Section 2
Section 2
Designer
PSC o r PSSC
Contractor
Supervisor
PSC o r PSSC
Subcontractor Supplier
ECS o r ECSS SC o r SSC
Typical design & build arrangement
Project Manager Adjudicator
Client
PSC o r PSSC DRSC
Supervisor Contractor
PSC o r PSSC
• impose only low risks o n both the Client and the Contractor
or
Dispute Avoidance
k Board 1
fl ■ fl
fl I fl
Adjudicator
fl Project Manager fl
fl or fl
fl Dispute Avoidance*r
7
1 L Board
The ECC structure
The ECC structure is ALWAYS have the Choose ONE main Option clause (A
modular in form with core clauses to F) which decides the mechanism
5 modules, normally for payment and t h e relevant
chosen by the Client schedule of cost components
3 Time
4 Quality management
5 Payment
6 Compensation events
7 Title
9 Termination
Main Option Clauses
Management contract
Activity Schedule (Option A)
Lump sum contract
---------1 ------------- —
Contractor prices
Project well defined
Standard method o f items in Bill of
a t tender b u t
measurement used Quantities at
change likely
tender stage
Contractor generally Most work Contractor tenders Contractor Contractor has limited
organises work only carried out by pr/ces (lump sum) gets paid financial risk, except
Subcontractors and Fee forecast for adequacy of
Defined Cost • Fee and
+ Fee • prices for work it
does itself
Financial risk of main Options
lient
Depends o n
pain/gain
mechanism
Contractor
Dispute resolution clauses
X3 - Multiple currencies
Secondary Option clauses
Click each number to reveal
X4 - Ultimate holding
company guarantee
Secondary Option clauses
Click each number to reveal
X5 - Sectional Completion
Secondary Option clauses
Click each number to reveal
X7 - Delay damages
Secondary Option clauses
Click each number to reveal
X8 - Undertakings to the
Client or Others
Secondary Option clauses
Click each number to reveal
X9 - Transfer of rights
Secondary Option clauses
Click each number to reveal
X16 - Retention
Secondary Option clauses
Click each number to reveal
In Scope
• if Option X4 is chosen - ultimate holding company guarantee
• if Option X8 is chosen - undertakings to the Client or Others
• if Option X1 3 is used - performance bond