The document outlines the project schedule for the Golden Tulip Residential development, detailing activities, planned durations, and start and finish dates from October 3, 2023, to March 3, 2025. Key activities include design, construction, and various specialized works such as plumbing, electrical, and structural tasks. The schedule is organized hierarchically with specific activity IDs for tracking progress.

Uploaded by

ramkrishnan2219
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

GT Copy

The document outlines the project schedule for the Golden Tulip Residential development, detailing activities, planned durations, and start and finish dates from October 3, 2023, to March 3, 2025. Key activities include design, construction, and various specialized works such as plumbing, electrical, and structural tasks. The schedule is organized hierarchically with specific activity IDs for tracking progress.

Uploaded by

ramkrishnan2219
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 29

Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23

Activity ID Activity Name Planned Planned Start Planned


Duration Finish

GTS1 Golden Tulip Residential 429 03-Oct-23 03-Mar-25

GTS1.2 Design 25 03-Oct-23 01-Nov-23

GTS1.2.1 Release of Tender Package (with Approval) 14 03-Oct-23 18-Oct-23


GTS1.2.2 Issue of Construction Drawings 5 03-Oct-23 07-Oct-23
GTS1.2.3 Procurement 25 03-Oct-23 01-Nov-23
GTS1.2.3.1 Water Proofing 25 03-Oct-23 01-Nov-23
GTS1.2.3.2 Electrical Works - Low Side 25 03-Oct-23 01-Nov-23
GTS1.2.3.3 Door and Shutters 25 03-Oct-23 01-Nov-23
GTS1.2.3.4 Plumbing Works 25 03-Oct-23 01-Nov-23
GTS1.2.3.5 STP 25 03-Oct-23 01-Nov-23
GTS1.2.3.6 WTP 25 03-Oct-23 01-Nov-23
GTS1.2.3.7 Basement Ventilation 25 03-Oct-23 01-Nov-23
GTS1.2.3.8 DG Sets 25 03-Oct-23 01-Nov-23
GTS1.2.3.9 Lift/Elevator 25 03-Oct-23 01-Nov-23
GTS1.2.3.10 Electrical High Side 25 03-Oct-23 01-Nov-23
GTS1.2.3.11 UPVC Windows 25 03-Oct-23 01-Nov-23
GTS1.2.3.12 Security System - CCTV / PA 25 03-Oct-23 01-Nov-23
GTS1.2.3.13 Hardscape and Softscape 25 03-Oct-23 01-Nov-23
GTS1.2.3.14 HVAC High Side 25 03-Oct-23 01-Nov-23
GTS1.2.3.15 Gas Bank and Piping 25 03-Oct-23 01-Nov-23
GTS1.2.3.16 Solar Hot Water System /Geyser 25 03-Oct-23 01-Nov-23
GTS1.2.3.17 Kitchen ( Pantry in Club House) 5 03-Oct-23 07-Oct-23
GTS1.2.3.18 Club House Interiors 5 03-Oct-23 07-Oct-23
GTS1.2.3.21 SPA 5 03-Oct-23 07-Oct-23
GTS1.2.3.19 Swimming Pool and Waterbodies 5 03-Oct-23 07-Oct-23
GTS1.2.3.20 Signages 5 03-Oct-23 07-Oct-23

GTS1.4 Construction 5 03-Oct-23 07-Oct-23

GTS1.4.1 Mobilization 5 03-Oct-23 07-Oct-23


GTS1.4.1.1 Civil & Structural 5 03-Oct-23 07-Oct-23
GTS1.1 Tower & Club House 429 03-Oct-23 03-Mar-25

GTS1.1.5 Phase-1 0 03-Oct-23 03-Oct-23


A2310 Tower-5 0 03-Oct-23 03-Oct-23
A2320 Tower-6 0 03-Oct-23 03-Oct-23
A2330 Tower-2 0 03-Oct-23 03-Oct-23
GTS1.1.6 Club House 0 03-Oct-23 03-Oct-23
GTS1.1.3 Phase-2 0 03-Oct-23 03-Oct-23
GTS1.1.1 TOWER 5 SUBSTRUCTURE 429 03-Oct-23 03-Mar-25
GTS1.1.1.1 Foundation Level 16 03-Oct-23 20-Oct-23
A2371 Anti-termite treatment 1 03-Oct-23 03-Oct-23
A2372 Footing PCC (Including retaining wall) 3 04-Oct-23 06-Oct-23
A2382 Footing Reinforcement (Including retaining wall) 7 06-Oct-23 13-Oct-23
A2392 Footing Form Work (Including retaining wall) 7 07-Oct-23 14-Oct-23
A2402 Footing Concrete(Including retaining wall) 2 16-Oct-23 17-Oct-23
A2403 De-Shuttering Footing 1 18-Oct-23 18-Oct-23
A2412 Backfilling & Compaction 2 19-Oct-23 20-Oct-23
GTS1.1.1.2 Basement-1 Level 44 21-Oct-23 12-Dec-23
A2423 RCC Retaining Wall (B1 TO P1) 20 21-Oct-23 14-Nov-23
A2443 P1 Level - Basement Slab Concrete( Includes Column concreting) 25 11-Nov-23 09-Dec-23

Page 1 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A2445 Backfilling & Compaction 2 11-Dec-23 12-Dec-23


GTS1.1.1.3 Slab De-shuttering & Shifting of Material 3 23-Dec-23 27-Dec-23
A2447 Basement Roof Slab De-shuttering & Shifting of Material 3 23-Dec-23 27-Dec-23
GTS1.1.1.4 Grade Slab 15 27-Jan-24 13-Feb-24
A2449 Anti- Termite Treatment 1 27-Jan-24 27-Jan-24
A2450 Basement Grade Slab 14 29-Jan-24 13-Feb-24
GTS1.1.1.5 SUPERSTRUCTURE 361 11-Dec-23 19-Feb-25
GTS1.1.1.5.1 P - 1 Level 22 11-Dec-23 05-Jan-24
A2850 Col. Reinforcement (Conventional Shuttering) 6 11-Dec-23 16-Dec-23
A2860 Col. Shuttering 7 11-Dec-23 18-Dec-23
A2870 Col. Casting 3 19-Dec-23 21-Dec-23
A2880 Col. Deshuttering 1 22-Dec-23 22-Dec-23
A2890 Slab Shuttering 9 23-Dec-23 03-Jan-24
A2900 Slab Reinforcement 10 22-Dec-23 03-Jan-24
A2910 Conduiting Works 3 01-Jan-24 03-Jan-24
A2912 Slab Casting 2 04-Jan-24 05-Jan-24
GTS1.1.1.5.2 P - 2 Level 23 06-Jan-24 02-Feb-24
A2920 Col. Reinforcement (Conventional Shuttering) 6 06-Jan-24 12-Jan-24
A2930 Col. Shuttering 7 06-Jan-24 13-Jan-24
A2940 Col. Casting 3 15-Jan-24 17-Jan-24
A2950 Col. Deshuttering 1 18-Jan-24 18-Jan-24
A2960 Slab Shuttering 9 19-Jan-24 30-Jan-24
A2970 Slab Reinforcement 10 19-Jan-24 31-Jan-24
A2980 Conduiting Works 3 29-Jan-24 31-Jan-24
A3000 Slab Casting 2 01-Feb-24 02-Feb-24
GTS1.1.1.5.3 P - 3 Level 23 03-Feb-24 29-Feb-24
A2990 Col. Reinforcement (Conventional Shuttering) 6 03-Feb-24 09-Feb-24
A3020 Col. Shuttering 7 03-Feb-24 10-Feb-24
A3030 Col. Casting 3 12-Feb-24 14-Feb-24
A3040 Col. Deshuttering 1 15-Feb-24 15-Feb-24
A3050 Slab Shuttering 9 16-Feb-24 26-Feb-24
A3070 Slab Reinforcement 10 16-Feb-24 27-Feb-24
A3080 Conduiting Works 3 24-Feb-24 27-Feb-24
A3090 Slab Casting 2 28-Feb-24 29-Feb-24
GTS1.1.1.5.4 GF Floor Level 19 01-Mar-24 22-Mar-24
A3059 Wall Starter (Miv an Shutterin g) 5 01-Mar-24 06-Mar-24
A3060 Wall Reinforcement 6 04-Mar-24 09-Mar-24
A3100 Conduiting Works 1 11-Mar-24 11-Mar-24
A3120 Wall Shuttering 2 12-Mar-24 13-Mar-24
A3122 Slab Shuttering 5 14-Mar-24 19-Mar-24
A3140 Slab Reinforcement 3 18-Mar-24 20-Mar-24
A3150 Slab Conduiting Works 1 21-Mar-24 21-Mar-24
A3160 Slab Casting 1 22-Mar-24 22-Mar-24
GTS1.1.1.5.5 1st Floor Level 15 23-Mar-24 12-Apr-24
A3130 Wall Starter (Miv an Shutterin g) 3 23-Mar-24 27-Mar-24
A3180 Wall Reinforcement 4 26-Mar-24 29-Mar-24
A3190 Conduiting Works 1 30-Mar-24 30-Mar-24
A3210 Wall Shuttering 2 01-Apr-24 02-Apr-24
A3220 Slab Shuttering 4 03-Apr-24 06-Apr-24

Page 2 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A3230 Slab Reinforcement 3 05-Apr-24 08-Apr-24


A3240 Slab Conduiting Works 1 11-Apr-24 11-Apr-24
A3310 Slab Casting 1 12-Apr-24 12-Apr-24
GTS1.1.1.5.6 2nd Floor Level 14 13-Apr-24 29-Apr-24
A3200 Wall Starter (Miv an Shutterin g) 3 13-Apr-24 16-Apr-24
A3250 Wall Reinforcement 4 15-Apr-24 18-Apr-24
A3260 Conduiting Works 1 19-Apr-24 19-Apr-24
A3280 Wall Shuttering 2 20-Apr-24 22-Apr-24
A3290 Slab Shuttering 3 23-Apr-24 25-Apr-24
A3300 Slab Reinforcement 3 24-Apr-24 26-Apr-24
A3380 Slab Conduiting Works 1 27-Apr-24 27-Apr-24
A3500 Slab Casting 1 29-Apr-24 29-Apr-24
GTS1.1.1.5.7 3rd Floor Level 14 30-Apr-24 16-May-24
A3270 Wall Starter (Miv an Shutterin g) 3 30-Apr-24 03-May-24
A3320 Wall Reinforcement 4 02-May-24 06-May-24
A3330 Conduiting Works 1 07-May-24 07-May-24
A3350 Wall Shuttering 2 08-May-24 09-May-24
A3360 Slab Shuttering 3 10-May-24 13-May-24
A3370 Slab Reinforcement 3 11-May-24 14-May-24
A3372 Slab Conduiting Works 1 15-May-24 15-May-24
A3373 Slab Casting 1 16-May-24 16-May-24
GTS1.1.1.5.8 4th Floor Level 14 17-May-24 01-Jun-24
A3340 Wall Starter (Miv an Shutterin g) 3 17-May-24 20-May-24
A3390 Wall Reinforcement 4 18-May-24 22-May-24
A3400 Conduiting Works 1 23-May-24 23-May-24
A3440 Wall Shuttering 2 24-May-24 25-May-24
A3480 Slab Shuttering 3 27-May-24 29-May-24
A3490 Slab Reinforcement 3 28-May-24 30-May-24
A3492 Slab Conduiting Works 1 31-May-24 31-May-24
A3493 Slab Casting 1 01-Jun-24 01-Jun-24
GTS1.1.1.5.9 5th Floor Level 14 03-Jun-24 18-Jun-24
A13711 Wall Starter (Miv an Shutterin g) 3 03-Jun-24 05-Jun-24
A13712 Wall Reinforcement 4 04-Jun-24 07-Jun-24
A13713 Conduiting Works 1 08-Jun-24 08-Jun-24
A13714 Wall Shuttering 2 10-Jun-24 11-Jun-24
A13715 Slab Shuttering 3 12-Jun-24 14-Jun-24
A13716 Slab Reinforcement 3 13-Jun-24 15-Jun-24
A13717 Slab Conduiting Works 1 17-Jun-24 17-Jun-24
A13718 Slab Casting 1 18-Jun-24 18-Jun-24
GTS1.1.1.5.10 6th Floor Level 14 19-Jun-24 04-Jul-24
A13719 Wall Starter (Miv an Shutterin g) 3 19-Jun-24 21-Jun-24
A13720 Wall Reinforcement 4 20-Jun-24 24-Jun-24
A13721 Conduiting Works 1 25-Jun-24 25-Jun-24
A13722 Wall Shuttering 2 26-Jun-24 27-Jun-24
A13723 Slab Shuttering 3 28-Jun-24 01-Jul-24
A13724 Slab Reinforcement 3 29-Jun-24 02-Jul-24
A13725 Slab Conduiting Works 1 03-Jul-24 03-Jul-24
A13726 Slab Casting 1 04-Jul-24 04-Jul-24
GTS1.1.1.5.11 7th Floor Level 14 05-Jul-24 20-Jul-24

Page 3 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A13727 Wall Starter (Miv an Shutterin g) 3 05-Jul-24 08-Jul-24


