Mode S M T W T F S S M T W T F S S M T W T
1 Project Idea 7 days Mon 05/09/22 Tue 13/09/22
2 Report 1 – Project 7 days Wed 14/09/22 Thu 22/09/22
3 Introduction 7 days Wed 14/09/22 Thu 22/09/22
4 Report 2 – Project Management 10 days Fri 23/09/22 Thu 06/10/22
Plan
5 Report 3 – SRS 10 days Fri 23/09/22 Thu 06/10/22
6 Report 4 – Software Design 18 days Fri 07/10/22 Tue 01/11/22
7 Code & Implement Iteration 1 10 days Fri 07/10/22 Thu 20/10/22
8 Code & Implement Iteration 2 15 days Fri 21/10/22 Thu 10/11/22
9 Report 5 – Test Document 27 days Wed 02/11/22 Thu 08/12/22
10 System Test 22 days Wed 02/11/22 Thu 01/12/22
11 Create Test case 7 days Wed 02/11/22 Thu 10/11/22
12 Execute Testcase 15 days Fri 11/11/22 Thu 01/12/22
13 Acceptance Test 5 days Fri 02/12/22 Thu 08/12/22
14 Report 6 – Software Guides 5 days Fri 09/12/22 Thu 15/12/22
15 Code & Implement Iteration 3 20 days Fri 11/11/22 Thu 08/12/22
16 Final Code and Report 9 days Fri 09/12/22 Wed 21/12/22