Section 3
Section 3
PROCURE. M A N A G E . DELIVER.
01 B 02 03 B 04 05 B 06 07 B 08 B 09
© ©@© © © © © ©
General
Provisions
Contractor's
main
Time Quality
management
Payment Compensation
events
Title Liabilities
and
Termination
and
responsibilities insurance dispute
resolution
3.1 General provisions
Actions
Communications
Early warning
Actions
10
(1) Accepted
Programme
16
Identified and defined terms
• Identified terms in Contract Data are in italics
10
(2) Completion
(certainty of
16 18 19 requirements)
Identified and defined terms
• Identified terms in Contract Data are in italics
(3) Completion
Date
11 14 16 17 18 19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
9 10
(5) Corrupt Act
11 14 16 17 18 19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
10
(6) Defect (two
types)
11 14 16 17 18 19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
10
(9) Equipment
11 14 16 17 18 19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
16 18 20
Identified and defined terms
• Identified terms in Contract Data are in italics
(16) Scope
17 18 19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
(17) Site
18 19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
(18) Site
Information
19 20
Identified and defined terms
• Identified terms in Contract Data are in italics
(19)
Subcontractor
20
Identified and defined terms
• Identified terms in Contract Data are in italics
(20) Working
Areas
Communications
Must be in a form that Use of a "communication Replies within period for Notifications and
can be read, copied and system" (13.2) reply or as in contract (13.3) certificates to
recorded (13.1) be communicated
• see simple examples in separately (13.7)
delegate packs
Project Manager and Supervisor
Pro
J i ec1: ana
9 er (?M) manages ECC for Client
PM \s the only person who may give an instruction changing the Scope or Key
Date (14.3)
Early warning
Contractor and PM have a duty to notify the other as soon as they are aware of a matter
which could
• increase the total of the Prices
• delay Completion
• delay meeting a Key Date or
• impair the performance of the works in use (1 5. 1) or
• adversely affect the creation or use of the Information Model (X1 0.3)
PM or Contractor may give an early warning by notifying the other of any other matter
which could increase Contractor's total cost
PM revises Early Warning Register to record decisions and issues within one
week (1 5.4)
Contractor may propose If the PM accepts the For Option A and B, the
changes to Client's Scope proposal, the PM issues an benefit is shared by the value
which reduces the total of instruction changing the engineering percentage
the Prices (16.1) Scope (16.2) (63.12) if:
• the change is to Client's
Scope and
• the total Defined Cost is
reduced by the
compensation event
3.2 Con tra ctor's main responsibilities
2 Contractor's design
3 People
5 Subcontracting
The Contractor's main responsibilities
• Contractor designs the parts of • Contractor owns its • Contractor may have
the works which the Scope rights (22.1) unless limited design liability
states it is to design Option X9 adopted (Option X1 5)
The Contractor
•employs each key person stated in Contract Data or
• employs replacement person accepted by PM (24.1)
If subcontracts, Contractor Con tractor submits for all Options Contractor additionally
still responsible for • name of each proposed submits for Options C t o F
Providing the Works (26.1) Subcontractor t o PM for •proposed pricing
acceptance (26.2) information (26.4)
•proposed subcontract documents
except pricing information unless
•NEC contract is proposed,
unamended except for
changes in main contract, or
• PM agrees no submission
required (26.3)
3.3 Time
Programme
Contractor does work so that condition stated for each Key Date is
met by Key Date (30.3)
Take over (35) is Contractor is Client takes over Client may take over PM certifies take
not the same as responsible for within 2 weeks of part of the works over of part of
Completion works until Completion unless before Completion - the works within
take over Client has stated in will be a one week
Contract Data it will compensation event
not take over "early", if before
i.e. before Completion Completion Date
Date (35.1) (60.1(15))
Programme
How frequent?
• on instruction by PM
• w h e n Contractor chooses
• at interval stated in Contract Data (32.2)
Stopping and starting work
Defects
Quality management system
defect
Defects notified correction
period
before Delivery defect
correction
defect period
after Delivery access defect
correction
period period
before defects date
Latest issue of
Defects Certificate
Defects
continues until
Defects Certificate
w i t h i n 4 weeks
assessment assessment
interval interval
Option Option
F
Option F 11.2(27)
BRk As C to E plus
• payment to Subcontractor for work which Contract Data states
ContractorwiW do itself or
• Contractor's management
Defined Cost
interest 51 .2
Y2.5 suspension of
performance of all or
part of works
Note that for final assessment, the Contractor may issue the assessment
Final Assessment
PM assesses final amount due and certifies final payment n o later than
• four weeks after Defects Certificate or
• thirteen weeks after termination certificate (53.1)
anaa
DDDF 8
Schedule of Cost Components
• Components
Definition
2 Process
3 Method of assessment
COMPB
Where are compensation events stated?