A13728 Wall Reinforcement 4 06-Jul-24 10-Jul-24
A13729 Conduiting Works 1 11-Jul-24 11-Jul-24
A13730 Wall Shuttering 2 12-Jul-24 13-Jul-24
A13731 Slab Shuttering 3 15-Jul-24 17-Jul-24
A13732 Slab Reinforcement 3 16-Jul-24 18-Jul-24
A13733 Slab Conduiting Works 1 19-Jul-24 19-Jul-24
A13734 Slab Casting 1 20-Jul-24 20-Jul-24
GTS1.1.1.5.12 8th Floor Level 14 22-Jul-24 06-Aug-24
A13735 Wall Starter (Miv an Shutterin g) 3 22-Jul-24 24-Jul-24
A13736 Wall Reinforcement 4 23-Jul-24 26-Jul-24
A13737 Conduiting Works 1 27-Jul-24 27-Jul-24
A13738 Wall Shuttering 2 29-Jul-24 30-Jul-24
A13739 Slab Shuttering 3 31-Jul-24 02-Aug-24
A13740 Slab Reinforcement 3 01-Aug-24 03-Aug-24
A13741 Slab Conduiting Works 1 05-Aug-24 05-Aug-24
A13742 Slab Casting 1 06-Aug-24 06-Aug-24
GTS1.1.1.5.13 9th Floor Level 14 07-Aug-24 23-Aug-24
A13751 Wall Starter (Miv an Shutterin g) 3 07-Aug-24 09-Aug-24
A13752 Wall Reinforcement 4 08-Aug-24 12-Aug-24
A13753 Conduiting Works 1 13-Aug-24 13-Aug-24
A13754 Wall Shuttering 2 14-Aug-24 16-Aug-24
A13755 Slab Shuttering 3 17-Aug-24 20-Aug-24
A13756 Slab Reinforcement 3 19-Aug-24 21-Aug-24
A13757 Slab Conduiting Works 1 22-Aug-24 22-Aug-24
A13758 Slab Casting 1 23-Aug-24 23-Aug-24
GTS1.1.1.5.14 10th Floor Level 14 24-Aug-24 10-Sep-24
A13759 Wall Starter (Miv an Shutterin g) 3 24-Aug-24 27-Aug-24
A13760 Wall Reinforcement 4 26-Aug-24 29-Aug-24
A13761 Conduiting Works 1 30-Aug-24 30-Aug-24
A13762 Wall Shuttering 2 31-Aug-24 02-Sep-24
A13763 Slab Shuttering 3 03-Sep-24 05-Sep-24
A13764 Slab Reinforcement 3 04-Sep-24 06-Sep-24
A13765 Slab Conduiting Works 1 09-Sep-24 09-Sep-24
A13766 Slab Casting 1 10-Sep-24 10-Sep-24
GTS1.1.1.5.15 11th Floor Level 14 11-Sep-24 27-Sep-24
A13767 Wall Starter (Miv an Shutterin g) 3 11-Sep-24 13-Sep-24
A13768 Wall Reinforcement 4 12-Sep-24 17-Sep-24
A13769 Conduiting Works 1 18-Sep-24 18-Sep-24
A13770 Wall Shuttering 2 19-Sep-24 20-Sep-24
A13771 Slab Shuttering 3 21-Sep-24 24-Sep-24
A13772 Slab Reinforcement 3 23-Sep-24 25-Sep-24
A13773 Slab Conduiting Works 1 26-Sep-24 26-Sep-24
A13774 Slab Casting 1 27-Sep-24 27-Sep-24
GTS1.1.1.5.16 12th Floor Level 14 28-Sep-24 15-Oct-24
A13775 Wall Starter (Miv an Shutterin g) 3 28-Sep-24 01-Oct-24
A13776 Wall Reinforcement 4 30-Sep-24 04-Oct-24
A13777 Conduiting Works 1 05-Oct-24 05-Oct-24
A13778 Wall Shuttering 2 07-Oct-24 08-Oct-24

Page 4 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A13779 Slab Shuttering 3 09-Oct-24 11-Oct-24


A13780 Slab Reinforcement 3 10-Oct-24 12-Oct-24
A13781 Slab Conduiting Works 1 14-Oct-24 14-Oct-24
A13782 Slab Casting 1 15-Oct-24 15-Oct-24
GTS1.1.1.5.17 13th Floor Level 14 16-Oct-24 01-Nov-24
A13783 Wall Starter (Miv an Shutterin g) 3 16-Oct-24 18-Oct-24
A13784 Wall Reinforcement 4 17-Oct-24 21-Oct-24
A13785 Conduiting Works 1 22-Oct-24 22-Oct-24
A13786 Wall Shuttering 2 23-Oct-24 24-Oct-24
A13787 Slab Shuttering 3 25-Oct-24 28-Oct-24
A13788 Slab Reinforcement 3 26-Oct-24 29-Oct-24
A13789 Slab Conduiting Works 1 30-Oct-24 30-Oct-24
A13790 Slab Casting 1 01-Nov-24 01-Nov-24
GTS1.1.1.5.18 Terrace Floor Level 14 02-Nov-24 18-Nov-24
A13791 Wall Starter (Miv an Shutterin g) 3 02-Nov-24 05-Nov-24
A13792 Wall Reinforcement 4 04-Nov-24 07-Nov-24
A13793 Conduiting Works 1 08-Nov-24 08-Nov-24
A13794 Wall Shuttering 2 09-Nov-24 11-Nov-24
A13795 Slab Shuttering 3 12-Nov-24 14-Nov-24
A13796 Slab Reinforcement 3 13-Nov-24 15-Nov-24
A13797 Slab Conduiting Works 1 16-Nov-24 16-Nov-24
A13798 Slab Casting 1 18-Nov-24 18-Nov-24
GTS1.1.1.5.19 Mumty / Over Head Tanks / Lift Machine Rooms 15 19-Nov-24 05-Dec-24
A4061 Wall Starter (Miv an Shutterin g) & OHT Works 3 19-Nov-24 21-Nov-24
A4100 Wall Reinforcement 5 20-Nov-24 25-Nov-24
A4110 Conduiting Works 1 26-Nov-24 26-Nov-24
A4120 Wall Shuttering 3 27-Nov-24 29-Nov-24
A4130 Slab Shuttering 3 29-Nov-24 02-Dec-24
A4140 Slab Reinforcement 3 30-Nov-24 03-Dec-24
A4150 Slab Conduiting Works 1 04-Dec-24 04-Dec-24
A4160 Slab Casting 1 05-Dec-24 05-Dec-24
GTS1.1.1.5.20 Slab De-shuttering & Shifting of Material 294 06-Jan-24 26-Dec-24
A4170 P - 1 Level 3 06-Jan-24 09-Jan-24
A4180 P - 2 Level 3 03-Feb-24 06-Feb-24
A4190 P - 3 Level 3 01-Mar-24 04-Mar-24
A4200 GF Floor Level 3 12-Apr-24 15-Apr-24
A4210 1st Floor Level 3 30-Apr-24 03-May-24
A4220 2nd Floor Level 3 17-May-24 20-May-24
A4230 3rd Floor Level 3 03-Jun-24 05-Jun-24
A4240 4th Floor Level 3 19-Jun-24 21-Jun-24
A4250 5th Floor Level 3 05-Jul-24 08-Jul-24
A4260 6th Floor Level 3 22-Jul-24 24-Jul-24
A4270 7th Floor Level 3 07-Aug-24 09-Aug-24
A4280 8th Floor Level 3 24-Aug-24 27-Aug-24
A4290 9th Floor Level 3 11-Sep-24 13-Sep-24
A4300 10th Floor Level 3 28-Sep-24 01-Oct-24
A4302 11th Floor Level 3 16-Oct-24 18-Oct-24
A4303 12th Floor Level 3 02-Nov-24 05-Nov-24
A4304 13th Floor Level 3 19-Nov-24 21-Nov-24

Page 5 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A4305 Terrace Floor Level 3 05-Dec-24 07-Dec-24


A4310 Mumty / Over Head Tanks / Lift Machine Rooms 3 23-Dec-24 26-Dec-24
GTS1.1.1.5.21 INTERNAL FINISHES & RELATED SERVICES 333 13-Jan-24 19-Feb-25
GTS1.1.1.5.21.1 Basement-1 69 17-Feb-24 11-May-24
A4320 Fire Sprinkler installation 14 17-Feb-24 04-Mar-24
A4350 Ventilation 20 20-Feb-24 13-Mar-24
A4370 Water Proofin g + Protective Pla ster 18 08-Mar-24 29-Mar-24
A4390 TREMIX/ VDF Flooring Works 26 18-Mar-24 19-Apr-24
A4400 Door frames installation (including fire doors) 7 20-Apr-24 27-Apr-24
A4410 Wiring and Continutity test 14 26-Feb-24 12-Mar-24
A4430 Primer and Paint 16 20-Apr-24 09-May-24
A4460 Installation of Electrical fixtures 10 30-Apr-24 11-May-24
A4480 Door Shutter installation (with Iron Mongery) & Door Painting 5 25-Apr-24 30-Apr-24
A4490 Miscellaneous works ( Drain System, Grating , Ramps & Marking) 25 26-Mar-24 25-Apr-24
GTS1.1.1.5.21.2 Podium- 1 Level 59 13-Jan-24 22-Mar-24
A4510 Fire Sprinkler Installation 12 13-Jan-24 27-Jan-24
A4540 Ventilation 17 16-Jan-24 05-Feb-24
A4550 Water Proofin g + Protective Pla ster 14 01-Feb-24 16-Feb-24
A4570 VDF Flooring Works 20 09-Feb-24 02-Mar-24
A4580 Door frames installation (including fire doors) 6 04-Mar-24 09-Mar-24
A4590 Wiring and Continutity test 12 22-Jan-24 05-Feb-24
A4610 Primer and Paint 14 04-Mar-24 19-Mar-24
A4640 Installation of Electrical fixtures 8 14-Mar-24 22-Mar-24
A4660 Door Shutter installation (with Iron Mongery) & Door Painting 5 07-Mar-24 12-Mar-24
GTS1.1.1.5.21.3 Podium- 2 Level 59 10-Feb-24 22-Apr-24
A4720 Fire Sprinkler Installation 12 10-Feb-24 23-Feb-24
A4750 Ventilation 17 13-Feb-24 02-Mar-24
A4760 Water Proofin g + Protective Pla ster 14 28-Feb-24 14-Mar-24
A4780 VDF Flooring Works 20 07-Mar-24 30-Mar-24
A4790 Door frames installation (including fire doors) 6 01-Apr-24 06-Apr-24
A4800 Wiring and Continutity test 12 19-Feb-24 02-Mar-24
A4820 Primer and Paint 14 01-Apr-24 18-Apr-24
A4850 Installation of Electrical fixtures 8 13-Apr-24 22-Apr-24
A4870 Door Shutter installation (with Iron Mongery) & Door Painting 5 04-Apr-24 11-Apr-24
GTS1.1.1.5.21.4 Podium- 3 Level 59 08-Mar-24 20-May-24
A4920 Fire Sprinkler Installation 12 08-Mar-24 21-Mar-24
A4950 Ventilation 17 11-Mar-24 30-Mar-24
A4960 Water Proofin g + Protective Pla ster 14 27-Mar-24 13-Apr-24
A4980 VDF Flooring Works 20 04-Apr-24 29-Apr-24
A4990 Door frames installation (including fire doors) 6 30-Apr-24 07-May-24
A5000 Wiring and Continutity test 12 16-Mar-24 30-Mar-24
A5020 Primer and Paint 14 30-Apr-24 16-May-24
A5050 Installation of Electrical fixtures 8 11-May-24 20-May-24
A5070 Door Shutter installation (with Iron Mongery) & Door Painting 5 04-May-24 09-May-24
GTS1.1.1.5.21.5 Ground Floor Level 53 16-Apr-24 17-Jun-24
GTS1.1.1.5.21.5.1 Apartment Areas 46 16-Apr-24 08-Jun-24
A5090 Toilet and Kitchen plumbing 21 16-Apr-24 10-May-24
A5091 Pressure Testing 12 20-Apr-24 04-May-24
A5092 Toilet Water Proofing with Testing 16 26-Apr-24 15-May-24

Page 6 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A5093 Toilet Flooring & Dado 18 02-May-24 22-May-24


A5094 Railing works 14 18-Apr-24 04-May-24
A5095 Putty and Primer 1st Coat Painting - Internal 18 26-Apr-24 17-May-24
A5096 Kitchen Platform & Tiles work 16 26-Apr-24 15-May-24
A5097 Flooring (excluding toilets) 24 03-May-24 30-May-24
A5098 Door Frame and Shutter Installation (with Ironmongery) 18 17-May-24 06-Jun-24
A5099 Windows Installation 12 20-May-24 01-Jun-24
A5100 Wiring and Cabling 14 15-May-24 30-May-24
A5101 Installation of Switches and DBs 12 20-May-24 01-Jun-24
A5102 Installation of sanitary fixtures and CP Fittings 16 07-May-24 24-May-24
A5103 Final Painting 14 24-May-24 08-Jun-24
GTS1.1.1.5.21.5.2 Common Area Works 37 06-May-24 17-Jun-24
A5310 Corridor Fire Sprinkler Pipe Installation 14 06-May-24 21-May-24
A5320 Corridor Fire Sprinkler Pressure Testing 2 22-May-24 23-May-24
A5330 Corridor flooring and Lift cladding 20 16-May-24 07-Jun-24
A5340 Corridor Railing works 18 09-May-24 29-May-24
A5350 Putty and Primer Painting 7 28-May-24 04-Jun-24
A5360 1st coat of Painting 7 30-May-24 06-Jun-24
A5370 Wiring and Continutity test 7 01-Jun-24 08-Jun-24
A5380 Installation of swtiches and fixtures 5 10-Jun-24 14-Jun-24
A5390 Final Coat 4 13-Jun-24 17-Jun-24
GTS1.1.1.5.21.6 1st Floor Level 53 04-May-24 04-Jul-24
GTS1.1.1.5.21.6.24 Apartment Areas 46 04-May-24 26-Jun-24
A13570 Toilet and Kitchen plumbing 21 04-May-24 28-May-24
A13580 Pressure Testing 12 09-May-24 22-May-24
A13590 Toilet Water Proofing with Testing 16 15-May-24 01-Jun-24
A13600 Toilet Flooring & Dado 18 20-May-24 08-Jun-24
A13610 Railing works 14 07-May-24 22-May-24
A13620 Putty and Primer 1st Coat Painting - Internal 18 15-May-24 04-Jun-24
A13630 Kitchen Platform & Tiles work 16 15-May-24 01-Jun-24
A13640 Flooring (excluding toilets) 24 21-May-24 17-Jun-24
A13650 Door Frame and Shutter Installation (with Ironmongery) 18 04-Jun-24 24-Jun-24
A13660 Windows Installation 12 06-Jun-24 19-Jun-24
A13670 Wiring and Cabling 14 01-Jun-24 17-Jun-24
A13680 Installation of Switches and DBs 12 06-Jun-24 19-Jun-24
A13690 Installation of sanitary fixtures and CP Fittings 16 24-May-24 11-Jun-24
A13700 Final Painting 14 11-Jun-24 26-Jun-24
GTS1.1.1.5.21.6.1 Common Area Works 37 23-May-24 04-Jul-24
A12310 Corridor Fire Sprinkler Pipe Installation 14 23-May-24 07-Jun-24
A12320 Corridor Fire Sprinkler Pressure Testing 2 08-Jun-24 10-Jun-24
A12330 Corridor flooring and Lift cladding 20 03-Jun-24 25-Jun-24
A12340 Corridor Railing works 18 27-May-24 15-Jun-24
A12350 Putty and Primer Painting 7 14-Jun-24 21-Jun-24
A12360 1st coat of Painting 7 17-Jun-24 24-Jun-24
A12370 Wiring and Continutity test 7 19-Jun-24 26-Jun-24
A12380 Installation of swtiches and fixtures 5 27-Jun-24 02-Jul-24
A12390 Final Coat 4 01-Jul-24 04-Jul-24
GTS1.1.1.5.21.7 2nd Floor Level 53 21-May-24 20-Jul-24
GTS1.1.1.5.21.7.27 Apartment Areas 46 21-May-24 12-Jul-24

Page 7 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A10490 Toilet and Kitchen plumbing 21 21-May-24 13-Jun-24


