PPM notes U 1-5-24
PPM notes U 1-5-24
Concept Of Management
The term management has different senses of use. Sometimes it is used in the sense of
an organisation in which different class of people work together to provide qualitative
and economical product by the use of human beings and other resources like machine,
money and material.
Or sometimes it may be defined as the process consisting of planning, organising,
activiting and controlling the performance to determine and accomplish the objective
by the use of men, machines, materials and money.
Planning
Organising
Staffing.
Directing
Controlling
Co-ordinating
Communicating.
Planning
Staffing
Staffing is filling the position in the organisation structure for defining recruitments.
It is a very important responsibility to select right person for right jobs in a
construction organisation.
Staffing is not only about the recruitment but also their training and developing
activities.
Directing
A manager needs to do more than just plan, organize, and staff her team to achieve a
goal.
She must also lead.
Leading involves motivating, communicating, guiding, and encouraging.
It requires the manager to coach, assist, and problem solve with employees.
Controlling
After the other elements are in place, a manager's job is not finished.
He needs to continuously check results against goals and take any corrective actions
necessary to make sure that his area's plans remain on track.
It is an important action for ensuring effective and efficient working.
It reviews the work plan to check and rectify the deviation.
Co-ordinating
It means developing harmony between employees and group of employees for smooth
and efficient functioning of construction work.
The work is divided into different departments in the large organisation. So there is a
great importance for good coordination.
Communicating
It is a process of transmitting receiving and understanding the ideas by others for the
purpose of effective desired results.
There are various methods of communication like verbal, written orders, reports etc.
Ineffective communication leads to confusion and misunderstanding etc.
Contractor
The contractor executes various types of works and also makes necessary
arrangements for labour, machinery, materials, in order to complete the project in the
limited scheduled time.
In some projects, the contractor may appoint sub-contractor.
There is a rate or bid between Contractor & owner before starting any project.
Material
Sufficient quantity of materials required for the completion of any project and should
also be available at the site.
Materials required for project are estimated before starting the project.
For example- bricks , cement ,stones ,timber ,water supply, electrical fitting etc.
Machine
Different types of machineries and equipments are required for any construction
work.
Although the cost of machinery is high but it works continuously under any adverse
situation & it also reduces the high requirement of manpower.
For example: Mixers, tractors, pumps, cranes, generators etc.
Manpower
Construction Scheduling
Bar Chart
WBS aids in the identification of objectives and allows the planner to see the total
picture of the project.
WBS is developed by considering the end objective and breaking it into smaller
manageable units on the basis of size, duration and responsibility.
WORK BREAKDOWN
STRUCTURE
1. Pre-tender stage
1. Pre-tender stage
The pre tender planning is carried out by the contractor after the receipt of tender
notice and before submitting the tender paper.
In this stage, the contractor plans his best method of construction for the future
contract & also makes plans & programmes for carrying out the work.
At this stage, contractor prepares himself for completing the work in the stipulated
time.
This is an important stage for a contractor to see whether the contract is profitable or
not.
The first part of pre-tender planning is to visit to the site before a contract is
undertaken.
The pre-tender planning report by visiting to the site of construction works represents
total information about the site such as geography of the area, local weather records &
availability of resources.
Steps:
Post-tender Stage
Steps:
The selection of most suitable & economical method out of all the alternative methods
considered at pre-tender stage should be carefully determined for execution of the
work.
The quantity of materials required at each stage of the work, locating sources of their
supplies, their comparative cost from different sources should be worked out properly.
Inter-relationship of various items of work should be studied and the proper sequence
of operation is finalized.
The requirement of construction labour, supervisory and managerial staffs should be
finalized and their selection & recruitment should be arranged.
Total number of requirement of machinery & equipments at various stages of work
should be worked out & arranged.
Repairing & maintenance of machinery & equipment should be properly arranged .
Accommodation for labour & staff along with the facilities required for them ,
temporary camp, office etc. should be planned & arranged properly.
The work programme of each work should be decided & its starting & completing
date also be finalized.
A good communication system between the members of construction team should be
established for the smooth running of project work.
In other words scheduling is the time table for executing each and every activity with
its fixed starting and finishing date.
Preparation of construction schedule
At first the whole project is divided into a small number of operations.
Then the inter-dependence among or between the operations are carefully studied and
their sequence is decided.
The quantity of work is to be determined which is to be done in each operation.
The total time to complete each operation & total project is determined.
Classification of Scheduling
Schedules can be classified into various groups such as;
• Material Schedule
• Labour Schedule
• Equipment Schedule
• Financial Schedule
Material Schedule
This type of schedule is prepared for moving and storing of material in advance
before starting of construction schedule acts as a guide for preparing materials
schedule.
The materials should be delivered at site at least one week before its use.
If the materials stored at site long before its use, it is likely to deteriorate in quality.
For example cement made its strength by 50% if stored for 6 months and steel may be
attacked by corrosion due to long storage at site.
