Chapter 7
Chapter 7
Quản lý Dự án
Dr. TRAN QUYNH LE
Dr. NGUYEN DUC DUY
Industrial Systems Engineering Department
Mechanical Engineering Faculty
Ho Chi Minh City University of Technology (HCMUT)–
VNUHCM
Chapter 7
Managing Risk
2
3
LEARNING OUTCOME
4
Risk Management Process
▪ Risk
• Uncertain or chance events that planning can not overcome or control.
▪ Risk Management
• A proactive attempt to recognize and manage internal events and external threats
that affect the likelihood of a project’s success.
➢ What can go wrong (risk event).
➢ How to minimize the risk event’s impact (consequences).
➢ What can be done before an event occurs (anticipation).
➢ What to do when an event occurs (contingency plans).
5
The Risk Event Graph
FIGURE 7.1
6
Risk Management’s Benefits
7
The Risk Management Process
8
Managing Risk
▪ Step 1: Risk Identification
• Generate a list of possible risks through brainstorming, problem identification and
risk profiling.
➢ Macro risks first, then specific events
The Risk
Breakdown
Structure
(RBS)
9
Managing Risk
10
Managing Risk
11
Risk Assessment Form
Defined Conditions for Impact Scales of a Risk on Major Project Objectives
(examples for negative impacts only)
12
Risk Assessment Form
FIGURE 7.4
13
Risk Severity Matrix
14
Risk Schedules
15
Managing Risk (cont’d)
16
Contingency Planning (Kế hoạch dự phòng)
▪ Contingency Plan
• An alternative plan that will be used if a possible foreseen risk event actually occurs.
• A plan of actions that will reduce or mitigate the negative impact
(consequences) of a risk event.
▪ Risks of Not Having a Contingency Plan
• Having no plan may slow managerial response.
• Decisions made under pressure can be potentially dangerous and costly.
17
Risk Response Matrix
FIGURE 7.7
18
Risk and Contingency Planning
▪ Technical Risks
• Backup strategies if chosen technology fails.
• Assessing whether technical uncertainties can be resolved.
▪ Schedule Risks
• Use of slack increases the risk of a late project finish.
• Imposed duration dates (absolute project finish date)
• Compression of project schedules due to a shortened project duration date.
19
Risk and Contingency Planning (cont’d)
▪ Costs Risks
• Time/cost dependency links: costs increase when problems take longer to solve
than expected.
• Deciding to use the schedule to solve cash flow problems should be avoided.
• Price protection risks (a rise in input costs) increase if the duration of a
project is increased.
▪ Funding Risks
• Changes in the supply of funds for the project can dramatically affect the
likelihood of implementation or successful completion of a project.
20
Opportunity Management
▪ Exploit.
• Eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.
▪ Share.
• Allocating some or all of the ownership of an opportunity to another party who is best able to
capture the opportunity for the benefit of the project.
▪ Enhance.
▪ Action is taken to increase the probability and/or the positive impact of an opportunity.
▪ Escalate /ˈes.kə.leɪt/.
• Sometimes projects encounter opportunities that are outside the scope of the project or exceed
the authority of the project manager.
▪ Accept.
• Accepting an opportunity is being willing to take advantage of it if it occurs, but not taking action
to pursue it.
21
Contingency Funding and Time Buffers
▪ Contingency Funds
• Funds to cover project risks—identified and unknown.
➢ Size of funds reflects overall risk of a project
• Budget reserves
➢ Are linked to the identified risks of specific work packages.
• Management reserves
➢ Are large funds to be used to cover major unforeseen risks (e.g., change in project
scope) of the total project.
▪ Time Buffers
• Amounts of time used to compensate for unplanned delays in the project
schedule.
22
Contingency Fund Estimate
23
Managing Risk (cont’d)
24
Change Management Control
▪ Sources of Change
• Project scope changes
• Implementation of contingency plans
• Improvement changes
25
Change Management Control
26
The Change Control Process
27
Benefits of a Change Control System
28
Change Request Form
29
Change Request Log
30
Key Terms
▪ Avoiding risk
▪ Budget reserve
▪ Change management system
▪ Contingency plan
▪ Management reserve
▪ Mitigating risk
▪ Risk
▪ Risk profile
▪ Risk severity matrix
▪ Scenario analysis
▪ Sharing risk
▪ Time Buffer
▪ Transferring risk
31
PERT and PERT Simulation
32
PERT—PROGRAM EVALUATION REVIEW TECHNIQUE
▪ Assumes each activity duration has a range that statistically follows a beta
distribution.
▪ PERT uses three time estimates for each activity: optimistic, pessimistic, and
a weighted average to represent activity durations.
• Knowing the weighted average and variances for each activity allows the project
planner to compute the probability of meeting different project durations.
33
Activity and Project Frequency Distributions
FIGURE A7.1
34
Activity Time Calculations
35
Activity Time Calculations (cont’d)
The variability in the activity time estimates is approximated by the
following equations:
The standard deviation for the activity:
36
Activity Times and Variances
37
Probability of Completing the Project
The equation below is used to compute the “Z” value found in statistical tables (Z =
number of standard deviations from the mean), which, in turn, tells the probability of
completing the project in the time specified.
38
Hypothetical Network
39
Hypothetical Network (cont’d)
40
Possible Project Duration
41
Z Values
42
Reading:
Risk management using a Bayesian belief
network
43
Risk management using a Bayesian belief network
44
Risk management using a Bayesian belief network
45
Risk management using a Bayesian belief network
46
Risk management using a Bayesian belief network
47
Risk management using a Bayesian belief network
48
Risk management using a Bayesian belief network
49
Risk management using a Bayesian belief network
50
This Page Intentionally Left Blank
51