ThermalProperitiesOfBldg Material Tech v1
ThermalProperitiesOfBldg Material Tech v1
Research Objective: The report focuses on providing the thermal performance of various construction
technologies, essential for sustainable building practices.
State-of-the-Art Facilities: Thermal transmittance (U- value) derivation happens through a rigorous
testing conducted in the state of the art, Guarded Hot Box (GHB).
i
• Part III: Derivation of U-values of Roofing Technologies
This research activity tests ten roofing assemblies for their thermal transmittance value that
may fall in one of the following categories:
1. Conventional Roofing Technologies: This includes business-as-usual roof assemblies such as
RCC slabs, Precast Hollow core slab, decking slab etc. that can be used as reference
baselines.
2. Alternative Roofing Technologies: This category includes region-specific roofing assemblies
used in vernacular architecture such as various kinds of Mangalore tiled roofs, thatch roofs
etc.
3. Emerging Roofing Technologies: This category refers to industrialized roofing technologies,
systems, and/ or products such as Tepper quad bubble deck, Light weight steel gauge roofing
etc.
Table 1: Thermal transmittance value database of all walling assemblies and technologies
Thickness U value
S. No. Wall types
(mm) (W/m2K)
Phase- I
1 Rattrap bond wall 250 2.11
2 Light Gauge framed steel structure with EPS 136 1.37
3 Light Gauge framed steel structure with PPGI Sheet 150 2.12
4 Reinforced EPS core Panel system 150 0.56
5 Glass fibre reinforced Gypsum Panel - Unfilled 124 2.06
Glass fibre reinforced Gypsum Panel - with RCC &
6 124 2.12
non-structural filling
Glass fibre reinforced Gypsum Panel - with partial
7 124 2.13
RCC filling
8 Brick Wall 250 2.41
Structural stay-in-place formwork system (Coffer) –
9 230 0.44
Insulated panel
Phase- II
10 Bamboo Crete 65 2.71
11 Wattle and Daub 45 3.61
12 Stabilized Adobe 230 2.11
13 Laterite Block Wall 205 2.17
14 Unstabilized Adobe 230 2.05
15 Compressed Stabilized Earth Block wall (CSEB) 230 2.79
16 Unstabilized Compressed Earth Block Wall 230 2.74
17 AAC Block Wall with Perlite-based Cement Plaster 230 0.76
18 Unstabilized Rammed Earth 230 2.13
ii
19 Stabilized Rammed Earth 230 2.09
AAC Block Wall with Cement Mortar and Cement
20 230 0.78
Plaster
21 AAC Block Wall with Lime mortar and Lime Plaster 220 0.82
22 Burnt Clay Brick with Lime Mortar and Lime Plaster 250 2.31
23 Limestone with Lime Mortar and Lime Plaster 224 2.84
24 Limestone with Cement Mortar and Cement Plaster 230 2.82
Phase-III
Hollow Clay Brick (100mm thick) with Cement
25 130 2.71
Plaster
Hollow Clay Brick (100mm thick) with Cement
26 158 0.89
Plaster and XPS
Hollow Clay Brick (200mm thick) with Rockwool
27 230 1.28
and Cement Plaster
Hollow Clay Brick (200mm thick) with Cement
28 230 1.83
Plaster
Hollow Clay Brick (200mm thick) with Cement
29 258 0.75
Plaster and XPS
30 RCC Wall (100 mm thick) 100 3.59
31 RCC Wall with EPS 153 0.58
32 RCC Wall with Styrofoam on both sides 154 0.65
33 RCC Wall with PVC panels on both sides 112 2.62
RCC Wall with PVC panels on both side and EPS
34 165 0.52
board
Table 2: Thermal transmittance value database of all roofing assemblies and technologies.
Thickness U-value
S/N Roof Types
(mm) (W/m2K)
1 Flat PUF-insulated roof panels with PPGI sheet 121.4 0.253
2 Curved PUF-insulated roof panels with PPGI sheet 121.4 0.246
TRIMDEK Profile with PUF insulation and
3 76.2 0.255
Aluminum sheet waterproofing
4 Timber + Single sided Mangalore tile roofing 93.0 1.505
5 Timber + Double sided Mangalore tile roofing 105.0 1.117
6 Bamboo + Single sided Mangalore tile roofing 108.0 1.502
7 Bamboo + Double sided Mangalore tile roofing 114.0 1.122
8 Thatch roof 246.0 0.234
9 Thatch roof + XPS insulation 321.0 0.177
Timber + Single sided Mangalore tile roofing +
10 105.0 1.484
Cement Fiber Board
iii
Advancing Building Energy Efficiency in India
Thermal Performance of Walling Material and Wall Technology
iv
October 2022
Supported by
Project Partners
v
Advancing Building Energy Efficiency in India
October 2022
CEPT University
vi
vii
Authors
Dr. Rajan Rawal, CEPT Research and Development Foundation, CEPT University
Dr. Sameer Maithel, Greentech Knowledge Solutions Pvt Ltd.
Dr. Yash Shukla, CEPT Research and Development Foundation, CEPT University
Sonal Kumar, Greentech Knowledge Solutions Pvt Ltd.
Greesha Gowri, CEPT Research and Development Foundation, CEPT University
Jayamin Patel, CEPT Research and Development Foundation, CEPT University
Satyendra Rana, Greentech Knowledge Solutions Pvt Ltd.
Vishnu Vardhan, CEPT Research and Development Foundation, CEPT University
Documentation support
Priyanka Bhanushali, CEPT Research and Development Foundation, CEPT University
Ananthakrishnan Ravi, Greentech Knowledge Solutions Pvt Ltd.
Anandh S Krishna, Greentech Knowledge Solutions Pvt Ltd.
Sneha Asrani, CEPT Research and Development Foundation, CEPT University
Bhavya Pathak, CEPT Research and Development Foundation, CEPT University
Nikhil Bhesaniya, CEPT Research and Development Foundation, CEPT University
Graphics and layout by
Mona Galsar, CEPT Research and Development Foundation, CEPT University
Please cite this document as:
Rawal, R., Maithel, S., Shukla, Y., Rana, S., Gowri, G., Patel, J., Kumar, S. & Vardhan, V., (2022,
October). Thermal performance of walling material and wall technology, Part-1. Retrieved from
http://carbse.org/, https://www.gkspl.in/publications/
Acknowledgements
Shakti Sustainable Energy Foundation works to strengthen the energy security of India by aiding the
design and implementation of policies that support renewable energy, energy efficiency and
sustainable transport solutions. We sincerely thank SSEF for giving the opportunity to explore this
study with the funding support. We also gratefully acknowledge all the brick and block
manufacturers for providing us with necessary study samples.
Disclaimer
The views/analysis expressed in this document do not necessarily reflect the views of Shakti
Sustainable Energy Foundation. The Foundation also does not guarantee the accuracy of any data
included in this publication nor does it accept any responsibility for the consequences of its use.
