0% found this document useful (0 votes)
23 views

rate

The document outlines detailed calculations and costs for various construction activities including Neeru finish plaster, sandfaced double coat plaster, vitrified tile flooring, and more. Each section provides quantities, rates, and total amounts for materials, labor, and additional expenses, culminating in a grand total for each type of work. The overall total amount for all items listed is 98729.89 for Neeru finish plaster, 144453.81 for sandfaced plaster, and other specific totals for additional tasks.

Uploaded by

Hrishikesh Moze
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views

rate

The document outlines detailed calculations and costs for various construction activities including Neeru finish plaster, sandfaced double coat plaster, vitrified tile flooring, and more. Each section provides quantities, rates, and total amounts for materials, labor, and additional expenses, culminating in a grand total for each type of work. The overall total amount for all items listed is 98729.89 for Neeru finish plaster, 144453.81 for sandfaced plaster, and other specific totals for additional tasks.

Uploaded by

Hrishikesh Moze
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

ITEM NEERU FINISH (SANALA )PLASTER 8MMTO 10MM THICK FOR CEILING IN CM UNIT

DETAILS 1;3 QUANTITY 329.1 SQM


ASSUMED
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL MORTAR FOR 1SQM= 0.012 CUM
FOR 329.1 SQM = 3.94 CUM
THEREFORE,3.94 CUM/(SUM OF
PROPOTION)
THEREFORE3.94 CUM/(1+3)
THEREFORE,VALUE FOR 1 IS
0.98

1. CEMENT 0.98 cum x 30 BAGS 30 BAGS 300 9000


2. RIVER SAND (0.98 cum x 2)+(0.245 cum)
Added 25% screening wastage 2.205 CUM 2133.00 4703.6
(Fine aggregate)
Add for sanala 329.1sqm x 0.1 bag per Sqm 33 BAGS 130 4290

TOTAL 17993.6
B WASTAGE @ 5% 899.68

C SCAFFOLDING @ 179.93
1%

D WATER & 359.87


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 329.1 Sqm 200 65820

TOTAL 85852.08
F PROFIT 12877.81
G TOTAL AMOUNT Sqm 98729.89
RATE FOR 299.99
1Sqm
NEERU FINISH (SANALA) PLASTER IN CM 1:3

SANDFACED DOUBLE COAT PLASTER FOR WALL CM 1:4


ITEM SANDFACED DOUBLE COAT PLASTER 18MM TO 20 MM THICK FOR WALL IN UNIT
DETAILS CM 1:4 QUANTITY 329.1 SQM
ASSUMED
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL MORTAR FOR 1SQM= 0.024 CUM
FOR 329.1 SQM = 7.89CUM
THEREFORE,7.89 CUM/(SUM OF
PROPOTION)
THEREFORE,7.89 CUM/(1+4)
THEREFORE,VALUE FOR 1 IS
1.58

1. CEMENT 1.58 cum x 30 BAGS 48 BAGS 300 14,400


(1 cum = 30 BAGS)
2. RIVER SAND (1.58 cum x4)+(0.39 cum) 6.71 CUM 2650.00 17781.5
Added 25% screening wastage
(Fine aggregate)

TOTAL 32181.5
B WASTAGE @ 5% 1609.07

C SCAFFOLDING @ 321.815
1%

D WATER & 643.63


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 329.1 Sqm 270 88857

TOTAL 125612.01
F PROFIT 18841.8
G TOTAL AMOUNT Sqm 144453.81
RATE FOR 438.93
1Sqm

VITRIFIED TILE FLOORING IN CM 1:5 WITH CEMENT SLURRY


ITEM VITRIFIED TILE FLOORING 35MM THICK SUB BASE IN CM 1:5 WIT CEMENT UNIT
DETAILS SLURRY QUANTITY 117 SQM
ASSUMED
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL
1. VITRIFIED TILE 117 SQM 550 64350
2. MORTAR FOR 1SQM= 0.042CUM
FOR 117 SQM = 4.91 CUM
THEREFORE,4.91 CUM/(SUM OF
PROPOTION)
THEREFORE,4.91 CUM/(1+5)
THEREFORE,VALUE FOR 1 IS
0.82

3 CEMENT 0.82 cum x 30 BAGS 25 BAGS 300 7500


(1 cum = 30 BAGS)
4 CRUSH SAND 0.82 cum x 5 4.1 CUM 1009 4136.9
(Fine aggregate)
5. ADD EXTRA
CEMENT FOR 0.1 BAG PER SQM X 117 SQM 12 BAGS 300 3600
BACKING PASTE
TOTAL 79586.9
B WASTAGE @ 5% 3979.34

C PLANT , 795.86
MACHINERY &
EQIPMENTS @ 1%

D WATER & 1591.73


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 117 Sqm 280 32760

TOTAL 119713.83
F PROFIT 17957.07
G TOTAL AMOUNT Sqm 137670.90
RATE FOR 1176.67
1Sqm

ITEM VITRIFIED TILE FOR WALL (DADO) 15MM THICK BACKING UNIT
DETAILS QUANTITY 28SQM
CM1:2 ASSUMED
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL
FOR 1SQM=0.018CUM 150 SQM 480 72000
FOR 28 SQM=0.504CUM
1 VITRIFIED TILE THEREFORE 0.0504CUM/(1+2)
THEREFORE 1 IS 0.17

2 CEMENT 0.17CUMX30 6 BAG 300 1800


1CUM=30 BAGS
3 SCREENED SAND 0.17CUMX2+(0.0425CUM)
(FINE AGGREGATE) ADD 25% SCREENING WASTAGE 0.2125 CUM 2650.00 563.12
TOTAL A 74463.12
B WASTAGE @ 5% 3723.15

