Assessing the Role of Instrumented Protective Function
Assessing the Role of Instrumented Protective Function
The publication of recent standards for safety instrumented systems has lead to the
need for more explicit understanding of their function and integrity in order to
ensure that they are designed and managed correctly. For existing systems this
brings about a need for assessment, which poses particular challenges for batch
chemical plant which has a flexible operational role. This paper describes the devel-
opment of a method for determining the required safety integrity levels for safety
instrumented systems fitted to batch reactors, and its application to a plant containing
a large number of such reactors, of varying design characteristics, and intended for a
wide range of possible duties.
INTRODUCTION
Baker Petrolite manufactures chemical products for use in the global hydrocarbon recov-
ery and processing industry. Their site at Kirkby, Merseyside operates multi-purpose batch
reactors capable of making a variety of products from a range of raw materials. Some of
the reactions carried out are exothermic in nature, capable of thermal runaway, and the
hazards resulting from this were assessed in the site’s COMAH Safety Report. The
Bases of Safety (BOS) for the reactors rely on process control and operational procedures,
and a mix of safety features or systems such as vessel containment, pressure relief, and
safety instrumented trip systems (SIS). All of the existing SIS were installed prior to the
publication of BS EN 61508 Functional Safety of Electrical/Electronic/Programmable
Electronic Safety Related Systems in 1998. This standard broadly requires that the func-
tion of a SIS should be defined, and that its integrity should be appropriate for this func-
tion. While the standard is not part of safety legislation and is not intended to be applied
retrospectively, it does now represent good engineering practice for SIS, and there is thus
an onus on duty-holders to apply it wherever it is relevant. As is the case in many older
plants, these “legacy” SIS posed questions because there was not a sufficiently detailed
definition of the role allocated to the instrumented safety layer, in the overall protective
arrangements, to enable the appropriate safety integrity level (SIL) to be identified.
While in some reactions the role of the SIS is clearly significant, e.g. a low temperature
trip on hazardous material additions to prevent accumulation, in other recipes made in
the same reactor this SIS would not be a required protection. It is desirable from a pro-
duction viewpoint to have flexibility of use of the reactors, but having a range of possible
duties makes determination of the SIL for the SISs more complex than for reactors with
a more dedicated role. The determination of an appropriate SIL is clearly important in
1
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
maintaining the BOS, but also because there are lifetime costs associated with SIS which
increase as the required SIL increases, and in some cases it may be more appropriate to
replace a SIS with another form of protection rather than modify an existing design.
This paper describes how the BOS of this group of reactors was defined more expli-
citly, so that the role of the SIS could be properly understood, and in so doing a model of
the overall protective arrangements was created which can be utilised in future to evaluate
the impact of any planned operational changes on the BOS.
2
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
process. Where necessary further experimental testing was commissioned until the charac-
teristics of the representative group was thoroughly understood.
3
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
of these individually, because of the large number of recipes in use and hence the team
developed a generic definition of the main batch reaction steps and some key permissives.
These were:
1. Charge reactor with quantity W1 of raw material A.
2. Start Agitator.
3. Charge reactor with quantity W2 of raw material(s) B (&C).
4. Heat to temperature T1.
5. Add catalyst and confirm addition.
6. Confirm cooling available.
7. Add reactive raw material M at rate Q1, (maximum quantity W3).
8. Confirm exotherm has started.
9. Continue to add M under cooling, rate not to exceed Q2, determined by Temperature
between T2 to T3.
These steps were found very useful, along with the lessons from past incidents and
other information on the possible outcomes of failures, in identifying the relevant causes of
runaway reaction, which can be summarised as shown in Figure 1. A principal cause of
unplanned exotherm was seen as accumulation of reactive material, due to causes such
as too high an addition rate, addition at too low a temperature, loss of agitation in the
reactor, or a delay in the start of the exotherm. Loss of cooling to the reactor during the
reaction stage could also give rise to unplanned exotherm. The team identified that for
a small number of recipes there is the potential that if the temperature of the batch went
outside the permitted range, due to not following the operating procedure correctly, con-
tamination, or possibly external fire, then a secondary exothermic reaction could begin
with similar consequences to loss of control of the primary reaction. Finally there was
the potential that unintended materials could be added in error which might react exother-
mically with the intended ingredients.
4
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
5
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
separately. Addition of the wrong material was only feasible through operator error, and a
separate study was begun to consider in detail in which reactions this was possible, and
what were the safeguards against it.
6
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
be a total risk due to the site, then clearly the risk contribution from any one of the
hazards on the site must not exceed some fraction of this total. The allocation of this frac-
tion is an important issue on which there is currently no published guidance from the
authorities. In the absence of guidance it is felt that a reasonable approach is to say
that the maximum tolerable frequency of occurrence for a single hazardous event
should be such that the sum of all hazardous events should not approach the threshold,
and this will normally lead to an overall risk level well within the ALARP region. In
this case there are 15 reactors to consider, which each contribute to the risks posed by
the site. Although it is in fact unlikely, for operational reasons, that all of the reactors
would be at the active reaction stage at the same time, it was decided that each reactor
should have a maximum frequency of occurrence of catastrophic failure which is not
more than 1/100th of the threshold value, or 1 1026 per year. This will mean that
in total, over all reactors, the total frequency of catastrophic runaway events will be
15 1026 per year which represents less than one fifth of the threshold of tolerable
risk for catastrophic events.
Allocation of the reactors to chemistry groups showed that every reactor could have
at least one reaction duty where the chemistry was such that the reaction characteristics
met the criterion for credible failure. This allocation of duties provides a high degree of
operational flexibility, and this situation was seen as presenting an opportunity whereby
some reactors could be restricted in duty, rather than upgraded or improved, should this
be shown to be necessary.
