Title of Micro Project: PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC
EMULSION OIL PAINT, LUSTER PAINT.
(D5) (D5)
Title of the Micro-Project: PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC
EMULSION OIL PAINT, LUSTER PAINT.
A) Process and Product Assessment (Convert above total marks out of 6 marks)
02 Literature review /
information collection
05 Quality of
prototype/Model
06 Report Preparation
(B) Individual Presentation / Viva (Convert above total marks out of 4 Marks)
07 Presentation
08 Viva
4.0 Action Plan (sequence and time required for major activities)
Sr. Planned start date Planned finish date Name of responsible
Details of Activity
No. team members
3. LITERATURE REVIEW
4. ABSTRACT
5. DIAGRAM OF FIXED
6. CONCLUSION
7. REFRENCES
5.0 Resources Required (Major resources such as raw material, some machining facility, software,
etc.)
Sr.
Name of resource/material Specifications Qty. Remark
No.
Internet www.slideshare.nic 2
2. www.onlinecreator.co.in
3. MS Word 1
35 Om Pandurang Yeole
This review examines the cost value, building production and infrastructure costs, and evaluation
approaches. It helps to understand the role of evaluation methods in synthesizing the cost and
project life-cycle.
5.0 Actual Methodology Followed (Write step wise work done, data collected and its analysis (if
any).
Rate analysis is the basis for arriving at a correct rate per unit work or supply of work specifications
such as labor, materials, and equipment. It can also be defined as the analytical study that leads to
the definition of unit rates of work by identifying the basic requirements.
6.0 Actual Resources Used (Mention the actual resources used for Micro Project).
Sr.
Name of resource/material Specifications Qty. Remark
No.
Internet www.slideshare.nic 2
2.
www.onlinecreator.co.in
3. MS Word 1
7.0 Output(s) of the Micro project: (drawings of prototype or survey, presentation is collected data,
findings, etc.)
Rate analysis is the basis for arriving at a correct rate per unit work or supply of work specifications
such as labor, materials, and equipment. It can also be defined as the analytical study that leads to
the definition of unit rates of work by identifying the basic requirements
8.0 Skill(s) developed / Learning outcome of this Micro Project:
We get to learn the proper use of renewable energy skills, expertise in the management of waste,
teamwork while doing the microproject, leadership of a member while designing the foam sheet of
the microproject, proper management of the process followed while working on the preparation of
the foam sheet.
9.0 Application(s) of this Micro project:
This app provides rate analysis for construction items, material requirements, and costing. It's useful
for architects, civil engineers, contractors, and others involved in construction..
INDEX
SR.NO. CONTENT PAGE
NO.
INTRODUCTION
1 1
FACTORS AFFE-
CTING RATE ANA-
2 LYSIS 2
3 ELEMENTS 3
4 ANALYSIS OF 5
RATES
5 REFFERENCE 13
6 CONCLUSION 14
INTRODUCTION
In order to determine the rate of a particular item,
the factors affecting the rate of that item are studied
carefully and then finally a rate is decided for that item.
This process of determining the rates of an item is
termed as analysis of rates or rate analysis.
The cost of materials in rate analysis is calculated as
combination of cost of material at origin, its
transportation costs, taxes. The rate of labour is based
on skill of the labour, such as skilled labour, semi-
skilled and unskilled labour. The cost of materials and
labours vary from place to place. Thus, the cost of each
construction work varies from place to place.
The capacity of doing work by an artisan or skilled
labour in the form of quantity of work per day is known
as the task work or out turn of the labour.
The cost of any construction project is calculated
based on each works associated with every
construction activity. Thus it is essential to calculate
cost of each small works.
What are the Factors Affecting
Analysis of Rates of Civil Works?
Factors which affect the rate analysis
of civil works are:
o Specification of the civil work and materials such as
quality of materials, proportion of mortar or concrete,
thickness of plastering, number of coats of painting,
depth of excavation, type of soil etc.
o Location of the construction site – Distance of
construction site from source of materials, availability
of labours, availability of water, machinery etc.
influence the rate analysis of construction work.
o Quantity of materials, number of different types of
labours and rates of materials and labours influence the
rate analysis.
o Profit of the contractor, miscellaneous expenses and
other overheads also influence the rate analysis.
What are the Elements of Rate
Analysis of Civil Works?
Elements which constitute the rate analysis are:
a) Material cost inclusive of wastage
b) Labour cost
c) Plant & machinery owning and operating charges
d) Water charges
e) Taxes
f) Insurance/ risk coverage charges
g) Contractor’s overheads and profit
Why Analysis of Rates is
Required in Construction
Projects?
The rate analysis may be required in construction
projects for following purposes:
o For the purpose of tendering. In the case of tendering,
the contractor may calculate cost of unit work involved
in each construction activity for justified quoting of
rates. The client may also require rate analysis to
calculate the cost of construction project.
o To assess the requirements of quantities of labours,
materials, machineries and capital to complete the
project.
o To optimise the use of labour, materials and
machineries and to know the alternatives to optimize
the resources.
o To assess the rate of unit work from time to time for
payment increase in material or labour costs or any
deviations in work specifications, extra items of work to
the contractor.
o To compare the cost of project with the sanctioned
capital of the project to take necessary action or
regularization of excess or less cost.
o To workout the budget of the construction project and
control the cash flows at various stages of construction
work.
o To find out the irrational rates quoted by the contractors
during tendering process.
o To serve as the basic data in case of dispute among
project owner and contractor.
ANALYSIS OF RATES :
●TEXTBOOK
●WIKIPEDIA
●FROM NEWSPAPERS
●WWW.CIVILWORKS.COM
CONCLUSION