Supported by
© Shakti Sustainable Energy Foundation
The Capital Court, 104B, 4th Floor,
Munirka Phase III,
New Delhi 110067
Website: https://shaktifoundation.in/
Project Partners
© Greentech Knowledge Solutions Pvt. Ltd. © CEPT Research and Development Foundation
197, Indraprastha Apartment, Pocket 3, (CRDF)
Sector 12, Dwarka, CEPT University
New Delhi -110078 K.L. Campus, Navrangpura, Ahmedabad 380009
Email: [email protected] Email: [email protected]
Website: https://www.gkspl.in/ Website: www.carbse.org
viii
CONTENTS
1. INTRODUCTION .................................................................................................................................. 1
1.1 LITERATURE REVIEW .............................................................................................................................. 2
1.2 REPORT LAYOUT ................................................................................................................................... 4
2. MATERIALS AND MEASUEMENT METHODS ........................................................................................ 5
2.1 SAMPLE COLLECTION ............................................................................................................................. 6
2.2 MEASUREMENT OF PROPERTIES ............................................................................................................... 8
3. RESULTS AND DISCUSSION ................................................................................................................. 9
3.1 FIRED CLAY BRICKS ................................................................................................................................ 9
3.2 NON-FIRED (CURED) BRICKS ................................................................................................................. 12
3.3 COMPARISON OF MATERIAL PROPERTIES ................................................................................................. 16
3.4 CLASSIFICATION OF WALLING MATERIALS ................................................................................................ 21
4. CALCULATION OF RETV ..................................................................................................................... 23
4.1 SAMPLE HOUSING PROJECT .................................................................................................................. 23
5. CONCLUSIONS .................................................................................................................................. 30
6. ANNEXURES...................................................................................................................................... 32
ANNEXURE I: DEFINITIONS ................................................................................................................................. 32
ANNEXURE II: METHODOLOGY FOR MEASUREMENT OF THERMAL PROPERTIES .............................................................. 33
ANNEXURE III: MEASUREMENT DATASHEETS......................................................................................................... 45
7. REFERENCES ................................................................................................................................... 107
ix
List of Figures
Figure 1: Location of all samples collected ......................................................................................... 7
Figure 2: Thermal conductivity as a function of dry density for fired-clay bricks ............................. 11
Figure 3: Thermal conductivity as a function of bulk density for non-fired bricks ............................ 16
Figure 4: Comparison of thermal conductivity of various walling materials ..................................... 17
Figure 5: Comparison of bulk density of various walling materials:.................................................. 18
Figure 6: Comparison of water absorption of various walling materials .......................................... 19
Figure 7: Comparison of compressive strength of various walling materials.................................... 20
Figure 8: Comparison of specific heat capacity of various walling materials .................................... 20
Figure 9: Site plan and typical unit plan of SMARTGHAR-III project, Rajkot ..................................... 24
Figure 10: Thermal transmittance values corresponding to various walling materials for a sample
envelope ........................................................................................................................................... 27
Figure 11: RETV values corresponding to various walling materials for a sample envelope ............ 28
Figure 12: Illustration to explain sample tag..................................................................................... 33
Figure 13: photograph of tagged bricks belonging to set 01 (left) & set 05 (right) .......................... 34
Figure 14: Photograph of thermal constant analyser testing brick samples using transient plane
source method ................................................................................................................................. 35
Figure 15: Illustration showing number of masonry units needed for testing thermal conductivity and
specific heat capacity........................................................................................................................ 36
Figure 16: Photograph of the Inert Gas Oven (left) & bricks prepared for drying (right) ................. 36
Figure 17: Photographs demonstrating different combinations of brick specimens placed for
measurement and hot disk probe sandwiched between two samples of fired clay brick ................ 36
Figure 18: Reference Measurement ................................................................................................. 37
Figure 19: Test Sample Preparation.................................................................................................. 37
Figure 20: Exterior Volume Measurement ....................................................................................... 38
Figure 21: Weight measurement of the dried test sample ............................................................... 38
Figure 22: Specific heat capacity measurement using gold disk sensor ........................................... 39
Figure 23: Illustration showing number of masonry units allotted for testing dry density and water
absorption ........................................................................................................................................ 39
Figure 24: Photograph showing dried sample being weighed to get dry mass (D) ........................... 40
Figure 25: Photograph showing dried brick samples being boiled (left) and brick samples immersed
in water afterwards (right) as per the procedure ............................................................................. 40
Figure 26: Photograph showing measurement of suspended weight (S)(left) and saturated weight
(W)(right) as per the procedure ....................................................................................................... 41
Figure 27: Illustration showing the number of samples required for the compressive strength test.
Left- 5 full sized samples, in case of bricks; Right- 12 samples cut from full blocks, in case of blocks
.......................................................................................................................................................... 42
Figure 28: Photograph of mortar filled bricks ready to be tested..................................................... 44
Figure 29: Photograph of Compression testing machine.................................................................. 44
x
List of Tables
Table 1: Representative thermal parameters of some common solids .............................................. 3
Table 2: State-wise distribution of samples collected. ....................................................................... 6
Table 3: Measured properties and corresponding testing standards & instruments used ................. 8
Table 4: Location and manufacturing process of fired clay samples selected. ................................... 9
Table 5: Average value of measured properties of fired clay samples selected. .............................. 10
Table 6: Source location of the flyash brick samples ........................................................................ 12
Table 7: Average value of measured properties of flyash brick samples .......................................... 13
Table 8: Source location of other non-fired walling material samples ............................................. 14
Table 9: Average value of measured properties of other non-fired walling material samples ......... 15
Table 10: Comparison of thermal conductivity given in ENS and measured values in this study ..... 17
Table 11: Classification of measured parameters based on mean values ........................................ 21
Table 12: Classification of solid bricks and blocks based on their density and their thermo-physical
characteristics................................................................................................................................... 22
Table 13: U-values for different walling material samples ............................................................... 25
Table 14: Number of cut or full-sized samples needed for each test as per standards .................... 33
Table 15: Different types of material samples received for testing and the corresponding
abbreviations assigned to them........................................................................................................ 34
xi
Introduction
1. Introduction
Buildings consume a significant amount of energy, thus contributing to climate change. According to
Energy Statistics (2017) published by the Ministry of Statistics, Planning and Implementation, the
building sector consisting of residential and commercial buildings, consumed nearly a third of the total
electricity produced in the year 2016. The policy think tank of the Government of India, Niti Aayog,
estimated that electricity demand from the building sector will increase by more than 800% in 2047
compared to 2012 (Sumedha Malaviya & Jairaj, 2017). The forecasted increase in electricity demand
by buildings is primarily attributed to the increase in built-up areas and increased use of electricity for
space cooling. As the major chunk of the country’s electricity generation is still being met by burning
fossil fuels, this surge in electricity demand would be detrimental to the environment.
To reduce energy consumption in buildings, the Energy Conservation Building Code (ECBC), was
developed and launched by the Ministry of Power (MoP) and the Bureau of Energy Efficiency (BEE),
Government of India, in May 2007, to set the minimum requirement of energy efficiency for new, large
commercial buildings. A revised version of ECBC was released in 2017 and in 2018, Ministry of Power
(MoP) launched Eco- Niwas Samhita (ENS), which is the Energy Conservation Building Code for
residential buildings. The objective behind implementing these codes is to reduce energy consumption
in newly constructed commercial and residential buildings.
Heat transmission from a building envelope (external walls, windows and roof) constitutes a large part
of the heat gain in a building. Both ECBC and ENS aim at reducing the heat transmission from the
building envelope. ENS defines Residential Envelope Transmittance Value (RETV) as the parameter
which accounts for heat conduction through external walls/windows and solar heat transmission through
window glazing. ENS specifies a maximum value of (15 W/m2) for meeting the RETV criterion. To a
great extent, RETV is dictated by the thermal conductivity value of an external wall. A majority of the
external wall construction in India is masonry construction using solid bricks and blocks. Thus,
exhaustive data of the thermal and physical properties of a wide range of walling bricks and blocks is of
paramount importance in calculating RETV and in the effective implementation of ENS, across different
climatic zones in India.
Thermophysical properties mentioned in the building codes and website of BEE are ‘typical values’
only for a few types of walling materials. Since a wide variety of masonry bricks and blocks is used in
the construction of buildings across the country, showing a large variation in thermophysical properties,
it is imperative to develop a database which can be used for accurate estimation of RETV for the
implementation of ENS and for simulating energy performance of any new or existing building.
To develop such a database a joint project (conducted by GKSPL and CEPT University) was initiated
to collect and test samples of commonly used walling materials. The aim of this project is to build a
nation-wide database of thermophysical properties of a wide range of walling materials used for
construction viz., solid fired clay brick, fly ash brick, concrete block, autoclaved aerated concrete (AAC)
block, cellular light weight concrete (CLC) block and compressed stabilized earth block (CSEB). Only
solid (without any perforations) units that can be measured using uniform protocol have been considered
in this project. Perforated building units require special measurement protocol. This project report
contains the following:
Although the thermal insulation property of a building material strictly depends on many factors, this
project aims at finding a suitable correlation between dry density and thermal conductivity values of
common building materials produced in India. It is intended that the proposed correlation will provide
a priori better estimate of thermal conductivity using the corresponding dry density (easily measurable)
value of a given solid masonry unit.
2 Centre for Advanced Research in Building Science and Energy, CEPT University
Introduction
Inside surface temperatures of walls, floors and roofs of a building envelope need to be estimated in
order to quantify thermal conform. If boundary conditions (temperature and heat flow rate at exposed
surfaces) are not changing with time, a technique of steady state, based on the calculation of the thermal
transmittance (U-value) of the building walls, is used to evaluate the inside surface temperatures. For
one-dimensional steady state conduction, the overall thermal transmittance or U-value (Wm−2 K −1 ) of
a wall composed of plane homogenous isotropic layers of materials is given as:
1
𝑈 = 𝑥𝑖 … (1.1)
∑𝑁
𝑖 =1 𝜆 + 𝑅𝑠𝑖 + 𝑅𝑠𝑜 + 𝑅𝑐
𝑖
Where N is the number of layers in the construction, 𝑥𝑖 (m) the thickness of layer i, 𝜆𝑖 (Wm−1 K −1 ) the
thermal conductivity of layer i, R (m2 KW −1) is the combined radiative and convective thermal
resistance, and subscript si, so, and c refer to the innermost surface, outermost surface and cavity
respectively. This equation shows that under steady state conditions, assessment of thermal performance
of the wall (or thermal comfort of the interior space) is done through an evaluation of its effective
resistance to heat transfer alone.
To understand this assessment, Table 1 gives representative values of thermal parameters for some
common solids used in buildings (Davies, 2004).
