Scaffolding procedure
Scaffolding procedure
NORTH
10 11 12 13 14 15 16 17 18
QIBLA PART 1 PART 2
PART 3 PART 4
PART 5 PART 6
LEGEND:
DEMISE LINE
EXISTING WALLS
TOP VIEW
EXISTING WALLS
AZ
STRUCTURE
SCAFFOLDING
ACOUSTIC WALL
BA
LIFT
LIFT
SCAFFOLDING DETAILS
1 NTS
BB
VOID
BC
ENGINEER:
SCAFFOLDING
SUPERVISION CONSULTANT:
FOYER
1M01
FIRE EXIT
BD
SCREEN 3 A=180M²
SCREEN 4 A=126M²
SC-03 66 SEATS+2H
SC-04 54 SEATS+2H
SUB-CONTRACTOR:
45
BE
VOID
FIRE EXIT SCREEN 5 A=151M²
SC-05 56 SEATS+2H
AMC CINEMAS
EXIT 10 CINEMAS-RIYADH,KSA
ISSUE STATUS
+201mm
SHOP DRAWING
BF DRAWING TITLE:
0000 L(0)01M 00
KEY PLAN:
13 14 15 16 17 18 19 20
NORTH
QIBLA
AW
STAIR 3
SCAFFOLDING
TOP VIEW
AY
EXIT CORRIDOR
2M01
STAIR 4
ACOUSTIC WALL
STAIR REI 120 NOTE:THE STAIRCASE
FIRE EXIT FROM LEVEL +10.00m TO
LEVEL +14.42m WILL BE
DONE BY TENANT
AZ
EMER. EXIT
SCREEN 11-IMAX-ELITE
SCE-11 46 VIP SEATS+1H
SCREEN 10 A=133M²
SC-10 47 SEATS+2H
SCREEN 7 A=168M²
SC-07 62 SEATS +2H
IMAX ENTRANCE
2M02
REMOVE
FRONT VIEW SIDE VIEW
UP 1
BA SCAFFOLDING DETAILS
FREEZER CHILLER
LIFT
1 NTS
2M04 2M05
LIFT
SCREEN 12-PRIME-ELITE
2M06
22 SEATS+1H
BB EMPLOYER:
ELITE-SCREEN 6 A=132M²
SCE-06
28 SEATS+2H
COMMON AREA
SCE-12
2M11
POT/DISH WASH
DUMB WAITER
2M03 ENGINEER:
RECEIVING
DEBOX AREA STORE
2M07 2M17
57 BC
SUPERVISION CONSULTANT:
BAR
ELITE-SCREEN 1 A=159M²
SCE-01 36 SEATS+2H
MAIN CONTRACTOR:
BD
12
13
FEMALE
DIASABLE WC
2M12
EXIT CORRIDOR
SUB-CONTRACTOR:
2M10
ELITE-SCREEN 2 A=157M²
SCE-02 36 SEATS+2H
BE ELITE MALE
TOILET
CLEANER ELITE-SCREEN 5 A=134M²
2M08
2M15 SCE-05 28 SEATS+2H
ELITE FEMALE
TOILET
2M16
PROJECT TITLE AND LOCATION:
shaft
AMC CINEMAS
FIRE EXIT ELITE-SCREEN 3 A=163M² ELITE-SCREEN 4 A=165M² FIRE EXIT EXIT 10 CINEMAS-RIYADH,KSA
STAIR 1 SCE-03 36 SEATS+2H SCE-04 36 SEATS+2H STAIR 2
ELECTRICAL LIFT / SERVICE
ROOM STAIR REI 120 03-F-025 STAIR REI 120
2M09
ISSUE STATUS
BF
SHOP DRAWING
DRAWING TITLE:
SECOND FLOOR MEZZANINE (SCAFFOLDING LAYOUT) DATE ISSUED: 02 JUNE 2024 SCALE: AS SHOWN PAPER SIZE : A1
1 1 : 125
DRAWN BY: MIRZA CHECKED BY: ENG.EMAD
0000 L(0)02SM 00
CUP-LOCK SYSTEM'
m0
FFL+ 3.645
Tube 1.00 m
Tube 1.00 m
0m 0.1
e 1.0 ebu
Tu b T
FFL+ 2.965
FFL+ 2.285
Tube 1.00 m
Tube 1.00 m
Tu b
e 1.0
0m 0m
e 1.0
Tub
FFL+ 1.605
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 3.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 3.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 3.00 M WOODEN PLANK
m0
FFL+ 3.645
Tube 1.00 m
Tube 1.00 m
0 m 0.1
e 1.0 ebu
Tu b T
3.00 M WOODEN PLANK
FFL+ 2.965
Tube 1.00 m
Tu b
e 1.0
0m 0m
e 1.0
Tub
FFL+ 1.605
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
TRANSOM - 1.25 m
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK 4.00 M WOODEN PLANK
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M mid rail ledger
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M working station
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
.00 m
ER 3
Spigot
LADD
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
TR
TR
M
M
spigot spigot spigot spigot spigot spigot spigot spigot spigot spigot
00
0
6.
