Eet402 Scheme
Eet402 Scheme
PART A
Answer all questions, each carries 3 marks. Marks
1 mark each
2 1. Standard good practices for selection of part of power systems (3)
2. Recommendations concerning safety and related matter in the wiring of
electrical installations of buildings or industrial structures, promoting
compatibility between such recommendations and those concerning the
equipment installed
3. General safety procedures and practices in electrical work
Any 3 points
3 (i) The luminaire, lamp and even the surface will accumulate dust over a period (3)
of time and the lamp lumen output will depreciate with time
(ii) The lumen output of the source or lamp is not fully utilized at the work
place. A part of the light is lost in the fittings and some part is directed to the
walls and ceilings where a part will be absorbed and a part will be reflected. This
is taken into account by a factor known as Coefficient of Utilization (CoU).
1.5 x 2 = 3 marks
4 Luminous intensity of the lamp is (3)
I = 1200/4π = 95.5 cd ------ 1 mark
cos θ = 8/10 = 0.8
Now, E = I cosθ/r2 ------- 1 mark
Page 1of 11
0400EET402052301
One earth electrode is exclusively used for for the connection of lightning arrestors. The
second earth electrode is used for the connection of neutral of the transformer at the LT
side. The third earth electrode is connected to body of the transformer, all non-current
carrying parts of the transformer, operating handle of GO switch etc. All the three earth
pits are inter connected.
8 Input current = = 22.89A (3)
Current rating of the cable = 1.5 x 22.89 = 34.34A
Size of the cable : 7/1.40 Cu cable of 40A capacity or 7/1.70 Al of 43A.
Starter: Star Delta starter
Motor Switch : 3 pole 40A SFU
Main switch : 3 pole 63A.
9 1. improve the power factor and efficiency of induction motor loads (3)
2. Can avoid the penalties of supply authority
3. Manual switching of capacitor banks are very difficult and not practicable.
Any three points ------- 3 marks
10 Continuous power rating-engine can supply rated power for an unlimited time (3)
Prime power rating: engine can supply a base load for an unlimited time, and
100% rated power for a limited time. Typical values are a base load of 70% of
the rated power, 100% rated power during 500 hours per year
Standby power rating: Maximum power that the engine can deliver and is
limited in time, less than 500 hours per year
Page 2of 11
0400EET402052301
PART B
Answer one full question from each module, each carries 14 marks.
Module I
11 a) (i) 1. IS732 Covers the essential requirements and precautions regarding wiring (6)
installations for ensuring satisfactory and reliable service and safety from all
possible hazards from the use of electricity
2. Applicable to design, selection, erection, inspection and testing of wiring
installations whether temporary or permanent
3. Relates to all wiring installations in non-industrial and industrial locations
(ii) 1. Contains guidelines on choosing proper size of various components of
earthing system especially earthing conductors (SWG) and earthing
2. Gives guidance on the methods which are adopted to earth and electrical
system for limiting the potential of current carrying conductors forming part
of the system ie. System earthing and Equipment earthing
3. This code applies to land based installation and it does not apply to ships, air
crafts or offshore installations
Explanation of each – 3 x 2 = 6 marks
b) standard distribution voltage for DC system shall be 220/440V. (8)
For single phase AC: 240V, 50 Hz, 2 wire
For three phase AC: 415V, 50 Hz, 4 wire
Low voltage- Not exceeding 250V
Medium voltage- Not exceeding 650V
HV- Not exceeding 33kV
EHV-Exceeding 33kV
Voltage limits for AC systems
The supply authorities are required to maintain the voltages on the system under
normal condition within the tolerances specified below:
• 6% in case of low and medium voltage installations
• 6% on the higher side or 9% on the lower side of high voltage systems
• 12.5% in case of extra high voltage systems
• Under Indian Electricity Rules, the voltage fluctuation may not vary by more
than 5% above or below the declared nominal voltage. ie. 228V to 252V for
nominal voltage of 240V & 394.25V to 435.75V for nominal voltage of 415V
• Frequency must be within ±1% of the declared frequency of 50Hz
OR
12 a) The Indian Electricity Act, 2003 seeks to replace Indian Electricity Act 1910, ()
The Electricity Supply Act 1948, and The Electricity Regulatory Commission
Act 1998
It is an act implemented by the parliament to consolidate the laws relating to
generation, transmission, distribution, trading and use of electricity and aims at
• Promoting measures to the development of electricity industry.
