Generators Systems
Generators Systems
Mechanical generators as a source of power are common in the humanitarian sector apart
from the public grid, mainly because they are usually available and can be acquired and
installed relatively quickly almost everywhere. Generators are built on a well-known technology
and it may not be hard to find a good technician to install one in many contexts. However,
operating a generator is expensive, requires frequent and complex maintenance as well as a
constant fuel supply. Generators can also cause many problems, such as noise, vibration,
pollution, and more.
As a main power supply when there is no public electricity grid available or when the grid
has a very poor reliability.
As a back-up power supply when investing in a more efficient power supply is not
possible: emergency, short-term installation, etc.
As a back-up power supply for buildings with very large energy needs (mainly buildings
equipped with air-conditioning or electric heaters).
As a back-up power supply for installations that holds cold chain capacities.
In any other case, a more complete evaluation should be performed to assess alternatives to
the generator. When considering a generator as a main or back-up power, do not
underestimate the time required for handling the equipment nor to include in the budget the
preparation of its installations.
Characteristics
The following are the main characteristics to consider when selecting the appropriate
equipment to cover needs.
Generator Power
The first thing to evaluate when looking for a generator is its size - how much power can it
generate?
Prime
Rated for This power is available during unlimited hours of usage with variable
Rated
a variable load factor. An overload of 10% is possible during maximum 1 hour
Power
load every 12 hours but not exceeding 25 hours per year.
(PRP)
Continuous
Rated for
Operation This power is available during unlimited hours of usage with a fixed
a constant
Power load factor. No overload allowed.
load
(COP)
Emergency
Rated for This power is available only during 25 hours per year with variable
Stand By
a variable load factor. 80% of this power is available during 200 hours per year.
Power
load No overload allowed.
(ESP)
Load Types
Most of the time, only PRP is relevant when purchasing a generator.When acquiring a
generator, check if the power of the generator is indicated without reference to a standardised
rating method. If no rating model is indicated, consult with the manufacturer or obtain
documentation from the seller.
Power can be rated either in watt (W), kilowatt (kW), volt-amps (VA) or kilo-volt-amps (kVA). For
the sake of clarity, 1kW = 1000W and 1kVA = 1000VA
A rating in watts indicates a real power (P); a rating in volt-amperes indicates an apparent
power (S). Only real power has to be considered when planning consumption. Real power is the
power actually consumed or utilised in an AC Circuit, and therefore it is the way power needs
and energy consumption is calculated in a diagnostic exercise.
If only the apparent power (in kVA) is indicated, you can evaluate the real power with the
following general formula:
P(W) = S(VA) × 0.8
0.8 of apparent power is the assumed real power factor. This may vary from one machine to
another, but 0.8 is a reliable average value.
When selecting a generator, it will at the very least need to accommodate the power calculated
in the diagnostic exercise. However take into account the following precautions:
Do not confuse kW and kVA: The installation power needs are commonly calculated in kW
while the power of the generator is usually rated in kVA. In that case, divide by 0.8 (or add 20%)
to convert the power of the installation from kW to kVA.
If the assumed energy needs of an installation are 6,380W, how do we size the
generator and what KVA must it be?
The power of the generator must be at least 6.4kW PRP while. To determine the
kVA:
Example:
Take lower operating rates (derates) into account: The power a generator can provide
decreases with increases in altitude and temperature. The following chart indicates
correlations in environmental factors to derates:
Note that temperature inside the generator room can be far higher than ambient temperature.
A generator has an apparent power of 10kVA, and will operate at 1,000m elevation,
and in a generator room with an average temperature of 45°C. What will the
anticipated power output be:
Elevation adjustment:
1,500 RPM: intended for intensive usage (running more than 6 hours) capable to reach
high power.
3,000 RPM: intended for short term usage, with better power/volume and power/weight
ratios but higher hourly consumption of fuel.
Noise Level
An engine is very noisy while running. Noise level is an important consideration while looking
for a generator, as it is usually running during working or resting hours. A continuous noise
even at very low level can become exhausting over long period of time.
Noise levels are indicated in dB(A) LWA. For comparison purpose here are some common
sounds.
An average office should be around 70dB(A), while noise level in a bedroom at night should be
lower than 50dB(A).
77dB @ 4m = 71dB @ 8m
Example:
The noise level in the building will be approximately 65 dB(A), maybe lower
depending on the acoustic isolation of the generator room and the office. This is an
acceptable level for an office but not for a guest-house at night.
In general, is recommended not to use generators that produce a noise level higher than 97
dB(A) LWA. If the generator will be used at night, it is recommended to use an acoustic canopy,
or build a sound wall to dampen some of the noise pollution.
