PMP- Practice Exam Questions

The document contains a series of questions and scenarios related to project management processes, focusing on integration, resource, risk, and cost management. It addresses various project management practices, including agile methodologies, stakeholder engagement, and handling disputes with vendors. Each question presents a specific situation requiring the application of project management knowledge to determine the best course of action.

Uploaded by

cooking -
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

PMP- Practice Exam Questions

The document contains a series of questions and scenarios related to project management processes, focusing on integration, resource, risk, and cost management. It addresses various project management practices, including agile methodologies, stakeholder engagement, and handling disputes with vendors. Each question presents a specific situation requiring the application of project management knowledge to determine the best course of action.

Uploaded by

cooking -
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Request that the sponsor removes the audits

Inform stakeholders that the project will miss its objectives

Hint Unmarked

Question 95 - Qid 6113138, Integration Management, 2. Process, 4.7 Close Project


or Phase

A plan-driven project has many deliverables planned to be released at the end of the
phase. The project manager wants to ensure that the deliverables are completed as
expected.

Which agile practices can the project manager recommend to the team to make certain
that the deliverables are completed and delivered as expected?

Definition of ready and iteration reviews

User stories and confidence votes

Definition of done and demonstrations

Backlog refinement and retrospectives

Hint Unmarked

Question 96 - Qid 6113139, Resource Management, 2. Process, 9.5 Manage Team

A project manager facilitates a discussion with the team about experimenting with
some agile practices in their plan-driven project. A suggestion of incorporating daily
standups is on the table. The team members, however, are unsure of what is expected
of them.

What can the project manager suggest the project team members do prior to the daily
standup?

Make sure their work progress is reflected in the burndown chart

Submit the necessary progress reports to the product owner

Estimate work items that will be developed after the daily standup

Resolve any defects that have been found in the previous day

Hint Unmarked

Question 97 - Qid 6113142, Risk Management, 2. Process, 11.6 Implement Risk


Responses

The project team is undergoing an agile transformation. This requires the team
members to maintain their original project plans in the current management tool, but
also enter performance data in the new tool built around agile practices. The team
identifies that the information in the two tools is out of sync. This risk has been
identified earlier in project planning.

What is the best course of action for the project manager?

Accept the risk since agile values individuals and interactions over processes and tools

Recognize that the risk has now become an issue and implement the planned response

Conduct a probability and impact assessment to determine a risk score

Communicate to the project sponsor that work may be delayed due to clerical errors

Hint Unmarked

Question 98 - Qid 6113143, Integration Management, 2. Process, 2.4 Organizational


Systems

Projects in a program are using various project management approaches, such as plan-
driven, agile, hybrid. The project teams are complaining that because of that, the team
members must enter the same work, hours, risks, and other data in multiple tools. The
redundant work is impeding on their productivity time.

What is the best course of action for the program manager?

Direct the teams to continue entering the data in the various systems

Determine what tools and data provide the appropriate oversight

Switch all projects in the program to the agile project management approach

Pause all data entry until a valuable solution can be determined

Hint Unmarked

Question 99 - Qid 6113144, Integration Management, 2. Process, 1.2 Foundational


Elements

An organization is to undertake a multi-phased project. The sponsor wants to pursue


the project objectives as they have been planned but also wants to accommodate and
adjust to new information and changes in the environment as the project progresses.

Which project management approach should the project manager select for this
project?

Waterfall

Agile

Hybrid
Phased

Hint Unmarked

Question 100 - Qid 6150814, Risk Management, 3. Business Environment, 11.4


Perform Quantitative Risk Analysis

Your sponsor has committed to building a high-speed rail from one major inland city,
Azules, to the coast. You have two possible routes, either Brazos or Corazon.

Given the costs, odds, and rewards of high demand and low demand of each route in
this decision tree, what is the expected monetary value of the route to Brazos?

1.6 billion

-2 billion

0.8 billion

10.8 billion

Hint Unmarked

Question 101 - Qid 6113147, Integration Management, 2. Process, 4.4 Manage


Project Knowledge

Senior leadership has returned from a conference where they have learned about the
agile practice of retrospectives. Even though the organization does not manage any
projects in an agile manner, they mandate that from now on this ceremony is included
in all projects.

How should the outputs from the retrospectives be stored and managed?
Senior leadership determines the location of the outputs and who may access the
contents

The project team stores the outputs in a location that the project manager can control
and limit changes

The project team determines a location that is accessible for relevant stakeholders to
view and track

The project manager establishes the location and allows the customer to view and
make recommendations

Hint Unmarked

Question 102 - Qid 6113155, Resource Management, 1. People, 9.0 Project


Resource Management

The resource management plan for an international project calls for a scrum team to be
colocated during the regular workweek. However, after five sprints were completed, the
project manager got a change request approved to cut costs by transitioning the team to
a virtual environment working remotely from their homes with the start of the sixth
sprint.