• Promoting competition
• Protecting interest of consumers
• Providing electric supply to all areas
Page 3of 11
0400EET402052301
500 50 30
N = 27.7 -------- 2 marks
0.6 0.5 90000
therefore 28 lamps are required.
Check space height ratios for length and width.
4 rows of 7 spaced as shown is an acceptable design. ------ 2 marks
---- 2 marks
OR
Page 4of 11
0400EET402052301
Page 5of 11
0400EET402052301
Page 6of 11
0400EET402052301
16 a) The feeder to a DB will be fed from SDB or MDB. It is necessary that the major (4)
protective fuse shall not blow off before or along with motor protective fuse in
the DB. There shall be grading or discrimination between these fuses. The fuses
in two systems are termed as minor and major fuses. For achieving grading, the
minor fuse should be lower than half of the major fuse. ----- 3 marks
Eg: (1) 32A will grade with 63A and above ------ 1 mark
b) 1. Insulation resistance test. (10)
2. Polarity test of switch.
3. Earth electrode resistance test
4. Earth continuity test
Explanation of each test – 2.5 x 4 = 10 marks
Module IV
17 a) Line diagram – 3 marks (4)
IL= = 876A
Taking a factor of safety, 4 runs of 3-1/2 core 240sq.mm PVC /XLPE insulated
armoured LT cable can be used.
Primary side CB : 11kV, 40A OCB
Secondary side CB : 415kV, 1000A VCB
Ratings – 1 marks
b) Total load in kW = 20 + (30+10) x 0.746 = 49.84 kW ---- 1 mark (10)
Assuming a pf of 0.8, load in kVA = 49.84/0.8 = 62.3 kVA
A 63kVA, 11kV/415V, 3 phase 50Hz transformer is to be mounted on a double
pole structure. ------- 1 mark
To find the size of cable to be run from the secondary side of the transformer,
the current rating should be found out.
63 103
IL 88 A
Full load current = 3 415 ------ 1 mark
We may choose 3-1/2 core 95sq.mm PVC insulated LT cable ----- 1 mark
3-1/2 core 95sq.mm cable should be run from the transformer to the distribution
box and from the distribution box the different feeder cables are to be selected
by taking into consideration of the load of each circuit.
The distribution box consists of one 100A incoming main switch and 3 nos. Of
outgoing switches.
1 no. 63A for 30hp agricultural load, 2 no.s of 40A for 20kW residential load
and 10hp motor loads.
Cable to be run are:
3-1/2 core 50mm2 cable from 63A switch
4 core 16mm2 cable for 40A switches ------ 1 mark
Single line diagram -------- 2 mark
Estimate of the materials ---------- 3 mark
OR
18 a) 1. Insulation resistance test (IR test) (4)
Page 7of 11
0400EET402052301
Page 8of 11
0400EET402052301
marks
Length of the conduit:
Length of the wire: ------ 1.5 mark
For motor1
For motor 2
For motor 3
Module V
19 a) 1. Minimum 1m clearance shall be provided on three sides of the generator set, (6)
minimum 2m clearance shall be provided between them
2. Fuel tank of DG sets shall be installed outside the generator room
3. Exhaust pipe of DG sets shall maintain a minimum height of 1.8m clearance
from the floor level
4. Voltmeters and frequency meters shall be connected before the circuit breaker
in the generator control panel
5. Watt hour meter and ammeters in each phase shall be provided
6. For generators of 500kVA and above, kVA/kW meter and pf meter shall also
be provided
7. Changeover switches of approved makes is permitted for capacities up to and
including 800A
8. Above 800A capacity, CB with castle key interlock shall be provided
9. Under voltage coil may be provided at grid side, ACB/MCCB on respective
switchboards at installations where generators are installed for preventing
chances of back feeding from generators to grid side
10. Separate Isolators shall be provided before the change over switch, if it has
no OFF position
11. Provide thermal O/L relay in the generator circuit
12. Generator capacity should be sufficient if it is called upon to start induction
motors of 60% of its rating, provided suitable starters are employed for limiting
the starting current.