Tank Capacity
A generator cannot be refuelled while it is running, thus the tank capacity is one of the main
factors determining autonomy. A conservative estimation of a 1500 RPM generator hourly
consumption is 0.15 L x rated power. A fuel tank must be chosen accordingly.
An 8kVA PRP generator powers an office without refuelling it during working day
(10 hours). Knowing these numbers, what is the suggested tank size?
0.15 × 8 = 1.2L / hr
Example:
1.2 × 10 = 12L
It is not recommended to run a tank below 1/5 of its capacity; low tank volumes can draw
particles and debris settled on the bottom of the tank into the fuel line, and is potentially
dangerous for the engine.
Fuel
Generators – like vehicles - can use either diesel or gasoline, and come with advantages and
disadvantages. Diesel generators are more expensive, however diesel is often cheaper than
gasoline and diesel generators have better power/volume and power/weight ratios than
gasoline generators.
The choice of fuel must be determined according to the local price and availability of both type
of fuel. One point to consider is what type of fuel vehicles in the organisations use, using the
same fuel for both generators and vehicles can reduce complexities of keeping multiple types
of fuel in stock. Safety may also be a concern for very large stock quantities of fuel - diesel fuel
also has a significantly higher flash point than gasoline, meaning it will ignite in the open air
only above 52°C while gasoline can ignite in below freezing temperatures.
Security
Generators must be equipped with a residual current circuit breaker, so that power surges and
short circuits can trip the breaker locally, making it easier to reset and preventing damage
from occurring further down the circuit. Additionally, generators usually have a manual
breaker/transfer switch to control the connection of electricity to the installed circuit of the
office or compound.
Generators should also have an emergency stop button, in case of fire, catastrophic
mechanical failures, or other issues. An emergency stop button should be clearly marked.
Generators with acoustic canopy should be equipped with an emergency stop push button
outside the canopy.
Generator Set Up
Generator Room/Storage Area
Some generators can be extremely heavy and bulky, and often their location around an office
or compound will depend on the ability for mechanical equipment or vehicles to load/offload
the full-sized generator.
Generators should be installed on a flat, even surface. Unlike vehicles, generators are not
designed to operate on slants or while tilted. A slight slant or grade may cause generators to
move slightly over time with vibration or exposure to the elements, which can damage
structures and equipment, or make servicing equipment difficult. If a heavy generator moves
in an enclosed space with a built-up structure around it, moving by hand may be impossible.
It is good practice to install some kind of shock absorber to reduce generator vibrations, such
as timber or rubber pieces. This helps reduce vibration by slightly raising the equipment, and
also help control heat while making the unit easier to inspect and identify leaks.
Depending on the layout of the required operating space, generators may be installed in stand-
alone rooms, be housed in some sort of open-sided generator shed, or may be exposed to air.
Ideally, generators will have at least a roof or other form of covering above them to protect
from rain, snow or excessive direct sunlight, all of which can impact the operation of a
generator. Due the size and weight of generators, the shed or room may have to be built after
the generator has been delivered, offloaded, and installed.
Passive
Air Vent
Exhaust Alternate
Air Intake
Hot Air
Output Fresh Air
Intake
The room or storage area must cover several purposes; isolate the generator to decrease the
noise and environmental impact on its surroundings, and preventing non-authorised access
from staff, visitors, animals, or others. Even if a generator is relatively exposed, such as a
covered awning with no walls, it is still advisable to have some sort of access control to the
physical generator. The generator’s storage areas may require additional physical built up
walls on one or more side of the generator to block noise and prevailing winds.
Although construction materials can vary, the orientation must be planned carefully, taking
advantage of the wind currents and minimising the noise and heat disturbances. A generator
space should always be well ventilated, including the use of soffit vents or entirely exposed
walls. If a generator is in a tightly enclosed space, specially made air outlet ducts are required.
Ensure all outlets don’t discharge into areas where humans and animals work or access
frequently. If no other option is available than to ventilate into areas where humans and
animals access, then all discharge points should be at least two meters from said spaces and
be well marked.
Wherever possible, position fuel or other dangerous goods so that the prevailing wind do not
enter into the radiator/exhaust outlet. If this is not possible, install a wind barrier.
Running a Generator
While there are general rules and best practices when running a generator, the best source of
information is always the user manual for the accompanying machine, which provides full
details about its usage and maintenance. Guidance coming from the manufacturer must
always be followed.
Running hours.
Refuelling.
Maintenance performed.
A simple but complete logbook should be used. A logbook should be kept near the generator,
and all persons managing the generator should be trained and sensitised in its correct use.