A10500 Pressure Testing 12 25-May-24 07-Jun-24
A10510 Toilet Water Proofing with Testing 16 31-May-24 18-Jun-24
A10520 Toilet Flooring & Dado 18 05-Jun-24 25-Jun-24
A10530 Railing works 14 23-May-24 07-Jun-24
A10540 Putty and Primer 1st Coat Painting - Internal 18 31-May-24 20-Jun-24
A10550 Kitchen Platform & Tiles work 16 31-May-24 18-Jun-24
A10560 Flooring (excluding toilets) 24 06-Jun-24 03-Jul-24
A10570 Door Frame and Shutter Installation (with Ironmongery) 18 20-Jun-24 10-Jul-24
A10580 Windows Installation 12 22-Jun-24 05-Jul-24
A10590 Wiring and Cabling 14 18-Jun-24 03-Jul-24
A10600 Installation of Switches and DBs 12 22-Jun-24 05-Jul-24
A10610 Installation of sanitary fixtures and CP Fittings 16 10-Jun-24 27-Jun-24
A10620 Final Painting 14 27-Jun-24 12-Jul-24
GTS1.1.1.5.21.7.26 Common Area Works 37 08-Jun-24 20-Jul-24
A12400 Corridor Fire Sprinkler Pipe Installation 14 08-Jun-24 24-Jun-24
A12410 Corridor Fire Sprinkler Pressure Testing 2 25-Jun-24 26-Jun-24
A12420 Corridor flooring and Lift cladding 20 19-Jun-24 11-Jul-24
A12430 Corridor Railing works 18 12-Jun-24 02-Jul-24
A12440 Putty and Primer Painting 7 01-Jul-24 08-Jul-24
A12450 1st coat of Painting 7 03-Jul-24 10-Jul-24
A12460 Wiring and Continutity test 7 05-Jul-24 12-Jul-24
A12470 Installation of swtiches and fixtures 5 13-Jul-24 18-Jul-24
A12480 Final Coat 4 17-Jul-24 20-Jul-24
GTS1.1.1.5.21.8 3rd Floor Level 53 06-Jun-24 06-Aug-24
GTS1.1.1.5.21.8.29 Apartment Areas 46 06-Jun-24 29-Jul-24
A10630 Toilet and Kitchen plumbing 21 06-Jun-24 29-Jun-24
A10640 Pressure Testing 12 11-Jun-24 24-Jun-24
A10650 Toilet Water Proofing with Testing 16 17-Jun-24 04-Jul-24
A10660 Toilet Flooring & Dado 18 21-Jun-24 11-Jul-24
A10670 Railing works 14 08-Jun-24 24-Jun-24
A10680 Putty and Primer 1st Coat Painting - Internal 18 17-Jun-24 06-Jul-24
A10690 Kitchen Platform & Tiles work 16 17-Jun-24 04-Jul-24
A10700 Flooring (excluding toilets) 24 22-Jun-24 19-Jul-24
A10710 Door Frame and Shutter Installation (with Ironmongery) 18 06-Jul-24 26-Jul-24
A10720 Windows Installation 12 09-Jul-24 22-Jul-24
A10730 Wiring and Cabling 14 04-Jul-24 19-Jul-24
A10740 Installation of Switches and DBs 12 09-Jul-24 22-Jul-24
A10750 Installation of sanitary fixtures and CP Fittings 16 26-Jun-24 13-Jul-24
A10760 Final Painting 14 13-Jul-24 29-Jul-24
GTS1.1.1.5.21.8.28 Common Area Works 37 25-Jun-24 06-Aug-24
A12490 Corridor Fire Sprinkler Pipe Installation 14 25-Jun-24 10-Jul-24
A12500 Corridor Fire Sprinkler Pressure Testing 2 11-Jul-24 12-Jul-24
A12510 Corridor flooring and Lift cladding 20 05-Jul-24 27-Jul-24
A12520 Corridor Railing works 18 28-Jun-24 18-Jul-24
A12530 Putty and Primer Painting 7 17-Jul-24 24-Jul-24
A12540 1st coat of Painting 7 19-Jul-24 26-Jul-24
A12550 Wiring and Continutity test 7 22-Jul-24 29-Jul-24
A12560 Installation of swtiches and fixtures 5 30-Jul-24 03-Aug-24

Page 8 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A12570 Final Coat 4 02-Aug-24 06-Aug-24


GTS1.1.1.5.21.9 4th Floor Level 53 22-Jun-24 23-Aug-24
GTS1.1.1.5.21.9.1 Apartment Areas 46 22-Jun-24 14-Aug-24
A10770 Toilet and Kitchen plumbing 21 22-Jun-24 16-Jul-24
A10780 Pressure Testing 12 27-Jun-24 10-Jul-24
A10790 Toilet Water Proofing with Testing 16 03-Jul-24 20-Jul-24
A10800 Toilet Flooring & Dado 18 08-Jul-24 27-Jul-24
A10820 Putty and Primer 1st Coat Painting - Internal 18 03-Jul-24 23-Jul-24
A10830 Kitchen Platform & Tiles work 16 03-Jul-24 20-Jul-24
A10840 Flooring (excluding toilets) 24 09-Jul-24 05-Aug-24
A10850 Door Frame and Shutter Installation (with Ironmongery) 18 23-Jul-24 12-Aug-24
A10860 Windows Installation 12 25-Jul-24 07-Aug-24
A10870 Wiring and Cabling 14 20-Jul-24 05-Aug-24
A10880 Installation of Switches and DBs 12 25-Jul-24 07-Aug-24
A10890 Installation of sanitary fixtures and CP Fittings 16 12-Jul-24 30-Jul-24
A10900 Final Painting 14 30-Jul-24 14-Aug-24
GTS1.1.1.5.21.9.30 Common Area Works 37 11-Jul-24 23-Aug-24
A12580 Corridor Fire Sprinkler Pipe Installation 14 11-Jul-24 26-Jul-24
A12590 Corridor Fire Sprinkler Pressure Testing 2 27-Jul-24 29-Jul-24
A12600 Corridor flooring and Lift cladding 20 22-Jul-24 13-Aug-24
A12610 Corridor Railing works 18 15-Jul-24 03-Aug-24
A12620 Putty and Primer Painting 7 02-Aug-24 09-Aug-24
A12630 1st coat of Painting 7 05-Aug-24 12-Aug-24
A12640 Wiring and Continutity test 7 07-Aug-24 14-Aug-24
A12650 Installation of swtiches and fixtures 5 16-Aug-24 21-Aug-24
A12660 Final Coat 4 20-Aug-24 23-Aug-24
GTS1.1.1.5.21.10 5th Floor Level 53 09-Jul-24 10-Sep-24
GTS1.1.1.5.21.10.1 Apartment Areas 46 09-Jul-24 31-Aug-24
A10910 Toilet and Kitchen plumbing 21 09-Jul-24 01-Aug-24
A10920 Pressure Testing 12 13-Jul-24 26-Jul-24
A10930 Toilet Water Proofing with Testing 16 19-Jul-24 06-Aug-24
A10940 Toilet Flooring & Dado 18 24-Jul-24 13-Aug-24
A10960 Putty and Primer 1st Coat Painting - Internal 18 19-Jul-24 08-Aug-24
A10970 Kitchen Platform & Tiles work 16 19-Jul-24 06-Aug-24
A10980 Flooring (excluding toilets) 24 25-Jul-24 22-Aug-24
A10990 Door Frame and Shutter Installation (with Ironmongery) 18 08-Aug-24 29-Aug-24
A11000 Windows Installation 12 10-Aug-24 24-Aug-24
A11010 Wiring and Cabling 14 06-Aug-24 22-Aug-24
A11020 Installation of Switches and DBs 12 10-Aug-24 24-Aug-24
A11030 Installation of sanitary fixtures and CP Fittings 16 29-Jul-24 16-Aug-24
A11040 Final Painting 14 16-Aug-24 31-Aug-24
GTS1.1.1.5.21.10.2 Common Area Works 37 27-Jul-24 10-Sep-24
A12670 Corridor Fire Sprinkler Pipe Installation 14 27-Jul-24 12-Aug-24
A12680 Corridor Fire Sprinkler Pressure Testing 2 13-Aug-24 14-Aug-24
A12690 Corridor flooring and Lift cladding 20 07-Aug-24 30-Aug-24
A12700 Corridor Railing works 18 31-Jul-24 21-Aug-24
A12710 Putty and Primer Painting 7 20-Aug-24 27-Aug-24
A12720 1st coat of Painting 7 22-Aug-24 29-Aug-24
A12730 Wiring and Continutity test 7 24-Aug-24 31-Aug-24

Page 9 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A12740 Installation of swtiches and fixtures 5 02-Sep-24 06-Sep-24


A12750 Final Coat 4 05-Sep-24 10-Sep-24
GTS1.1.1.5.21.11 6th Floor Level 53 25-Jul-24 27-Sep-24
GTS1.1.1.5.21.11.1 Apartment Areas 46 25-Jul-24 19-Sep-24
A11050 Toilet and Kitchen plumbing 21 25-Jul-24 19-Aug-24
A11060 Pressure Testing 12 30-Jul-24 12-Aug-24
A11070 Toilet Water Proofing with Testing 16 05-Aug-24 23-Aug-24
A11080 Toilet Flooring & Dado 18 09-Aug-24 30-Aug-24
A11090 Railing works 14 27-Jul-24 12-Aug-24
A11100 Putty and Primer 1st Coat Painting - Internal 18 05-Aug-24 26-Aug-24
A11110 Kitchen Platform & Tiles work 16 05-Aug-24 23-Aug-24
A11120 Flooring (excluding toilets) 24 10-Aug-24 09-Sep-24
A11130 Door Frame and Shutter Installation (with Ironmongery) 18 26-Aug-24 17-Sep-24
A11140 Windows Installation 12 28-Aug-24 11-Sep-24
A11150 Wiring and Cabling 14 23-Aug-24 09-Sep-24
A11160 Installation of Switches and DBs 12 28-Aug-24 11-Sep-24
A11170 Installation of sanitary fixtures and CP Fittings 16 14-Aug-24 02-Sep-24
A11180 Final Painting 14 02-Sep-24 19-Sep-24
GTS1.1.1.5.21.11.2 Common Area Works 37 13-Aug-24 27-Sep-24
A12760 Corridor Fire Sprinkler Pipe Installation 14 13-Aug-24 29-Aug-24
A12770 Corridor Fire Sprinkler Pressure Testing 2 30-Aug-24 31-Aug-24
A12780 Corridor flooring and Lift cladding 20 24-Aug-24 18-Sep-24
A12790 Corridor Railing works 18 17-Aug-24 06-Sep-24
A12800 Putty and Primer Painting 7 05-Sep-24 13-Sep-24
A12810 1st coat of Painting 7 09-Sep-24 17-Sep-24
A12820 Wiring and Continutity test 7 11-Sep-24 19-Sep-24
A12830 Installation of swtiches and fixtures 5 20-Sep-24 25-Sep-24
A12840 Final Coat 4 24-Sep-24 27-Sep-24
GTS1.1.1.5.21.12 7th Floor Level 53 10-Aug-24 15-Oct-24
GTS1.1.1.5.21.12.1 Apartment Areas 46 10-Aug-24 07-Oct-24
A11190 Toilet and Kitchen plumbing 21 10-Aug-24 04-Sep-24
A11200 Pressure Testing 12 16-Aug-24 29-Aug-24
A11210 Toilet Water Proofing with Testing 16 22-Aug-24 10-Sep-24
A11220 Toilet Flooring & Dado 18 27-Aug-24 18-Sep-24
A11230 Railing works 14 13-Aug-24 29-Aug-24
A11240 Putty and Primer 1st Coat Painting - Internal 18 22-Aug-24 12-Sep-24
A11250 Kitchen Platform & Tiles work 16 22-Aug-24 10-Sep-24
A11260 Flooring (excluding toilets) 24 28-Aug-24 26-Sep-24
A11270 Door Frame and Shutter Installation (with Ironmongery) 18 12-Sep-24 04-Oct-24
A11280 Windows Installation 12 14-Sep-24 28-Sep-24
A11290 Wiring and Cabling 14 10-Sep-24 26-Sep-24
A11300 Installation of Switches and DBs 12 14-Sep-24 28-Sep-24
A11310 Installation of sanitary fixtures and CP Fittings 16 31-Aug-24 20-Sep-24
A11320 Final Painting 14 20-Sep-24 07-Oct-24
GTS1.1.1.5.21.12.2 Common Area Works 37 30-Aug-24 15-Oct-24
A12850 Corridor Fire Sprinkler Pipe Installation 14 30-Aug-24 17-Sep-24
A12860 Corridor Fire Sprinkler Pressure Testing 2 18-Sep-24 19-Sep-24
A12870 Corridor flooring and Lift cladding 20 11-Sep-24 05-Oct-24
A12880 Corridor Railing works 18 03-Sep-24 25-Sep-24

Page 10 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A12890 Putty and Primer Painting 7 24-Sep-24 01-Oct-24