C PLANT ,MACHINERY 744.63


& EQUIPMENTS @
1%

D WATER & 1489.26


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 28 SQM 280.00 7840

TOTAL 88360.16
F PROFIT 13254.02
G TOTAL AMOUNT CUM 101614.18
RATE FOR 3629.07
1CUM
VITRIFIED TILE FOR WALL (DADO) 15MM THICK BACKING CM1:2

NEERU FINISH (SANALA) PLASTER 12MMTO 15MM THICK FOR WALL


IN CM 1;4
ITEM UNIT
DETAILS QUANTITY 329.1 SQM
NEERU FINISH (SANALA) PLASTER 12MMTO 15MM THICK ASSUMED
FOR WALL
IN CM 1;4
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL
FOR 1SQM=0.018CUM
FOR 329.1SQM=1.80CUM
1. MORTOR THEREFORE 5.92 CUM /(1+2) `
THEREFORE 1 IS 1.98

2 CEMENT 1.98 CUM X 30 60 BAG 300.00 18000


1CUM=30 BAGS
1.98 CUMX4+(0.495CUM)
3 RIVER SAND ADD 25% SCREENING WASTAGE 2.475 CUM 2650.00 5247.5

FINE AGGREAGATE 329.1SQMX0.1BAG PER SQM 33 BAG 130.00 4290

TOTAL 27537.5

B WASTAGE @ 5% 1376.87

C PLANT ,MACHINERY 275.375


& EQUIPMENTS @
1%

D WATER & 550.75


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 329.1 SQM 220 72402

TOTAL 102142.49
F PROFIT 15321.37
G TOTAL AMOUNT SQM 117463.86
RATE FOR 356.92
1SQM

BRICK BAT WATERPROOF TREATMENT


ITEM BRICK BAT WATERPROOF TREATMENT 100MM THICK INCM1:4 UNIT
DETAILS WITH SMOOTH SURFACE FINISH QUANTITY 28 SQM
ASSUMED
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL

28 SQMX35NO 980 NO 7.00 6860


1 BRICKS
FOR 1SQM=0.053
FOR 28SQM=1.484
THEREFORE1.484
THEREFORE 1.484
CUM(1+3)
THE VALUE FOR ONE IS 0.3
2 CEMENT 0.3CUMX30 9 BAGS 300 2700
1CUM=30BAGS
3 CRUSH SAND 0.3X3 0.9 CUM 990 891

TOTAL 10451
B WASTAGE @ 5% 522.55

C PLANT, MACHINERY 104.51


& EQUIPMENTS @
1%

D WATER & 209.02


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 28 CUM 280 7840

TOTAL 19227.08
F PROFIT 2884.062
G TOTAL AMOUNT 28 CUM 22111.14
RATE FOR 789.68
1CUM

KOTA STONE FLOORING (HAND DREESED /MACHINECUT)50M M


ITEM KOTA STONE FLOORING (HAND DREESED UNIT
DETAILS QUANTITY 117SQM
/MACHINECUT)50M M THICK SUB BASE 1:5 WITH CEMENT ASSUMED
PASTE BACKING
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL CONSIDERING 20%HAND
DRESSING /CUTTING WASTAGE
117SQM+35SQM
FOR 1SQM=0.060CUM 152 SQM 280 42560
FOR 152SQM=91.2(SUM OF
PROPOTION)
THEREFORE 91.2CUM/(1+5)
1. KOTA STONE THEREFORE VALUE FOR 1 IS
2. MORTOR 15.2
3 CEMENT
4 CRUSH SAND 15.2CUMX30 30 BAG 300 9000
5 ADD EXTRA 1CUM=30BAGS
6 CEMENT FOR 5 CUM 990.00 4950
BACKING PASTE 15.2CUMX5

0.1 BAG PER SQMX15.2SQM 10 BAG 280 2800

TOTAL 59310
B WASTAGE @ 5% 2965.5

C PLANT, MACHINERY 593.1


& EQUIPMENTS @
1%

D WATER & 1186.2


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 117 SQM 380.00 44460.00

TOTAL 109514.8
F PROFIT 16427.22
G TOTAL AMOUNT 125942.02
RATE FOR 1076.42
1sqm

RUBBLE SOLING 230MM THICK WITH MURUM BLINDAGE COARSE


ITEM RUBBLE SOLING 230MM THICK WITH MURUM BLINDAGE COARSE UNIT
DETAILS QUANTITY 35 CUM
ASSUMED
ITEM NO. ITEM NO. CALCULATIONS QUANTITY UNIT RATE/UNIT AMOUNT
A MATERIAL 35CUM+3.5CUM
38.5 CUM 560 21560
(ADD 10%DRESSING WASTAGE)
50MM LOOSE MURUM LAYERED
OVER RUBBLE SOLING FOR
FILLING THE SAME INTO SOLING
GAPS
1. RUBBLE 50MM/230MM=20%
2. MURUM FOR 35 CUMX20%=7CUM 7 CUM 430.00 3010
BLINDAGE COARSE

TOTAL 24570
B WASTAGE @ 5% 1228.5

C PLANT ,MACHINERY 245.7


& EQUIPMENTS @
1%

D WATER & 491.4


ELECTRICITY
CURING @ 2%

E LABOUR CHARGES 38.5 CUM 530 20405

TOTAL 48140.6
F PROFIT 7221.09
G TOTAL AMOUNT CUM 55361.69
RATE FOR 1437.96
1CUM

You might also like