MSRA For Lifting & Shifting of Tanks & Equipment's (M1)
MSRA For Lifting & Shifting of Tanks & Equipment's (M1)
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 1 of 34
TABLE OF CONTENTS
1. Introduction 3
2. Purpose 3
3. Scope Matrix 4
3.1 Engineering: 4
3.2 Offloading Tanks & equipment’s from Open flatbed trailers and shifting 4
5. References 7
6. Organization: 8
6.2 Responsibilities: 9
7. Job Sequence 10
7.1 Offloading tanks and equipment’s from open flatbed trailers and shifting 10
8. Specification of equipment 12
8.1 Jacks 12
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 2 of 34
10.2 Offloading tanks and equipment’s from open flatbed trailer and shifting. 24
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 3 of 34
1. INTRODUCTION
Al Faris is proposing for Lifting and shifting of the tanks and other equipments to the final location.
This method statement represents the procedure to be followed, drawings, engineering, and risk
assessments to ensure the safe and secure Lifting & shifting the above stated tanks and equipments.
2. PURPOSE
This method statement is concerned with the lifting of tanks by using 70 Ton mobile crane, 30 Ton
mobile crane, 5 Ton forklift, Loading platform and pallet trolley/skate rollers
It is the aim of this method statement to define and describe the cargo handling, equipment’s involved
and safe working procedures.
Ground
1 Butter Melting Vat 1 1750 3128 x 2128 x 1400
Floor
Butter oil / Vegetable oil Ground
2 2 3500 2550(D) x 5275(H)
storage tank Floor
Ground
3 Butter oil transfer pump 1 80 4500 x 6500
Floor
CIP return pump (Self Ground
4 1 80 4500 x 6500
priming) Floor
Ground
5 Mixing Cum Holding tank 3 1800 2000(D) x 3600(H)
Floor
Ground
6 Rinse Water Tank 1 1000 1800(D) x 3955(H)
Floor
Ground
7 Acid Tank 1 1450 2000 (D) x 3955(H)
Floor
Ground
8 Lye Tank 1 1450 2000 (D) x 3955(H)
Floor
Ground
9 Buffer Tank 1 1800 2000(D) x 3900(H)
Floor
Ground
10 Single stage flush cooler 1 375 1000(D) x 3200(H)
Floor
Sugar Storage Tank with Bin Ground
11 1 2500 3508(D) x 6858(H)
Activator Floor
Ground
12 Bin Activator with Motor 1 1250 2200(D) x 1250(H)
Floor
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 4 of 34
Ground
Powder Silo 1 2000 3508(D) x 6858(H)
13 Floor
Ground
14 Bin Activator with Motor 1 1250 2200(D) x 1250(H)
Floor
First
15 Crystallization tank 5 2050 2000(D) x 4300(H)
Floor
Note: This document is prepared based on information received from the client.
3. SCOPE MATRIX
3.1 Engineering:
AL
S.NO AL FARIS
DESCRIPTION MAHASTEEL
3.2 Offloading Tanks & equipment’s from Open flatbed trailers and shifting
AL
S.NO DESCRIPTION AL FARIS
MAHASTEEL
Providing the clear access to shift the tank to the proposed final
5
location.
Supply of crane, skate rollers, jacks, power cat machine, Pallet
6
trolley for complete operation.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 5 of 34
8 Lift the tank from the trailer by using LTM 1070-4.1 & STC 300.
9 Top and tail the tanks using 70 Ton & 30 Ton crane.
11 Skid the tank from the offloading location to the final location.
AL
S.NO DESCRIPTION AL FARIS
MAHASTEEL
Providing the clear access to shift the tank to the proposed final
4
location.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 6 of 34
11 Top and tail the tanks using 70 Ton & 30 Ton crane.
AL
S.NO DESCRIPTION AL FARIS
MAHASTEEL
7 Floor protection
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 7 of 34
5. REFERENCES
Referenced Documents:
The following documents from Client are referenced herein and shall be considered part of this
Planning.
