have safe
distance according to the calculation and drawings.
• Guardrails, mid rails and toe boards should be provided as
per the standard.
• Standard single ladders need to extend at least 0.9m above
the landing level, secured at top and base
• At every 6mtr there should be a landing platform
• All the ladders must be installed of the frame.
• Erection of scaffolds to be done in accordance with to
approved drawings procedure if the scaffold exceeds 12-
meter height.
• No work will be undertaken in these adverse weather
conditions unless SEVEN /EllisDon/WME are prior
informed and having approval in accordance with the client
safety standard and Permit to Work Procedure.
How the Risk level can be
Design calculation and shop • National Center for Meteorology source shall be consider
assessed without knowing
drawing shall be submitted
the design and correct and followed and any warning released by the said officials
for consultant approval. will be shared with the project employees via TBTs. All
location? clarify!
materials shall be protected and secured accordingly.
• Refer to SEVEN scaffolding procedure. 0DMQL00-DLVR-
00-SEV-HS-PRO-00024-Scaffolding Procedure
5 Cantilever platforms Collapse of scaffolding Operatives and Personal injury 4 5 20 • Only trained & 3rd party component certified scaffolders 1 5 5 Scaffolding
(Using Tube & Coupler / workers inside must be allowed to erect cantilever platform. inspector
Using Cantilever Bracket) Overloading of scaffolding exclusion zone Fatality • Full time scaffolding supervisor to monitor the erection
Page 6 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

sequence as per approved method. Scaffolders


Fall hazard Property damage • All workmen working on cantilever platform should wear
helmet with chin strip, safety glasses safety shoes and Site Engineer
Falling of tools and Double Lanyard full body harness and must be 100% tie-off
materials • Do not use ladders or make shift devices on top of cantilever
platform or place planks on guardrails/mid-rails to gain
Unstable surface/loose extra height
ruble • Ensure that build-up of debris on working or access
platforms is removed.
Unsafe access • Scaffolding supervisor should inspect the workplace to
avoid overloading of materials and instruct regarding of
Bad Weather conditions overloading.
• Proper access and egress to be provided and ensured while
erecting, dismantling, and modifying any cantilever
platform.
• Alteration and modifications shall be done only by
competent scaffolders and shall be in inspected by the
scaffold inspector.
• Guardrails, mid rails and toe boards should be provided as
per the standard.
• All Cantilever platforms (Using Tube & Coupler / Using
Cantilever Bracket) shall be erected according to the
manufacturer recommendation or according to the industrial
best practices.
• All cantilever platforms shall be inspected and certified by
an Approved Third Party Inspection agency.
• Cantilever platforms shall be used for the intended purpose
and shall always maintain the safe working load as certified
by the Approved Third Party Inspection agency.
• Design calculation and third party inspection certificate
shall be provided.
• No work will be undertaken in these adverse weather
conditions unless SEVEN /EllisDon/WME are prior
informed and having approval in accordance with the client
safety standard and Permit to Work Procedure.
• National Center for Meteorology source shall be consider
and followed and any warning released by the said officials
will be shared with the project employees via TBTs. All
Page 7 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

materials shall be protected and secured accordingly.


• Refer to SEVEN scaffolding procedure. 0DMQL00-DLVR-
00-SEV-HS-PRO-00024-Scaffolding Procedure
6 Alteration and Collapse of scaffolding Operatives and Personal injury 3 5 15 • Alteration and modifications shall be done only by 1 5 5 Scaffolding
modification workers inside competent scaffolders and shall be in inspected by the Supervisor
Fall hazard exclusion zone Fatality scaffold inspector. Red tag will be used for modification.
• All scaffold before handing over must be inspected and Scaffolders
Falling of tools and Property damage Green Tag shall be placed near the access of the scaffold by
materials the inspector. Site Engineer
7 Inspection of scaffold and Fall hazard Operatives and Personal injury 4 5 20 • All scaffold before handing over must be inspected and 1 5 5 Scaffolding
tagging workers inside Green Tag shall be placed near the access of the scaffold by Inspector
Collapse of scaffolding exclusion zone Fatality the appointed scaffold inspector.
• Inspect erected scaffolds regularly to ensure that they are Scaffolders
Property damage maintained in a safe condition.
• After any modification and alteration, the scaffold must be Site Engineer
inspected by the scaffold inspector.
Why the workers are inside
the exclusion zone during the • Red Tag - Scaffold under construction, alternation or status
scaffold inspection, deemed unsafe. Unsafe scaffold, No one allowed to use.
modification and dismantling? • Green Tag- Scaffold complete, inspected – Applied all the
Clarify! legal standards and Fit to use without harness.
• Yellow Tag - In the event a scaffold or platform cannot be
erected by the applicable codes, i.e., handrails or equivalent
fall protection, a Yellow tag will be utilized. This Yellow
tag will have a warning message, "Safety Harnesses Shall
Be Worn, 100% TIE OFF".
• Inspect erected scaffolds regularly to ensure that they are
maintained in a safe condition.
8 Scaffolding Dismantling Collapse of scaffolding Operatives and Personal injury 4 5 20 • Prior to start Dismantling of the scaffold PTW shall be in 1 5 5 Scaffolding
workers inside place. inspector
Fall hazard exclusion zone Fatality • Team should be briefed about the task and safety tool box
talk must be given. Scaffolders
Falling of tools and Property damage • Dismantling shall be done by competent approved 3rd party
materials. certified scaffolders only. Site Engineer
• Scaffolding shall be done in the reverse order of erection
Slip trip and fall sequence
• Full time scaffolding supervisor to monitor the dismantling
Bad Weather conditions sequence.