A12900 1st coat of Painting 7 26-Sep-24 04-Oct-24
A12910 Wiring and Continutity test 7 28-Sep-24 07-Oct-24
A12920 Installation of swtiches and fixtures 5 08-Oct-24 12-Oct-24
A12930 Final Coat 4 11-Oct-24 15-Oct-24
GTS1.1.1.5.21.13 8th Floor Level 53 28-Aug-24 01-Nov-24
GTS1.1.1.5.21.13.1 Apartment Areas 46 28-Aug-24 23-Oct-24
A11330 Toilet and Kitchen plumbing 21 28-Aug-24 23-Sep-24
A11340 Pressure Testing 12 02-Sep-24 17-Sep-24
A11350 Toilet Water Proofing with Testing 16 09-Sep-24 27-Sep-24
A11360 Toilet Flooring & Dado 18 13-Sep-24 05-Oct-24
A11370 Railing works 14 30-Aug-24 17-Sep-24
A11380 Putty and Primer 1st Coat Painting - Internal 18 09-Sep-24 30-Sep-24
A11390 Kitchen Platform & Tiles work 16 09-Sep-24 27-Sep-24
A11400 Flooring (excluding toilets) 24 14-Sep-24 14-Oct-24
A11410 Door Frame and Shutter Installation (with Ironmongery) 18 30-Sep-24 21-Oct-24
A11420 Windows Installation 12 03-Oct-24 16-Oct-24
A11430 Wiring and Cabling 14 27-Sep-24 14-Oct-24
A11440 Installation of Switches and DBs 12 03-Oct-24 16-Oct-24
A11450 Installation of sanitary fixtures and CP Fittings 16 19-Sep-24 08-Oct-24
A11460 Final Painting 14 08-Oct-24 23-Oct-24
GTS1.1.1.5.21.13.2 Common Area Works 37 18-Sep-24 01-Nov-24
A12940 Corridor Fire Sprinkler Pipe Installation 14 18-Sep-24 04-Oct-24
A12950 Corridor Fire Sprinkler Pressure Testing 2 05-Oct-24 07-Oct-24
A12960 Corridor flooring and Lift cladding 20 28-Sep-24 22-Oct-24
A12970 Corridor Railing works 18 21-Sep-24 12-Oct-24
A12980 Putty and Primer Painting 7 11-Oct-24 18-Oct-24
A12990 1st coat of Painting 7 14-Oct-24 21-Oct-24
A13000 Wiring and Continutity test 7 16-Oct-24 23-Oct-24
A13010 Installation of swtiches and fixtures 5 24-Oct-24 29-Oct-24
A13020 Final Coat 4 28-Oct-24 01-Nov-24
GTS1.1.1.5.21.14 9th Floor Level 53 14-Sep-24 18-Nov-24
GTS1.1.1.5.21.14.1 Apartment Areas 46 14-Sep-24 09-Nov-24
A11470 Toilet and Kitchen plumbing 21 14-Sep-24 10-Oct-24
A11480 Pressure Testing 12 20-Sep-24 04-Oct-24
A11490 Toilet Water Proofing with Testing 16 26-Sep-24 15-Oct-24
A11500 Toilet Flooring & Dado 18 01-Oct-24 22-Oct-24
A11510 Railing works 14 18-Sep-24 04-Oct-24
A11520 Putty and Primer 1st Coat Painting - Internal 18 26-Sep-24 17-Oct-24
A11530 Kitchen Platform & Tiles work 16 26-Sep-24 15-Oct-24
A11540 Flooring (excluding toilets) 24 03-Oct-24 30-Oct-24
A11550 Door Frame and Shutter Installation (with Ironmongery) 18 17-Oct-24 07-Nov-24
A11560 Windows Installation 12 19-Oct-24 02-Nov-24
A11570 Wiring and Cabling 14 15-Oct-24 30-Oct-24
A11580 Installation of Switches and DBs 12 19-Oct-24 02-Nov-24
A11590 Installation of sanitary fixtures and CP Fittings 16 07-Oct-24 24-Oct-24
A11600 Final Painting 14 24-Oct-24 09-Nov-24
GTS1.1.1.5.21.14.2 Common Area Works 37 05-Oct-24 18-Nov-24
A13030 Corridor Fire Sprinkler Pipe Installation 14 05-Oct-24 21-Oct-24

Page 11 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A13040 Corridor Fire Sprinkler Pressure Testing 2 22-Oct-24 23-Oct-24


A13050 Corridor flooring and Lift cladding 20 16-Oct-24 08-Nov-24
A13060 Corridor Railing works 18 09-Oct-24 29-Oct-24
A13070 Putty and Primer Painting 7 28-Oct-24 05-Nov-24
A13080 1st coat of Painting 7 30-Oct-24 07-Nov-24
A13090 Wiring and Continutity test 7 02-Nov-24 09-Nov-24
A13100 Installation of swtiches and fixtures 5 11-Nov-24 15-Nov-24
A13110 Final Coat 4 14-Nov-24 18-Nov-24
GTS1.1.1.5.21.15 10th Floor Level 53 03-Oct-24 04-Dec-24
GTS1.1.1.5.21.15.1 Apartment Areas 46 03-Oct-24 26-Nov-24
A11610 Toilet and Kitchen plumbing 21 03-Oct-24 26-Oct-24
A11620 Pressure Testing 12 08-Oct-24 21-Oct-24
A11630 Toilet Water Proofing with Testing 16 14-Oct-24 01-Nov-24
A11640 Toilet Flooring & Dado 18 18-Oct-24 08-Nov-24
A11650 Railing works 14 05-Oct-24 21-Oct-24
A11660 Putty and Primer 1st Coat Painting - Internal 18 14-Oct-24 04-Nov-24
A11670 Kitchen Platform & Tiles work 16 14-Oct-24 01-Nov-24
A11680 Flooring (excluding toilets) 24 19-Oct-24 16-Nov-24
A11690 Door Frame and Shutter Installation (with Ironmongery) 18 04-Nov-24 23-Nov-24
A11700 Windows Installation 12 06-Nov-24 19-Nov-24
A11710 Wiring and Cabling 14 01-Nov-24 16-Nov-24
A11720 Installation of Switches and DBs 12 06-Nov-24 19-Nov-24
A11730 Installation of sanitary fixtures and CP Fittings 16 23-Oct-24 11-Nov-24
A11740 Final Painting 14 11-Nov-24 26-Nov-24
GTS1.1.1.5.21.15.2 Common Area Works 37 22-Oct-24 04-Dec-24
A13120 Corridor Fire Sprinkler Pipe Installation 14 22-Oct-24 07-Nov-24
A13130 Corridor Fire Sprinkler Pressure Testing 2 08-Nov-24 09-Nov-24
A13140 Corridor flooring and Lift cladding 20 02-Nov-24 25-Nov-24
A13150 Corridor Railing works 18 25-Oct-24 15-Nov-24
A13160 Putty and Primer Painting 7 14-Nov-24 21-Nov-24
A13170 1st coat of Painting 7 16-Nov-24 23-Nov-24
A13180 Wiring and Continutity test 7 19-Nov-24 26-Nov-24
A13190 Installation of swtiches and fixtures 5 27-Nov-24 02-Dec-24
A13200 Final Coat 4 30-Nov-24 04-Dec-24
GTS1.1.1.5.21.16 11th Floor Level 53 19-Oct-24 20-Dec-24
GTS1.1.1.5.21.16.1 Apartment Areas 46 19-Oct-24 12-Dec-24
A11750 Toilet and Kitchen plumbing 21 19-Oct-24 13-Nov-24
A11760 Pressure Testing 12 24-Oct-24 07-Nov-24
A11770 Toilet Water Proofing with Testing 16 30-Oct-24 18-Nov-24
A11780 Toilet Flooring & Dado 18 05-Nov-24 25-Nov-24
A11790 Railing works 14 22-Oct-24 07-Nov-24
A11800 Putty and Primer 1st Coat Painting - Internal 18 30-Oct-24 20-Nov-24
A11810 Kitchen Platform & Tiles work 16 30-Oct-24 18-Nov-24
A11820 Flooring (excluding toilets) 24 06-Nov-24 03-Dec-24
A11830 Door Frame and Shutter Installation (with Ironmongery) 18 20-Nov-24 10-Dec-24
A11840 Windows Installation 12 22-Nov-24 05-Dec-24
A11850 Wiring and Cabling 14 18-Nov-24 03-Dec-24
A11860 Installation of Switches and DBs 12 22-Nov-24 05-Dec-24
A11870 Installation of sanitary fixtures and CP Fittings 16 09-Nov-24 27-Nov-24

Page 12 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A11880 Final Painting 14 27-Nov-24 12-Dec-24


GTS1.1.1.5.21.16.2 Common Area Works 37 08-Nov-24 20-Dec-24
A13210 Corridor Fire Sprinkler Pipe Installation 14 08-Nov-24 23-Nov-24
A13220 Corridor Fire Sprinkler Pressure Testing 2 25-Nov-24 26-Nov-24
A13230 Corridor flooring and Lift cladding 20 19-Nov-24 11-Dec-24
A13240 Corridor Railing works 18 12-Nov-24 02-Dec-24
A13250 Putty and Primer Painting 7 30-Nov-24 07-Dec-24
A13260 1st coat of Painting 7 03-Dec-24 10-Dec-24
A13270 Wiring and Continutity test 7 05-Dec-24 12-Dec-24
A13280 Installation of swtiches and fixtures 5 13-Dec-24 18-Dec-24
A13290 Final Coat 4 17-Dec-24 20-Dec-24
GTS1.1.1.5.21.17 12th Floor Level 53 06-Nov-24 07-Jan-25
GTS1.1.1.5.21.17.1 Apartment Areas 46 06-Nov-24 30-Dec-24
A11890 Toilet and Kitchen plumbing 21 06-Nov-24 29-Nov-24
A11900 Pressure Testing 12 11-Nov-24 23-Nov-24
A11910 Toilet Water Proofing with Testing 16 16-Nov-24 04-Dec-24
A11920 Toilet Flooring & Dado 18 21-Nov-24 11-Dec-24
A11930 Railing works 14 08-Nov-24 23-Nov-24
A11940 Putty and Primer 1st Coat Painting - Internal 18 16-Nov-24 06-Dec-24
A11950 Kitchen Platform & Tiles work 16 16-Nov-24 04-Dec-24
A11960 Flooring (excluding toilets) 24 22-Nov-24 19-Dec-24
A11970 Door Frame and Shutter Installation (with Ironmongery) 18 06-Dec-24 27-Dec-24
A11980 Windows Installation 12 09-Dec-24 21-Dec-24
A11990 Wiring and Cabling 14 04-Dec-24 19-Dec-24
A12000 Installation of Switches and DBs 12 09-Dec-24 21-Dec-24
A12010 Installation of sanitary fixtures and CP Fittings 16 26-Nov-24 13-Dec-24
A12020 Final Painting 14 13-Dec-24 30-Dec-24
GTS1.1.1.5.21.17.2 Common Area Works 37 25-Nov-24 07-Jan-25
A13300 Corridor Fire Sprinkler Pipe Installation 14 25-Nov-24 10-Dec-24
A13310 Corridor Fire Sprinkler Pressure Testing 2 11-Dec-24 12-Dec-24
A13320 Corridor flooring and Lift cladding 20 05-Dec-24 28-Dec-24
A13330 Corridor Railing works 18 28-Nov-24 18-Dec-24
A13340 Putty and Primer Painting 7 17-Dec-24 24-Dec-24
A13350 1st coat of Painting 7 19-Dec-24 27-Dec-24
A13360 Wiring and Continutity test 7 21-Dec-24 30-Dec-24
A13370 Installation of swtiches and fixtures 5 31-Dec-24 04-Jan-25
A13380 Final Coat 4 03-Jan-25 07-Jan-25
GTS1.1.1.5.21.18 13th Floor Level 53 22-Nov-24 25-Jan-25
GTS1.1.1.5.21.18.1 Apartment Areas 46 22-Nov-24 17-Jan-25
A12030 Toilet and Kitchen plumbing 21 22-Nov-24 16-Dec-24
A12040 Pressure Testing 12 27-Nov-24 10-Dec-24
A12050 Toilet Water Proofing with Testing 16 03-Dec-24 20-Dec-24
A12060 Toilet Flooring & Dado 18 07-Dec-24 28-Dec-24
A12070 Railing works 14 25-Nov-24 10-Dec-24
A12080 Putty and Primer 1st Coat Painting - Internal 18 03-Dec-24 23-Dec-24
A12090 Kitchen Platform & Tiles work 16 03-Dec-24 20-Dec-24
A12100 Flooring (excluding toilets) 24 09-Dec-24 06-Jan-25
A12110 Door Frame and Shutter Installation (with Ironmongery) 18 23-Dec-24 15-Jan-25
A12120 Windows Installation 12 26-Dec-24 08-Jan-25

Page 13 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A12130 Wiring and Cabling 14 20-Dec-24 06-Jan-25


A12140 Installation of Switches and DBs 12 26-Dec-24 08-Jan-25
A12150 Installation of sanitary fixtures and CP Fittings 16 12-Dec-24 31-Dec-24
A12160 Final Painting 14 31-Dec-24 17-Jan-25
GTS1.1.1.5.21.18.2 Common Area Works 37 11-Dec-24 25-Jan-25
A13390 Corridor Fire Sprinkler Pipe Installation 14 11-Dec-24 27-Dec-24
A13400 Corridor Fire Sprinkler Pressure Testing 2 28-Dec-24 30-Dec-24
A13410 Corridor flooring and Lift cladding 20 21-Dec-24 16-Jan-25
A13420 Corridor Railing works 18 14-Dec-24 04-Jan-25
A13430 Putty and Primer Painting 7 03-Jan-25 10-Jan-25
A13440 1st coat of Painting 7 06-Jan-25 15-Jan-25
A13450 Wiring and Continutity test 7 08-Jan-25 17-Jan-25
A13460 Installation of swtiches and fixtures 5 18-Jan-25 23-Jan-25
A13470 Final Coat 4 22-Jan-25 25-Jan-25
GTS1.1.1.5.21.19 Terrace Floor Level 53 09-Dec-24 11-Feb-25
GTS1.1.1.5.21.19.1 Apartment Areas 46 09-Dec-24 03-Feb-25
A12170 Toilet and Kitchen plumbing 21 09-Dec-24 02-Jan-25
A12180 Pressure Testing 12 13-Dec-24 27-Dec-24
A12190 Toilet Water Proofing with Testing 16 19-Dec-24 07-Jan-25
A12200 Toilet Flooring & Dado 18 24-Dec-24 16-Jan-25
A12210 Railing works 14 11-Dec-24 27-Dec-24
A12220 Putty and Primer 1st Coat Painting - Internal 18 19-Dec-24 09-Jan-25
A12230 Kitchen Platform & Tiles work 16 19-Dec-24 07-Jan-25
A12240 Flooring (excluding toilets) 24 26-Dec-24 24-Jan-25
A12250 Door Frame and Shutter Installation (with Ironmongery) 18 09-Jan-25 31-Jan-25
A12260 Windows Installation 12 11-Jan-25 27-Jan-25
A12270 Wiring and Cabling 14 07-Jan-25 24-Jan-25
A12280 Installation of Switches and DBs 12 11-Jan-25 27-Jan-25
A12290 Installation of sanitary fixtures and CP Fittings 16 30-Dec-24 18-Jan-25
A12300 Final Painting 14 18-Jan-25 03-Feb-25
GTS1.1.1.5.21.19.2 Common Area Works 37 28-Dec-24 11-Feb-25
A13480 Corridor Fire Sprinkler Pipe Installation 14 28-Dec-24 15-Jan-25
A13490 Corridor Fire Sprinkler Pressure Testing 2 16-Jan-25 17-Jan-25
A13500 Corridor flooring and Lift cladding 20 08-Jan-25 01-Feb-25
A13510 Corridor Railing works 18 01-Jan-25 23-Jan-25
A13520 Putty and Primer Painting 7 22-Jan-25 29-Jan-25
A13530 1st coat of Painting 7 24-Jan-25 31-Jan-25
A13540 Wiring and Continutity test 7 27-Jan-25 03-Feb-25
A13550 Installation of swtiches and fixtures 5 04-Feb-25 08-Feb-25
A13560 Final Coat 4 07-Feb-25 11-Feb-25
GTS1.1.1.5.21.20 Mumty Level 27 27-Dec-24 29-Jan-25
A9930 Parapet Wall Works 10 27-Dec-24 07-Jan-25
A9940 Water Proofin g 7 08-Jan-25 17-Jan-25
A9950 Flooring 10 18-Jan-25 29-Jan-25
GTS1.1.1.5.21.21 Staircases Flooring/ Railing / Painting 217 17-May-24 03-Feb-25
A9960 Mumty to 10th Floor 16 16-Jan-25 03-Feb-25
A9970 10th to 5th Floor 21 08-Nov-24 02-Dec-24
A9980 5th to Ground Floor 21 13-Aug-24 06-Sep-24
A9990 Ground Floor to B1 Level 21 17-May-24 10-Jun-24