Refer Documents:
The following documents from Al Faris and shall be considered part of this method statement.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 8 of 34
6. ORGANIZATION:
Client
Representative
Client
Safety Officer
Alternative Lifting
Manager
AlFaris Engineering
AlFaris Supervisor
Equipments
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 9 of 34
6.2 Responsibilities:
The responsibilities for each of the positions in the organization chart are:
Main Contractor : AL MAHA STEEL YARD CONT. LLC
Al Faris:
Technical Manager : He is the responsible person on behalf of Al Faris in all aspects of the operation
even though he is not involved in day-to-day work of this project. He can be made
to involve in the project if and only if the problem at site cannot be solved by the
personnel’s present at site.
Project Engineer : He will Co-ordinate with the Main Contractor and various contractors.
Responsible for the quality and safety of the works. He is empowered to make
decisions on their behalf. He is responsible for making all necessary variations to
the engineering, developing, preparing and additional studies required to fulfil
the requirement of the project.
Supervisor/Foreman : He is responsible for execution of job at site. His responsibilities include use of
the cranes and other equipment, their mobilization / demobilization,
assembly/erection, preparations, directing riggers and other personnel, co-
operating with Main Contractor personnel, and executing the job as per the
approved method statement. He will be directly reporting & co-ordinating to the
Al Faris project engineer. He will be having the power to bring the minor
variation to the plan in accordance with the given method statement as per site
condition.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 10 of 34
7. JOB SEQUENCE
7.1 Offloading tanks and equipment’s from open flatbed trailers and shifting
1. Rig up the main lift crane LTM1070-4.1, 70Ton crane and tailing crane STC-300, 30 Ton mobile
crane at the proposed location.
2. Offload all the tools & accessories.
3. Move the trailer along with the tank to the crane lifting location.
4. Lift the tank from the trailer by 70ton crane & 30ton crane.
5. Tilt the tank to vertical by using 70ton crane & 30ton crane.
6. Lift the agitator and assemble with tank.
Ground floor Tanks and Equipment’s:
7. Lift the tank by crane and offload in front of the room.
8. By using pallet trollies/skate rollers, skid the tank from offloading location to final marking
location.
9. Place jacks and jack up the tank.
10. Remove skate rollers and jack down the tank to the final marking location.
11. Same procedure will be applicable for other tanks and equipment’s in ground floor.
First floor Tanks and Equipment’s:
12. Lift the tank and offload it on the loading platform.
13. Lash the tank with loading platform.
14. Rearrange the lifting gears and lift the loading platform along with tanks.
15. Arrest the loading platform with permanent structures.
16. Skid out the tank from the loading platform by using skate rollers/pallet trollies.
17. Jack down the tank on to the final marking location.
18. Same procedure will be applicable for other tanks and equipment’s in first floor.
19. Demobilize the tools and equipment from site.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 11 of 34
6. Lift the tank by using 70ton crane & 30ton crane and tilt the tank vertical.
7. Lift the agitator and assemble with tank.
Ground floor Tanks and Equipment’s:
8. Lift the tank by crane and offload in front of the room.
9. By using pallet trollies/skate rollers, skid the tank from offloading location to final marking
location.
10. Place jacks and jack up the tank.
11. Remove skate rollers and jack down the tank to the final marking location.
12. Same procedure will be applicable for other tanks and equipment’s in ground floor.
First floor Tanks and Equipment’s:
13. Lift the tank and offload it on the loading platform.
14. Lash the tank with loading platform.
15. Rearrange the lifting gears and lift the loading platform along with tanks.
16. Arrest the loading platform with permanent structures.
17. Skid out the tank from the loading platform by using skate rollers/pallet trollies.
18. Jack down the tank on to the final marking location.
19. Same procedure will be applicable for other tanks and equipment’s in first floor.
20. Demobilize the tools and equipment from site.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 12 of 34
8. SPECIFICATION OF EQUIPMENT
8.1 Jacks
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 13 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 14 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 15 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 16 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 17 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 18 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 19 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 20 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 21 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 22 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 23 of 34
a) All COG (centre of gravity) information is to be specified prior to mobilization of any equipment.
b) All the Al Faris equipment’s within this procedure will have the current valid 3rd party certificate at
the time of execution.
c) All personnel will have documented evidence of competence to do the work and operate any
machinery that they are intended for this purpose.
d) Prior to commencement of work, work areas and exclusion zone will be set up and demarcated using
hazard bunting tape.
e) Ground need to be clear, levelled & compacted.
f) Ground should be able to withstand the load imposed during this operation at working location.