𝟑
(𝐦𝟐 /𝐬) (𝐖𝐬𝟎.𝟓 ⁄𝐦𝟐 . 𝐊)
(𝐖⁄𝐦. 𝐊) (𝐤𝐠⁄𝐦 ) (𝐉⁄𝐤𝐠. 𝐊)
Lightweight
0.22 570 840 0.46 324
masonry
Heavyweight
0.90 1850 840 0.58 1183
masonry
Lightweight
0.73 1800 840 0.48 1051
concrete block
Heavyweight
1.31 2240 840 0.70 1570
concrete block
4 Centre for Advanced Research in Building Science and Energy, CEPT University
Materials and Measurement Methods
In India several types of building masonry units are used for construction, predominantly solid bricks
and blocks. At present, 80% of all bricks produced in India are fired clay bricks. In terms of the
production of solid fired clay bricks, India can be broadly divided into two regions – (a) Indo-Gangetic
plain and (b) Peninsular and coastal India. Indo-Gangetic plains accounts for about 70% of total brick
production. Major brick producing states in this region are Punjab, Haryana, Uttar Pradesh, Bihar and
West Bengal. Rest of the 30% of bricks are produced in peninsular and coastal region of India in which
states of Gujarat, Maharashtra, Madhya Pradesh, Odisha, and Tamil Nadu are the main contributors.
In both these regions, the majority of clay bricks are still made manually and are fired in the conventional
Bull’s Trench Kilns and Clamps. A very small proportion of fired clay bricks are made in semi or fully-
mechanized brick plants. Most of the mechanization in the Indian brick industry is found only in the
processes leading to the production of green bricks; i.e. clay extraction, mixing of clay and moulding of
bricks. Barring a handful of plants that use modern tunnel kilns, most mechanized plants are still using
traditional kilns for firing bricks. Solid fired clay bricks produced from mechanized plants are denser
and have higher compressive strength as compared to the hand moulded bricks.
The use of fly ash (a by-product of coal combustion) brick as an alternative to fired clay bricks in
building construction is also slowly gaining steam in India. Yet, these bricks are mostly being used in
construction activities in the urban areas. Fly ash bricks are made in mechanized plants where pan-mixer
is used to mix fly ash with sand, stone-dust, lime and cement to prepare the required blend of mixture.
Bricks are shaped out of this mixture using a vibro-hydraulic power compacting machine and are cured
with water to attain the required strength.
Other less common types of solid bricks or blocks used in construction include solid concrete, calcium
silicate, autoclaved aerated concrete, compressed stabilized earth block, etc. Similar to fly ash bricks,
these alternative building units are also produced in semi-mechanized or mechanized plants where a
particular proportion of raw materials is mixed together using a mixer, and bricks or blocks are moulded
using the resultant mixture.
It was decided therefore to collect samples of building materials from different parts of the country in
order to encompass the effect of diverse material composition and manufacturing processes on material
properties.
A total of sixty-two samples were collected from thirteen different states of India to represent the wide
range of solid masonry building units used in construction. Individual datasheets containing information
about the collection site and manufacturing processes are given in the annexure. Table 2 shows the
details of state-wise distribution of samples collected for measurements and Figure 1 shows their
location on the map.
6 Centre for Advanced Research in Building Science and Energy, CEPT University
Materials and Measurement Methods
CSEB
AAC
Concrete Brick
1. Thermal conductivity
2. Specific heat
3. Dry density
4. Water absorption
5. Compressive strength.
Annexure I provides definitions of all the tested parameters. Table 3 describes the instruments used and
applicable testing standards followed by CARBSE for testing each parameter. Thermal conductivity and
specific heat were measured using Thermal Constants analyser as per ISO/DIS 22007-2:2015 as seen in
Table 3. Similarly, dry density, water absorption, and compressive strength were measured following
specific standards of measurement as seen in Table 3. The testing procedure specifying environmental
conditions and sample requirements for each parameter is elaborated along with photographs of the
samples in Annexure II.
Table 3: Measured properties and corresponding testing standards & instruments used
Applicable Testing
S/N Testing parameter Instrument
Standard
ISO/DIS 22007-2:2015
Thermal Conductivity and
1 Thermal Constants Analyser (for both bricks and
Specific heat
blocks) (ISO, 2008)
8 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
The annexure III contains individual datasheets with the measured thermophysical properties of all the
sixty-two samples. The number of samples collected are sufficient to statistically determine a correlation
between any two parameters. Only fired clay bricks and non-fired or cured bricks are considered for
examining the influence of dry density on thermal conductivity.
10 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
Analysis of the data presented in Table 5 shows that the dry density and thermal conductivity of hand-
moulded bricks -show a wide range from 1264 − 1887 kg⁄m3 and 0.38 − 0.76 W⁄m. K respectively,
whereas the dry density and thermal conductivity for machine moulded (extruded or soft-mud moulded)
bricks varies between 1648 − 2119 kg⁄m3 and 0.41 − 1.12 W⁄m. K respectively.
Figure 2 shows the variation of thermal conductivity with dry density for fired clay bricks. Using
Microsoft Excel, an exponential correlation is fit to the data. Goodness of fit (𝑅 2 = 0.70) shows that
dry density is a major factor that governs thermal conductivity of solid fired clay bricks. Thus, for a
given value of dry density 𝜌 (kg⁄m3 ), the following equation can be used to make an estimation of
thermal conductivity 𝜆 (W⁄m. K) for fired clay bricks:
1.00
y = 0.0652e0.0012x
R² = 0.77
0.80
0.60
0.40
0.20
0.00
1200 1400 1600 1800 2000 2200
Bulk Density, ρ (kg/m3)
12 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
Bulk
Density Thermal Specific heat Compressive Water
conductivity strength
S.No Sample absorption
𝝆 𝝀 𝑪𝒑 (%)
(𝐤𝐠⁄𝐦𝟑 (𝐖⁄𝐦. 𝐊) (𝐉⁄𝐤𝐠. 𝐊) (𝐌𝐏𝐚)
)
The bulk density and the thermal conductivity of fly ash bricks show a wide range, ranging from 1299 −
2048 kg⁄m3 and 0.36 − 0.97 W⁄m. K , respectively. Table 8 shows the sample type and location and
Table 9 shows average value of measured properties of other non-fired walling material samples tested.
14 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
Table 9: Average value of measured properties of other non-fired walling material samples
Figure 3 shows the variation of thermal conductivity with bulk density for non-fired bricks. Using
Microsoft Excel, an exponential correlation is fit to the data1. Goodness of fit (𝑅 2 = 0.68) indicates that
bulk density has a significant impact on thermal conductivity.
For a given value of bulk density 𝜌 (kg⁄m3 ), the following equation can be used to build an estimate of
thermal conductivity 𝜆 (W⁄m. K) for non-fired bricks:
Non-Fired Bricks
1.20
Thermal Conductivity, , λ (W/mK)
1.00
y = 0.1009e0.0011x
0.80 R² = 0.68
0.60
0.40
0.20
0.00
500 700 900 1100 1300 1500 1700 1900 2100 2300
Bulk Density, ρ (Kg/m3)
1For the analysis outlier data of samples CB01 (Phase I) and CC01 and CC02 (both Phase II) have been
excluded.
16 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
Table 10: Comparison of thermal conductivity given in ENS and measured values in this study
2Refer Table 7: Thermal properties of building and insulation materials, page 23 Eco-Niwas Samhita 2018: Part I:
Building Envelope
1000
732
616
500
0
Fired Clay Fired Clay Fired Clay Flyash Bricks Concrete CSEB CLC AAC
(Hand (Soft Mud (Extruded) Block
Moulded) Moulded)
18 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
60.0
53
50.0
40.0
30.0
20.0 18.0 16.4 17.6 16.7
10.0 11.2 8.8
0.0
Fired Clay Fired Clay Fired Clay Flyash Bricks Concrete CSEB CLC AAC
(Hand (Soft Mud (Extruded) Block
Moulded) Moulded)
60.00
50.00
40.00
33.93
30.00
20.00
13.44 11.74 11.42 13.18
10.00
5.91
2.20 3.05
0.00
Fired Clay Fired Clay Fired Clay Flyash Bricks Concrete CSEB CLC AAC
(Hand (Soft Mud (Extruded) Block
Moulded) Moulded)
1050
1000
961 957
950
930 934 936
922 922
900
850 853
800
Fired Clay Fired Clay Fired Clay Flyash Bricks Concrete CSEB CLC AAC
(Hand (Soft Mud (Extruded) Block
Moulded) Moulded)
20 Centre for Advanced Research in Building Science and Energy, CEPT University
Results and Discussions
The tested solid bricks and blocks are classified into three categories (heavy density, medium density,
and low density) and their thermo-physical characteristics are shown in Table 12. For easy interpretation,
each cell is colour coded. The colour represents whether that parameter falls under Low, Medium, and
High category as per classification given in Table 11.
Thermal
Conductivity ≤ 0.3 0.3 <x ≤ 0.8 > 0.8
(W/m.K)
Volumetric Heat
Capacity 500 < x ≤ 1000 1000 < x ≤ 1750 1750 < x ≤ 2250
(kJ/kg.m3)
22 Centre for Advanced Research in Building Science and Energy, CEPT University
Calculation of RETV
4. Calculation of RETV
The residential envelope transmittance value (RETV) is a measure of the average external heat gain into
a building, normalized over all hours throughout the year and averaged over the entire envelope area of
the building. It is quantified from three basic components of heat gain through external walls and
windows of the building:
The examination of RETV brings out the strong influence of external walls, glazing types and external
shading devices on steady state thermal performance of the whole building envelope. As mentioned in
Eco-Niwas Samhita (ENS) or Energy Conservation Building Code for residential buildings, for the
purpose of energy conservation, the maximum permissible RETV has been set at 15 W⁄m2 (BEE,
2017).
