PMP- Practice Exam Questions
PMP- Practice Exam Questions
Hint Unmarked
A plan-driven project has many deliverables planned to be released at the end of the
phase. The project manager wants to ensure that the deliverables are completed as
expected.
Which agile practices can the project manager recommend to the team to make certain
that the deliverables are completed and delivered as expected?
Hint Unmarked
A project manager facilitates a discussion with the team about experimenting with
some agile practices in their plan-driven project. A suggestion of incorporating daily
standups is on the table. The team members, however, are unsure of what is expected
of them.
What can the project manager suggest the project team members do prior to the daily
standup?
Estimate work items that will be developed after the daily standup
Resolve any defects that have been found in the previous day
Hint Unmarked
The project team is undergoing an agile transformation. This requires the team
members to maintain their original project plans in the current management tool, but
also enter performance data in the new tool built around agile practices. The team
identifies that the information in the two tools is out of sync. This risk has been
identified earlier in project planning.
Accept the risk since agile values individuals and interactions over processes and tools
Recognize that the risk has now become an issue and implement the planned response
Communicate to the project sponsor that work may be delayed due to clerical errors
Hint Unmarked
Projects in a program are using various project management approaches, such as plan-
driven, agile, hybrid. The project teams are complaining that because of that, the team
members must enter the same work, hours, risks, and other data in multiple tools. The
redundant work is impeding on their productivity time.
Direct the teams to continue entering the data in the various systems
Switch all projects in the program to the agile project management approach
Hint Unmarked
Which project management approach should the project manager select for this
project?
Waterfall
Agile
Hybrid
Phased
Hint Unmarked
Your sponsor has committed to building a high-speed rail from one major inland city,
Azules, to the coast. You have two possible routes, either Brazos or Corazon.
Given the costs, odds, and rewards of high demand and low demand of each route in
this decision tree, what is the expected monetary value of the route to Brazos?
1.6 billion
-2 billion
0.8 billion
10.8 billion
Hint Unmarked
Senior leadership has returned from a conference where they have learned about the
agile practice of retrospectives. Even though the organization does not manage any
projects in an agile manner, they mandate that from now on this ceremony is included
in all projects.
How should the outputs from the retrospectives be stored and managed?
Senior leadership determines the location of the outputs and who may access the
contents
The project team stores the outputs in a location that the project manager can control
and limit changes
The project team determines a location that is accessible for relevant stakeholders to
view and track
The project manager establishes the location and allows the customer to view and
make recommendations
Hint Unmarked
The resource management plan for an international project calls for a scrum team to be
colocated during the regular workweek. However, after five sprints were completed, the
project manager got a change request approved to cut costs by transitioning the team to
a virtual environment working remotely from their homes with the start of the sixth
sprint.
After the team begins working remotely, what will be the best method to understand the
impact of the change on the team's productivity?
Check the product burndown chart to look for any changes to the trendline
Calculate the CPI at the end of each sprint to determine the change in the team's
productivity
Review the product burnup chart to compare velocity before and after the change
Update the project schedule network diagram to reflect the changes in the team's
environment
Hint Unmarked
Question 103 - Qid 6113157, Resource Management, 1. People, 9.1 Plan Resource
Management
As part of the Plan Resource Management process, project team members hold a
brainstorming session to charter working agreements. The team identifies 37
agreements that include communication guidelines, decision-making and conflict
resolution processes, core hours, a definition of a story point, how and when user
stories will move through the Kanban board, etc.
Verify that all of the project team members support the working agreements and
document the agreements in the project charter
Review the team's working agreements at the start of every daily standup and during
the sprint review meetings
Ask the project team members for their top five to ten agreements and document the
information in the team charter
Hint Unmarked
Question 104 - Qid 6113159, Resource Management, 1. People, 9.5 Manage Team
Submit a change request to revise the project management plan to eliminate the
requirement for retrospectives
Take a proactive step in improving his own emotional intelligence (EI) to become a more
e<ective leader
Reduce the story size by splitting user stories and use relative estimation with the entire
team to estimate
Lead a training session with the project team members to help them become
emotionally competent
Hint Unmarked
A project is six months into its nine-month projected duration. The project manager
reports that the project is at least three months behind schedule because certain key
stakeholders were resistant to consequential changes due to the project.