4. All temporary attachments on load should be made secure or removed prior to the operation.
5. During the operation, communication between the team will be through walkie talkie.
6. On the day of operation, there will be a toolbox talk that will review the following items:
a) Procedure, requirements, and details specified in the work plans and drawings. Review of safety
items such as weather concerns, plant activity, escape routes, locations of fire-fighting and personal
safety equipment etc.
c) Complete and sign off all appropriate checklist and safety permits.
e) Check the placement of all banners and barricades that define the safety boundaries of the work
areas.
f) Discuss and give due consideration if any additional appropriate steps that any participant feels if
necessary, to perform a safe and timely operation.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 24 of 34
10.2 Offloading tanks and equipment’s from open flatbed trailer and shifting.
a) LTM1070-4.1, 70ton crane will be used as main lift crane and STC300 30ton crane will be used
as tailing crane for tilting the tanks.
b) Rig up the Main lift crane (70-ton crane) and tailing crane (30ton crane) at the proposed lifting
location.
d) Move the trailer along with tanks and equipment’s near to the crane lifting location.
e) Connect 70ton crane lifting gears to top end of the tank and 30ton crane lifting gears to the tail
end of the tank.
f) By using both cranes, lift the tank from the trailer and move the trailer away from the location.
g) Once the trailer is move away from the lifting location, tilt the tank to vertical position by using
70ton crane and 30ton crane.
h) After tilting the tank, disconnect the lifting gears from the tail end of the tank.
j) Lift the agitator by using 30ton crane and assemble it with tank.
l) Lift the tank by using main lifting crane and offload it on the pre-arranged skate rollers/pallet
trolley.
n) By using skate rollers/pallet trolley, skid the tank from the offloading location to the final marking
location.
o) Once the tank reaches the final marking location, stop the skidding activity.
p) Place jacks and jack up the tank and remove the skate rollers.
r) Same procedure will be applicable for other tanks and equipment’s in ground floor.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 25 of 34
t) Disconnect the lifting gears and lash the tank with loading platform.
v) Lift the loading platform along with tank and swing towards first floor of the factory.
w) Arrest the loading platform with permanent structures by connecting webbing belts.
x) Once the platform is arrested with building, unlash the tank from the loading platform.
y) By using skate rollers/pallet trolley, skid the tank from the loading platform to the final marking
location.
z) Once the tank reaches the final marking location, stop the skidding activity.
aa) Place jacks and jack up the tank and remove the skate rollers.
cc) Same procedure will be applicable for other tanks and equipment’s in first floor.
ee) Demobilize all the tools and equipment from the site.
a) LTM1070-4.1, 70ton crane will be used as main lift crane and STC300 30ton crane will be used as tailing
crane for tilting the tanks.
b) Rig up the Main lift crane (70-ton crane) and tailing crane (30ton crane) at the proposed lifting location.
d) Move the container with tanks and equipment’s near to the crane lifting location.
e) Connect 70ton crane lifting gears to the container and offload the container from the trailer.
f) By using forklift, pull out the tanks and equipment’s from container.
g) Connect 70ton crane lifting gears to top end of the tank and 30ton crane lifting gears to the tail end of
TECH-03-MS/02/001 Rev01 25Nov2021
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 26 of 34
the tank.
h) Top and tail the tank to vertical position by using 70ton crane and 30ton crane.
i) After tilting the tank, disconnect the lifting gears from the tail end of the tank.
k) Lift the agitator by using 30ton crane and assemble it with tank.
m) Lift the tank by using main lifting crane and offload it on the pre-arranged skate rollers/pallet trolley.
o) By using skate rollers/pallet trolley, skid the tank from the offloading location to the final marking
location.
p) Once the tank reaches the final marking location, stop the skidding activity.
q) Place jacks and jack up the tank and remove the skate rollers.
s) Same procedure will be applicable for other tanks and equipment’s in ground floor.
u) Disconnect the lifting gears and lash the tank with loading platform.
w) Lift the loading platform along with tank and swing towards first floor of the factory.
x) Arrest the loading platform with permanent structures by connecting webbing belts.
y) Once the platform is arrested with building, unlash the tank from the loading platform.
z) By using skate rollers/pallet trolley, skid the tank from the loading platform to the final marking location.
aa) Once the tank reaches the final marking location, stop the skidding activity.
