ECCD fencing

The document outlines an Occupational Health and Safety worksheet for the construction of compound fencing and wall in Khatoed, detailing estimation amounts and required safety measures. It includes a breakdown of personal protective equipment and common protective measures, along with their weightage and applicability. Additionally, it provides a detailed estimate for construction activities, including excavation, masonry, and concrete work, with associated costs and dimensions.

Uploaded by

Pema Gyelpo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

ECCD fencing

The document outlines an Occupational Health and Safety worksheet for the construction of compound fencing and wall in Khatoed, detailing estimation amounts and required safety measures. It includes a breakdown of personal protective equipment and common protective measures, along with their weightage and applicability. Additionally, it provides a detailed estimate for construction activities, including excavation, masonry, and concrete work, with associated costs and dimensions.

Uploaded by

Pema Gyelpo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Occupational Health and Safety worksheet for Building works

Name of work :-Construction of compound fencing and wall in Khatoed


Location :-
Khatoed, Jigmechhoeling
Estimation amount : 460,852.22
15.8248 4.0000

SI No Particular Weightage Weightage (%)


A INSURANCE 30% 1.2000
PERSONAL PROTECTIVE
B EQUIPMENT 30% 1.2000
COMMON PROTECTIVE
C MEASURES 40% 1.6000
Required/Not
Sl.No Particulars Weightage Remarks
required
A INSURANCE 1.2 Yes
PERSONAL PROTECTIVE
B 1.2 0.1091
EQUIPMENT( 30%)
1 Protective clothing 0.1091 Yes
2 Safty helmet 0.1091 Yes
3 Safty belt/safty harness 0 No
4 Safty shoes 0.1091 Yes
5 Protective gloves 0.1091 Yes
6 Safty goggle and spectacles 0 No
7 Safty Net 0 No
8 Ear muffs/plug 0 No
9 Welding shield/glass 0 No
10 Protective mask 0 No
11 Leather gloves 0 No
Appliable PPE (%) 0.4364
COMMON PROTECTIVE
C 1.6000 0.1200
MEASURES( 40%)
1 First Aid kits 0.12 Yes
2 Medical examination 0 No
Accommodation, Sanitation
3 0.12 Yes
and washing facilities
4 Safty signs and signboard 0.12 Yes
5 Boundary fence 0.12 Yes
6 Fire and electrical safty 0 No
7 Fall protection
Trained OHS Officers/Safty 0.12 Yes
8 supervisor/Safty
Safty and Health orientation 0 No
9 representative
to new workers and safty 0 No
10 traning
House keeping 0 No
Traffic management at
11 0 No
construction site
12 Trained first aider 0 No
Trenching and excavation
13 0 No
safty
Appliable PPE (%) 0.6000
Occupational Health and Safety worksheet for Building works

Name of work :-Construction of compound fencing and wall in Khatoed


Location :-
Khatoed, Jigmechhoeling
Estimation amount : 460,852.22
this work (%) 2.2364
this work (Nu.) 10306.50

Prepared by Checked by

Dewas Biswa
Assistant Engineer Dzongkhag Chief Engineer
No 0

Remarks
Yes 1.2000

No 0
Yes 0.1091

No 0

Yes
0.12
Name of work: Construction of compound fencing for Khataoed ECCD
Title: Detail Estimate
Location: Khatoed, Jigmechhoeling BSR 2024 Base rate: Gelephu
Sl.n Dimension (m)
o BSR ref Description No L B H Qty Unit Rate Amount
CHAIN - LINK FENCING