6.
BE
BE
TU
TU
G
NG
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
Steel Ladder 3.00 m
IN
I
AC
AC
BR
BR
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
.00 m
hand rail ledger
ER 3
LADD
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M mid rail ledger
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M working station
spigot spigot spigot spigot spigot spigot spigot spigot spigot spigot
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
TR
TR
M
M
00
00
6.
6.
BE
BE
TU
TU
G
NG
IN
I
AC
AC
BR
BR
Cuplock Standard 3.00 m
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
STANDARD 3.0M
m
.00
ER 3
LADD
Base Jack 60 cm
LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M LEDGER 1.80M
Elevation of Access
POST
500mm.
STANDARD
Ф 35°-55°
WOODEN PLANK
300mm.
max.
400 MM.
300mm.
O.C. SPACING
PUTLOG COUPLER
max.
500 MM.
max.
500mm.
TRANSOM / LEDGER
WORKING PLATFORM
DETAIL OF CUPLOCK
BRC CLAMP
200mm.
Minimum
Station Work DETAIL 3D. Timber DETAIL TYP. BRACING DETAIL SPIGOT CONNECTION DETAIL BASE JACK DETAIL
CUP-LOCK SYSTEM'
LEDGER 1.25M
LEDGER 1.25M
3 BOARDS WIDE
STANDARD 3.0M
STANDARD 3.0M
SWIVEL GUARDRAILS
LEDGER 1.25M
LADDER 3.50 M
500mm.
1150
900
500mm.
Ф 35°-55°
300mm.
max.
300mm.
max.
200mm.
LEDGER 1.25M
Minimum
°
75
spigot spigot
LADDER
TYP. BRACING DETAIL OPENING DETAIL LEDGER 1.25M
LEDGER 1.25M
STANDARD 3.0M
STANDARD 3.0M
500 MM.
LADDER 3.50 M
O.C. SPACING
TYPICAL
STANDARD
WOODEN PLANK
TOE BOARD
TRANSOM / LEDGER
BRC CLAMP
LEDGER 1.25M
SPIGOT CONNECTION DETAIL
Station Work DETAIL
LEDGER 1.25M
spigot spigot
POST
LEDGER 1.25M
O.C. SPACING
500 MM.
max.
STANDARD 3.0M
STANDARD 3.0M
LADDER 3.50 M
SCAFFOLD BOARD
WORKING PLATFORM
LEDGER 1.25M
Signature
00 10-Jun-2024 Kifayat Ullah Dr. Abdul Khader Danny Eastes Christos Grammatikopoulos
Page 1 of 11
Date: 10-06-2024
Page 2 of 11
Date: 10-06-2024
Risk Matrix
Page 3 of 11
Date: 10-06-2024
Risk Risk
Who might be Who is
Steps Activity Hazards Risk Description Ranking Risk Control Measures Ranking
harmed Responsible
L S R L S R
1 Mobilization of tools and Site or road accidents Personnel onDelay in work, loss 3 3 9 • The required documents shall be presented before entering 1 3 3 Logistic
equipment- the site time, personal injury the site that includes personal iqama, driver’s license and Supervisor
Damage or unapproved Strain or sprain valid insurance registration, and 3rd party certificate of the
(Trailer & Forklift, materials injury equipment and its lifting gears and shall be witnessed by Site Engineer
Scaffolding materials - HSE dept.
cup lock) Heavy Materials • Plant, equipment & operators of the must be 3rd party Site Foreman
certificate
Hand tools- Hammers & Wrong or damaged tools, • Maintain 10km/hr. speed limit on site. Procurement
Spanners) • 3rd party certified banksmen will assist the drivers/operators Engineer
Miss use of tools while reversing the vehicles.
• All Scaffold Materials on site shall be the standard and Scaffolding
approved prior to entry on site & Visual inspection shall be inspector.
done by scaffolding inspector.