Even though PRP generator types are rated for “unlimited” usage, this does not mean
generators can run for an unlimited continuous time. Generators are still machines, which
suffer from degradation and can overheat or break down. The continuous operation of
generators may vary from machine to machine, but generally speaking the generators that
humanitarian agencies obtain in field contexts are not designed to operate for more than 8 to
12 hours of continuous use at one single time. Running a generator for longer than an 8 to 12
hour period can dramatically shorten the life of a generator and lead to a higher frequency of
break downs.
Generators usually must be switched off for a cool down period, which is why many agencies
will install two primary generators in a compound or office. The two generators are generally
installed near each other if not in the same storage room, and are both connected to the main
electrical circuit of the facility. If two generators are installed in tandem, there should be a
large external transfer switch to route power coming from either one or the other generator at
one time. A no point should both generators be able to supply an electrical current to the same
closed circuit at the same time – this could cause catastrophic damage to facilities and
equipment.
The use of two generators can be planned according to needs – either both generators should
have identical power supplying capability, or the secondary generator is used for hours when
load requirements are less. Solar power and other backup power supplies can also be
connected to the external transfer switch. Usually, the act of switching between generators
includes starting the incoming generator while the outgoing is still running. This will allow the
incoming generator to warm up. It will also allow the main transfer switch to move between
generators while power is being supplied, to minimise disruption to offices or living quarters.
Generators above a certain size and made for medium to long term usage generally have an
internal switch used to connect or disconnect the unit from the main installed circuit of the
office or compound. If the generator switch is set so that the generator is not connected, the
motor will still run and the alternator will still produce electricity, however the main circuit will
not be able to receive an electrical current.
Generators must never be started or stopped while connected to the installation, also
called “loaded”
When a generator turns on, there may be spikes or stalls to the power produced, due to air in
the fuel lines, debris or other normal parts of the start-up process. These surges in power can
exceed the load rating of any given installation and can damage equipment if not properly
protected. It is a good practice to have a poster or leaflet in the language of the persons
operating the generator explaining the process to start and stop the equipment that includes
photos of the main parts to touch and the actions to be taken.
1. Make sure that the generator circuit breaker is open (if the generator does not have a
circuit breaker: make sure that the installation main breaker is open).
2. Check the oil level.
3. Check the fuel level.
4. Check the water level (for water-cooled generators only).
5. Make sure that there is no leakage (no oil or fuel under the generator).
6. Start the generator.
7. Wait 2 minutes.
8. Close the circuit to the main circuit of the office or compound.
9. Record time of start on the associated logbook.
A generator must be regularly maintained to ensure it provides quality power throughout its
life. Routine maintenance is relatively straight forward - there are general guidelines on what
and when services are needed to prevent failures or enhance the equipment functioning.
While generator maintenance best practice is following the manufacturer's maintenance and
schedule, the following controls and operations can be applied as a close approximation,
especially if the manufacturer guidelines are unknown.
MAINTENANCE FREQUENCY
MAINTENANCE
OPERATION
Daily or every 8 Every Every 150 Every 250 Every 500
hours Month hours hours hours
General Inspection
Check Grounding
connection
MAINTENANCE
OPERATION
Daily or every 8 Every Every 150 Every 250 Every 500
hours Month hours hours hours
Service hours are tracked in “running hours,” meaning only the hours while the generator is
actually on and supplying power. Note that even if running a generator for an average of 12
hours, reaching 250 or 500 hours of total running time can occur extremely quickly, meaning
the service intervals for generators can be quite frequent. Small investments made in replacing
components and maintaining generators on a regular basis can save expensive and
unnecessary upgrades or even replacement of the entire unit in the future.
When performing routine maintenance, each action taken should be logged, as well as the
readings and parameters recorded along with the date of inspection and the hour meter
reading. These sets of readings are compared with the next set of data collected. Any
considerable variation of reading may indicate faulty performance of the unit.
Preventative maintenance thus ensures that the organisation has an uninterrupted power
supply for all their needs. If a generator is rarely used, it is essential to start it at least once a
week to keep it in good condition.
Intensive Usage Occasional Usage
Corrective Maintenance
In some programs or sites of operation, it makes sense to have a trained repair technician
permanently as part of the team. In most cases, is recommended to identify and establish a
long-term agreement or other form of service contract with a trusted provider. Service
providers should be in charge of the main maintenance and be ready in case of breakdowns.
Important criteria when selecting a third-party provider is their ability to supply spare parts for
the required equipment. If a third-party provider cannot supply spare parts, then organisations
will need to maintain a stock of their own spare parts.
A generator set is the combination of an engine and an alternator plus wiring, controls,
protections and connections. These are the components that need to be checked when looking
for a failure.
It is recommended to refer to the user manual for specific fault-finding instructions as designs
vary between manufacturers. Unless a problem is immediately identifiable, a professional
generator technician or a qualified electrician may be required.
Safety Considerations