Page 14 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

GTS1.1.1.5.21.22 Lift / Elevator Works 51 09-Dec-24 08-Feb-25


A10000 Supply of Lifts 20 09-Dec-24 01-Jan-25
A10010 Installation of Lifts 28 02-Jan-25 05-Feb-25
A10020 Testing & Commissioning of Lifts 3 06-Feb-25 08-Feb-25
GTS1.1.1.5.21.23 Final Painting 28 18-Jan-25 19-Feb-25
A10030 Common Area Final Painting 28 18-Jan-25 19-Feb-25
GTS1.1.1.26 External Texture Painting 48 07-Dec-24 04-Feb-25
A10240 Elevation One 12 07-Dec-24 20-Dec-24
A10250 Elevation Two 12 21-Dec-24 04-Jan-25
A10260 Elevation Three 12 06-Jan-25 21-Jan-25
A10270 Elevation Four 12 22-Jan-25 04-Feb-25
GTS1.1.1.6 Building Shaft Works 35 03-Jan-25 14-Feb-25
GTS1.1.1.6.3 Finishes 10 01-Feb-25 12-Feb-25
A10280 Painting (White Wash) 10 01-Feb-25 12-Feb-25
GTS1.1.1.6.1 Services 35 03-Jan-25 14-Feb-25
A10290 Plumbing Works 21 18-Jan-25 11-Feb-25
A10300 Electrical Works 21 08-Jan-25 03-Feb-25
A10310 Fire Protection System 35 03-Jan-25 14-Feb-25
GTS1.1.1.7 Cleaning & Handing over 10 20-Feb-25 03-Mar-25
A10340 Cleaning & Handing over of the Tower -5 10 20-Feb-25 03-Mar-25
GTS1.1.9 TOWER 6 SUBSTRUCTURE 429 03-Oct-23 03-Mar-25
GTS1.1.9.1 Foundation Level 16 03-Oct-23 20-Oct-23
A14887 Anti-termite treatment 1 03-Oct-23 03-Oct-23
A14888 Footing PCC (Including retaining wall) 3 04-Oct-23 06-Oct-23
A14898 Footing Reinforcement (Including retaining wall) 7 06-Oct-23 13-Oct-23
A14908 Footing Form Work (Including retaining wall) 7 07-Oct-23 14-Oct-23
A14918 Footing Concrete(Including retaining wall) 2 16-Oct-23 17-Oct-23
A14928 Backfilling & Compaction 2 19-Oct-23 20-Oct-23
A15488 De-Shuttering Footing 1 18-Oct-23 18-Oct-23
GTS1.1.9.2 Basement-1 Level 44 21-Oct-23 12-Dec-23
A14938 RCC Retaining Wall (B1 TO P1) 20 21-Oct-23 14-Nov-23
A14948 P1 Level - Basement Slab Concrete( Includes Column concreting) 25 11-Nov-23 09-Dec-23
A15478 Backfilling & Compaction 2 11-Dec-23 12-Dec-23
GTS1.1.9.3 Slab De-shuttering & Shifting of Material 3 23-Dec-23 27-Dec-23
A15458 Basement Roof Slab De-shuttering & Shifting of Material 3 23-Dec-23 27-Dec-23
GTS1.1.9.4 Grade Slab 15 27-Jan-24 13-Feb-24
A15468 Basement Grade Slab 14 29-Jan-24 13-Feb-24
A15498 Anti- Termite Treatment 1 27-Jan-24 27-Jan-24
GTS1.1.9.5 SUPERSTRUCTURE 361 11-Dec-23 19-Feb-25
GTS1.1.9.5.1 P - 1 Level 22 11-Dec-23 05-Jan-24
A13808 Col. Reinforcement (Conventional Shuttering) 6 11-Dec-23 16-Dec-23
A14968 Col. Shuttering 7 11-Dec-23 18-Dec-23
A14978 Col. Casting 3 19-Dec-23 21-Dec-23
A14988 Col. Deshuttering 1 22-Dec-23 22-Dec-23
A14998 Slab Shuttering 9 23-Dec-23 03-Jan-24
A15008 Slab Reinforcement 10 22-Dec-23 03-Jan-24
A15018 Conduiting Works 3 01-Jan-24 03-Jan-24
A15028 Slab Casting 2 04-Jan-24 05-Jan-24
GTS1.1.9.5.2 P - 2 Level 23 06-Jan-24 02-Feb-24

Page 15 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A13818 Col. Reinforcement (Conventional Shuttering) 6 06-Jan-24 12-Jan-24


A15038 Col. Shuttering 7 06-Jan-24 13-Jan-24
A15048 Col. Casting 3 15-Jan-24 17-Jan-24
A15058 Col. Deshuttering 1 18-Jan-24 18-Jan-24
A15068 Slab Shuttering 9 19-Jan-24 30-Jan-24
A15078 Slab Reinforcement 10 19-Jan-24 31-Jan-24
A15088 Conduiting Works 3 29-Jan-24 31-Jan-24
A15098 Slab Casting 2 01-Feb-24 02-Feb-24
GTS1.1.9.5.3 P - 3 Level 23 03-Feb-24 29-Feb-24
A13828 Col. Reinforcement (Conventional Shuttering) 6 03-Feb-24 09-Feb-24
A15108 Col. Shuttering 7 03-Feb-24 10-Feb-24
A15118 Col. Casting 3 12-Feb-24 14-Feb-24
A15128 Col. Deshuttering 1 15-Feb-24 15-Feb-24
A15138 Slab Shuttering 9 16-Feb-24 26-Feb-24
A15148 Slab Reinforcement 10 16-Feb-24 27-Feb-24
A15158 Conduiting Works 3 24-Feb-24 27-Feb-24
A15168 Slab Casting 2 28-Feb-24 29-Feb-24
GTS1.1.9.5.4 GF Floor Level 19 01-Mar-24 22-Mar-24
A13838 Wall Reinforcement 6 04-Mar-24 09-Mar-24
A15178 Wall Shuttering 2 12-Mar-24 13-Mar-24
A15188 Slab Reinforcement 3 18-Mar-24 20-Mar-24
A15198 Slab Conduiting Works 1 21-Mar-24 21-Mar-24
A15208 Slab Casting 1 22-Mar-24 22-Mar-24
A15518 Wall Starter (Miv an Shutterin g) 5 01-Mar-24 06-Mar-24
A15528 Conduiting Works 1 11-Mar-24 11-Mar-24
A15538 Slab Shuttering 5 14-Mar-24 19-Mar-24
GTS1.1.9.5.5 1st Floor Level 15 23-Mar-24 12-Apr-24
A13848 Wall Starter (Miv an Shutterin g) 3 23-Mar-24 27-Mar-24
A15218 Wall Reinforcement 4 26-Mar-24 29-Mar-24
A15228 Conduiting Works 1 30-Mar-24 30-Mar-24
A15238 Wall Shuttering 2 01-Apr-24 02-Apr-24
A15248 Slab Shuttering 4 03-Apr-24 06-Apr-24
A15258 Slab Reinforcement 3 05-Apr-24 08-Apr-24
A15548 Slab Conduiting Works 1 11-Apr-24 11-Apr-24
A15558 Slab Casting 1 12-Apr-24 12-Apr-24
GTS1.1.9.5.6 2nd Floor Level 14 13-Apr-24 29-Apr-24
A13858 Wall Starter (Miv an Shutterin g) 3 13-Apr-24 16-Apr-24
A15268 Wall Reinforcement 4 15-Apr-24 18-Apr-24
A15278 Conduiting Works 1 19-Apr-24 19-Apr-24
A15288 Wall Shuttering 2 20-Apr-24 22-Apr-24
A15298 Slab Shuttering 3 23-Apr-24 25-Apr-24
A15308 Slab Reinforcement 3 24-Apr-24 26-Apr-24
A15568 Slab Conduiting Works 1 27-Apr-24 27-Apr-24
A15578 Slab Casting 1 29-Apr-24 29-Apr-24
GTS1.1.9.5.7 3rd Floor Level 14 30-Apr-24 16-May-24
A13868 Wall Starter (Miv an Shutterin g) 3 30-Apr-24 03-May-24
A15318 Wall Reinforcement 4 02-May-24 06-May-24
A15328 Conduiting Works 1 07-May-24 07-May-24
A15338 Wall Shuttering 2 08-May-24 09-May-24

Page 16 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A15348 Slab Shuttering 3 10-May-24 13-May-24


A15358 Slab Reinforcement 3 11-May-24 14-May-24
A15588 Slab Conduiting Works 1 15-May-24 15-May-24
A15598 Slab Casting 1 16-May-24 16-May-24
GTS1.1.9.5.8 4th Floor Level 14 17-May-24 01-Jun-24
A13878 Wall Starter (Miv an Shutterin g) 3 17-May-24 20-May-24
A15368 Wall Reinforcement 4 18-May-24 22-May-24
A15378 Conduiting Works 1 23-May-24 23-May-24
A15388 Wall Shuttering 2 24-May-24 25-May-24
A15398 Slab Shuttering 3 27-May-24 29-May-24
A15408 Slab Reinforcement 3 28-May-24 30-May-24
A15608 Slab Conduiting Works 1 31-May-24 31-May-24
A15618 Slab Casting 1 01-Jun-24 01-Jun-24
GTS1.1.9.5.9 5th Floor Level 14 03-Jun-24 18-Jun-24
A18838 Wall Starter (Miv an Shutterin g) 3 03-Jun-24 05-Jun-24
A18848 Wall Reinforcement 4 04-Jun-24 07-Jun-24
A18858 Conduiting Works 1 08-Jun-24 08-Jun-24
A18868 Wall Shuttering 2 10-Jun-24 11-Jun-24
A18878 Slab Shuttering 3 12-Jun-24 14-Jun-24
A18888 Slab Reinforcement 3 13-Jun-24 15-Jun-24
A18898 Slab Conduiting Works 1 17-Jun-24 17-Jun-24
A18908 Slab Casting 1 18-Jun-24 18-Jun-24
GTS1.1.9.5.10 6th Floor Level 14 19-Jun-24 04-Jul-24
A18918 Wall Starter (Miv an Shutterin g) 3 19-Jun-24 21-Jun-24
A18928 Wall Reinforcement 4 20-Jun-24 24-Jun-24
A18938 Conduiting Works 1 25-Jun-24 25-Jun-24
A18948 Wall Shuttering 2 26-Jun-24 27-Jun-24
A18958 Slab Shuttering 3 28-Jun-24 01-Jul-24
A18968 Slab Reinforcement 3 29-Jun-24 02-Jul-24
A18978 Slab Conduiting Works 1 03-Jul-24 03-Jul-24
A18988 Slab Casting 1 04-Jul-24 04-Jul-24
GTS1.1.9.5.11 7th Floor Level 14 05-Jul-24 20-Jul-24
A18998 Wall Starter (Miv an Shutterin g) 3 05-Jul-24 08-Jul-24
A19008 Wall Reinforcement 4 06-Jul-24 10-Jul-24
A19018 Conduiting Works 1 11-Jul-24 11-Jul-24
A19028 Wall Shuttering 2 12-Jul-24 13-Jul-24
A19038 Slab Shuttering 3 15-Jul-24 17-Jul-24
A19048 Slab Reinforcement 3 16-Jul-24 18-Jul-24
A19058 Slab Conduiting Works 1 19-Jul-24 19-Jul-24
A19068 Slab Casting 1 20-Jul-24 20-Jul-24
GTS1.1.9.5.12 8th Floor Level 14 22-Jul-24 06-Aug-24
A19078 Wall Starter (Miv an Shutterin g) 3 22-Jul-24 24-Jul-24
A19088 Wall Reinforcement 4 23-Jul-24 26-Jul-24
A19098 Conduiting Works 1 27-Jul-24 27-Jul-24
A19108 Wall Shuttering 2 29-Jul-24 30-Jul-24
A19118 Slab Shuttering 3 31-Jul-24 02-Aug-24
A19128 Slab Reinforcement 3 01-Aug-24 03-Aug-24
A19138 Slab Conduiting Works 1 05-Aug-24 05-Aug-24
A19148 Slab Casting 1 06-Aug-24 06-Aug-24

Page 17 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

GTS1.1.9.5.13 9th Floor Level 14 07-Aug-24 23-Aug-24


A19158 Wall Starter (Miv an Shutterin g) 3 07-Aug-24 09-Aug-24
A19168 Wall Reinforcement 4 08-Aug-24 12-Aug-24
A19178 Conduiting Works 1 13-Aug-24 13-Aug-24
A19188 Wall Shuttering 2 14-Aug-24 16-Aug-24
A19198 Slab Shuttering 3 17-Aug-24 20-Aug-24
A19208 Slab Reinforcement 3 19-Aug-24 21-Aug-24
A19218 Slab Conduiting Works 1 22-Aug-24 22-Aug-24
A19228 Slab Casting 1 23-Aug-24 23-Aug-24
GTS1.1.9.5.14 10th Floor Level 14 24-Aug-24 10-Sep-24
A19238 Wall Starter (Miv an Shutterin g) 3 24-Aug-24 27-Aug-24
A19248 Wall Reinforcement 4 26-Aug-24 29-Aug-24
A19258 Conduiting Works 1 30-Aug-24 30-Aug-24
A19268 Wall Shuttering 2 31-Aug-24 02-Sep-24
A19278 Slab Shuttering 3 03-Sep-24 05-Sep-24
A19288 Slab Reinforcement 3 04-Sep-24 06-Sep-24
A19298 Slab Conduiting Works 1 09-Sep-24 09-Sep-24
A19308 Slab Casting 1 10-Sep-24 10-Sep-24
GTS1.1.9.5.15 11th Floor Level 14 11-Sep-24 27-Sep-24
A19318 Wall Starter (Miv an Shutterin g) 3 11-Sep-24 13-Sep-24
A19328 Wall Reinforcement 4 12-Sep-24 17-Sep-24
A19338 Conduiting Works 1 18-Sep-24 18-Sep-24
A19348 Wall Shuttering 2 19-Sep-24 20-Sep-24
A19358 Slab Shuttering 3 21-Sep-24 24-Sep-24
A19368 Slab Reinforcement 3 23-Sep-24 25-Sep-24
A19378 Slab Conduiting Works 1 26-Sep-24 26-Sep-24
A19388 Slab Casting 1 27-Sep-24 27-Sep-24
GTS1.1.9.5.16 12th Floor Level 14 28-Sep-24 15-Oct-24
A19398 Wall Starter (Miv an Shutterin g) 3 28-Sep-24 01-Oct-24
A19408 Wall Reinforcement 4 30-Sep-24 04-Oct-24
A19418 Conduiting Works 1 05-Oct-24 05-Oct-24
A19428 Wall Shuttering 2 07-Oct-24 08-Oct-24
A19438 Slab Shuttering 3 09-Oct-24 11-Oct-24
A19448 Slab Reinforcement 3 10-Oct-24 12-Oct-24
A19458 Slab Conduiting Works 1 14-Oct-24 14-Oct-24
A19468 Slab Casting 1 15-Oct-24 15-Oct-24
GTS1.1.9.5.17 13th Floor Level 14 16-Oct-24 01-Nov-24
A19478 Wall Starter (Miv an Shutterin g) 3 16-Oct-24 18-Oct-24
A19488 Wall Reinforcement 4 17-Oct-24 21-Oct-24
A19498 Conduiting Works 1 22-Oct-24 22-Oct-24
A19508 Wall Shuttering 2 23-Oct-24 24-Oct-24
A19518 Slab Shuttering 3 25-Oct-24 28-Oct-24
A19528 Slab Reinforcement 3 26-Oct-24 29-Oct-24
A19538 Slab Conduiting Works 1 30-Oct-24 30-Oct-24
A19548 Slab Casting 1 01-Nov-24 01-Nov-24
GTS1.1.9.5.18 Terrace Floor Level 14 02-Nov-24 18-Nov-24
A19558 Wall Starter (Miv an Shutterin g) 3 02-Nov-24 05-Nov-24
A19568 Wall Reinforcement 4 04-Nov-24 07-Nov-24
A19578 Conduiting Works 1 08-Nov-24 08-Nov-24