What might have been done di<erently during project planning to avoid this situation?
Hint Unmarked
Two team members are arguing over how to organize the work packages in the work
breakdown structure (WBS). One says the work packages should be arranged in the
order the work is planned to be carried out, while the other insists the order of the work
packages in the WBS does not matter. The two ask the project manager for advice.
Any approach is good as long as the team members avoid the conflict.
Hint Unmarked
You are leading a project to design a high-e<iciency solar cell. The project needs
copper, silver, and silicon among other materials. You have ordered custom-built
manufacturing equipment, secured permission to install a solar array on the roof for
testing, and reserved a conference room for daily stand-up meetings.
Resource histogram
Hint Unmarked
Question 108 - Qid 6113733, Cost Management, 2. Process, 7.3 Determine Budget
During project execution, several unexpected issues have developed and are now
threatening the project schedule and budget.
What is the best course of action for the project manager to address the issues?
Use contingency reserves
Hint Unmarked
Question 109 - Qid 6113755, Risk Management, 2. Process, 11.2 Identify Risks
To produce the deliverables, the project will procure goods and services from outside
the organization. The project manager has instructed the team to develop a
comprehensive list of individual project risks related to those procurements.
Hint Unmarked
Question 110 - Qid 6113796, Cost Management, 2. Process, 7.4 Control Costs
How much more will it cost to complete the project if the cost performance remains
unchanged?
$160,000
$149,254
$120,000
$89,254
Hint Unmarked
What is the best course of action for the project manager in this situation?
File a contract claim and then work directly with the vendor to resolve the issue
Terminate the contract, document lessons learned, and find another vendor
Hint Unmarked
Question 112 - Qid 6125216, Resource Management, 1. People, 9.5 Manage Team
You want to recognize the contributions of some of the high-performing team members
so far in the project.
Which of the following do you need to guide you through this process?
Stakeholder register
Quality metrics
Hint Unmarked
You are managing a project to construct a bridge at a location that is highly regulated by
multiple levels of government. You are in the process of developing a plan that will
establish the criteria and the activities for developing, monitoring, and controlling the
schedule.
The charter, project management plan, estimation databases, and PMO templates
The project scope statement, risk register, and project team assignments
Hint Unmarked
One of the project activities requires that a search of a large area is conducted to find
debris from an explosion of a failed prototype. The project is now in planning, and there
is a debate among the team members on the type and quantity of resources needed to
complete this activity.
Select any resource and quantity to complete the task by the due date
Research various levels of resource capability and skills, types, and sizes
Hint Unmarked
Question 115 - Qid 6151382, Cost Management, 2. Process, 7.1 Plan Cost
Management
A project manager is developing a cost management plan and needs to determine the
best source of funding for a project that is dictated by a legal requirement. The cost of
capital is estimated at 9.7% for non-dividend paying equity, 6.7% for debt, and 5.1% for
self-funding. The NPV of the project is $500,000, and the opportunity cost is $750,000.
Fund the project with equity since there are no dividend obligations
Select the self-funding option since it provides the lowest cost of capital
Recommend the termination of the project since another project has a higher NPV
Hint Unmarked
Hint Unmarked
Question 117 - Qid 6151389, Scope Management, 2. Process, 5.5 Validate Scope
You are assigned to a software development project, and you are conducting a product
review with an important client. Although the deliverables were previously verified, the
client detects a defect and rejects one of the deliverables.
Hint Unmarked
Question 118 - Qid 6151393, Integration Management, 1. People, 4.3 Direct and
Manage Project Work
Not all team members are properly checking out resources used in the project.
Hint Unmarked
Question 119 - Qid 6151395, Scope Management, 2. Process, 5.6 Control Scope
In a pharmaceutical project, human trials have been started. The CEO is thrilled about
the success of the trials up to this point. She announces that the size of the patient pool
for the trials should double from the one originally planned and results tracked in the
new system launching this week.
Hint Unmarked
14
16
18
Hint Unmarked