TI®N
21 in clause 60.1
3 in main Options B and D, in clauses 60.4 to 60.6
also in secondary Options X2, X1 2.3(6) & (7), X1 4.2, X1 5.2 and Y2.5
13
5 12 13
13
12 13
Both PM and Contractor can make sure that process and time
scales are adhered to
When Contractor notifies, PM replies within one week with "yes" or " n o "
Dividing date
• if arising from instruction or notification, certificate, or changed decision,
then date of communication by PM or Supervisor
• otherwise date of notification of compensation event (63.1)
If ?/Wand Contractor both agree, rates and lump sums may be used as a
basis for assessment (63.2)
Prices are not reduced for a compensation event that reduces Defined
Cost unless specifically stated (63.3)
Assessment
• length of time that, due to compensation event, planned Completion is later than
planned Completion shown on Accepted Programme current at dividing date (63.5)
• length of time that, due to compensation event, planned date when Condition will be
met is later than date shown on Accepted Programme current at dividing date (63.5)
Decision by PM
X
PM replies within 2 weeks The reply is one of following If reply is rejection, the PM
of receipt of quotation (62.3) must
(62.3)) • accept quotation • ask Con tra ctor to provide
• reject quotation, because it revised quotation (with
has not been prepared in reasons) or
accordance with contract • t e l l Contractor it will make
own assessment
If PM fails within allowed If there was more than If failure continues for a
time to reply to quotation one quotation, notification further 2 weeks after
Contractor may notify identifies the preferred reminder, the Contractor's
reminder (62.6) quotation quotation is treated as having
been accepted (62.6)
PM'S assessment
PM makes assessment if
PM makes own assessment within the time allowed for Con tractor (64.3)
PM's assessment
PM assesses the programme for the remaining work in assessment of compensation event if
If PM fails within allowed If there was more than If failure continues for a
time to assess quotation one original quotation further 2 weeks after
Contractor may notify from Contractor, reminder, the Contractor's
reminder (64.4) notification identifies the original quotation is
preferred quotation treated as having been
accepted (64.4)
Implementation
Once implemented
• the Prices and Completion Date and Key Dates are changed accordingly (66.2)
• the assessment is not revised (even if wrong) except as permitted by the contract (66.3)
• only the Adjudicator or tribunal can change the assessment if one Party still disagrees
(W1/W2/W3). The Dispute Avoidance Board cannot change the assessment
C notifies CE
IS THERE A CE? PM notifies CE 8 Week time bar - for
Deemed acceptance after two certain CEs (61 .3)
weeks from Con tractor advising
<1 week
no decision received (61 .4)
PM states if any assumptions to Instruct quote Should early warning have been given?
be used (61.6) (61.2/4) (61.5/63.7)
PM can request alternative quotes INSTRUCT QUOTATION
(62.1)
PM DECISION
Deemed acceptance after two weeks PM reply (62.3)
from Con tractor advising no decision accept/reject/self-assess <2 Weeks
received (62.6)
IMPLEMENTATION
PM If not accepted
• accepts quotation and • notification is a compensation
notifies instruction event, so Contractor gets paid
• instructs a revised for quotation (60.1(20))
quotation or • PM may still issue instruction and
• notifies quotation not normal compensation event
accepted process is followed (65.3)
3.7 Title
Title
2 Use of material
Title and use of material
Whatever title Contractor has to Plant and Materials passes to Client
• when brought into Working Areas (70.2) or
• if they are outside the Working Areas, when they are marked by Supervisor (70.1)
82 Recovery of costs
• each Party pays for events for which they are liable
• net contribution
84 Insurance policies
0
86 Insurance by Client
Termination
2 Resolving disputes
Termination
F di*
L _______
Termination is of Contractor's obligation to Provide the kVor s(90.1)
• 3 options, W 1, W2 and W3