13. Generator room shall be made of non-inflammable materials
14. Standard size of earthing cables and conductors for generators shall be
provided
15. Proper protection schemes should also be provided for generators
16. Central pollution control board approved type acoustic enclosure shall be
provided for all generators
Any 6 points ----- 6 marks
b) Total watt-hr per day for all appliances taken together (8)
Watt-hrs used by CFL lamps = 3 x 18 x 4 = 216
Watt-hrs used by ceiling fans = 2 x 60 x 8 = 960
Watt-hrs used by refrigerator = 125 x 24 x 0.5 = 1500
Watt-hrs used by night lamp = 5 x 7 = 35
Watt-hrs used by washing machine = 125 x 1 = 125
Total watt-hr required per day = 216 +960 +1500 + 35 +125 = 2836 W- hr.
Page 9of 11
0400EET402052301
– -- - ----- 1mark
Watt-hr per day to be generated by the solar panels = 1.3 x 2836
= 3686.8W-hr
The size of the solar panel, if the location of the building is in trivandrum
Minimum solar irradiation for trivandrum = 4.83 kWh/m 2/day
Panel generation factor (with MPPT controller) = 4.83 x derating factor
= 4.83 x 0.69 = 3.33 Wh/Wp/day
Watt hr/day for all the appliances taken together = 2836 Wh/day
Panel size required = 3686.8/3.33 = 1107.15 Wp ------ 1mark
Therefore, number of PV modules = Panel size required / Rated Wp of the PV
module
We may choose 110Wp module
Number of PV modules = 1107.15 / 110 = 10.065 ( say 10 modules)
The capacity of the solar plant is therefore 10 x 110 = 1100 Wp
The surface area of each module is 0.85 m2
Therefore the roof area required for installing the solar PV system will be about
10 x 0.85 = 8.5m2 ------ 1mark
Size of the battery
Wh/day required by the load = 2836
Battery must supply 2836 / 0.85 = 3336 Wh/day (based on 85% efficiency)
Battery must supply 3336/ 0.5 = 6672 Wh (based on 50% depth of discharge)
Battery must be sized 6672 x 2 = 13344 Wh/day (based on 2 cloudy days)
Say 13400 Wh. ------ 1mark
With 24V battery, Ah capacity = 13400 / 24 = 558 Ah (say 600Ah)
Therefore, we can choose 8 nos. Of 150Ah, 12V batteries connected as two in
series and four in parallel (4 x 150 = 600 Ah at 24 V) and this will be able to
supply the load for 2 days without interruption.
Size of charge controller ------ 1mark
Since the battery voltage is selected as 24V, the PV modules shall be connected
as two numbers in series and five numbers in parallel. so that the open circuit
voltage of the PV module will be around 21 x 2 = 42 V and the short circuit
current of each module is 6.98 A (from the table)
Therefore, the total short circuit current from all the 5 PV modules connected in
parallel will be equal to = 6.98 x 5 = 34.9 A
Hence the current rating of the charge controller = 130% of the short circuit
current
= 1.3 x 34.9 = 45.37A (say 50A) ------ 1mark
Therefore, we can choose a charge controller rated for 24V, 50A capacity
The power output of the PV array is 1100W. hence the capacity of the inverter
can be fixed as 1200VA ------ 1mark
The final specification of the inverter can be 24V DC inputs, 240V AC output,
1200VA grid connected inverter. ------ 1mark
Page 10of 11
0400EET402052301
OR
20 a) On-grid system (8)
4 x 2 = 8 marks
b) Diagram of Rising main panel of a 5 storied building with control circuits– 6 (6)
marks
****
Page 11of 11