Where an instrumented protective system guards against hazardous events with a
severity outcome which is less than major injury (fractures, unconsciousness, loss of a
limb) it is assumed that an “ungraded” system will provide adequate integrity, and defi-
nition of a maximum tolerable frequency is not necessary. Exceptions to this are where
it is considered that the demand rate may be high, or where the system is required for
asset protection requirements, where SIL 1 is considered appropriate.
7
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
8
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
9
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
No agitation is the probability that the agitation fails or is not effective and the reac-
tion is allowed to continue. In some cases agitation is not significant.
Low temperature addition proceeds is the probability that the reactive ingredient
is added at a temperature below the specified range, allowing a possible accumulation of
unreacted material, and is only a concern in certain cases.
Delayed exotherm trip function was still in design at the time of assessment and
hence a probability of failure on demand at ungraded level was assumed.
Heat generated exceeds natural cooling allows credit to be taken for the fact that
in some cases the natural cooling of the reactor will be sufficient to prevent runaway even
if an exotherm occurs.
Wrong material added is only possible in certain chemistry groups, which were
identified through a separate human error study. An assessment of the error probability
was made using the HEART technique (Williams 1985) which gave the probability of
adding the wrong bulk chemical to a reactor and not detecting the error as 0.00017 per
batch. In the group referred to as the resins the probability of error is reduced further
because these recipes have a laboratory test of the mixed materials, for quality control pur-
poses, before addition of the reactive material, and this would also have to be in error for
the operation to continue.
Secondary decomposition is only possible in a small number of chemistry groups,
and in certain reactors. Decomposition arising from accumulation was felt to be included in
the previous failure contributions, so a separate fault tree analysis of the non-accumulation
cases was carried out.
Frequency of Unplanned exotherm sums the previous contributions for calcu-
lation purposes.
Relief fails to open recognises that there is a probability that this protection (using
bursting discs) will not work as intended, estimated as a probability of failure on demand
of 0.01 (Smith, 1997).
Vessel strength not sufficient quantifies the probability that the reactor will actu-
ally fail under pressure if an uncontrolled exotherm is initiated, and the safety systems
and relief fail to curtail it. In this case the temperature within the reactor will rise to a
level determined by the heat of reaction, volume of material present, and the natural
heat loss from the system, with corresponding increase in pressure. A reactor vessel
built to an appropriate standard and in good condition is likely to withstand several
times its rated design pressure before it fails catastrophically. Pressure vessels are nor-
mally tested in use to 1.5 times the design pressure, and it would be expected that defor-
mation would occur rather than rupture, up to certain elevated pressures. The multiple of
design pressure at which catastrophic failure is actually likely to happen is not well estab-
lished. The Dutch authorities calculation method (CPR 14E 1997) expects a safety factor
of around 2.5, and suggests that rupture consequences be calculated at this multiple of the
design rating. However some practical pressure system design guides require a higher
safety factor to be applied, for example a factor of 4 (Borzileri 1999). In this assessment
it was decided that good construction standards and inspection regime made it reasonable
to assume a safety factor of at least 3.
10
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
Where the maximum foreseeable operational pressure (Pmax) was less than the
design pressure rating (Pdesign) of the vessel, the probability of rupture in use was
assumed to be very small. Where Pmax exceeds Pdesign, the probability of rupture was
assumed to increase, reaching 1 when Pmax/Pdesign is three. The allocation is shown
in the following table.
Pmax/Pdesign (ignoring
pressure relief) Probability of failure
1 0.001
Between 1 and 2 0.01
Between 2 and 3 0.1
3 or above 1
Injuries Result was set at a probability of 0.1 recognising that even in the event of a
catastrophic rupture it is quite likely that injuries could be avoided. Contributing factors
here include that the onset of such a failure would be expected to be relatively slow, allow-
ing time for escape and evacuation, and there would be some shielding provided by the
building and other plant.
CONCLUSIONS
A strategy for evaluating the role of SIS in reactor safety has been developed which allows
the appropriate SIL to be determined in accordance with current standards. The highly
interactive nature of this project provided an invaluable learning opportunity for all
11
SYMPOSIUM SERIES NO. 151 # 2006 IChemE
concerned and raised the awareness of a large cross section of site personnel. The method
takes account of the flexibility of production required in a realistic business scenario, and
allows the contribution to safety from a range of protective layers to be included. The
resulting model should be of benefit in the future in assessing the safety implications of
any planned operational change, and determining the best combination of protective
measures.
REFERENCES
Borzileri, C., Pressure Safety Standard UCRL-AR-128970 Rev 1, May 1999.
Committee for the Prevention of Disasters, Netherlands, CPR 12 E ‘Red Book’, Methods
for Determining and Processing Probabilities, 1997.
Committee for the Prevention of Disasters, Netherlands, CPR 14E, ‘Yellow Book’,
Methods for the Calculation of Physical Effects, Part 2, 1997.
Environmental Protection Agency, CEPP, How to prevent Runaway Reactions, 1999.
Gertman, G I, Blackman, H S, Human Reliability & Safety Analysis Data Handbook,
Wiley Interscience, 1994.
HSE, Reducing Risks, Protecting People, HSE Books, 2001 (R2P2).
Kirwan, B, A Guide to Human Reliability Assessment, Taylor & Francis, 1994.
Lees, F P, Loss Prevention in the Process Industries, Butterworth Heinemann, 1996.
Smith D J, Reliability, Maintainability and Risk, Butterworth-Heinemann, 1997.
Williams J C: HEART – A proposed method for achieving high reliability in process
operation by means of human factors engineering technology, Proceeding of sympo-
sium ‘Achievement of reliability in operating plant’, The Safety and Reliability
Society (Manchester, UK), 1985.
12