After the team begins working remotely, what will be the best method to understand the
impact of the change on the team's productivity?

Check the product burndown chart to look for any changes to the trendline

Calculate the CPI at the end of each sprint to determine the change in the team's
productivity

Review the product burnup chart to compare velocity before and after the change

Update the project schedule network diagram to reflect the changes in the team's
environment

Hint Unmarked

Question 103 - Qid 6113157, Resource Management, 1. People, 9.1 Plan Resource
Management

As part of the Plan Resource Management process, project team members hold a
brainstorming session to charter working agreements. The team identifies 37
agreements that include communication guidelines, decision-making and conflict
resolution processes, core hours, a definition of a story point, how and when user
stories will move through the Kanban board, etc.

What should the project manager do next?


Submit a change request to revise the resource management plan to incorporate the
team's working agreements

Verify that all of the project team members support the working agreements and
document the agreements in the project charter

Review the team's working agreements at the start of every daily standup and during
the sprint review meetings

Ask the project team members for their top five to ten agreements and document the
information in the team charter

Hint Unmarked

Question 104 - Qid 6113159, Resource Management, 1. People, 9.5 Manage Team

A project manager implements the project management plan meticulously but is


struggling with leading the project team e<ectively. There is a great deal of unhealthy
tension between the project team members as well as with the project manager. The
project manager has had several outbursts during sprint retrospectives, which has
caused the meeting to be abruptly adjourned.

What should the project manager do first?

Submit a change request to revise the project management plan to eliminate the
requirement for retrospectives

Take a proactive step in improving his own emotional intelligence (EI) to become a more
e<ective leader

Reduce the story size by splitting user stories and use relative estimation with the entire
team to estimate

Lead a training session with the project team members to help them become
emotionally competent

Hint Unmarked

Question 105 - Qid 6113216, Stakeholder Management, 2. Process, 13.2 Plan


Stakeholder Engagement

A project is six months into its nine-month projected duration. The project manager
reports that the project is at least three months behind schedule because certain key
stakeholders were resistant to consequential changes due to the project.

What might have been done di<erently during project planning to avoid this situation?

Better execution of the Manage Stakeholder Engagement process

Development of a stakeholder engagement assessment matrix


Creation of a comprehensive stakeholder register

Establishment of a more robust communications management plan

Hint Unmarked

Question 106 - Qid 6113623, Schedule Management, 2. Process, 6.3 Sequence


Activities

Two team members are arguing over how to organize the work packages in the work
breakdown structure (WBS). One says the work packages should be arranged in the
order the work is planned to be carried out, while the other insists the order of the work
packages in the WBS does not matter. The two ask the project manager for advice.

What is the project manager's best response?

Work is decomposed and sequenced in the Define Activities process.

Any approach is good as long as the team members avoid the conflict.

The chronological order of tasks is defined in the Sequence Activities process.

The approach should be defined by the project management o<ice (PMO).

Hint Unmarked

Question 107 - Qid 6113718, Resource Management, 2. Process, 9.3 Acquire


Resources

You are leading a project to design a high-e<iciency solar cell. The project needs
copper, silver, and silicon among other materials. You have ordered custom-built
manufacturing equipment, secured permission to install a solar array on the roof for
testing, and reserved a conference room for daily stand-up meetings.

What is the result of your e<orts?

Resource histogram

Resource management plan

Resource assignment matrix

Physical resource assignments

Hint Unmarked

Question 108 - Qid 6113733, Cost Management, 2. Process, 7.3 Determine Budget

During project execution, several unexpected issues have developed and are now
threatening the project schedule and budget.

What is the best course of action for the project manager to address the issues?
Use contingency reserves

Review project funding requirements

Use management reserves

Review organizational process assets

Hint Unmarked

Question 109 - Qid 6113755, Risk Management, 2. Process, 11.2 Identify Risks

To produce the deliverables, the project will procure goods and services from outside
the organization. The project manager has instructed the team to develop a
comprehensive list of individual project risks related to those procurements.

What is the best course of action for the project team?

Consult the project charter

Review procurement documentation

Develop a procurement register

Check the probability and impact matrix

Hint Unmarked

Question 110 - Qid 6113796, Cost Management, 2. Process, 7.4 Control Costs

You are managing a renovation project of a house which is to be completed at a budget


of $100,000. Earned value analysis shows that so far you have completed 40% of the
work and spent $60,000.

How much more will it cost to complete the project if the cost performance remains
unchanged?