Excavation in foundation trenches or drains not


exceeding 1.5m in width or area 10 sq.m on plan, ### cu.m 221.50 5,176.46
including dressing & ramming,disposal of surplus
1 EW0106soil within 50m lead & 1.5m lift- All types of soil
wall foundation 1.0 60.20 0.7 0.53 ###
Gate foundation
Providing and laying Hand packed stone filling or 2.0 0.80 0.8 0.98 1.25
2 SM0072soling with stones 4.40 cu.m ### 7,178.42
wall foundation 1.0 60.20 0.7 0.1 4.21
Gate foundation 2.0 0.80 0.8 0.15 0.19
Providing and laying in position plain cement
concrete excluding the cost of centering and
shuttering - All work upto plinth level 1:3:6 (1 6.44 cu.m ### ###
cement: 3 sand: 6 graded crushed rock 20mm
3 CW0005nominal size)
wall foundation 1.0 60.20 0.7 0.08 3.16
Top of wall 1.0 60.20 0.4 0.05 1.20
Gate foundation 2.0 0.80 0.8 0.08 0.10
Base of angle post ### 0.40 0.4 0.4 1.98
Providing & laying Random Rubble Masonry with
hard stone in foundation & plinth. In cement ### cu.m ### ###
4 SM0006mortar 1:5
Wall for fence base 1.0 60.20 0.4 0.6 ###
Deduct PCC area ### 0.40 0.4 0.4 (1.98)
Steel work in single section incl. cutting, hoisting,
fixing and applying priming coat of red lead paint:
In Tees, angles and channels ### kg 101.40 ###
5 SW0003
ISA 50x50x6 25 1.925 4.5 216.56
Support 6 1.925 4.5 51.98
Steel work welded, in built up sections, trusses,
### frame-works incl. cutting, hoisting, fixing and 44.70 kg 100.46 4,490.56
appl. priming coat of red lead paint: In Tees,
6 angles, flats and channels
Two gate Angle section ISA 40x40x5 Vt 4 1.5 3.00 18.00
Hz 4 0.9 3.00 10.80
Hold fast 4 0.5 3.00 6.00
Flat 40x5 Hz 6 0.9 1.57 8.48
sliding bold flat 30x3 2 0.5 0.71 0.71
Semi-circular hing 2 0.5 0.71 0.71
Providing & fixing G.I chain - link mesh including
fixing of post or struts, G.I staples (excluding the
cost of posts/struts, earthwork, concrete etc.) 90.30 sq.m 432.56 ###
7 RW02094mm (8 SWG) x 50mm
fencing 1 60.2 1.5 90.30
Filling of trenches, sides of foundations etc, in
layers <200mm using selected excavated earth, 3.61 cu.m 111.32 401.87
8 EW0195ramming etc within lead 50m & lift 1.5m.
Sides of wall 1.0 60.20 0.1 0.6 3.61
Providing & fixing Thermo-Mechanically Treated
reinforcement bar (Yield Strength 500 MPa) for ### kg 87.33 5,396.12
R.C.C work including cutting, bending, binding,
9 RC0083and placing in position complete
Plain bar for gate Vt. 10 dia bar ### 1.70 0.62 ###
sq.bar 10x10 2.0 1.20 0.79 1.88
Gate side post vt 4 - 12dia bar 8.0 2.70 0.89 ###
stirrup 8 dia @ 150c/c ### 1.15 0.4 ###
Footing 10dia @ 150 c/c bothway ### 0.70 0.62 ###

Page 4 of 8
Name of work: Construction of compound fencing for Khataoed ECCD
Title: Detail Estimate
Location: Khatoed, Jigmechhoeling BSR 2024 Base rate: Gelephu
Sl.n Dimension (m)
o BSR ref Description No L B H Qty Unit Rate Amount
Providing & laying in position reinforced cement
concrete excluding the cost of centering,
shuttering and reinforcement - all work upto 0.71 cu.m ### 3,912.46
plinth level 1:2:4 ( 1 cement: 2 sand: 4 graded
10 RC0003crushed rock 20mm nominal size)
Base footing pad 2.00 0.80 0.8 0.20 0.26
Column 2.00 0.30 0.3 2.50 0.45
Providing & fixing centering and shuttering
(formwork), including strutting, propping etc. and
### 7.28 Sq.m 707.41 5,149.94
removal of formwork: Columns, Pillars, post,
11 struts etc.
Footing pad 2.00 3.20 0.20 1.28
Column 2.00 1.20 2.50 6.00
12 PL0041Providing & laying 20mm cement plaster C.M 1:4 6.00 sq.m 284.57 1,707.42
On sides of gate 2.0 1.20 2.5 6.00
Providing and applying finishing coats, with :-
### Aluminium paint, two coats on new work 22.17 Sq.m 96.84 2,146.94
13
On angle post 31 1.5 0.21 9.77
Flat 2 62 0.1 12.40
Providing & applying one coat of primers -
5.52 sq.m 43.37 239.40
14 PT0010 Cement primer
On sides of gate 2.0 1.20 2.3 5.52
Finishing wall with Water - Proof Cement paint.
5.52 sq.m 100.39 554.15
15 PT0030 New work, three coats
On sides of gate 2.0 1.20 2.3 5.52
Providing & applying white or colour washing: ### sq.m 31.92 1,537.27
16 PT0020 White washing with lime - new work - three coats
2.0 60.20 0.4 48.16
PERMANENT
Earth STRUCTURE
work in excavation over areas, depth
>300mm, width >1.5m, area >10 Sq.m on plan,
including disposal of excavated earth within 50m 32.13 cu.m 209.56 6,733.16
lead and 1.5m lift & disposed soil to be neatly
17EW0031dressed: All type of soil
Above ECCD Breast wall 0.5 20 1.53 1.5 22.95
Retaining wall below building 0.5 8 1.53 1.5 9.18
Excavation in foundation trenches or drains not
exceeding 1.5m in width or area 10sq.m on plan, 21.42 cu.m 221.5 4,744.53
including dressing & ramming, disposal of surplus
18 EW0106soil within 50m lead & 1.5m lift. All types of soil
Above ECCD Breast wall 1.0 20 1.53 0.5 15.30
Retaining wall below building 1.0 8 1.53 0.5 6.12
Providing and laying hand packed stone soling or
### 6.43 Cu.m1,633.10 ###
19 filling with stones .
Above ECCD Breast wall 1.0 20 1.53 0.15 4.59
Retaining wall below building 1.0 8 1.53 0.15 1.84
Providing and laying in position plain cement
concrete excluding the cost of centering and
shuttering - All work upto plinth level. 1:3:6 (1 3.22 cu.m 4701.59 ###
cement : 3 sand : 6 graded crushed rock 20 mm
20 CW0005nominal size)
Base Above ECCD Breast wall 1.0 20 1.53 0.08 2.30
Retaining wall below building 1.0 8 1.53 0.08 0.92
Providing & laying Random Rubble Masonry with
hard stone in foundation & plinth In cement 51.24 cu.m 4391.19 ###
21 SM0006mortar 1:5
Base Above ECCD Breast wall 1.0 20 0.92 2 36.60
Retaining wall below building 1.0 8 0.92 2 14.64