TECH-03-MS/02/001 Rev01 25Nov2021
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 27 of 34
bb) Place jacks and jack up the tank and remove the skate rollers.
dd) Same procedure will be applicable for other tanks and equipment’s in first floor.
ff) Demobilize all the tools and equipment from the site.
The safety and health of our employees is of upmost importance and the prevention of occupational
injuries and illnesses will be given the highest priority. The details incorporated in the health, safety and
environmental policy and environmental management guide are an integral part of Al Faris HSE
management system.
Al Faris desire to provide safe and healthy working environment, shall be accomplished by the
following:
d) To provide training for all employees to help them work safely and protect the environment.
e) To comply at all times with all statutory obligations with regards to health, safety and
environmental protection.
g) To analyse risks associated with its operations and define effective remedial or contingency plans.
a) Safety induction will be conducted for all workers on their arrival at the jobsite prior to their field
assignment.
b) At site, Al Faris supervisor and client representative will give toolbox talk for 5 to 10 minutes to
discuss the following subject prior to the commencement of daily work.
c) Hazards associated with the day's work or process and instructions on job safety will also be
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 28 of 34
Accident prevention is of vital concern to everyone in the company. All workers are responsible
for exercising maximum care and good judgment in preventing accidents. By doing so, they are
required to comply with safety regulations stipulated by the site general safety rules and
regulations.
Al Faris scope of work will be concentrated on the job site. With the other programs on hand, Al
Faris will be focusing on safety target "Zero Accidents". That is the ultimate objective.
4. P.P.E
All workers shall wear approved type of safety helmet, safety footwear, safety goggles and safety
gloves at the work site. Other personal protective equipment, e.g. safety harnesses shall be used
as the work situation requires.
5. Housekeeping
a) All materials, equipment and apparatus should be stored neatly in the designated area.
b) All scraps, waste materials and oily rags should be collected, segregated and accordingly disposed
to designated place on daily basis.
6. Fire Prevention
Smoking will be allowed only in the designated, approved areas. Smoking is prohibited in vehicles
or at work site.
a) Supervisor concerned shall furnish a written report on all accidents, regardless of their severity and
submit it to the Engineer for his action.
b) All accidents shall be investigated immediately by the Supervisor/HSE Officer to clarify the cause
and take corrective measures against recurrence of similar accident.
c) Any incident or accident shall be brought to the notice of client HSE officer immediately to take
TECH-03-MS/02/001 Rev01 25Nov2021
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 29 of 34
8. Spill Kit
Spill proof tray will be used to collect oils in case of any spillage found in the hydraulic
equipment’s.
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 30 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 31 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 32 of 34
Job Title: Lifting & shifting of Tanks and equipment’s. Rev : 00 Page: 33 of 34
PLOT LIMIT05
E471572.612
N2750328.559
06 05 04 03 02 01
05
1500
BICYCLE
2000
04
X +0.200m +0.150m Z +0.100m 04 03 02 01 +0.100m
PARKING
3000
03
SECTION I.P. LVL. I.P. LVL. SECTION I.P. LVL. GARBAGE I.P. LVL.
02
CONTAINERS
01
UP
UP UP
RCol
A.R.U.D1
A'
75
FED FED
SOLID WASTE A
HANDLING
4130
PLASTIC PALLET CHEMICAL STORE ALL SECTIONS
CARTOON SPACE STORE R00M 3.65 x 5.25 m
FINISHED GOOD MATERIAL STORAGE 3.05 x 9.80 m
29.89 sq.m
3.65 x 5.25 m +1.35m
7000
+1.35m F.F.LVL.
33.02 x 9.80 m +1.35m F.F.LVL.
MANHOLE
F.F.LVL.
U / G EFFLUENT TANK
ALD ALD 8.00 x 19.00 x 2.00 (WL.)
3346 A1 80,000 Gals Capacity
CLEAR
R.U.D1
PIT SIZE
DOCK
3329 +1.35m
+0.075m
F.F.LVL.