• Damage materials to be removed from site. HSE Dept.
• All tools must be properly checked (color coded) and tested
prior to operation and be assured of good condition prior
delivery, tools must be included in Subcontractor register.
• Check tools for damage before use Damage tools store in
safe lock room to restrict it usage
• Operatives must be trained when using all tools
2 Access to and from site Slips, trips and falls Worker Visitors Serious personal 3 4 12 • All waste materials to be removed from the work area as 1 4 4 Site Engineer
injury, or other soon as possible – before break times and the end of the shift
unwanted situations by using of pedestrian walk way that shall be segregated Site Foreman
from the main access displaying appropriate signages.
• All trailing cables to be positioned above head height by Workers
using nonconductive hangers.
??? • Ensure all materials are delivered to the site with the aid of
mechanical means when possible.
• All personnel must acquire PTW before commencing of the
activity with approved documents in hand.
3 Site preparation for Un authorized entry People inside Personal injury 3 5 15 • PTW shall be acquired before commencing of work. 1 5 5 Scaffolding
erection of scaffolding exclusion zone. • Tool box and task briefing shall be done prior to start of the inspector
Falling into the excavation Fatality activity.
• The Approved MESRA must be in hand and briefed to the Scaffolders
Falling of material.
Page 4 of 11
Date: 10-06-2024
Page 5 of 11
Date: 10-06-2024
Page 8 of 11
Date: 10-06-2024
Page 10 of 11
Date: 10-06-2024
to load.
11 Manual Handling Over exertion Fall hazards Workers Slip, trip and fall 3 3 9 • Personnel shall be briefed/trained on proper manual material 1 3 3 Site Engineer
(Slip ,Trip & fall) involved in the related injuries. handling techniques. Demonstrates how to do manual
task lifting. Site Foreman
WRULDS(work • Legs shall carry the weight not the back
related upper limb • Do not bend the back while picking up a load, keep the back Workers
disorders) straight
• Before manual lifting make sure the surroundings are safe
to carry the load.
• PPE must be in good condition, shoes shall be anti-slip
resistant
• The topic (manual handling) shall be time to time reminded
to the employees
• Remind personnel through tool box talk to observe proper
positioning when working. However, we cannot totally
obtain excellent ergonomics in construction but at least we
can improve our working position by adjusting our working
platform as iron worker’s/steel erectors to avoid over
reaching or over bending.
• For Each operative maximum 20kg is permissible to lift at a
time.
• If the load is exceeding, buddy system shall be implemented
or mechanical aid such as pallet trolleys shall be used.
Additional Site Requirements
12 Interface with other Lack of coordination and Work force Injury, loss of time, 3 3 9 • Coordination meeting to be set up when possible. 1 3 3 Site Engineer
subcontractor activities communication Exposure involved in the • Project plans review by all parties Communication between
to unknown hazards from activity delay in work various contractors encouraged on supervisory level. Site Foreman
Resident protection by activities by others progress • Signage, barriers to be put in place to mark the work
project exposure locations where activities can be hazardous to others.
• Operatives to be briefed by all site.
13 External factor - Sand Dust Workforce Health problems , 3 3 9 • Proper PPE according client standards to be followed 1 3 3 Site Foreman
storm High winds involved in the respiratory problems • Water shall be sprayed on daily basis on site to minimize the
activity caused by silica dust dust. Workers
• All vehicle should maintain the site.
• NIOSH approved respirator shall be always worn during the
activity.
Page 11 of 11
WME Comment:-Pre-qualification documents to be
submitted separately for consultant approval.
MANAR ALESKAN
Fo r m w o r k & S c a ffo l d i n g
Handbook
www.manaraleskan.com.sa
About US
51
52
53
54
55
H20 Beam Connection
56
58
59
60
61
62
63
64
65
One Side Wall Formwork
66
One Side Wall Formwork
67
68
69
70
71 71
72
180 cm
73 73
74 74
75 75
76 76
90 X 180 90 X 180 90 X 180 90 X 180 90 X 180
480
80
2
180
80 2
180 2
77 77
80 2
180 2
180
3.60m
3.00m
90 X 180
90 X 180
90 X 180
78
79
80
8 15.60
81
82
83
81
18
85
18
86
87
88
89
91 90
91 92
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
108
109
110
111
112 100
113
114
115
116
117
100
119
120
121
122
123
124
125
126
134
128
129
130
131
132
133
134
143 135
136 145
137