Page 18 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A19588 Wall Shuttering 2 09-Nov-24 11-Nov-24


A19598 Slab Shuttering 3 12-Nov-24 14-Nov-24
A19608 Slab Reinforcement 3 13-Nov-24 15-Nov-24
A19618 Slab Conduiting Works 1 16-Nov-24 16-Nov-24
A19628 Slab Casting 1 18-Nov-24 18-Nov-24
GTS1.1.9.5.19 Mumty / Over Head Tanks / Lift Machine Rooms 15 19-Nov-24 05-Dec-24
A13888 Wall Reinforcement 5 20-Nov-24 25-Nov-24
A13898 Conduiting Works 1 26-Nov-24 26-Nov-24
A13908 Wall Shuttering 3 27-Nov-24 29-Nov-24
A13918 Slab Shuttering 3 29-Nov-24 02-Dec-24
A13928 Slab Reinforcement 3 30-Nov-24 03-Dec-24
A13938 Slab Conduiting Works 1 04-Dec-24 04-Dec-24
A15628 Slab Casting 1 05-Dec-24 05-Dec-24
A15638 Wall Starter (Miv an Shutterin g) & OHT Works 3 19-Nov-24 21-Nov-24
GTS1.1.9.5.20 Slab De-shuttering & Shifting of Material 294 06-Jan-24 26-Dec-24
A13948 P - 1 Level 3 06-Jan-24 09-Jan-24
A13958 P - 2 Level 3 03-Feb-24 06-Feb-24
A13968 P - 3 Level 3 01-Mar-24 04-Mar-24
A13978 GF Floor Level 3 12-Apr-24 15-Apr-24
A13988 1st Floor Level 3 30-Apr-24 03-May-24
A13998 2nd Floor Level 3 17-May-24 20-May-24
A14008 3rd Floor Level 3 03-Jun-24 05-Jun-24
A14018 4th Floor Level 3 19-Jun-24 21-Jun-24
A14028 5th Floor Level 3 05-Jul-24 08-Jul-24
A14038 6th Floor Level 3 22-Jul-24 24-Jul-24
A14048 7th Floor Level 3 07-Aug-24 09-Aug-24
A14058 8th Floor Level 3 24-Aug-24 27-Aug-24
A14068 9th Floor Level 3 11-Sep-24 13-Sep-24
A14078 10th Floor Level 3 28-Sep-24 01-Oct-24
A14088 Mumty / Over Head Tanks / Lift Machine Rooms 3 23-Dec-24 26-Dec-24
A15418 11th Floor Level 3 16-Oct-24 18-Oct-24
A15428 12th Floor Level 3 02-Nov-24 05-Nov-24
A15438 13th Floor Level 3 19-Nov-24 21-Nov-24
A15448 Terrace Floor Level 3 05-Dec-24 07-Dec-24
GTS1.1.9.5.21 INTERNAL FINISHES & RELATED SERVICES 333 13-Jan-24 19-Feb-25
GTS1.1.9.5.21.1 Basement-1 69 17-Feb-24 11-May-24
A14098 Fire Sprinkler installation 14 17-Feb-24 04-Mar-24
A14108 Ventilation 20 20-Feb-24 13-Mar-24
A14118 Water Proofin g + Protective Pla ster 18 08-Mar-24 29-Mar-24
A14128 TREMIX/ VDF Flooring Works 26 18-Mar-24 19-Apr-24
A14138 Door frames installation (including fire doors) 7 20-Apr-24 27-Apr-24
A14148 Wiring and Continutity test 14 26-Feb-24 12-Mar-24
A14158 Primer and Paint 16 20-Apr-24 09-May-24
A14168 Installation of Electrical fixtures 10 30-Apr-24 11-May-24
A14178 Door Shutter installation (with Iron Mongery) & Door Painting 5 25-Apr-24 30-Apr-24
A14188 Miscellaneous works ( Drain System, Grating , Ramps & Marking) 25 26-Mar-24 25-Apr-24
GTS1.1.9.5.21.2 Podium- 1 Level 59 13-Jan-24 22-Mar-24
A14198 Fire Sprinkler Installation 12 13-Jan-24 27-Jan-24
A14208 Ventilation 17 16-Jan-24 05-Feb-24

Page 19 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A14218 Water Proofin g + Protective Pla ster 14 01-Feb-24 16-Feb-24


A14228 VDF Flooring Works 20 09-Feb-24 02-Mar-24
A14238 Door frames installation (including fire doors) 6 04-Mar-24 09-Mar-24
A14248 Wiring and Continutity test 12 22-Jan-24 05-Feb-24
A14258 Primer and Paint 14 04-Mar-24 19-Mar-24
A14268 Installation of Electrical fixtures 8 14-Mar-24 22-Mar-24
A14278 Door Shutter installation (with Iron Mongery) & Door Painting 5 07-Mar-24 12-Mar-24
GTS1.1.9.5.21.3 Podium- 2 Level 59 10-Feb-24 22-Apr-24
A14288 Fire Sprinkler Installation 12 10-Feb-24 23-Feb-24
A14298 Ventilation 17 13-Feb-24 02-Mar-24
A14308 Water Proofin g + Protective Pla ster 14 28-Feb-24 14-Mar-24
A14318 VDF Flooring Works 20 07-Mar-24 30-Mar-24
A14328 Door frames installation (including fire doors) 6 01-Apr-24 06-Apr-24
A14338 Wiring and Continutity test 12 19-Feb-24 02-Mar-24
A14348 Primer and Paint 14 01-Apr-24 18-Apr-24
A14358 Installation of Electrical fixtures 8 13-Apr-24 22-Apr-24
A14368 Door Shutter installation (with Iron Mongery) & Door Painting 5 04-Apr-24 11-Apr-24
GTS1.1.9.5.21.4 Podium- 3 Level 59 08-Mar-24 20-May-24
A14378 Fire Sprinkler Installation 12 08-Mar-24 21-Mar-24
A14388 Ventilation 17 11-Mar-24 30-Mar-24
A14398 Water Proofin g + Protective Pla ster 14 27-Mar-24 13-Apr-24
A14408 VDF Flooring Works 20 04-Apr-24 29-Apr-24
A14418 Door frames installation (including fire doors) 6 30-Apr-24 07-May-24
A14428 Wiring and Continutity test 12 16-Mar-24 30-Mar-24
A14438 Primer and Paint 14 30-Apr-24 16-May-24
A14448 Installation of Electrical fixtures 8 11-May-24 20-May-24
A14458 Door Shutter installation (with Iron Mongery) & Door Painting 5 04-May-24 09-May-24
GTS1.1.9.5.21.5 Ground Floor Level 53 16-Apr-24 17-Jun-24
GTS1.1.9.5.21.5.1 Apartment Areas 46 16-Apr-24 08-Jun-24
A14468 Flooring (excluding toilets) 24 03-May-24 30-May-24
A14478 Putty and Primer 1st Coat Painting - Internal 18 26-Apr-24 17-May-24
A14488 Railing works 14 18-Apr-24 04-May-24
A14498 Toilet Water Proofing with Testing 16 26-Apr-24 15-May-24
A14508 Toilet and Kitchen plumbing 21 16-Apr-24 10-May-24
A14518 Pressure Testing 12 20-Apr-24 04-May-24
A14528 Toilet Flooring & Dado 18 02-May-24 22-May-24
A14538 Kitchen Platform & Tiles work 16 26-Apr-24 15-May-24
A14548 Windows Installation 12 20-May-24 01-Jun-24
A14558 Door Frame and Shutter Installation (with Ironmongery) 18 17-May-24 06-Jun-24
A14568 Wiring and Cabling 14 15-May-24 30-May-24
A14578 Installation of Switches and DBs 12 20-May-24 01-Jun-24
A14588 Installation of sanitary fixtures and CP Fittings 16 07-May-24 24-May-24
A14598 Final Painting 14 24-May-24 08-Jun-24
GTS1.1.9.5.21.5.2 Common Area Works 37 06-May-24 17-Jun-24
A14608 Corridor Fire Sprinkler Pipe Installation 14 06-May-24 21-May-24
A14618 Corridor Fire Sprinkler Pressure Testing 2 22-May-24 23-May-24
A14628 Corridor flooring and Lift cladding 20 16-May-24 07-Jun-24
A14638 Corridor Railing works 18 09-May-24 29-May-24
A14648 Putty and Primer Painting 7 28-May-24 04-Jun-24

Page 20 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A14658 1st coat of Painting 7 30-May-24 06-Jun-24


A14668 Wiring and Continutity test 7 01-Jun-24 08-Jun-24
A14678 Installation of swtiches and fixtures 5 10-Jun-24 14-Jun-24
A14688 Final Coat 4 13-Jun-24 17-Jun-24
GTS1.1.9.5.21.6 1st Floor Level 53 04-May-24 04-Jul-24
GTS1.1.9.5.21.6.24 Apartment Areas 46 04-May-24 26-Jun-24
A18698 Flooring (excluding toilets) 24 21-May-24 17-Jun-24
A18708 Putty and Primer 1st Coat Painting - Internal 18 15-May-24 04-Jun-24
A18718 Railing works 14 07-May-24 22-May-24
A18728 Toilet Water Proofing with Testing 16 15-May-24 01-Jun-24
A18738 Toilet and Kitchen plumbing 21 04-May-24 28-May-24
A18748 Pressure Testing 12 09-May-24 22-May-24
A18758 Toilet Flooring & Dado 18 20-May-24 08-Jun-24
A18768 Kitchen Platform & Tiles work 16 15-May-24 01-Jun-24
A18778 Windows Installation 12 06-Jun-24 19-Jun-24
A18788 Door Frame and Shutter Installation (with Ironmongery) 18 04-Jun-24 24-Jun-24
A18798 Wiring and Cabling 14 01-Jun-24 17-Jun-24
A18808 Installation of Switches and DBs 12 06-Jun-24 19-Jun-24
A18818 Installation of sanitary fixtures and CP Fittings 16 24-May-24 11-Jun-24
A18828 Final Painting 14 11-Jun-24 26-Jun-24
GTS1.1.9.5.21.6.1 Common Area Works 37 23-May-24 04-Jul-24
A17448 Corridor Fire Sprinkler Pipe Installation 14 23-May-24 07-Jun-24
A17458 Corridor Fire Sprinkler Pressure Testing 2 08-Jun-24 10-Jun-24
A17468 Corridor flooring and Lift cladding 20 03-Jun-24 25-Jun-24
A17478 Corridor Railing works 18 27-May-24 15-Jun-24
A17488 Putty and Primer Painting 7 14-Jun-24 21-Jun-24
A17498 1st coat of Painting 7 17-Jun-24 24-Jun-24
A17508 Wiring and Continutity test 7 19-Jun-24 26-Jun-24
A17518 Installation of swtiches and fixtures 5 27-Jun-24 02-Jul-24
A17528 Final Coat 4 01-Jul-24 04-Jul-24
GTS1.1.9.5.21.7 2nd Floor Level 53 21-May-24 20-Jul-24
GTS1.1.9.5.21.7.27 Apartment Areas 46 21-May-24 12-Jul-24
A15648 Flooring (excluding toilets) 24 06-Jun-24 03-Jul-24
A15658 Putty and Primer 1st Coat Painting - Internal 18 31-May-24 20-Jun-24
A15668 Railing works 14 23-May-24 07-Jun-24
A15678 Toilet Water Proofing with Testing 16 31-May-24 18-Jun-24
A15688 Toilet and Kitchen plumbing 21 21-May-24 13-Jun-24
A15698 Pressure Testing 12 25-May-24 07-Jun-24
A15708 Toilet Flooring & Dado 18 05-Jun-24 25-Jun-24
A15718 Kitchen Platform & Tiles work 16 31-May-24 18-Jun-24
A15728 Windows Installation 12 22-Jun-24 05-Jul-24
A15738 Door Frame and Shutter Installation (with Ironmongery) 18 20-Jun-24 10-Jul-24
A15748 Wiring and Cabling 14 18-Jun-24 03-Jul-24
A15758 Installation of Switches and DBs 12 22-Jun-24 05-Jul-24
A15768 Installation of sanitary fixtures and CP Fittings 16 10-Jun-24 27-Jun-24
A15778 Final Painting 14 27-Jun-24 12-Jul-24
GTS1.1.9.5.21.7.26 Common Area Works 37 08-Jun-24 20-Jul-24
A17538 Corridor Fire Sprinkler Pipe Installation 14 08-Jun-24 24-Jun-24
A17548 Corridor Fire Sprinkler Pressure Testing 2 25-Jun-24 26-Jun-24

Page 21 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A17558 Corridor flooring and Lift cladding 20 19-Jun-24 11-Jul-24