ColR
7600
A3
I.P. LVL.
B
ColR
78
LEVELLER
2060x3000
R.U.D1
PIT SIZE
DOCK
A.R.U.D
M
0.49
0.592
W.M.B 0.850
15127
0.786
1.754
0.91
1.00
3.492
A
1.00
0.625
0.50
C/C 2.216
AIR LOCK LIFT SHAFT
0.28
Recirculation
0.25
A.R.U.D
1.240
1.00
2.350
VOLUMETRIC CAP.19000 L
Line
R
Height 4.237 m Height 4.237 m
B2
Product
2.00 X 2.50
WaterSteam 2.500
SUGAR STORAGE SILO
Heater
Tank 02 (4 KL) Tank 01 (4 KL)
0.63 0.70
POWDER & SUGAR
SYSTEM
Ø3.508
1.451
1.030
CIP SSV
STORAGE AND S
0.10
CIP
Booster 0.650 CLUSTER
Pump 1.040
DEBAGGING ROOM A.R.U.D
H
2.00
LEVELLER
1.00
2060x3000
R.U.D1
PIT SIZE
CLUSTER
15.127 X 8.70 M
DOCK
Product
Pump
Pump
CIP Pump
Recirculation 8700
Pump
CLUSTER Product
POWDER DEBAGGING
Pump
A
0.500
6.000
SYSTEM
1.308
1.00
1.00
+1.35m OIL HANDLING AREA
High Shear Mixer
POWDER
L
CIP
C/C 2.816
F.F.LVL. 5.375 x 5.00 Flow Plate
VOLUMETRIC CAP.19000 L
POWDER STORAGE SILO
Steam Hot Water Battery
PALLET
Y
5000
HEIGHT 7.00M.
Motorised Hoist
I
Ø3.508
0.75
STORAGE
CIP SSV RECOVERY
1.30
SYSTEM
Heater 1.50 Butter Oil Tank
(12 KL) 0.3
Vegetable Oil Tank
(12 KL)
Ladder
SECTION
+1.35m 5375
2.25
N
Height 5.3815 m Height 5.3815 m
0.50 CG
W.M.B
Pump 0.625
Oil Barrels Oil Barrels
0.625
Ladder
LEVELLER
G
Ladder Platform Width 0.625 m
2060x3000
0.38 0.36
R.U.D1
1.000
PIT SIZE
0.5485 SD SD
DOCK
0.592
0.50
1.200
V.W02 V.W02 V.W02 V.W03 V.W02 V.W02 A.R.U.D
SANY (30Te)
Steam Hot Water Battery
ElEvatiOn - 02
Pump
Imulsion tank
SECTION (250 L)
0.80
B4
STC300S
5.475 X 7.50 M R
0.50
Pump
HEIGHT 7.00
+1.35m
E
W.M.B
0.35 0.30
7500
F.F.LVL.
LEVELLER
2060x3000
R.U.D1
PIT SIZE
A
DOCK
Butter Melting System
2000 +0.050m
Pump
1.35
V.W02 I.P. LVL.
RIO Panel
0.30
5475
1.25
0.58
INTERLOCK PAVING
LEVELLER
2060x3000
( PAVERS/INTERLOCKS
R.U.D1
PIT SIZE
DOCK
SODP01
S.D02
D1
R00M DRIVER'S RM.
1500
12 11 10 09 08 07
15 PANTRY E
14 15 16 17
3100
3100
DISINFECTION AREA
S
3.00 x 3.10
3600
WIND
003
06 W4
HANDICAP TOIL. 3.00 x 3.10 13 12 11 10 09 08 07 06 05 04 03 02 01 3300
05
5.00 x 3.40 m 6281
LIFT SHAFT 3000 1.975 x 3.10
1800
04
UP TO MEZZ. FLOOR
PANTRY
R9
2.20 x 1.60
03
5000 UP D5 TOI.
5700
02 V1
4000
00
UP
01 D1 D3 D1 9981
UP +1.35m
3700
+0.45m
R75
1.50 M. WIDE PASSAGE D1 D1 PASSAGE 4200
F.F.LVL. F.F.LVL.