In this chapter, for a sample building envelope, RETV has been calculated in correspondence to different
external wall materials where other components affecting RETV are taken as constant. This enables the
selection of building material in order to improve energy efficiency in residential buildings.
Figure 9: Site plan and typical unit plan of SMARTGHAR-III project, Rajkot
Table 13 provides U-value of 200mm thick wall of each tested walling unit, with 15mm plaster on both
sides. Figure 11 shows the residential envelope transmittance values (RETV) for the given sample
housing envelope taking different external wall materials.
24 Centre for Advanced Research in Building Science and Energy, CEPT University
Calculation of RETV
The U-value of the 230 mm thick wall made from different type of solid bricks was found to vary
between 0.7 W/m2.K to 2.93 W/m2.K as shown in Figure 10.
26 Centre for Advanced Research in Building Science and Energy, CEPT University
Calculation of RETV
Figure 10: Thermal transmittance values corresponding to various walling materials for a sample envelope
Figure 11: RETV values corresponding to various walling materials for a sample envelope
28 Centre for Advanced Research in Building Science and Energy, CEPT University
Calculation of RETV
Following conclusions can be drawn based on the analysis of the U-value of the standard wall with 230
mm thickness (200 mm brick + 15 mm plaster) and RETV calculations for a specific tower of Smart
GHAR 3 project located at Rajkot (composite climate):
• The choice of brick to construct external wall (U-value ranging between 0.7 W/m2K to 2.93
W/m2K) has a large impact on the RETV value. The maximum value of RETV for Smart GHAR-
3 is 19.65 W/m2, which is more than double the minimum RETV of 9.13 W/m2. Thirty-one, out
of forty-two solid brick types meet the RETV threshold of 15 W/m2 as specified by Eco-Niwas
Samhita, 2018.
• AAC and CLC blocks have the lowest U value (~ 0.8 W/m2K) and lowest RETV value (~ 9.5
W/m2), which is well below the RETV threshold of 15 W/m2.
• Solid concrete and calcium silicate bricks exhibit high U value (~ 2.0 to 3.0 W/m2K) and RETV,
generally exceeding the threshold of 15 W/m2.
• Commonly available hand moulded fired clay (excluding extruded bricks) and fly ash bricks
exhibit moderate U value (1.3 – 2.25 W/m2K) and in majority of cases meet the RETV threshold
of 15 W/m2.
5. Conclusions
1. The project collected and tested sixty-two samples of 11 types of solid bricks and blocks from
14 states of the country covering variation in material composition and manufacturing process
employed. Each of the sixty-two sample sets were characterized for the following properties.
• Thermal conductivity
• Specific heat
• Bulk density
• Water absorption
• Compressive strength.
2. The tested bricks can be classified under three categories
Heavy density bricks (>1800 kg/m3): Extruded fired clay brick, solid concrete and calcium
silicate brick can be classified as heavy density bricks. Characteristics based on mean of the
tested values are:
o Physical characteristics: Low water absorption (≤12%) and high compressive strength (>15
N/mm2).
o Thermal characteristics: High thermal conductivity (> 0.8 W/m.K) and high volumetric heat
capacity (> 1750 kJ/kg.m3).
Application: Suitable for use in load bearing construction. High dead load is a disadvantage for
their application in mid- and high-rise buildings. The material can be used to provide high
thermal mass.
Medium density bricks (1000-1800 kg/m3): Hand moulded clay fired bricks, fly ash bricks,
CSEB blocks and C&D/Surkhi bricks can be classified as medium density bricks.
Characteristics based on mean of the tested values are:
Application: These are the most commonly used bricks, and they can be used both for load
bearing as well as in frame construction.
Low density bricks (< 1000 kg/m3): AAC, CLC and expanded clay aggregate bricks can be
classified as low-density bricks. Characteristics based on mean of the tested values are:
o Physical characteristics: High water absorption (>30%) and low compressive strength (<3.5
N/mm2).
30 Centre for Advanced Research in Building Science and Energy, CEPT University
Conclusions
o Thermal characteristics: Low thermal conductivity (≤ 0.3 W/m.K) as well as low volumetric
heat capacity ( 500 -1000 kJ/kg.m3) .
Application: These bricks are not suitable for load bearing construction and generally used as
walling material in framed construction. When used in mid- and high-rise construction, apart
from better thermal insulation, they bring additional advantage of low weight and hence savings
in the structural cost. Suitable care needs to be taken during construction to avoid formation of
cracks and water leakage.
3. For a specific type of brick, a large variation in thermal conductivity and bulk density was
observed. For example, the measured thermal conductivity values for solid fired clay brick were
found to vary from 0.38 to 1.12 W/m.K. Correlations have been developed between the bulk
density and the thermal conductivity for fired clay bricks and non-fired bricks, these are as
follows:
• Fired clay brick: For a given value of bulk density 𝜌 (kg⁄m3 ), the following equation can
be used to make an estimation of thermal conductivity 𝜆 (W⁄m. K).
• Non-fired brick: For a given value of bulk density 𝜌 (kg⁄m3 ), the following equation can
be used to build an estimate of thermal conductivity 𝜆 (W⁄m. K).
4. It is recommended that BEE can take action to amend the database of thermal properties values
given in Table 7 of Eco-Niwas Samhita: Part I (2018). The results show that the mean values of
thermal conductivity given in ENS for all common walling materials (except AAC block) are
significantly higher (28-53%) compared to the mean values reported in this study. This means
that using the thermal conductivity values given in ENS is likely to result in higher RETV
estimations. Also, the correlations can be included in Eco-Niwas Samhita so that by measuring
the bulk density, thermal conductivity of the brick can be determined for RETV calculations.
5. U-value of 200 mm bricks wall with 15 mm plaster on both sides (total wall assembly thickness
of 230 mm) was calculated for the tested bricks. The highest U-value of 2.93 W/m2.K was more
than four times higher compared to the lowest U-value of 0.7 W/m2.K. Further RETV value for
a sample affordable housing project located at Rajkot was calculated for the tested bricks. It was
observed that the choice of brick to construct external wall has a large impact on the RETV
value. For the given project, the maximum value of RETV was 19.65 W/m2, which is more than
double the minimum RETV of 9.13 W/m2. Thus, choice of brick for the external walls is a key
to meet the RETV standard of Eco-Niwas Samhita.
6. Annexures
Annexure I: Definitions
Thermal conductivity
As per IS 3069:1994 thermal conductivity is defined as “the time rate of heat flow through unit thickness
of an infinite slab of a homogeneous material in a direction perpendicular to the surface, induced by unit
temperature difference”. It is expressed in W/m-K as per the measurement standard ISO/DIS 22007-
2:2015.
As per IS 3069:1994 (BIS, 1994) volumetric specific heat or heat capacity per unit volume is defined as
“the quantity of heat required to raise the temperature of unit volume by one degree”. It is expressed in
MJ/m3K as per measurement standard ISO/DIS 22007-2:2015.
Water absorption
As per IS2248:1992 (BIS, 1992a) water absorption is defined as “the increase in weight of a test
specimen after immersion in water, at a constant temperature and for a specified period, expressed as a
percentage of the dry weight”.
Bulk density
As per ASTM C20 “the bulk density of a specimen in grams per cubic centimetre is the quotient of its
dry weight divided by the exterior volume, including pores”. It is expressed in Kg/m3 as per IS
3069:1994. For walling units such as bricks and blocks, the dry density is equivalent to bulk density.
Compressive strength:
As per IS 3069:1994 the compressive strength of a material is defined as “the capacity of a material to
withstand mechanical pressure up to the point of fracture, and in the case of materials which do not fail
by shattering, the compressive strength may be deduced arbitrarily from a load deformation curve.”
Measured in N/mm2 as per measurement standard IS 3495 (part1):1992.
32 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure II
Based on the applicable standards, a definite number of samples were required for testing each parameter
mentioned in Section 2.2. Table 14 shows the number of samples needed for each test as per standards
(cut or full-sized samples). In case of bricks full size samples were required and the blocks were cut to
smaller sizes to match the brick size for all tests.
Table 14: Number of cut or full-sized samples needed for each test as per standards
Figure 13: photograph of tagged bricks belonging to set 01 (left) & set 05 (right)
Sample tag
Each of the received sixty-two material samples were visually inspected for damages and were marked
with a sample tag name based on the material type (abbreviated name of the material), the sample and
specimen number as seen in Figure 12. Table 15 shows the different abbreviations assigned to the tested
materials. For example, first sample set of fired clay bricks despatched to CARBSE was tagged as
’RB01’ where, RB represents fired clay brick and ‘01’ is the 1st sample. Further, for testing purpose
individual brick/test specimens were named in a numerical order. For example, each brick within the
first sample set of fired clay brick was tagged from RB0101 to RB0120 (i.e., 20 bricks of set 01 of fired
clay brick) as seen in Figure 13. The tagged samples were safely stored in their respective packaging
until the time of testing. The tested samples were marked with the letter ’T’ and stored separately in case
further retesting was necessary.
Table 15: Different types of material samples received for testing and the corresponding abbreviations assigned
to them.
