Additional Lecture Note for MRP (a Basic MRP Explosion Problem)
Additional Lecture Note for MRP (a Basic MRP Explosion Problem)
¨ Scheduled Receipts: orders that have already released and are scheduled to
arrive as of the beginning of the period
¨ Projected available balance : amount of inventory that is expected at the end
of a period
Projected available balance (t)= projected available balance (t-1) + scheduled
receipts(t) + planned order receipts(t) – gross requirement(t)
Note: “safety stock” of an item will be retained throughout periods once it is
obtained.
¨ Net requirements: the amount needed when the projected available balance
plus the scheduled receipts in a period are not sufficient to cover the gross
requirement.
¨ Planned order receipts: the amount that will be ordered and when that amount
must be received
¨ Planed order releases: this determines when orders should be placed (i.e.,
released) so that they are received when needed
9- 33
Extra MRP Example
Item On-Hand Lead Time (W eeks)
X X 50 2
A 75 3
B 25 1
A(2) B(1) C 10 2
D 20 2
9- 35
Week: 1 2 3 4 5 6 7 8 9 10
X X
LT=2
Gross requirements
Scheduled receipts
95
each X C
LT=2
Gross requirements
Scheduled receipts
45 40
each X C
LT=2
Gross requirements
Scheduled receipts
45 40
Question Bowl
9- 43
44
Question Bowl
Question Bowl
Question Bowl
9- 46
47
Question Bowl
a. BOM file
b. Exception report
c. Planning report
d. All of the above
e. None of the above
Answer: a. BOM file (Correct answer can
also include Master Schedule and Inventory
Records File.) 9- 47
48
Question Bowl
9- 48
49
Question Bowl
a. Work overtime
b. Renegotiate the due date and reschedule
c. Subcontract to an outside shop
d. All of the above
e. None of the above
Question Bowl