DINING 1800 AIR LOCK
LOBBY ENTRANCE
5.30 x 5.30 D5 4.20 x 2.10 m
2.50 x 5.00 m
W3
UP GENERAL NOTES:
CHANGING AREA
3100 D1
5300
3100
WC All dimensions in 'mm' & weight in Tons Unless specified.
FEMALE
D1
5000
R7500
D5
MALE TOILET
3600
SUB-ELECTRICAL WC D4 2500
+0.025m (Eg: C.O.G, Dimension, weight & Work area drawing etc.,)
2700
TOILET D5 D5 D5 D5 D5 7271
3.00 x 1.80 D5 D1
Hirer should ensure no underground services below the jack
D
3000 5300 5000 D4
WC WC WC WC WC WC
ALD02 location & the ground to bear the load from crane jack.
NTRANCE W1 W3 V1 V1 V1 V1 V1 V1 W3
D'
03
1500
ERANDAH UP
3481
02
Z R4 U / G STORM WATER TANK
SECTION
500 2.50 x 4.00 x 2.00 (WL.)
5,000 Gals Capacity
01
X DRIVEWAY
MANHOLE
LOCATION: DIC
SECTION
AL FARIS
05' 04 03 +0.025m 02 01
HUMP
6000
I.P. LVL.
+0.050m
I.P. LVL. U / G HOLDING TANK
13.00 x 6.00 x 2.00 (WL.)
40,000 Gals Capacity DRIVEWAY R9
11 NOS OF CAR PARKINGS 0 000
450
MANHOLE MANHOLE
CLIENT: AL MAHA STEEL YARD CONT. LLC
R
GUARD
PROJECT: LIFTING OF TANK
11 12 13 14 15 16 17 18 19 20 21
DRG.TITLE: RIGGING SKETCH SHOWING LIFTING OF TANK
SIL06193CRRSM1 1 of 6
Operating radius
Boom angle
LIEBHERR LTM 1070-4.1
MOBILE CRANE (70 Te) Under sheave height
Boom length
Swing angle
STC300S
SANY (30Te)
MA
IN
BO
Boom Counter Outrigger
OM
configuration weights dimensions
m
LEN
.68
GT
- 23
H-
Crane capacity
TH
28.
NG
Operating radius
9m
LE
Boom angle
OM
Boom length
MA
Swing angle
Outrigger Span 5.2X6.0 m Outrigger Span 8.0X6.3 m 00 21-09-22 Issued for Review PRP SS
REV DATE DESCRIPTION DRN CKD APR
Crane Counter Weight 5.9 t Crane Counter Weight 14.5 t LOCATION: DIC
GROUND FLOOR ELEVATION VIEW-SHOWING TOP AND TAILING OF TANK Load Analysis, Max. Lift Weight - 2.32Ton Load Analysis, Max. Lift Weight - 4.20Ton
Weight of the Hook Block 0.32 t Weight of the Hook Block 0.45 t PROJECT: LIFTING OF TANK
Boom angle
Boom length
Swing angle
MA
IN B
OO
Boom Counter Outrigger
configuration weights dimensions
ML
EN
No. of part lines
GT
Wt. of load to be lifted
H-
Crane capacity
28.
Operating radius
Boom angle
9m
Under sheave height
Boom length
Swing angle
% of Chart Capacity %
DRG.No.: SI-L-06193-CR-RS-M1 3 of 6
24.85
128.06m [420.15']
PLOT LIMIT05
E471572.612
N2750328.559
13 12 11 10 09 08 07 06 05 04 03 02 01
ElEvatiOn - 03
X Z
SECTION SECTION
A'
SOD03
5.00 X 6.00
A
A1
(10.00 X 3.35 M)
Clear Height7.00m
SECTION
S.D01
6.225
A
1.75
0.30 0.25
W.M.B W.M.B W.M.B
2.725
2.975 x 3.30
0.80
0.25
0.25
0.25
MATERIAL USED
Pump Pump Pump
0.25 0.25 0.25
1.00
+1.35m
F.F.LVL.