Page 5 of 8
Name of work: Construction of compound fencing for Khataoed ECCD
Title: Detail Estimate
Location: Khatoed, Jigmechhoeling BSR 2024 Base rate: Gelephu
Sl.n Providing and laying in position plain cement Dimension (m)
o BSR refconcrete in retaining walls, return walls, walls
Description No L B H Qty Unit Rate Amount
(any thickness) including attached pilasters,
columns, piers, abutments, pillars, posts, struts,
buttresses, string or lacing courses, parapets,
coping, bed blocks, anchor blocks, plain window
sills, fillets etc. upto floor five level, excluding the 0.84 cu.m 5951.89 4,999.59
cost of centering and shuttering 1:2:4 (1 cement:
2 sand: 4 graded crushed rock 20mm nominal
22 CW0022size)
Base Above ECCD Breast wall 1.0 20 0.6 0.05 0.60
Retaining wall below building 1.0 8 0.6 0.05 0.24
Filling of trenches, sides of foundation etc. in
layers <200mm using selected excavated earth, 21.00 cu.m 111.32 2,337.72
23 EW0195ramming etc. within lead 50m & lift 1.5m
Base Above ECCD Breast wall 0.5 20 1 1.5 15.00
Retaining wall below building 0.5 8 1 1.5 6.00

Providing & fixing centering and shuttering


(formwork), including strutting, propping etc. and 5.42 sq.m 392.21 2,125.78
24 RC0090removal of formwork Foundation and plinth etc.
Base Above ECCD Breast wall 1.0 23.06 0.08 1.73
Retaining wall below building 1.0 11.06 0.08 0.83
Base Above ECCD Breast wall 2.0 20 0.05 2.00
Retaining wall belowHealth
Incorporation of Occupational building
and safety 2.0 8.6 0.05 0.86
measures at construction sites as per the attached
requireemnts list. The standards and
specifications for the Insurance, OHS materials
(or) equipment shall be in compliance with the
labour and Employment Act - 2007, Regulation on 1 1 L/s ### ###
Occupational Health, Safety and Welfare - 2012,
and other relevant national documents. All OHS
items will remain as the property of the bidder
25 OHS001upon completion of the project

Page 6 of 8
Name of work: Construction of compound fencing for Khataoed ECCD
Title: Travel Expenses
Location: Khatoed, Jigmechhoeling

Total Expenses
Travel Distance

allowance ( B )

Allowance ( C )
No. of visit per

Both way to &

Approve Min.
Particular of

Rate per Km
Total travel

Total TADA
Total Daily
Allowance

(D=B+C)
official

(A * D)
Daily
Sl.no

days
(A)

Chief fro
DE/other
1 official 2 2 69 16 2208 ### 2 3000 5208 ###
2 Site Engineer 6 2 69 16 2208 ### 2 3000 5208 ###
3 Technician 6 2 69 16 2208 ### 2Total
2500 4708
travel ###
Expense ###

Prepared by Checked by

(Dewas Biswa) (Tashi Chhophel)


Assistant Engineer Chief Dzongkhag Engineer
oed ECCD

hag Engineer