Page 8 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

• Exclusion zone shall be set around and appropriate signages


like danger scaffolding dismantling in progress shall be
posted.
• All the scaffolders must wear safety helmet with chin strip,
safety glasses safety shoes and double lanyard full body
harness and must be 100% tie-off.
• All tools must be secured by appropriate tool lanyards.
• The dismantling shall be done according to the approved
method only.
• Use proper access only.
• All raising and lowering of materials to be carried out in a
controlled manner i.e. Hand to hand, by light-line and fitting
bags
• Operatives to stand on the platform minimum 2 planks to be
secured by the toe board clips during dismantling
• Below 6 meter of height the FBH should be by passed from
the shock absorbers.
• All dismantle material shall be shifted to designated areas to
avoid trip hazard.
• Do not use ladders or make shift devices on top of scaffolds
or place planks on guardrails/mid-rails to gain extra height.
• No work will be undertaken in these severe weather
conditions unless SEVEN /EllisDon/WME are prior
informed and having approval in accordance with the client
safety standard and Permit to Work Procedure.
• National Center for Meteorology source shall be consider
and followed and any warning released by the said officials
will be shared with the project employees via TBTs.
• All materials shall be protected and secured accordingly.
• Proper access and egress to be provided and ensured while
erecting, dismantling, and modifying any scaffold.
• The lifeline/proper anchorage and full body harness with
double lanyard to be ensured while doing any activity on
scaffold unless it is on green tag.
9 Storing of material Inappropriate material Workers, store Minor or major 3 3 9 • Materials to be stored in a designated area, do not stock 1 3 3 Site Engineer
(scaffold materials) storage. keeper injury, materials in access or escape routes.
• Materials to be stored on stable level base to avoid from Site Foreman
Falling of materials onto Property damage.
Page 9 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh


What are the materials
person storing on racks? toppling down. Store keeper
• Storage of material must be located as close as possible to
Improper access for work force to avoid double manual handling.
personal to reach out for • Materials must not be stacked more than 3 times the
upper rack materials minimum base width.
• Material shifting on higher locations shall be through
designated location of scaffolding
Overloading of racks Workers, store Minor or major 3 3 9 • Heavy materials to be placed in below level racks. 1 3 3 Site Engineer
keeper injury, • Proper platform shall be provided to the store in-charge to
reach out for the top racks. Site Foreman
Property damage. • Make sure the safe load is clearly mentioned on the racks
and tagging for material should be maintained by store Store keeper
keepers.
• Ensure Loads shall not exceed as considered in calculations.
10 Shifting of materials from Heavy materials, sharp, hot, Workers Hand Injuries/ back 3 3 9 • Materials to be loaded in/out close to the point of lift. 1 3 3 Site Engineer
storage to work place by wrong posture injuries, loss time, • Mechanical aid to be used where possible. Gloves to be
mechanical Aid. ( delay in work worn when handling materials that are likely to cause injury Site Foreman
Hydraulic trolley or progress to hands.
forklift ) • Ensure competent, trained and experienced person perform
Strain and sprain the task
injuries • Route of carriage of materials to be clear from tripping
hazards/ obstructions.
The subcontractor store • Materials not to be lifted above people.
located in Cinema building • All materials to be stored in a safe manner on a suitable
first floor, where will be the surface.
forklift usage? clarify!
• All workers must have sort of information about the objects
being used or lifted.
• Make sure the equipment(Forklift) is in safe operating
conditions
• Flagman should assist the operator while reversing
• Do not overload the equipment and the line of site to the
operator must not be blocked.
• Make sure the hydraulic trolley is inspected prior to use
• Do not overload the trolley
• Do not push or dragged on incline and decline position.
• Keep your foot away from the pallet trolley- accidental
release of lever by the operator may cause foot injuries due