A17568 Corridor Railing works 18 12-Jun-24 02-Jul-24
A17578 Putty and Primer Painting 7 01-Jul-24 08-Jul-24
A17588 1st coat of Painting 7 03-Jul-24 10-Jul-24
A17598 Wiring and Continutity test 7 05-Jul-24 12-Jul-24
A17608 Installation of swtiches and fixtures 5 13-Jul-24 18-Jul-24
A17618 Final Coat 4 17-Jul-24 20-Jul-24
GTS1.1.9.5.21.8 3rd Floor Level 53 06-Jun-24 06-Aug-24
GTS1.1.9.5.21.8.29 Apartment Areas 46 06-Jun-24 29-Jul-24
A15788 Flooring (excluding toilets) 24 22-Jun-24 19-Jul-24
A15798 Putty and Primer 1st Coat Painting - Internal 18 17-Jun-24 06-Jul-24
A15808 Railing works 14 08-Jun-24 24-Jun-24
A15818 Toilet Water Proofing with Testing 16 17-Jun-24 04-Jul-24
A15828 Toilet and Kitchen plumbing 21 06-Jun-24 29-Jun-24
A15838 Pressure Testing 12 11-Jun-24 24-Jun-24
A15848 Toilet Flooring & Dado 18 21-Jun-24 11-Jul-24
A15858 Kitchen Platform & Tiles work 16 17-Jun-24 04-Jul-24
A15868 Windows Installation 12 09-Jul-24 22-Jul-24
A15878 Door Frame and Shutter Installation (with Ironmongery) 18 06-Jul-24 26-Jul-24
A15888 Wiring and Cabling 14 04-Jul-24 19-Jul-24
A15898 Installation of Switches and DBs 12 09-Jul-24 22-Jul-24
A15908 Installation of sanitary fixtures and CP Fittings 16 26-Jun-24 13-Jul-24
A15918 Final Painting 14 13-Jul-24 29-Jul-24
GTS1.1.9.5.21.8.28 Common Area Works 37 25-Jun-24 06-Aug-24
A17628 Corridor Fire Sprinkler Pipe Installation 14 25-Jun-24 10-Jul-24
A17638 Corridor Fire Sprinkler Pressure Testing 2 11-Jul-24 12-Jul-24
A17648 Corridor flooring and Lift cladding 20 05-Jul-24 27-Jul-24
A17658 Corridor Railing works 18 28-Jun-24 18-Jul-24
A17668 Putty and Primer Painting 7 17-Jul-24 24-Jul-24
A17678 1st coat of Painting 7 19-Jul-24 26-Jul-24
A17688 Wiring and Continutity test 7 22-Jul-24 29-Jul-24
A17698 Installation of swtiches and fixtures 5 30-Jul-24 03-Aug-24
A17708 Final Coat 4 02-Aug-24 06-Aug-24
GTS1.1.9.5.21.9 4th Floor Level 53 22-Jun-24 23-Aug-24
GTS1.1.9.5.21.9.1 Apartment Areas 46 22-Jun-24 14-Aug-24
A15928 Flooring (excluding toilets) 24 09-Jul-24 05-Aug-24
A15938 Putty and Primer 1st Coat Painting - Internal 18 03-Jul-24 23-Jul-24
A15948 Toilet Water Proofing with Testing 16 03-Jul-24 20-Jul-24
A15958 Toilet and Kitchen plumbing 21 22-Jun-24 16-Jul-24
A15968 Pressure Testing 12 27-Jun-24 10-Jul-24
A15978 Toilet Flooring & Dado 18 08-Jul-24 27-Jul-24
A15988 Kitchen Platform & Tiles work 16 03-Jul-24 20-Jul-24
A15998 Windows Installation 12 25-Jul-24 07-Aug-24
A16008 Door Frame and Shutter Installation (with Ironmongery) 18 23-Jul-24 12-Aug-24
A16018 Wiring and Cabling 14 20-Jul-24 05-Aug-24
A16028 Installation of Switches and DBs 12 25-Jul-24 07-Aug-24
A16038 Installation of sanitary fixtures and CP Fittings 16 12-Jul-24 30-Jul-24
A16048 Final Painting 14 30-Jul-24 14-Aug-24
GTS1.1.9.5.21.9.30 Common Area Works 37 11-Jul-24 23-Aug-24

Page 22 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A17718 Corridor Fire Sprinkler Pipe Installation 14 11-Jul-24 26-Jul-24


A17728 Corridor Fire Sprinkler Pressure Testing 2 27-Jul-24 29-Jul-24
A17738 Corridor flooring and Lift cladding 20 22-Jul-24 13-Aug-24
A17748 Corridor Railing works 18 15-Jul-24 03-Aug-24
A17758 Putty and Primer Painting 7 02-Aug-24 09-Aug-24
A17768 1st coat of Painting 7 05-Aug-24 12-Aug-24
A17778 Wiring and Continutity test 7 07-Aug-24 14-Aug-24
A17788 Installation of swtiches and fixtures 5 16-Aug-24 21-Aug-24
A17798 Final Coat 4 20-Aug-24 23-Aug-24
GTS1.1.9.5.21.10 5th Floor Level 53 09-Jul-24 10-Sep-24
GTS1.1.9.5.21.10.1 Apartment Areas 46 09-Jul-24 31-Aug-24
A16058 Flooring (excluding toilets) 24 25-Jul-24 22-Aug-24
A16068 Putty and Primer 1st Coat Painting - Internal 18 19-Jul-24 08-Aug-24
A16078 Toilet Water Proofing with Testing 16 19-Jul-24 06-Aug-24
A16088 Toilet and Kitchen plumbing 21 09-Jul-24 01-Aug-24
A16098 Pressure Testing 12 13-Jul-24 26-Jul-24
A16108 Toilet Flooring & Dado 18 24-Jul-24 13-Aug-24
A16118 Kitchen Platform & Tiles work 16 19-Jul-24 06-Aug-24
A16128 Windows Installation 12 10-Aug-24 24-Aug-24
A16138 Door Frame and Shutter Installation (with Ironmongery) 18 08-Aug-24 29-Aug-24
A16148 Wiring and Cabling 14 06-Aug-24 22-Aug-24
A16158 Installation of Switches and DBs 12 10-Aug-24 24-Aug-24
A16168 Installation of sanitary fixtures and CP Fittings 16 29-Jul-24 16-Aug-24
A16178 Final Painting 14 16-Aug-24 31-Aug-24
GTS1.1.9.5.21.10.2 Common Area Works 37 27-Jul-24 10-Sep-24
A17808 Corridor Fire Sprinkler Pipe Installation 14 27-Jul-24 12-Aug-24
A17818 Corridor Fire Sprinkler Pressure Testing 2 13-Aug-24 14-Aug-24
A17828 Corridor flooring and Lift cladding 20 07-Aug-24 30-Aug-24
A17838 Corridor Railing works 18 31-Jul-24 21-Aug-24
A17848 Putty and Primer Painting 7 20-Aug-24 27-Aug-24
A17858 1st coat of Painting 7 22-Aug-24 29-Aug-24
A17868 Wiring and Continutity test 7 24-Aug-24 31-Aug-24
A17878 Installation of swtiches and fixtures 5 02-Sep-24 06-Sep-24
A17888 Final Coat 4 05-Sep-24 10-Sep-24
GTS1.1.9.5.21.11 6th Floor Level 53 25-Jul-24 27-Sep-24
GTS1.1.9.5.21.11.1 Apartment Areas 46 25-Jul-24 19-Sep-24
A16188 Flooring (excluding toilets) 24 10-Aug-24 09-Sep-24
A16198 Putty and Primer 1st Coat Painting - Internal 18 05-Aug-24 26-Aug-24
A16208 Railing works 14 27-Jul-24 12-Aug-24
A16218 Toilet Water Proofing with Testing 16 05-Aug-24 23-Aug-24
A16228 Toilet and Kitchen plumbing 21 25-Jul-24 19-Aug-24
A16238 Pressure Testing 12 30-Jul-24 12-Aug-24
A16248 Toilet Flooring & Dado 18 09-Aug-24 30-Aug-24
A16258 Kitchen Platform & Tiles work 16 05-Aug-24 23-Aug-24
A16268 Windows Installation 12 28-Aug-24 11-Sep-24
A16278 Door Frame and Shutter Installation (with Ironmongery) 18 26-Aug-24 17-Sep-24
A16288 Wiring and Cabling 14 23-Aug-24 09-Sep-24
A16298 Installation of Switches and DBs 12 28-Aug-24 11-Sep-24
A16308 Installation of sanitary fixtures and CP Fittings 16 14-Aug-24 02-Sep-24

Page 23 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A16318 Final Painting 14 02-Sep-24 19-Sep-24


GTS1.1.9.5.21.11.2 Common Area Works 37 13-Aug-24 27-Sep-24
A17898 Corridor Fire Sprinkler Pipe Installation 14 13-Aug-24 29-Aug-24
A17908 Corridor Fire Sprinkler Pressure Testing 2 30-Aug-24 31-Aug-24
A17918 Corridor flooring and Lift cladding 20 24-Aug-24 18-Sep-24
A17928 Corridor Railing works 18 17-Aug-24 06-Sep-24
A17938 Putty and Primer Painting 7 05-Sep-24 13-Sep-24
A17948 1st coat of Painting 7 09-Sep-24 17-Sep-24
A17958 Wiring and Continutity test 7 11-Sep-24 19-Sep-24
A17968 Installation of swtiches and fixtures 5 20-Sep-24 25-Sep-24
A17978 Final Coat 4 24-Sep-24 27-Sep-24
GTS1.1.9.5.21.12 7th Floor Level 53 10-Aug-24 15-Oct-24
GTS1.1.9.5.21.12.1 Apartment Areas 46 10-Aug-24 07-Oct-24
A16328 Flooring (excluding toilets) 24 28-Aug-24 26-Sep-24
A16338 Putty and Primer 1st Coat Painting - Internal 18 22-Aug-24 12-Sep-24
A16348 Railing works 14 13-Aug-24 29-Aug-24
A16358 Toilet Water Proofing with Testing 16 22-Aug-24 10-Sep-24
A16368 Toilet and Kitchen plumbing 21 10-Aug-24 04-Sep-24
A16378 Pressure Testing 12 16-Aug-24 29-Aug-24
A16388 Toilet Flooring & Dado 18 27-Aug-24 18-Sep-24
A16398 Kitchen Platform & Tiles work 16 22-Aug-24 10-Sep-24
A16408 Windows Installation 12 14-Sep-24 28-Sep-24
A16418 Door Frame and Shutter Installation (with Ironmongery) 18 12-Sep-24 04-Oct-24
A16428 Wiring and Cabling 14 10-Sep-24 26-Sep-24
A16438 Installation of Switches and DBs 12 14-Sep-24 28-Sep-24
A16448 Installation of sanitary fixtures and CP Fittings 16 31-Aug-24 20-Sep-24
A16458 Final Painting 14 20-Sep-24 07-Oct-24
GTS1.1.9.5.21.12.2 Common Area Works 37 30-Aug-24 15-Oct-24
A17988 Corridor Fire Sprinkler Pipe Installation 14 30-Aug-24 17-Sep-24
A17998 Corridor Fire Sprinkler Pressure Testing 2 18-Sep-24 19-Sep-24
A18008 Corridor flooring and Lift cladding 20 11-Sep-24 05-Oct-24
A18018 Corridor Railing works 18 03-Sep-24 25-Sep-24
A18028 Putty and Primer Painting 7 24-Sep-24 01-Oct-24
A18038 1st coat of Painting 7 26-Sep-24 04-Oct-24
A18048 Wiring and Continutity test 7 28-Sep-24 07-Oct-24
A18058 Installation of swtiches and fixtures 5 08-Oct-24 12-Oct-24
A18068 Final Coat 4 11-Oct-24 15-Oct-24
GTS1.1.9.5.21.13 8th Floor Level 53 28-Aug-24 01-Nov-24
GTS1.1.9.5.21.13.1 Apartment Areas 46 28-Aug-24 23-Oct-24
A16468 Flooring (excluding toilets) 24 14-Sep-24 14-Oct-24
A16478 Putty and Primer 1st Coat Painting - Internal 18 09-Sep-24 30-Sep-24
A16488 Railing works 14 30-Aug-24 17-Sep-24
A16498 Toilet Water Proofing with Testing 16 09-Sep-24 27-Sep-24
A16508 Toilet and Kitchen plumbing 21 28-Aug-24 23-Sep-24
A16518 Pressure Testing 12 02-Sep-24 17-Sep-24
A16528 Toilet Flooring & Dado 18 13-Sep-24 05-Oct-24
A16538 Kitchen Platform & Tiles work 16 09-Sep-24 27-Sep-24
A16548 Windows Installation 12 03-Oct-24 16-Oct-24
A16558 Door Frame and Shutter Installation (with Ironmongery) 18 30-Sep-24 21-Oct-24

Page 24 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A16568 Wiring and Cabling 14 27-Sep-24 14-Oct-24


A16578 Installation of Switches and DBs 12 03-Oct-24 16-Oct-24
A16588 Installation of sanitary fixtures and CP Fittings 16 19-Sep-24 08-Oct-24
A16598 Final Painting 14 08-Oct-24 23-Oct-24
GTS1.1.9.5.21.13.2 Common Area Works 37 18-Sep-24 01-Nov-24
A18078 Corridor Fire Sprinkler Pipe Installation 14 18-Sep-24 04-Oct-24
A18088 Corridor Fire Sprinkler Pressure Testing 2 05-Oct-24 07-Oct-24
A18098 Corridor flooring and Lift cladding 20 28-Sep-24 22-Oct-24
A18108 Corridor Railing works 18 21-Sep-24 12-Oct-24
A18118 Putty and Primer Painting 7 11-Oct-24 18-Oct-24
A18128 1st coat of Painting 7 14-Oct-24 21-Oct-24
A18138 Wiring and Continutity test 7 16-Oct-24 23-Oct-24
A18148 Installation of swtiches and fixtures 5 24-Oct-24 29-Oct-24
A18158 Final Coat 4 28-Oct-24 01-Nov-24
GTS1.1.9.5.21.14 9th Floor Level 53 14-Sep-24 18-Nov-24
GTS1.1.9.5.21.14.1 Apartment Areas 46 14-Sep-24 09-Nov-24
A16608 Flooring (excluding toilets) 24 03-Oct-24 30-Oct-24
A16618 Putty and Primer 1st Coat Painting - Internal 18 26-Sep-24 17-Oct-24
A16628 Railing works 14 18-Sep-24 04-Oct-24
A16638 Toilet Water Proofing with Testing 16 26-Sep-24 15-Oct-24
A16648 Toilet and Kitchen plumbing 21 14-Sep-24 10-Oct-24
A16658 Pressure Testing 12 20-Sep-24 04-Oct-24
A16668 Toilet Flooring & Dado 18 01-Oct-24 22-Oct-24
A16678 Kitchen Platform & Tiles work 16 26-Sep-24 15-Oct-24
A16688 Windows Installation 12 19-Oct-24 02-Nov-24
A16698 Door Frame and Shutter Installation (with Ironmongery) 18 17-Oct-24 07-Nov-24
A16708 Wiring and Cabling 14 15-Oct-24 30-Oct-24
A16718 Installation of Switches and DBs 12 19-Oct-24 02-Nov-24
A16728 Installation of sanitary fixtures and CP Fittings 16 07-Oct-24 24-Oct-24
A16738 Final Painting 14 24-Oct-24 09-Nov-24
GTS1.1.9.5.21.14.2 Common Area Works 37 05-Oct-24 18-Nov-24
A18168 Corridor Fire Sprinkler Pipe Installation 14 05-Oct-24 21-Oct-24
A18178 Corridor Fire Sprinkler Pressure Testing 2 22-Oct-24 23-Oct-24
A18188 Corridor flooring and Lift cladding 20 16-Oct-24 08-Nov-24
A18198 Corridor Railing works 18 09-Oct-24 29-Oct-24
A18208 Putty and Primer Painting 7 28-Oct-24 05-Nov-24
A18218 1st coat of Painting 7 30-Oct-24 07-Nov-24
A18228 Wiring and Continutity test 7 02-Nov-24 09-Nov-24
A18238 Installation of swtiches and fixtures 5 11-Nov-24 15-Nov-24
A18248 Final Coat 4 14-Nov-24 18-Nov-24
GTS1.1.9.5.21.15 10th Floor Level 53 03-Oct-24 04-Dec-24
GTS1.1.9.5.21.15.1 Apartment Areas 46 03-Oct-24 26-Nov-24
A16748 Flooring (excluding toilets) 24 19-Oct-24 16-Nov-24
A16758 Putty and Primer 1st Coat Painting - Internal 18 14-Oct-24 04-Nov-24
A16768 Railing works 14 05-Oct-24 21-Oct-24
A16778 Toilet Water Proofing with Testing 16 14-Oct-24 01-Nov-24
A16788 Toilet and Kitchen plumbing 21 03-Oct-24 26-Oct-24
A16798 Pressure Testing 12 08-Oct-24 21-Oct-24
A16808 Toilet Flooring & Dado 18 18-Oct-24 08-Nov-24