34 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure II
Testing procedure
Thermal Conductivity:
Thermal conductivity was determined for each material type using the transient plane heat source (hot
disc) method and the reference standard used is ISO/DIS 22007-2:2015. The main instrument used is
Hot Disk TPS 2500S as seen in Table 3. Additionally, the Inert Gas Oven was used for preconditioning
the samples as described below.
Figure 14: Photograph of thermal constant analyser testing brick samples using transient plane source method
Preconditioning
1. Three masonry unit samples as shown in Figure 15 was dried in the inert gas oven at a
temperature of 105 °C for the period of 24 hrs. as seen in Figure 16.
2. After drying, all 3 specimens were conditioned at 22 °C and 50 % RH until less than 1 % mass
change is observed over 24 hrs. period (maintained in the lab) (ISO, 2015).
Measurement
Thermal conductivity was measured at 25 ± 1 °C and 50% ± 10% RH conditions using Thermal constant
analyzer in accordance with transient plane source method as seen in Figure 14Figure 14. The procedure
was followed through as per ISO/DIS 22007-2:2015.
Calculation
As per standard procedure the hot disk probe operating as a temperature sensor was placed sandwiched
between two brick/block specimens for measurement. 10 measurements were carried out by using
random combinations of 3 specimens as shown in Figure 17 and the average was reported.
Figure 15: Illustration showing number of masonry units needed for testing thermal conductivity and specific
heat capacity
Figure 16: Photograph of the Inert Gas Oven (left) & bricks prepared for drying (right)
Figure 17: Photographs demonstrating different combinations of brick specimens placed for measurement and
hot disk probe sandwiched between two samples of fired clay brick
36 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure II
Specific Heat:
While preparing the brick samples for hygrothermal measurements, significant random cavity spots
were observed in the brick samples. Hence, specific heat capacity of brick was measured using gold disk
sensor in the Transient Plane Source set up. The refined measurement procedure is described below:
Procedure
1. Initially a reference measurement was carried out by keeping the gold disk sensor empty as seen
in Figure 18.
2. A small homogeneous piece of brick (test sample) without any air cavity was cut from the
conditioned brick as seen in Figure 19.
3. As seen in Figure 20, a beaker was fully filled with water letting the excess water drop out of it.
The test sample was dropped into the beaker and the weight of the displaced water due to its
submersion was measured. Using the values of the weight of the displaced water and the density
of water, the exterior volume of the test sample was calculated.
38 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure II
5. Five measurements of specific heat capacity (per unit mass) were carried out by keeping the
sample in the gold disk sensor as seen in Figure 227, and providing values of the reference
measurement, the exterior volume and the weight of the test sample of the brick.
Figure 22: Specific heat capacity measurement using gold disk sensor
Dry density:
Dry/ Bulk density was measured based on ASTM C20. The Instruments used were Inert gas oven, water
bath and precision weighing. Since measurement for dry density and water absorption (explained further
in the next section) involves the same procedure as per respective standards, the same set of samples
were used to characterize both parameters.
Measurement
1. Five bricks or three block sample as seen in Figure 238, were dried at a temperature of 105 °C
until a constant mass was achieved.
2. After drying, the sample was cooled to room temperature and its weight was obtained, denoted
by dry mass (D) as seen in Figure 24.
3. After dry mass measurement, the sample was submerged into boiling water for the period of 2
hours as seen in Figure 25.
Figure 23: Illustration showing number of masonry units allotted for testing dry density and water absorption
Figure 24: Photograph showing dried sample being weighed to get dry mass (D)
Figure 25: Photograph showing dried brick samples being boiled (left) and brick samples immersed in water
afterwards (right) as per the procedure
4. After the boiling period, samples were cooled to room temperature while still completely
covered with water. Samples were kept immersed in water for 22 hrs. as seen in Figure 25 before
weighing again.
5. Suspended weight (S) of each sample was measured while suspended in water as per the
procedure in ASTM C20 seen in Figure 26.
40 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure II
6. After determining the suspended weight, excess water was removed by blotting each sample
lightly with a moistened smooth linen or cotton cloth.
7. Saturated weight (W) was obtained by weighing the sample in air as per the procedure in ASTM
C20 seen in Figure 26.
Calculation
After measuring Dry Weight (D), Suspended Weight (S), and Saturated Weight (W) in Kg below
calculations were carried out to determine the Block Density (ASTM International, 2010).
Figure 26: Photograph showing measurement of suspended weight (S)(left) and saturated weight (W)(right) as
per the procedure
Water Absorption:
Water absorption was measured based on IS 3495 (for bricks) and IS 2185 (for blocks). The Instruments
used were Inert gas oven and precision weighing scale as shown in Figure 161 and Figure 24,Figure 250
(right) and Figure 261 (right).
Measurement
1. Five brick or three block samples, as seen in Figure 23 were dried at a temperature of 105 °C until
a constant mass was achieved.
2. After drying, the sample was cooled to room temperature and its weight was obtained, denoted by
dry weight (M1) as seen in Figure 24.
3. After dry weight measurement, the sample was submerged into clean water kept at a temperature of
27 ± 2°C for 24 hours as seen in Figure 250 (right).
4. After 24 hours, excess water was removed by blotting each sample lightly with a moistened smooth
linen or cotton cloth and Saturated weight (M2) was obtained by weighing the sample.
Calculation
After measuring Dry Weight (M1), and Saturated Weight (M2) in Kg below calculations were carried
out to determine the Water Absorption (Bureau of Indian Standards (BIS), 1992).
𝑀2−𝑀1
Water Absorption = X 100 %
M1
Compressive Strength
Compressive strength was measured based on IS 3495 for bricks and IS 2185 for blocks. The instrument
used was the Compression testing machine.
Preconditioning
1. Five brick/twelve block samples as seen in Figure 27 with smooth even surfaces were immersed
in water at room temperature for 24 hrs.
2. The samples were removed, and surplus moisture was drained out.
Figure 27: Illustration showing the number of samples required for the compressive strength test. Left- 5 full
sized samples, in case of bricks; Right- 12 samples cut from full blocks, in case of blocks
42 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure II
3. The frog in case of bricks and any other voids in the brick bed face was made even with cement
mortar filling as seen in Figure 28.
4. The samples were then stored under damp jute bags for 24 hrs. followed by immersion in clean
water for 3 days.
5. After this process, excess moisture was wiped clean from the samples.
Measurement
1. The clean sample was placed within the machine with mortar fill facing upwards between two
to three plywood sheets of 3mm thickness, centred between the two plates of the machine as
seen in Figure 29, and load was applied axially at a uniform rate of 14 N/mm2 per minute till
failure occurred.
2. Maximum load at failure was noted.
Calculation
44 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 01
General information
Sample type
LMB Bricks,
Address/Contact Mr. Ashok Tiwari,
President, Bengal Brick Field Owners Association
Datasheet 02
General information
Sample type
Electricity
15,500 kWh per month
consumption
Production
10,000 bricks in 8 hours.
capacity
Maya Ashtech
Address/Contact
Mr. Devanand Jewani (+91-9830804971)
46 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 03
General information
Sample type
Datasheet 04
General information
Sample type
48 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 05
General information
Sample type
Datasheet 06
General information
Sample type
Kumar bricks
Address/Contact
Mr. Vijay
50 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 07
General information
Sample type
Datasheet 08
General information
Sample type
Datasheet 09
52 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
General information
Sample type
Datasheet 10
General information
Sample type
Bharat bricks
Address/Contact
Mr. Kulbhushan, +91-9425052825
54 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 11
General information
Sample type
Bharat bricks
Address/Contact
Mr. Kulbhushan, +91-9425052825
Datasheet 12
General information
Sample type
56 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 13
General information
Concrete brick
Sample type
Datasheet 14
General information
Sample type
58 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 15
General information
Sample type
Datasheet 16
General information
Sample type
60 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 17
General information
Sample type
Datasheet 18
General information
Sample type
62 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 19
General information
Sample type
Datasheet 20
General information
Sample type
64 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 21
General information
Sample type
Datasheet 22
General information
Sample type
66 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 23
General information
Sample type
Location Nagpur
Datasheet 24
General information
Sample type
Location Nagpur
68 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 25
General information
AAC block
Sample type
Datasheet 26
General information
Sample type
70 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 27
General information
Sample type
Datasheet 28
General information
Sample type
72 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 29
General information
Concrete block
Sample type
Raw material Stone dust, cement, and aggregate (M10 concrete mix)
• Mixture preparation: Pan-mixer is used to mix raw
material (Cement + stone dust + 6mm aggregate)
Production processes
• Shaping: Bricks are shaped by a double-vibro-hydraulic
power compacting machine and then cured by water.
Production capacity 12,000 blocks per week
Venus Concrete Products
Address/Contact Rajesh V. (+91-9611554455)
Production units = 1) Bommanahalli 2) Anekal
Datasheet 30
General information
Sample type
74 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 31
General information
Concrete block
Sample type
Raw material Stone dust, cement, lime, fly ash and coarse aggregate
Datasheet 32
General information
Sample type
Raw material Excavated clay, fly ash, bottom ash and paddy husk
• Bricks are fired in a clamp.
