afcons
afcons
1053
H
1070 SUPREME COURT REPORTS [2010] 8 S CR.
H
AFCONS INFRASTRUCTURE LTD. v. CHERIAN VARKEY1073
CONSTRUCTION CO. (P) LTD. [RV RAVEENDRAN, J.]
(a} arbitration;
G
(b} conciliation:
(d) mediation. A
(2) where a dispute has been referred -
(b) to Lok Ada/at, the Court shall refer the same to the Lok
Ada lat in accordance with the provisions of sub-section (1) c
of section 20 of the Legal Services Authority Act, 1987 (39
of 1987) and all other provisions of that Act shall apply in
respect of the dispute so referred to the Lok Adalat;
(c) for judicial settlement. the Court shall refer the same
to a suitable institution or person and such institution or D
person shall be deemed to be a Lok Adalat and all the
provisions of the Legal Services Authority Act, 1987 (39
of 1987) shall apply as if the dispute were referred to a
Lok Adalat under the provisions of that Act;
E
(d) for mediation, the Court shall effect a compromise
between the parties and shall follow such procedure as
may be prescribed."
A of a possible settlement and then refer the same for any one
of the ADR processes. If sub-section ( 1) of Section 89 is to be
literally followed, every Trial Judge before framing issues, is
required to ascertain whether there exists any elements of
settlement which may be acceptable to the parties, formulate
s the terms of settlement, give them to parties for observations
and then reformulate the terms of a possible settlement before
referring. it to arbitration, conciliation. judicial settlement, Lok
Adalat or mediation. There is nothing that is left to be done by
the alternative dispute resolution forum If all these have to be
c done by the trial court before referring the parties to alternative
dispute resolution processes, the court itself may as well
proceed to record the settlement as nothing more is required
to be done, as a Judge cannot do these unless he acts as a
conciliator or mediator and holds detailed discussions and
negotiations running into hours.
0
10. Section 73 of AC Act shows that formulation and
reformulation of terms of settlement is a process carried out at
the final stage of a conciliation process, when the settlement
is being arrived at. What is required to be done at the final stage
E of conciliation by a conciliator is borrowed lock, stock and
barrel into section 89 and the court is wrongly required to
formulate the terms of settlement and reformulate them at a
stage prior to reference to an ADR process. This becomes
evident by a comparison of the wording of the two provisions.
F
H
AFCONS INFRASTRUCTURE LTD. v. CHERIAN VARKEY1079
CONSTRUCTION CO. (P) LTD. [R.V. RAVEENDRAN, J.]
All over the country the courts have been referring cases under
section 89 to mediation by assuming and understanding
'mediation' to mean a dispute resolution process by negotiated
H settlement ·.vith the assistance of a neutral third party. Judicial
AFCONS INFRASTRUCTURE LTD. v. CHERIAN VARKEY1085
CONSTRUCTION CO. (P) LTD. [R.V. RAVEENDRAN, J.]
to their nature : A
19. All other suits and cases of civil nature in particular the F
following categories of cases (whether pending in civil courts
or other special Tribunals/Forums) are normally suitable for
ADR processes :
H
1088 SUPREME COURT REPORTS [2010] 8 S.C.R.
Arbitration
E 23. Arbitration is an adjudicatory dispute resolution
process by a private forum, governed by the provisions of the
AC Act. The said Act makes it clear that there can be reference
to arbitration only if there is an 'arbitration agreement' between
the parties. If there was a pre-existing arbitration agreement
F between the parties, in all probability, even before the suit
reaches the stage governed by Order 10 of the Code, the
matter would have stood referred to arbitration either by
invoking section 8 or section 11 of the AC Act, and there would
be no need to have recourse to arbitration under section 89 of
G the Code. Section 89 therefore pre-supposes that there is no
pre-existing arbitration agreement. Even if there was no pre-
existing arbitration agreement, the parties to the suit can agree
for arbitration when the choice of ADR processes is offered to
them by the court under section 89 of the Code. Such
H agreement can be by means of a joint memo or joint application
AFCONS INFRASTRUCTURE LTD. v. CHERIAN VARKEY1091
CONSTRUCTION CO. (P) LTD. [RV RAVEENDRAN, J.]
(Emphasis supplied)
(Emphasis supplied)
E ,.
(24.3) The position was reiterated by this Court in Jagdish
Chander v. Ramesh Chander [2007 (5) SCC 719] thus :
(Emphasis supplied) F
(24.4) Therefore, where there is no pre-existing arbitration
agreement between the parties, the consent of all the parties
to the suit will be necessary, for referring the subject matter of
the suit to arbitration under section 89 of the Code.
H
1094 SUPREME COURT REPORTS [2010] 8 S.C.R
A Conciliation
Summation
(b) The court should first consider whether the case falls
under any of the category of the cases which are
required to be tried by courts and not fit to be
referred to any ADR processes. If it finds the case G
falls under any excluded category, it should record
a brief order referring to the nature of the case and
why it is not fit for reference to ADR processes. It
will then proceed with the framing of issues and
trial. H
1098 SUPREME COURT REPORTS (2010] 8 S C.R
the proceedings. A
(vi) Normally the court should not send the original record
. of the case when referring the matter for an ADR forum. It
should make available only copies of relevant papers to
the ADR forum. (For this purpose, when pleadings are filed B
the court may insist upon filing of an extra copy). However
if the case is referred to a Court annexed Mediation Centre
which is under the exclusive control and supervision of a
Judicial Officer, the original file may be made available
wherever necessary.
c
33. The procedure and consequential aspects referred to
in the earlier two paragraphs are intended to be general
guidelines subject to such changes as the concerned court may
deem fit with reference to the special circumstances of a case.
We have referred to the procedure and process rather D
elaborately as we find that section 89 has been a non-starter
with many courts. Though the process under Section 89
appears to be lengthy and complicated, in practice the process
is simple: know the dispute; exclude 'unfit' cases; ascertain
consent for arbitration or conciliation; if there is no consent, E
select Lok Adalat for simple cases and mediation for all other
cases, reserving reference to a Judge assisted settlement only
in exceptional or special cases.
Conclusion
F
34. Coming back to this case, we may refer to the decision
in Sukanya Holdings relied upon by the respondents, to
contend that for a reference to arbitration under section 89 of
the Code, consent of parties is not required. The High Court
assumed that Sukanya Holdings has held that section 89 G
enables the civil court to refer a case to arbitration even in the
absence of an arbitration agreement. Sukanya Holdings does
not lay down any such proposition. In that decision, this Court
was considering the question as to whether an application
under section 8 of the AC Act could be maintained even where H
1102 SUPREME COURT REPORTS [2010] 8 S.C.R.
H
AFCONS INFRASTRUCTURE LTD. v. CHERIAN VARKEY1103
CONSTRUCTION CO. (P) LTD. [R.V. RAVEENDRAN, J.]
(i) The trial court did not adopt the proper procedure while
enforcing Section 89 of the Code. Failure to invoke
Section 89 suo moto after completion of pleadings and
8
considering it only after an application under Section 89
was filed, is erroneous.