MNPHI Nadhee Weekly report 122

The Naadhee project, managed by Apex Realty Pvt Ltd for MNPHI, is currently 71% complete with a total duration of 48 months and an elapsed time of 1007 days. Key activities include the completion of multiple floor slabs and significant progress in finishing and MEP works, with various tasks at different completion percentages. The project is on track for completion by December 1, 2026.

Uploaded by

Ravendra Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views

MNPHI Nadhee Weekly report 122

The Naadhee project, managed by Apex Realty Pvt Ltd for MNPHI, is currently 71% complete with a total duration of 48 months and an elapsed time of 1007 days. Key activities include the completion of multiple floor slabs and significant progress in finishing and MEP works, with various tasks at different completion percentages. The project is on track for completion by December 1, 2026.

Uploaded by

Ravendra Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

NADHEE - WEEKLY REPORT

Project Name: Naadhee


Overall
Contractor: Apex Realty Pvt Ltd.
Completion %
71%
Client: MNPHI
Start date: 12/01/22 Total project duration: 48 Months Reporting Date: 6/2/25
Completion date: 12/01/26 Total elapsed days: 1007days Week Number: 160
Consultant: Riyan Pvt Ltd Lost work days: 36 days Dates: 6/2/25
SN Activity Due Date Completed % Comments
Completion of foundation works (Excavation,
1 26/03/23 100% Completed on 01/10/22.
PCC, Raft)
2 Basement Floor/1st Slab (1 no’s slab) 25/05/23 100% Completed on 24/12/22.
Completion of Ground, Mezzanine and 1st
3 20/08/23 100% Completed on 23/06/23
floor slabs (3 no’s slabs)
Tower A 8th Floor Slab Concrete Completed on 23/12/23
Tower B 8th Floor Slab Concrete Completed on 12/01/24
Completion of 2nd, 3rd, 4th,5th ,6th ,7th ,08th
Tower A 09th Floor Slab Concrete Completed on 26/01/24
4 ,09th, Terrace floor and Roof Slab 22/08/24 100%
Tower B 09th Floor Slab Concrete Completed on 10/02/24
(10 no’s slab)
T- A Terrace Floor Slab Concrete Completed on 01/03/24
T- B Terrace Floor Slab Concrete Completed on 15/03/24
Ground Floor Block Masonry work – 70% completed.
First Floor Block Masonry work – 100% completed.
Finishing Work-Completion of Basement, First Floor plastering work 100% Completed
5 Ground, Mezzanine and 1st floor (up to 1st 29/07/24 61% 01st Floor Waterproofing Work 100% Completed
floor level) 01st Floor Screed Work 100% Completed
01st Floor Tiling Work 28% Completed
01st Floor External Plastering 75% Completed
02nd to 05th Floor External plastering Work 85% Completed
02nd to 05th Floor Internal Plaster-100% Completed
02nd Floor Waterproofing Work 100% Completed
03rd Floor Waterproofing Work 100% Completed
Finishing Work-Completion of 2nd, 3rd, 4th
6 09/12/24 71% 04th Floor Waterproofing Work 100% Completed
and 5th floor.
05th Floor Waterproofing Work 92% Completed
02nd to 5th Floor Screed Work 90% Completed
02nd to 5th Floor Tiling Work 77% Completed
02nd to 5th Floor Window Fixing Work 92%Completed
06th to 09th Floor External Plastering Work 92% Completed
06th to 09th Floor Internal Plaster-98% Completed
06th to 09th Floor Waterproofing Work 72% Completed
Finishing Work-Completion of 6th, 7th, 8th 06th to 09th Floor Screed Work 67% Completed
7 16/06/25 62%
and 9th floor. 06th to 09th Floor Tiling Work 62% Completed
06th to 09th Floor External Paint Work 16% completed.
06th to 09th Floor Window Fixing Work-88%Completed
Terrace Floor Block Work – 85% Completed
Swimming Tiling work -30% Completed
Open Terrace Floor Water Proofing -85% Completed
Finishing Work Completion of Lift m/c room,
8 06/05/25 49.5% (Deck)
Above Terrace & other misc. facilities
Terrace Roof Tiling Work -100% Completed
Terrace Floor Screed Work 80% Completed
Terrace Floor Tiling work -70% Completed
Mezzanine plumping work -35% Completed
Ground floor plumping work- 15% Completed
01st -Floor Wall Conduiting Work 100% Completed
MEP Work-Completion of Ground,
9 02/10/24 60% 01st - Floor Internal Plumbing 100% Completed
Mezzanine and 1st floor (up to 1st floor level)
01st – Floor Wall Conduiting Work 90% Completed
01st – Floor AC Piping Work 80% Completed

02nd to 05th -Floor- Wall Conduiting 100% Completed


MEP Work-Completion of 2nd, 3rd, 4th and 02nd to 05th -Floor- Int Plumbing Work- 100% Completed
10 12/02/25 75%
5th floor. 03rd to 05th -Floor- Wiring Work -80% Completed
02nd to 05th – Floor -AC Piping Work 80% Completed

06th to 9th Floor - Wall Conduiting work 100% Completed


MEP Work-Completion of 6th, 7th, 8th and 06th Floor- Wiring Work -85% Completed
11 16/06/25 45%
9th floor. 06th to 9th - Floor Internal Plumping Work- 90% Completed
06th to 09th – Floor -AC Piping Work 60% Completed

Wall Conduiting work- 85% Completed


MEP Work Completion of Lift m/c shaft,
12 20/06/25 22% 1st to 6th - Floor Firefighting piping- 65 % completed
Above Terrace & other misc. facilities
Lift M/C-Shaft Preparation – 55% completed

Approved by: Prepared by:


Name: Kallol Biswas Name: Ravendra Sharma
Designation: GM - Projects Designation: Planning Manager