Different+Types+of+FIDIC+Contracts
Different+Types+of+FIDIC+Contracts
Overview:
Used for building and engineering works where the design is provided by the Employer.
The contractor is responsible for construction according to the design.
Key Features:
Practical Example:
Scenario: A government plans to build a highway. The Employer provides a detailed design for
the project, and contractors bid based on quantities provided in the Bill of Quantities.
Key Consideration:
During excavation, the contractor discovers unexpected soil conditions (hard rock
instead of soft soil). The contractor claims additional costs and time under Clause 4.12
(Unforeseeable Physical Conditions).
The claim is assessed based on records, the baseline program, and actual quantities.
www.ipmtedu.com
2. The Yellow Book: Conditions of Contract for Plant and Design-Build
Overview:
Used for design-build projects where the contractor is responsible for both design and
construction.
Commonly used in industrial projects, power plants, and turnkey infrastructure.
Key Features:
Lump-sum contract where the contractor bears greater responsibility for risks related to
design and construction.
Practical Example:
Scenario: A private energy company awards a contract to build a solar power plant. The
contractor is responsible for designing and constructing the plant to meet performance
specifications.
Key Consideration:
If the performance tests fail, the Employer can withhold payments or request
rectification under Clause 7.5 (Rejection).
Any delay caused by design errors would be at the contractor’s risk unless there is a
force majeure event.
Overview:
Ideal for Engineering, Procurement, and Construction (EPC) or turnkey projects where
the contractor assumes almost all project risks.
Used for large-scale infrastructure projects, like oil refineries or power plants.
Key Features:
Practical Example:
Scenario: A multinational company hires a contractor to design, procure, and build a chemical
plant. The Employer specifies the output capacity and key performance criteria.
www.ipmtedu.com
Key Consideration:
During execution, steel prices rise significantly. However, under the Silver Book, the
contractor cannot claim additional costs due to price escalation. They bear this risk as it
is a fixed-price contract.
If delays occur due to unforeseen events, the contractor may invoke Clause 19 (Force
Majeure) for EOT.
Overview:
Used for small-scale projects or those with simple works and a short duration.
The focus is on minimizing administrative burdens.
Key Features:
Practical Example:
Scenario: A local authority awards a contract for repairing a small bridge. The works are
straightforward and expected to last three months.
Key Consideration:
Any variation is negotiated and agreed upon between the parties with minimal
formalities.
If there’s a delay due to rain, the contractor can request an EOT with minimal
documentation compared to other FIDIC contracts.
5. The Gold Book: Conditions of Contract for Design, Build, and Operate (DBO)
Overview:
www.ipmtedu.com
Key Features:
Contractor maintains and operates the facility after completion for an agreed period.
Practical Example:
Overview:
Practical Example:
Scenario: A port authority awards a dredging project to deepen the harbor channel to
accommodate larger ships.
Key Consideration:
Contract
Employer’s Role Contractor’s Role Risk Allocation Typical Use Cases
Type
Employer
Executes work as per
Red Book Provides design retains design Highways, buildings
design
risk
Responsible for Contractor
Yellow Specifies output Power plants,
design and bears design
Book requirements industrial facilities
construction risk
www.ipmtedu.com
Contract
Employer’s Role Contractor’s Role Risk Allocation Typical Use Cases
Type
Contractor
Silver Provides Delivers fully Oil refineries, turnkey
bears most
Book performance specs functional facility infrastructure
risks
Green Executes Shared, but
Minimal involvement Small projects, repairs
Book straightforward works simple
Specifies output and Contractor Water treatment
Gold Handles design, build,
maintenance bears life-cycle plants, long-term
Book and operate phases
standards risk infrastructure
Blue Executes marine
Supervises progress Shared Dredging, reclamation
Book works
Understanding the differences between FIDIC forms is essential for selecting the right contract
for your project. Each form shifts risk and responsibility differently, so proper risk assessment is
critical before tendering.
www.ipmtedu.com