Page 25 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A16818 Kitchen Platform & Tiles work 16 14-Oct-24 01-Nov-24


A16828 Windows Installation 12 06-Nov-24 19-Nov-24
A16838 Door Frame and Shutter Installation (with Ironmongery) 18 04-Nov-24 23-Nov-24
A16848 Wiring and Cabling 14 01-Nov-24 16-Nov-24
A16858 Installation of Switches and DBs 12 06-Nov-24 19-Nov-24
A16868 Installation of sanitary fixtures and CP Fittings 16 23-Oct-24 11-Nov-24
A16878 Final Painting 14 11-Nov-24 26-Nov-24
GTS1.1.9.5.21.15.2 Common Area Works 37 22-Oct-24 04-Dec-24
A18258 Corridor Fire Sprinkler Pipe Installation 14 22-Oct-24 07-Nov-24
A18268 Corridor Fire Sprinkler Pressure Testing 2 08-Nov-24 09-Nov-24
A18278 Corridor flooring and Lift cladding 20 02-Nov-24 25-Nov-24
A18288 Corridor Railing works 18 25-Oct-24 15-Nov-24
A18298 Putty and Primer Painting 7 14-Nov-24 21-Nov-24
A18308 1st coat of Painting 7 16-Nov-24 23-Nov-24
A18318 Wiring and Continutity test 7 19-Nov-24 26-Nov-24
A18328 Installation of swtiches and fixtures 5 27-Nov-24 02-Dec-24
A18338 Final Coat 4 30-Nov-24 04-Dec-24
GTS1.1.9.5.21.16 11th Floor Level 53 19-Oct-24 20-Dec-24
GTS1.1.9.5.21.16.1 Apartment Areas 46 19-Oct-24 12-Dec-24
A16888 Flooring (excluding toilets) 24 06-Nov-24 03-Dec-24
A16898 Putty and Primer 1st Coat Painting - Internal 18 30-Oct-24 20-Nov-24
A16908 Railing works 14 22-Oct-24 07-Nov-24
A16918 Toilet Water Proofing with Testing 16 30-Oct-24 18-Nov-24
A16928 Toilet and Kitchen plumbing 21 19-Oct-24 13-Nov-24
A16938 Pressure Testing 12 24-Oct-24 07-Nov-24
A16948 Toilet Flooring & Dado 18 05-Nov-24 25-Nov-24
A16958 Kitchen Platform & Tiles work 16 30-Oct-24 18-Nov-24
A16968 Windows Installation 12 22-Nov-24 05-Dec-24
A16978 Door Frame and Shutter Installation (with Ironmongery) 18 20-Nov-24 10-Dec-24
A16988 Wiring and Cabling 14 18-Nov-24 03-Dec-24
A16998 Installation of Switches and DBs 12 22-Nov-24 05-Dec-24
A17008 Installation of sanitary fixtures and CP Fittings 16 09-Nov-24 27-Nov-24
A17018 Final Painting 14 27-Nov-24 12-Dec-24
GTS1.1.9.5.21.16.2 Common Area Works 37 08-Nov-24 20-Dec-24
A18348 Corridor Fire Sprinkler Pipe Installation 14 08-Nov-24 23-Nov-24
A18358 Corridor Fire Sprinkler Pressure Testing 2 25-Nov-24 26-Nov-24
A18368 Corridor flooring and Lift cladding 20 19-Nov-24 11-Dec-24
A18378 Corridor Railing works 18 12-Nov-24 02-Dec-24
A18388 Putty and Primer Painting 7 30-Nov-24 07-Dec-24
A18398 1st coat of Painting 7 03-Dec-24 10-Dec-24
A18408 Wiring and Continutity test 7 05-Dec-24 12-Dec-24
A18418 Installation of swtiches and fixtures 5 13-Dec-24 18-Dec-24
A18428 Final Coat 4 17-Dec-24 20-Dec-24
GTS1.1.9.5.21.17 12th Floor Level 53 06-Nov-24 07-Jan-25
GTS1.1.9.5.21.17.1 Apartment Areas 46 06-Nov-24 30-Dec-24
A17028 Flooring (excluding toilets) 24 22-Nov-24 19-Dec-24
A17038 Putty and Primer 1st Coat Painting - Internal 18 16-Nov-24 06-Dec-24
A17048 Railing works 14 08-Nov-24 23-Nov-24
A17058 Toilet Water Proofing with Testing 16 16-Nov-24 04-Dec-24

Page 26 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A17068 Toilet and Kitchen plumbing 21 06-Nov-24 29-Nov-24


A17078 Pressure Testing 12 11-Nov-24 23-Nov-24
A17088 Toilet Flooring & Dado 18 21-Nov-24 11-Dec-24
A17098 Kitchen Platform & Tiles work 16 16-Nov-24 04-Dec-24
A17108 Windows Installation 12 09-Dec-24 21-Dec-24
A17118 Door Frame and Shutter Installation (with Ironmongery) 18 06-Dec-24 27-Dec-24
A17128 Wiring and Cabling 14 04-Dec-24 19-Dec-24
A17138 Installation of Switches and DBs 12 09-Dec-24 21-Dec-24
A17148 Installation of sanitary fixtures and CP Fittings 16 26-Nov-24 13-Dec-24
A17158 Final Painting 14 13-Dec-24 30-Dec-24
GTS1.1.9.5.21.17.2 Common Area Works 37 25-Nov-24 07-Jan-25
A18438 Corridor Fire Sprinkler Pipe Installation 14 25-Nov-24 10-Dec-24
A18448 Corridor Fire Sprinkler Pressure Testing 2 11-Dec-24 12-Dec-24
A18458 Corridor flooring and Lift cladding 20 05-Dec-24 28-Dec-24
A18468 Corridor Railing works 18 28-Nov-24 18-Dec-24
A18478 Putty and Primer Painting 7 17-Dec-24 24-Dec-24
A18488 1st coat of Painting 7 19-Dec-24 27-Dec-24
A18498 Wiring and Continutity test 7 21-Dec-24 30-Dec-24
A18508 Installation of swtiches and fixtures 5 31-Dec-24 04-Jan-25
A18518 Final Coat 4 03-Jan-25 07-Jan-25
GTS1.1.9.5.21.18 13th Floor Level 53 22-Nov-24 25-Jan-25
GTS1.1.9.5.21.18.1 Apartment Areas 46 22-Nov-24 17-Jan-25
A17168 Flooring (excluding toilets) 24 09-Dec-24 06-Jan-25
A17178 Putty and Primer 1st Coat Painting - Internal 18 03-Dec-24 23-Dec-24
A17188 Railing works 14 25-Nov-24 10-Dec-24
A17198 Toilet Water Proofing with Testing 16 03-Dec-24 20-Dec-24
A17208 Toilet and Kitchen plumbing 21 22-Nov-24 16-Dec-24
A17218 Pressure Testing 12 27-Nov-24 10-Dec-24
A17228 Toilet Flooring & Dado 18 07-Dec-24 28-Dec-24
A17238 Kitchen Platform & Tiles work 16 03-Dec-24 20-Dec-24
A17248 Windows Installation 12 26-Dec-24 08-Jan-25
A17258 Door Frame and Shutter Installation (with Ironmongery) 18 23-Dec-24 15-Jan-25
A17268 Wiring and Cabling 14 20-Dec-24 06-Jan-25
A17278 Installation of Switches and DBs 12 26-Dec-24 08-Jan-25
A17288 Installation of sanitary fixtures and CP Fittings 16 12-Dec-24 31-Dec-24
A17298 Final Painting 14 31-Dec-24 17-Jan-25
GTS1.1.9.5.21.18.2 Common Area Works 37 11-Dec-24 25-Jan-25
A18528 Corridor Fire Sprinkler Pipe Installation 14 11-Dec-24 27-Dec-24
A18538 Corridor Fire Sprinkler Pressure Testing 2 28-Dec-24 30-Dec-24
A18548 Corridor flooring and Lift cladding 20 21-Dec-24 16-Jan-25
A18558 Corridor Railing works 18 14-Dec-24 04-Jan-25
A18568 Putty and Primer Painting 7 03-Jan-25 10-Jan-25
A18578 1st coat of Painting 7 06-Jan-25 15-Jan-25
A18588 Wiring and Continutity test 7 08-Jan-25 17-Jan-25
A18598 Installation of swtiches and fixtures 5 18-Jan-25 23-Jan-25
A18608 Final Coat 4 22-Jan-25 25-Jan-25
GTS1.1.9.5.21.19 Terrace Floor Level 53 09-Dec-24 11-Feb-25
GTS1.1.9.5.21.19.1 Apartment Areas 46 09-Dec-24 03-Feb-25
A17308 Flooring (excluding toilets) 24 26-Dec-24 24-Jan-25

Page 27 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A17318 Putty and Primer 1st Coat Painting - Internal 18 19-Dec-24 09-Jan-25
A17328 Railing works 14 11-Dec-24 27-Dec-24
A17338 Toilet Water Proofing with Testing 16 19-Dec-24 07-Jan-25
A17348 Toilet and Kitchen plumbing 21 09-Dec-24 02-Jan-25
A17358 Pressure Testing 12 13-Dec-24 27-Dec-24
A17368 Toilet Flooring & Dado 18 24-Dec-24 16-Jan-25
A17378 Kitchen Platform & Tiles work 16 19-Dec-24 07-Jan-25
A17388 Windows Installation 12 11-Jan-25 27-Jan-25
A17398 Door Frame and Shutter Installation (with Ironmongery) 18 09-Jan-25 31-Jan-25
A17408 Wiring and Cabling 14 07-Jan-25 24-Jan-25
A17418 Installation of Switches and DBs 12 11-Jan-25 27-Jan-25
A17428 Installation of sanitary fixtures and CP Fittings 16 30-Dec-24 18-Jan-25
A17438 Final Painting 14 18-Jan-25 03-Feb-25
GTS1.1.9.5.21.19.2 Common Area Works 37 28-Dec-24 11-Feb-25
A18618 Corridor Fire Sprinkler Pipe Installation 14 28-Dec-24 15-Jan-25
A18628 Corridor Fire Sprinkler Pressure Testing 2 16-Jan-25 17-Jan-25
A18638 Corridor flooring and Lift cladding 20 08-Jan-25 01-Feb-25
A18648 Corridor Railing works 18 01-Jan-25 23-Jan-25
A18658 Putty and Primer Painting 7 22-Jan-25 29-Jan-25
A18668 1st coat of Painting 7 24-Jan-25 31-Jan-25
A18678 Wiring and Continutity test 7 27-Jan-25 03-Feb-25
A18688 Installation of swtiches and fixtures 5 04-Feb-25 08-Feb-25
A19638 Final Coat 4 07-Feb-25 11-Feb-25
GTS1.1.9.5.21.20 Mumty Level 27 27-Dec-24 29-Jan-25
A14698 Parapet Wall Works 10 27-Dec-24 07-Jan-25
A14708 Water Proofin g 7 08-Jan-25 17-Jan-25
A14718 Flooring 10 18-Jan-25 29-Jan-25
GTS1.1.9.5.21.21 Staircases Flooring/ Railing / Painting 217 17-May-24 03-Feb-25
A14728 Mumty to 10th Floor 16 16-Jan-25 03-Feb-25
A14738 10th to 5th Floor 21 08-Nov-24 02-Dec-24
A14748 5th to Ground Floor 21 13-Aug-24 06-Sep-24
A14758 Ground Floor to B1 Level 21 17-May-24 10-Jun-24
GTS1.1.9.5.21.22 Lift / Elevator Works 51 09-Dec-24 08-Feb-25
A14768 Supply of Lifts 20 09-Dec-24 01-Jan-25
A14778 Installation of Lifts 28 02-Jan-25 05-Feb-25
A14788 Testing & Commissioning of Lifts 3 06-Feb-25 08-Feb-25
GTS1.1.9.5.21.23 Final Painting 28 18-Jan-25 19-Feb-25
A14798 Common Area Final Painting 28 18-Jan-25 19-Feb-25
GTS1.1.9.26 External Texture Painting 48 07-Dec-24 04-Feb-25
A14808 Elevation One 12 07-Dec-24 20-Dec-24
A14818 Elevation Two 12 21-Dec-24 04-Jan-25
A14828 Elevation Three 12 06-Jan-25 21-Jan-25
A14838 Elevation Four 12 22-Jan-25 04-Feb-25
GTS1.1.9.6 Building Shaft Works 35 03-Jan-25 14-Feb-25
GTS1.1.9.6.3 Finishes 10 01-Feb-25 12-Feb-25
A14848 Painting (White Wash) 10 01-Feb-25 12-Feb-25
GTS1.1.9.6.1 Services 35 03-Jan-25 14-Feb-25
A14858 Plumbing Works 21 18-Jan-25 11-Feb-25
A14868 Electrical Works 21 08-Jan-25 03-Feb-25

Page 28 of 29
© PLANNER
VISHNU RAMAKRISHNAN
Golden Tulip Residential Classic Schedule Layout 01-Nov-23 11:23
Activity ID Activity Name Planned Planned Start Planned
Duration Finish

A14878 Fire Protection System 35 03-Jan-25 14-Feb-25


GTS1.1.9.7 Cleaning & Handing over 10 20-Feb-25 03-Mar-25
A15508 Cleaning & Handing over of the Tower -5 10 20-Feb-25 03-Mar-25

Page 29 of 29