$160,000

$149,254

$120,000

$89,254

Hint Unmarked

Question 111 - Qid 6125212, Procurement Management, 2. Process, 12.3 Control


Procurements
A major dispute arises with a vendor on a project. The project manager claims that the
vendor has failed to perform its contractual obligations, while the vendor complains
that the project is behind on payments.

What is the best course of action for the project manager in this situation?

Refer this issue to a third party for mediation or arbitration

File a contract claim and then work directly with the vendor to resolve the issue

Terminate the contract, document lessons learned, and find another vendor

Conduct a procurement audit

Hint Unmarked

Question 112 - Qid 6125216, Resource Management, 1. People, 9.5 Manage Team

You want to recognize the contributions of some of the high-performing team members
so far in the project.

Which of the following do you need to guide you through this process?

Organizational process assets

Stakeholder register

Project team assignments

Quality metrics

Hint Unmarked

Question 113 - Qid 6150715, Schedule Management, 2. Process, 6.2 Define


Activities

You are managing a project to construct a bridge at a location that is highly regulated by
multiple levels of government. You are in the process of developing a plan that will
establish the criteria and the activities for developing, monitoring, and controlling the
schedule.

Which of the following should you gather to complete this process?

The charter, project management plan, estimation databases, and PMO templates

Government standards, the assumption log, schedule management plan, and


milestone list

The resource breakdown structure, lessons learned register, and scheduling


methodology

The project scope statement, risk register, and project team assignments
Hint Unmarked

Question 114 - Qid 6151376, Resource Management, 2. Process, 9.2 Estimate


Activity Resources

One of the project activities requires that a search of a large area is conducted to find
debris from an explosion of a failed prototype. The project is now in planning, and there
is a debate among the team members on the type and quantity of resources needed to
complete this activity.

What should the project manager do first?

Select any resource and quantity to complete the task by the due date

Request the team to vote and make a decision based on majority

Research various levels of resource capability and skills, types, and sizes

Utilize a PMIS to manage resource pools and allocate resources

Hint Unmarked

Question 115 - Qid 6151382, Cost Management, 2. Process, 7.1 Plan Cost
Management

A project manager is developing a cost management plan and needs to determine the
best source of funding for a project that is dictated by a legal requirement. The cost of
capital is estimated at 9.7% for non-dividend paying equity, 6.7% for debt, and 5.1% for
self-funding. The NPV of the project is $500,000, and the opportunity cost is $750,000.

What is the project manager's best course of action?

Fund the project with equity since there are no dividend obligations

Select the self-funding option since it provides the lowest cost of capital

Perform an alternatives analysis since there are multiple factors to consider

Recommend the termination of the project since another project has a higher NPV

Hint Unmarked

Question 116 - Qid 6151383, Cost Management, 3. Business Environment, 7.2


Estimate Costs

You are in the process of developing an approximation of the monetary resources


needed to complete project work for a large-scale multinational project which will take
at least seven years to complete. Your previous projects have all been domestic with
short timeframes.
As part of the process you are currently performing, what might you need to do
di<erently compared with your past projects?

Create a stakeholder engagement assessment matrix

Develop a more robust risk management plan

Consider additional enterprise environmental factors

Include additional organizational process assets

Hint Unmarked

Question 117 - Qid 6151389, Scope Management, 2. Process, 5.5 Validate Scope

You are assigned to a software development project, and you are conducting a product
review with an important client. Although the deliverables were previously verified, the
client detects a defect and rejects one of the deliverables.

What should you do?

Submit a change request to fix the deliverable

Refund the customer for the value of the deliverable

Ask the project team to repair the defect

Begin the claims administration process

Hint Unmarked

Question 118 - Qid 6151393, Integration Management, 1. People, 4.3 Direct and
Manage Project Work

Not all team members are properly checking out resources used in the project.

What is the best option for the project manager?

Wait until there is a need or the team is impacted

Escalate the issue to the functional managers

Discuss the checkout rationale with the team

Remove the process of checking out resources

Hint Unmarked

Question 119 - Qid 6151395, Scope Management, 2. Process, 5.6 Control Scope

In a pharmaceutical project, human trials have been started. The CEO is thrilled about
the success of the trials up to this point. She announces that the size of the patient pool
for the trials should double from the one originally planned and results tracked in the
new system launching this week.

What should the project manager do first?

Ramp up production to match the demand of the CEO

Consider what might be included in a change request

Adjust the scope baseline to reflect the increased trial size

Communicate the change in the scope to the project stakeholders

Hint Unmarked

Question 120 - Qid 6114007, Schedule Management, 2. Process, 6.5 Develop


Schedule

Following is an illustration of a project network activity node that includes some


information about activity D.

Given the information provided, what is the total float of activity D?

14

16

18

Hint Unmarked