• Government supplied clay excavated from lakes
• Internal fuel: NTPC Ramagundam fly ash + paddy husk +
boiler ash
• Coal: Singareni mines
Production processes • Composition
▪ NTPC ash: 28 tractors (3 ton/ tractor) = 84 ton
▪ Clay: 24 tractors (3 ton/tractor) = 72 ton
▪ Husk: 6 ton
▪ Boiler ash: 6 ton
▪ ~ 54% ash w/w
Fuel consumption Coal: 17 ton per two lakh bricks
• 2 lakh bricks per clamp (15 days cycle)
Production capacity
• 30 lakh bricks per year
NBC Brick kiln - Mr. Nageshwar Rao – (+91-9440501259)
Address/Contact
Tata Trust – Ms. Sarah Khosla – (+91-8280569700)
76 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 33
General information
Sample type
Datasheet 34
General information
Solid burnt clay brick
Sample type
78 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 35
General information
Sample type
Datasheet 36
General information
Sample type
Raw material Fly ash, pond ash, stone dust, granite dust and cement
• Mixture preparation: Pan-mixer is used to mix raw
material (20 kg Fly ash + 20 kg Pond ash + 30 kg stone
Production processes dust + 30 kg Granite dust + 4 kg Cement)
• Shaping: Bricks are shaped by a vibro-hydraulic power
compacting machine and then cured by water.
Address/Contact P K Bricks (+91-9443461272)
80 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 37
General information
Sample type
Datasheet 38
General information
Sample type
82 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 39
General information
Sample type
Datasheet 40
General information
AAC block
Sample type
84 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 41
General information
Sample type
Datasheet 42
General information
Sample type
86 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 43
General information
Concrete Block
Sample type
Datasheet 44
General information
Concrete Block
Sample type
88 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 45
General information
Concrete Block
Sample type
Datasheet 46
General information
Sample type
90 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 47
General information
Sample type
Datasheet 48
General information
Sample type
92 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 49
General information
Sample type
Location Puducherry
Datasheet 50
General information
Sample type
94 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 51
General information
Sample type
Datasheet 52
General information
Sample type
96 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 53
General information
Sample type
• Raw materials are mixed with water, and are moulded in the
Production processes form of blocks by hydraulic press
• The moulded blocks are cured with water for strength
Address/Contact Ace Infracon Products
Datasheet 54
General information
Sample type
• Raw materials are mixed with water, and are moulded in the
Production processes form of blocks by hydraulic press
• The moulded blocks are cured with water for strength
Address/Contact OASIS Enterprises
98 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 55
General information
Sample type
Raw material Fly Ash, Stone Crusher Dust, Lime, Plaster of Paris
• Raw materials are mixed with water, and are moulded in the
Production processes form of blocks by hydraulic press
• The moulded blocks are cured with water for strength
Address/Contact Bairwa Ash Bricks Store
Datasheet 56
General information
Sample type
100 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 57
General information
Sample type
Datasheet 58
General information
Sample type
102 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 59
General information
Sample type
Datasheet 60
General information
Sample type
104 Centre for Advanced Research in Building Science and Energy, CEPT University
Annexure III
Datasheet 61
General information
Sample type
Datasheet 62
General information
Sample type
106 Centre for Advanced Research in Building Science and Energy, CEPT University
7. References
ASTM. (2015). ASTM C20-2015: Standard Test Methods for Apparent Porosity, Water Absorption,
Apparent Specific Gravity, and Dry density of Burned Refractory Brick and Shapes by Boiling
Water 1. ASTM International. https://doi.org/10.1520/C0020-00R15
BIS. (1992a). IS 2248 (1992): Glossary of terms relating to clay products for buildings.
BIS. (1992b). IS 3495-1 to 4 (1992): Methods of tests of burnt clay building bricks: Part 1 Determination
of compressive strength Part 2 Determination of water absorption Part 3 Determination of
efflorescence, Part 4: Determination of warpage.
BIS. (1994). IS 3069 (1994): Glossary of terms, symbols and units relating to thermal insulation
materials.
BIS. (2005). IS 2185-1 (2005): Part 1-4: Concrete masonry units - specifications.
Dondi, M., Mazzanti, F., Principi, P., Raimondo, M., & Zanarini, G. (2004). Thermal Conductivity of
Clay Bricks. In Journal of Materials in Civil Engineering (Issue 1).
Gualtieri, M. L., Gualtieri, A. F., Gagliardi, S., Ruffini, P., Ferrari, R., & Hanuskova, M. (2010).
Thermal conductivity of fired clays: Effects of mineralogical and physical properties of the raw
materials. Applied Clay Science, 49(3), 269–275. https://doi.org/10.1016/j.clay.2010.06.002
ISO. (2008). ISO 22007-2:2008(E) ISO 22007-2 Plastics-Determination of thermal conductivity and
thermal diffusivity.
Sumedha Malaviya, S., & Jairaj, B. (2017). India’s Move to Make Buildings Efficient | World Resources
Institute. https://www.wri.org/blog/2017/11/indias-move-make-buildings-efficient
107
Advancing Building Energy Efficiency in India
108
October 2022
Supported by
Project By
Construction Agency
109
Advancing Building Energy Efficiency in India
October 2022
MAT Lab
110
Authors
Dr. Rajan Rawal, CEPT Research and Development Foundation, CEPT University
Dr. Yash Shukla, CEPT Research and Development Foundation, CEPT University
Agam Shah, CEPT Research and Development Foundation, CEPT University
Greesha Gowri, CEPT Research and Development Foundation, CEPT University
Bhavya Pathak, CEPT Research and Development Foundation, CEPT University
Prof. Sankalpa, CEPT University
Manu Narendran, MAT-Lab
Nikhil Bhesaniya, CEPT Research and Development Foundation, CEPT University
Subham Das, CEPT Research and Development Foundation, CEPT University
Documentation support
Please cite this document as: Rawal, R., Shukla, Y., Shah, A., Gowri, G., Pathak, B., Sankalpa,
Narendran, M., Bhesaniya, N., & Das S., (2022, October). Thermal performance of walling material
and wall technology, Part-2. Retrieved from http://carbse.org/.
Acknowledgements
We sincerely thank SSEF for giving the opportunity to explore the study with the funding support. We
gratefully acknowledge all the wall assembly manufacturers for providing us with the necessary study
sample. We also acknowledge MAT-Lab and the supporting artisans for expert execution of all the
traditional wall assembly samples.
111
Disclaimer
The views/analysis expressed in this document do not necessarily reflect the views of the funding
agencies. The funding agencies also does not guarantee the accuracy of any data included in this
publication nor does it accept any responsibility for the consequences of its use.