Labour Schedule
• The labour schedule is prepared for deciding the actual number of skilled and
unskilled labour which is required for the construction work.
• With the help of this schedule required labour can be arranged in time.
• It helps in reducing labour cost.
Equipment Schedule
This type of schedule is prepared to decide the type and quantity of equipments as
also on which date the equipment will be needed. So that they can be arranged when
requirement.
The aim of this schedule is to derive maximum advantage of the equipment when it is
required and remove it from the site when the job is over.
Financial Schedule
Financial schedule is prepared to estimate the amount of money that owner or
contractor has to spend as finance for the project work.
In maximum construction project the owner will pay a stated percentage of the value
to the contractor for the completion of work in each month. it is about 90% of the cost
at the completion of the work & rest 10% is retained.
• In a bar chart, there are two co-ordinate axes, i.e. x-axis (Horizontal) & y-axis
(Vertical).
• Along x-axis, time required for the completion of work is represented & along y-axis,
the activities are represented.
• In a bar chart, the activities are represented by thick crossed horizontal lines.
• Time required for completion of the activity may be represented in days or weeks.
• This chart is known as bar chart because the activities are represented by number of
parallel bars in it.
• The length of each bar indicate the duration of time required to complete a particular
activity.
• Also bar chart represents the actual progress of the work by thick dark bars.
• A daily record should be maintained by the supervisor about the progress of the work
and handed over it to the sectional officer who in turn will handover it to chief-
supervisor or engineer for finalizing it, so that the progress of the work can be
completed within a particular period of time.
• So a bar chart gives a clearer picture of the progress of work without study any
detailed report.
• We can also check the accuracy of work and can compare the actual progress of work
with the schedule.
Steps in preparing a bar chart
• In preparing a construction schedule by bar chart, at first the project is sub divided
into various objectives.
• Determine the quantity of work & requirement of time to complete the work.
b) Easy to understand.
c) Difficult to setup and maintain a large project because it is essentially a manual graphical
procedure.
b) Bar chart can only be applicable for small projects but not suitable for large projects.
c) The bar chart doesn’t show clearly the inter-dependence among the various activities.
d) The bar chart doesn’t show the actual progress of the work as it only represents the
estimate time. So the actual progress of the work can not be monitored.
e) The bar chart gives no idea about the maximum progress necessary for it’s completion. It
gives the information only about the rate of progress.
f)The bar chart does not help the work of controlling ,monitoring and updating the project.
These limitations of bar chart may be discussed under the following heads.
EVENT
• An event is either start or completion of an activity.
• It doesn’t require time or resources.
• It is represented by node usually circle.
ACTIVITY
DUMMY ACTIVITY
• This activity neither uses any resource nor any time for its completion but is required
in the logical sequence of network is called a dummy activity.
• It may be represented by a dotted arrow or solid arrow with zero time duration.
Early Start Time(EST):-The earliest possible time at which an activity may start is
called its early start time.
Early Finish Time(EFT):-It is the sum of EST of an activity andtime required for its
completion i.e. EFT= EST+t
Late Finish Time(LFT):- The sum of LFT of an activity and the time
required for its completion i.e. LFT= LST+t.
Total Float:-The difference between the maximum time allowed for an activity and
estimated duration is called total float. It is the duration of time by which an activity can be
start late , without disturbing the total project schedule.
Free Float:- The duration of time by which the completion of time of an activity can be
delayed without affecting the start of the succeeding activity.
Critical Activities:- The activities with zero float are called critical
activities, which are required to be completed onschedule.
Critical Path:- The path of network joining the critical events along
with no float is called critical path of network.
Programme Evaluation and Review Technique (PERT) :-
• It is a probabilistic model.
Example:-
• Launching of a satellite.
1. Optimistic time:-
• The minimum possible time which an activity requires for its completion
under ideal condition is called optimistic time.
• It does not include any type of delay at any stage.
• It is denoted by “t o”.
2. Pessimistic time:-
• The maximum time that may be taken by an activity if there is delay at every
stage except natural calamities like earthquake, flood etc. is called pessimistic
time.
• It is denoted by “t p”.
3. Most likely time:-
• The most realistic estimate of time which an activity may take for its
completion under normal condition is called most likely time.
• It is denoted by “t m”.
4. Expected time:-
It is taken as the weighted average of the time estimates i.e optimistic time, pessimistic time and
most likely time.
• It is denoted by “t e”.
te =to+4tm+tp
6
5. Earliest expected time(TE)
The earliest expected completion time of event is equal to the sum of the
expected times of the preceding activities.
6. Latest allowable time(TL)
The latest possible time an event can take without delaying the final
completion date of the project is called latest allowable time.
7. Slack time
Slack=TL-TE
8. Length of the Project
The sum of the expected times of all the activities along the critical path of the
network of a project.
9. Variance of an activity
Vt= (tp-to/6)2
10. Standard deviation of an activity
St= (tp-to/6)
1. Its full form is Project Evaluation and Its full form is Critical Path Method.
Review Technique.