Page 10 of 11
Date: 10-06-2024

Risk Assessment for Cinema Scaffolding Rev 00


Next revision: - 10-12-2024

Project: - Exit 10 – Al Hamra Development Project. Riyadh

to load.
11 Manual Handling Over exertion Fall hazards Workers Slip, trip and fall 3 3 9 • Personnel shall be briefed/trained on proper manual material 1 3 3 Site Engineer
(Slip ,Trip & fall) involved in the related injuries. handling techniques. Demonstrates how to do manual
task lifting. Site Foreman
WRULDS(work • Legs shall carry the weight not the back
related upper limb • Do not bend the back while picking up a load, keep the back Workers
disorders) straight
• Before manual lifting make sure the surroundings are safe
to carry the load.
• PPE must be in good condition, shoes shall be anti-slip
resistant
• The topic (manual handling) shall be time to time reminded
to the employees
• Remind personnel through tool box talk to observe proper
positioning when working. However, we cannot totally
obtain excellent ergonomics in construction but at least we
can improve our working position by adjusting our working
platform as iron worker’s/steel erectors to avoid over
reaching or over bending.
• For Each operative maximum 20kg is permissible to lift at a
time.
• If the load is exceeding, buddy system shall be implemented
or mechanical aid such as pallet trolleys shall be used.
Additional Site Requirements
12 Interface with other Lack of coordination and Work force Injury, loss of time, 3 3 9 • Coordination meeting to be set up when possible. 1 3 3 Site Engineer
subcontractor activities communication Exposure involved in the • Project plans review by all parties Communication between
to unknown hazards from activity delay in work various contractors encouraged on supervisory level. Site Foreman
Resident protection by activities by others progress • Signage, barriers to be put in place to mark the work
project exposure locations where activities can be hazardous to others.
• Operatives to be briefed by all site.
13 External factor - Sand Dust Workforce Health problems , 3 3 9 • Proper PPE according client standards to be followed 1 3 3 Site Foreman
storm High winds involved in the respiratory problems • Water shall be sprayed on daily basis on site to minimize the
activity caused by silica dust dust. Workers
• All vehicle should maintain the site.
• NIOSH approved respirator shall be always worn during the
activity.

Page 11 of 11
WME Comment:-Pre-qualification documents to be
submitted separately for consultant approval.
MANAR ALESKAN
Fo r m w o r k & S c a ffo l d i n g

More than branches


in KSA at your Service

Formwork & Scaffolding


Experts

Handbook
www.manaraleskan.com.sa
About US

Manar Aleskan Documents 04


Cuplock System 06
Shorbrace System 25
Steel Waler System 40
SP60 Panel System 57
Profex Panel System 68
Profemax Panel System 84
Variform System 118
Steel Fabrication 127
General Entertainment Authority projects
24
29
39
Steel Waller 750 mm
Steel Waller 1000 mm
Steel Waller 1250 mm
Steel Waller 1500 mm
Steel Waller 1750 mm
Steel Waller 2000 mm
Steel Waller 2500 mm
Steel Waller 3000 mm
Steel Waller 3500 mm
Steel Waller 4000 mm
Steel Waller 4500 mm
Steel Waller 5000 mm
Steel Waller 5500 mm
Steel Waller 6000 mm

51
52
53
54
55
H20 Beam Connection

56
58
59
60
61
62
63
64
65
One Side Wall Formwork

66
One Side Wall Formwork

67
68
69
70
71 71
72
180 cm

73 73
74 74
75 75
76 76
90 X 180 90 X 180 90 X 180 90 X 180 90 X 180

480

80
2

180

80 2
180 2

75 X 180 75 X 180 75 X 180 75 X 180 75 X 180 75 X 180 75 X 180 180.0

77 77
80 2
180 2

60 X 180 60 X 180 60 X 180 60 X 180 60 X 180 60 X 180 60 X 180

180

3.60m
3.00m
90 X 180
90 X 180

90 X 180

78
79
80
8 15.60

81
82
83
81
18

85
18

86
87
88
89
91 90
91 92
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108

108
109
110
111
112 100
113
114
115
116
117
100
119
120
121
122
123
124
125
126
134
128
129
130
131
132
133
134
143 135
136 145
137
Head Office
Address : Ksa - Dammam - Dhahran Jubail Highway - Bin Hindi Tower
Tel. : +966 13 840 7013
Fax : +966 13 840 6582
Email : [email protected]

www.manaraleskan.com.sa
manar_aleskan

You might also like