Phases I and II were supported by SSEF and included the testing of following technologies:
1. Rat-trap bond wall
2. Light Gauge framed steel structure with EPS
3. Light Gauge framed steel structure with PPGI Sheet
4. Reinforced EPS core Panel system
5. Glass fibre reinforced Gypsum Panel -Unfilled
6. Glass fibre reinforced Gypsum Panel -with RCC & non-structural filling
7. Glass fibre reinforced Gypsum Panel -with partial RCC filling
8. Burnt clay brick wall
9. Structural stay-in-place formwork system with Insulated panel
10. Bamboo Crete
11. Wattle and Daub
12. Stabilized Adobe Wall
13. Laterite Block Wall
14. Unstabilized Adobe Wall
15. Compressed Stabilized Earth Block (CSEB) wall
16. Unstabilized Compressed Earth Block (CEB) Wall
17. AAC Block with Perlite-based cement plaster
18. Unstabilized Rammed Earth
19. Stabilized Rammed Earth
20. AAC Block wall with cement mortar and cement plaster
21. AAC Block wall with lime mortar and lime plaster
22. Burnt Clay Brick wall with lime mortar and lime plaster
23. Limestone block wall with cement mortar and cement plaster
24. Limestone block wall with lime mortar and lime plaster
Phase III was supported by NVF and included the testing of following technologies:
1. Hollow clay brick (100 mm thickness) with cement plaster
2. Hollow clay brick (100 mm thickness) with cement plaster and XPS
3. Hollow clay brick (200 mm thickness) with rockwool and cement plaster
4. Hollow clay brick (200 mm thickness) with cement plaster
5. Hollow clay brick (200 mm thickness) with cement plaster and XPS
6. RCC Wall (100 mm Thickness)
7. RCC Wall (100 mm Thickness) with EPS
8. RCC Wall (100 mm Thickness) with Styrofoam on both sides
9. RCC Wall (100 mm Thickness) with PVC Panels on both sides
10. RCC Wall (100 mm Thickness) with EPS Board on one side and PVC Panels on both sides
112
CONTENTS
1. Introduction ............................................................................................................................. 122
2. Assessment of Research Lab capacity and capabilities ............................................................... 123
2.1 CARBSE, CEPT University, Ahmedabad .................................................................................. 123
2.2 Guarded Hot Box (GHB) ......................................................................................................... 123
3. Testing Procedure .................................................................................................................... 125
3.1 General Procedure................................................................................................................. 125
3.2 GHB testing procedure for masonry walls ............................................................................. 125
3.3 GHB Testing Procedure of BMTPC Certified Walls: ................................................................ 125
4. Identification of Walling Technologies ...................................................................................... 127
4.1 Sampling criteria .................................................................................................................... 127
4.2 Selected Walling Technologies .............................................................................................. 129
4.3 Procurement of Samples ....................................................................................................... 130
5. Results ..................................................................................................................................... 133
6. Annexures ................................................................................................................................ 136
Annexure I: Summary of the Selected Walling Technologies ...................................................... 136
Annexure II: Schematic Drawings of the Test Samples ................................................................ 199
7. References ............................................................................................................................... 241
113
LIST OF FIGURES
Figure 1: Project outline and research activity protocol...................................................................... 122
Figure 2: Exploded view of the Guarded Hot-Box apparatus. .............................................................. 123
Figure 3: Photographs of the metering chamber attached to the specimen frame and the entire
assembly of GHB opened up and closed. ............................................................................................. 124
Figure 4: Sectional illustration of the Guarded Hot Box (GHB) apparatus ........................................... 124
Figure 5: Photographs showing thermal imaging (left) and testing of Rattrap bond wall assembly in
GHB ...................................................................................................................................................... 126
Figure 6: Photographs showing sealing procedure with XPS (left) and silicone sealant (right) to avoid
heat transfer through gaps .................................................................................................................. 126
Figure 7: Cover pages of 3 different editions of BMTPC Compendium of Prospective Emerging
Technologies for Mass Housing. .......................................................................................................... 127
Figure 8: Cover page of the latest Annual report by MoHUA (left) and the list of 16 technologies
assigned to be adopted for PMAY mission (right) ................................................................................ 128
Figure 9: Thermal performance evaluation of the selected wall assemblies. ...................................... 135
Figure 10: Photograph of a housing project by Laurie Baker employing rat-trap bond wall assembly.136
Figure 11: Different brick faces used in wall construction (left) and 3d illustration of a typical Rat-trap
bond Wall (right). ................................................................................................................................. 137
Figure 12: Photographs showing the construction of Rat-trap bond wall within the specimen frame of
GHB. ..................................................................................................................................................... 137
Figure 13: Photograph showing walls and floor plates of LGFSS assembled at a site. ......................... 138
Figure 14: 3D illustration of LGFSS - EPS with specifications ............................................................... 139
Figure 15: 3D illustration of LGFSS – PPGI sheet with specifications. .................................................. 139
Figure 16: Photographs of LGFSS with EPS wall sample (left) & the sample wall installed within the
specimen frame of GHB (right). ........................................................................................................... 140
Figure 17: Photographs of LGFSS with PPGL sheet wall sample (left) & the sample installed within the
specimen frame of GHB (right). ........................................................................................................... 140
Figure 18: Photograph of an affordable housing construction employing Reinforced EPS core panels.
............................................................................................................................................................. 141
Figure 19: 3d illustration showing specifications of EPS core panel .................................................... 142
Figure 20: Example of on-siteshotcreting (left), Sample of EPS core panel received from the
manufacturer (middle) and EPS core panel fixed into the specimen frame of GHB (right). ................ 142
Figure 21: Photograph of an affordable housing construction employing GFRG panel. Source: (MoHUA,
2017).................................................................................................................................................... 144
114
Figure 22: 3D illustrations (top) and photographs of the GFRG Panel samples: Unfilled, partly filled and
fully filled (bottom). ............................................................................................................................. 144
Figure 23: Components of a typical GFRG panel (left), on-site preparation of GFRG partly filled panel
(middle) and GFRG fully filled panel fixed into the GHB specimen frame (right). ................................ 145
Figure 24: 3d illustration showing specifications of Unfilled GFRG Panel ............................................ 145
Figure 25: 3d illustration showing specifications of GFRG Panel with RCC and non-structural filling .. 146
Figure 26: 3d illustration showing specifications of GFRG Panel with partial RCC filling ..................... 146
Figure 27: 3D illustration of a conventional brick wall. ........................................................................ 147
Figure 28: Photographs showing brick wall constructed within the specimen frame of GHB. ............ 147
Figure 29: Photographs of the assembly of ‘Coffor’ panels without insulation (first) and filled with
concrete on-site(second). .................................................................................................................... 148
Figure 30: 3D sectional illustration of insulated coffor panel sample used as the specimen for the test.
............................................................................................................................................................. 149
Figure 31: Photograph of an insulated coffor panel sample without concreting. ................................ 149
Figure 32: 3d illustration of the bamboo crete wall............................................................................. 151
Figure 33: Photographs showing the Bamboo crete wall sample without cement plaster constructed
regionally by the artisan (left) and Bamboo crete wall sample cement-plastered on both the sides .. 151
Figure 34: Photograph of Wattle-and-Daub technology employed by Hunnarshala Foundation at
Khamir Craft Resource Centre, Kutch, Gujarat in the year 2007. ........................................................ 153
Figure 35: 3d illustration of the wattle-and-daub wall ........................................................................ 153
Figure 36: Photograph showing Wattle prepared by artisans fixed in a wooden frame (left) and Daub
prepared regionally and brought to the testing facility for plastering (right). ..................................... 154
Figure 37 Application of daub on the wattle (left), GHB specimen frame exposed to outside conditions
to dry the walling assembly sample ..................................................................................................... 154
Figure 38: 3d illustration showing specifications of the stabilized adobe wall .................................... 156
Figure 39: Photographs of (a)Pugging of the mud mix for the adobe; (b) Pouring mud mix in the mould;
(c)Removing blocks from the mould; (d) Levelling of a course of the blocks; (e) Dried stabilized adobe
wall ...................................................................................................................................................... 156
Figure 40: Photograph of the artisan cutting the laterite block to fit each course into the specimen
frame; Sideways photograph of the reduced laterite block (right) ...................................................... 157
Figure 41: 3d illustration of the laterite block wall .............................................................................. 158
Figure 42 Left-Right: Photograph of the artisan cutting the laterite block to fit each course into the
specimen frame; Sideways photograph of the reduced laterite block (right) ..................................... 158
Figure 43 3d illustration of the unstabilized adobe wall ...................................................................... 160
115
Figure 44 Artisan laying the second course of the unstabilized adobe (left); Completed wall assembly
of the unstabilized adobe (right) ......................................................................................................... 160
Figure 45 3d illustration of the CSEB wall ............................................................................................ 161
Figure 46 (a) Making of the CSEB mix; (b) Filling the mix in the mould of the press machine; (c)
Compressing the mix using a manual press machine; (d) Preparation of the mortar for assembly; (e)
Laying of the second course of the CSEB; (d)Finishing of the CSEB wall assembly in the GHB box. .... 162
Figure 47 3d illustration of unstabilized compressed earth block wall ................................................ 164
Figure 48 Cutting the unstabilized CEB for the second course unit (left); Finished unstabilized CEB wall
assembly in the GHB box. .................................................................................................................... 164
Figure 49: 3d illustration of AAC block wall ......................................................................................... 165
Figure 50: 3D illustration of Unstabilized rammed earth wall. ............................................................ 166
Figure 51: Unstabilized rammed earth block and wall sample preparation. ....................................... 167
Figure 52: 3D illustration of Stabilized rammed earth wall .................................................................. 168
Figure 53: Stabilized rammed earth block and wall sample preparation. ............................................ 169
Figure 54: 3D Illustration of AAC block wall with cement mortar and cement plaster ........................ 170
Figure 55: 3D Illustration of AAC block wall with lime mortar and lime plaster................................... 171
Figure 56: Preparation of AAC block wall with lime mortar and lime plaster. ..................................... 172
Figure 57: 3D Illustration of burnt clay brick wall with lime mortar and lime plaster .......................... 173
Figure 58: Preparation of burnt clay brick wall with lime mortar and lime plaster.............................. 174
Figure 59: 3D Illustration of limestone wall with lime mortar and lime plaster ................................... 175
Figure 60: Preparation of limestone wall with lime mortar and lime plaster. ..................................... 176
Figure 61: 3D Illustration of limestone wall with cement mortar and cement plaster ........................ 177
Figure 62: Preparation of limestone wall with cement mortar and cement plaster ........................... 178
Figure 63: 3D Illustration of hollow clay brick wall (100 mm thick) with cement plaster on both sides
............................................................................................................................................................. 179
Figure 64: Preparation of hollow clay brick wall with cement plaster on both sides ........................... 180
Figure 65: 3D Illustration of hollow clay brick wall (100 mm thick) with XPS insulation on one side ... 181
Figure 66: Preparation of hollow clay brick wall with cement plaster on both sides and XPS insulation
on one side .......................................................................................................................................... 182
Figure 67 : 3D Illustration of hollow clay brick wall (200 mm thick) with rockwool insulation infill..... 183
Figure 68: Preparation of hollow clay brick wall with rockwool infill ................................................... 184
Figure 69: 3D Illustration of hollow clay brick wall (200 mm thick) with cement plaster on both sides
............................................................................................................................................................. 185
Figure 70: Preparation of hollow clay brick wall with rockwool infill ................................................... 186
Figure 71: 3D Illustration of hollow clay brick walls (200 mm thick) with XPS insulation on one side . 187
116
Figure 72: Preparation of hollow clay brick wall (200mm thick) with XPS insulation........................... 188
Figure 73: 3D Illustration of 100 mm thick RCC wall ............................................................................ 189
Figure 74: Preparation of 100mm thick RCC wall ................................................................................ 190
Figure 75: 3D Illustration of RCC wall with EPS board on one side ...................................................... 191
Figure 76: Preparation of RCC wall with EPS board on one side .......................................................... 192
Figure 77: 3D Illustration of RCC wall with Styrofoam (EPS) board on both sides ............................... 193
Figure 78: Preparation of RCC wall with Styrofoam (EPS) board on both sides ................................... 194
Figure 79: 3D Illustration of RCC wall with PVC panels on both sides .................................................. 195
Figure 80: Preparation of RCC wall with PVC panels on both sides ..................................................... 196
Figure 81: 3D Illustration of RCC wall with EPS board and PVC panels on both sides .......................... 197
Figure 82: Preparation of RCC wall with EPS board on one side and PVC panels on both sides .......... 198
Figure 83: Schematic drawings of Rat-trap bond wall ......................................................................... 199
Figure 84 : Schematic drawings of LGFSS wall sample: External wall type 1 with EPS as per
specifications and drawings found in BMTPC Performance appraisal certificate (PAC) no: 1014-S/2014.