10000
1.483
(10.00 X 8.70 M)
CLUSTER
Clear Height7.00m
2.00
CIP Pump
Crystallisation Tank 05 Pump Pump Crystallisation Tank 04
(6 KL) (6 KL)
1.80
PACKAGING AREA
0.35
0.35
77.98 x 24.20 M
+10.35m
B4
SANY (30Te)
11a 10a F.F.LVL.
STC300S
FUTURE EQUIPMENT AREA
SOD03
FED
MARSHALING
5.00 X 6.00
66
UP AREA
TO Roof Floor
67
68
69
70
46 +10.35m
F.F.LVL.
47
48 +10.35m C1
51 50 49 F.F.LVL.
1500
3100
3400
11750 44 61 8500 53 11881
45 60 2.10 X 3.10 39 38 37 36 35 34 33 32 31 30 29 28 27 54
4700
55
46 LIFT SHAFT 59 DN
2700 D2 +10.35m
2400
47 58
2.20 x 1.60
2700
2100
6300
48 57
LOBBY F.F.LVL.
2500
26231 49 56
50 55
51 54
DN 52 53 11600 4300
8700
8700
+8.85m UP
1700
1400
D2 R.F.LVL.
11700
5300
W7 27981
4000
ROOF DECK +8.85m D' D
MATERIAL USED R.F.LVL.
FOR ROOF SHOULD
14 BE SRI > 78
5.
50
'] GENERAL NOTES:
Z
All dimensions in 'mm' & weight in Tons Unless specified.
SECTION
12' 12 11 10 09' 05' 04 03 02 01
X
ElEvatiOn - 01 SECTION This drawing is made on information provided by the hirer.
(Eg: C.O.G, Dimension, weight & Work area drawing etc.,)
Hirer should ensure no underground services below the jack
location & the ground to bear the load from crane jack.
03
02
AL FARIS
E471532.581
N2750222.445
FIRST FLOOR PLAN VIEW SHOWING LIFTING OF TANK PROJECT: LIFTING OF TANK
DRG.No.: SIL06193CRRSM1 4 of 6
Operating radius
Boom length
Swing angle
STC300S
SANY (30Te)
MA
IN B
OO
Boom Counter Outrigger
configuration weights dimensions
ML
m
EN
.68
GT
No. of part lines
- 23
H-
TH
Crane capacity
28.
NG
Operating radius
9m
LE
Boom angle
OM
Boom length
MA
Swing angle
Outrigger Span 5.2X6.0 m Outrigger Span 8.0X6.3 m 00 21-09-22 Issued for Review PRP SS
REV DATE DESCRIPTION DRN CKD APR
Crane Counter Weight 5.9 t Crane Counter Weight 14.5 t LOCATION: DIC
FIRST FLOOR ELEVATION VIEW-SHOWING TOP AND TAILING OF TANK Load Analysis, Max. Lift Weight - 1.57Ton Load Analysis, Max. Lift Weight - 2.75Ton
Weight of the Hook Block 0.32 t Weight of the Hook Block 0.45 t PROJECT: LIFTING OF TANK
Boom angle
Boom length
Swing angle
MA
IN
BO
OM
Boom Counter Outrigger
configuration weights dimensions
LEN
No. of part lines
GT
Wt. of load to be lifted
H-
Crane capacity
28.
Operating radius
Boom angle
9m
Under sheave height
Boom length
Swing angle
% of Chart Capacity %
DRG.No.: SI-L-06193-CR-RS-M1 6 of 6
23.67
Personnel involved in
offloading activities may get Suitable lifting gears with adequate
Improper handling capacities should be selected prior to
slip from trailer & fall.
of lifting gears. job.
Damage to the client
Unsafe access for Visual inspection of lifting gears before
5. Offloading property and damages to Supervisor/
connecting and use.
skidding tools & tools.
disconnecting Foreman/
accessories 3 4 12 Maintain daily check list of crane. 1 3 3
lifting gears to the Finger injuries, slip and fall
load. Rigger/Crane
injuries. Operator and riggers must competent operator
Non‐use of PPE. and certified.
Fall of load while lifting.
Tipping hazard Check SWL of crane and work under the
limit.
AL FARIS
Signature
Minor injuries or
2 ‐Minor 2 4 6 8 10 12 >10 & <100 Minor effect Minor impact
health effects