............................................................................................................................................................. 200
Figure 85: Schematic drawings of LGFSS wall sample with PPGI sheet as per specifications and
drawings found in BMTPC Performance appraisal certificate (PAC) no:1014-S/2014. ........................ 202
Figure 86 : Schematic drawings of Reinforced EPS core panel wall sample as per specifications and
drawings found in the BMTPC Performance Appraisal Certificate (PAC) no: 1020-S/2015. ................ 203
Figure 87: Schematic drawings of Glass Fibre Reinforced Gypsum building Panel wall sample; Class-1
unfilled panel, as per specifications and drawings found in BMTPC Performance Appraisal Certificate
(PAC) no: 1009-S/2012 and structural design manual. ........................................................................ 204
Figure 88 : Schematic drawings of Glass Fibre Reinforced Gypsum building Panel wall sample; Class-1
fully filled load-bearing panel as per specifications and drawings found in BMTPC Performance
Appraisal Certificate (PAC) no: 1009-S/2012 and structural design manu........................................... 205
Figure 89 : Schematic drawings of Glass Fibre Reinforced Gypsum building Panel wall sample; Class-1
partially filled load-bearing panel with non-structural core filling as per specifications found in BMTPC
Performance Appraisal Certificate (PAC) no: 1009-S/2012.................................................................. 207
Figure 90: Schematic drawings of burnt clay brick wall sample ........................................................... 208
Figure 91 : Schematic drawing of Structural Stay-in-Place Formwork (Coffor) wall sample with
insulation as per specifications found in BMTPC Performance Appraisal Certificate (PAC) no: 1035-S/
2018. .................................................................................................................................................... 209
Figure 92 : Schematic plan and elevation of the Bamboo-Crete Wall ................................................. 211
Figure 93: Schematic drawings of the Wattle and Daub Wall .............................................................. 212
Figure 94 : Schematic drawings of the Stabilized Adobe Wall ............................................................. 213
117
Figure 95 : Schematic drawings of the Laterite Block Wall .................................................................. 214
Figure 96 : Schematic drawings of the Unstabilized Adobe Wall ......................................................... 215
Figure 97: Schematic drawings of the Compressed Stabilized Earth Block (CSEB) Wall ...................... 216
Figure 98 : Schematic drawings of the Unstabilized Compressed Earth Block (CEB) Wall ................... 217
Figure 99: Schematic drawings of the Autoclave Aerated Concrete Block Wall with Perlite-based
cement plaster ..................................................................................................................................... 218
Figure 100 : Schematic drawings of the Unstabilized Rammed Earth Wall ......................................... 219
Figure 101 : Schematic drawings of the Stabilized Rammed Earth Wall .............................................. 220
Figure 102: Schematic drawings of AAC block wall with cement mortar and cement plaster ............. 221
Figure 103 : Schematic drawings of AAC block wall with lime mortar and lime plaster ...................... 222
Figure 104: Schematic Illustration of burnt clay brick wall with lime mortar and lime plaster ............ 224
Figure 105: Schematic drawings of Limestone wall with lime mortar and lime plaster ....................... 226
Figure 106: Schematic drawings of Limestone wall with cement mortar and cement plaster ............ 227
Figure 107: Schematic drawings of hollow clay (100 mm )brick with cement plaster coat on both sides
............................................................................................................................................................. 228
Figure 108: Schematic drawings of hollow clay bricks (100 mm) wall with extruded polysterene board
on one side and cement plaster coat on both sides ............................................................................ 229
Figure 109: Schematic drawings of hollow clay bricks (200 mm) wall with rockwool insulation infill and
cement plaster ..................................................................................................................................... 231
Figure 110 : Schematic drawings of hollow clay (100 mm) brick with cement plaster ........................ 232
Figure 111 : Schematic drawings of hollow clay (200 mm) brick with XPS on one side and cement
plaster coat on both sides.................................................................................................................... 233
Figure 112: Schematic drawings of 100 mm thick RCC Wall ................................................................ 235
Figure 113 : Schematic drawings of 100 mm thick RCC Wall with EPS board on one side .................. 236
Figure 114 : Schematic drawings of 100 mm thick RCC Wall with Styrofoam (EPS) on both sides ...... 237
Figure 115: Schematic drawings of 100 mm thick RCC Wall with PVC boards on both sides .............. 238
Figure 116:Schematic drawings of 100 mm thick RCC Wall with EPS insulation board on one side and
PVC boards on both sides .................................................................................................................... 239
118
LIST OF TABLES
Table 1: List of wall construction selected for U value testing. ............................................................ 129
Table 2: List of walling technologies selected along with source region, manufacturer information, and
PAC number. ........................................................................................................................................ 130
Table 3: Second Party information and its list of services .................................................................... 132
Table 4: U-value database of all selected walling assemblies and technologies. ................................ 133
Table 5: Walling technology and testing details for Rat-trap bond wall .............................................. 199
Table 6 : Walling technology and testing details for LGFSS wall sample with EPS board ..................... 201
Table 7 : Walling technology and testing details for LGFSS wall sample with PPGI sheet.................... 202
Table 8: Walling technology and testing details for Reinforced EPS core panel wall ........................... 203
Table 9: Walling technology and testing details for GFRG Panel wall- unfilled .................................... 205
Table 10 : Walling technology and testing details for GFRG Panel wall- fully filled ............................. 206
Table 11 : Walling technology and testing details for GFRG Panel wall- partially filled ....................... 207
Table 12: Walling technology and testing details for burnt clay brick wall sample.............................. 208
Table 13 : Walling technology and testing details for of Structural Stay-in-Place Formwork (Coffor) wall
sample with insulation ......................................................................................................................... 210
Table 14 : Walling technology and testing details for Bamboo-Crete Wall.......................................... 211
Table 15 : Walling technology and testing details for Wattle and Daub Wall ...................................... 212
Table 16 : Walling technology and testing details for Stabilized Adobe Wall ...................................... 213
Table 17 : Walling technology and testing details for Laterite Block Wall ........................................... 214
Table 18: Walling technology and testing details for Unstabilized Adobe Wall ................................... 215
Table 19: Walling technology and testing details for Compressed Stabilized Earth Block (CSEB) Wall 216
Table 20: Walling technology and testing details for Unstabilized Compressed Earth Block Wall....... 217
Table 21:Walling technology and testing details for AAC Block Wall with Perlite-based cement plaster
............................................................................................................................................................. 218
Table 22 : Walling technology and testing details for Unstabilized Rammed Earth Wall ..................... 219
Table 23 : Walling technology and testing details for Stabilized Rammed Earth Wall ......................... 220
Table 24: Walling technology and testing details for AAC block wall with cement mortar and plaster221
Table 25: Walling technology and testing details for AAC block wall with lime mortar and lime plaster
............................................................................................................................................................. 223
Table 26: Walling technology and testing details for burnt clay brick wall with lime mortar and lime
plaster .................................................................................................................................................. 225
Table 27 : Walling technology and testing details for Limestone wall with lime mortar and lime plaster
............................................................................................................................................................. 226
119
Table 28: Walling technology and testing details for Limestone wall with cement mortar and plaster
............................................................................................................................................................. 227
Table 29: Walling technology and testing details for hollow clay (100 mm )brick with cement plaster
............................................................................................................................................................. 228
Table 30 : Walling technology and testing details for hollow clay bricks (100 mm) wall with extruded
polysterene board on one side and cement plaster coat on both sides .............................................. 230
Table 31: Walling technology and testing details for hollow clay bricks (200 mm) wall with rockwool
insulation infill and cement plaster...................................................................................................... 231
Table 32 : Walling technology and testing details for hollow clay (100 mm) brick with cement plaster
............................................................................................................................................................. 232
Table 33:Walling technology and testing detaibls for hollow clay (200 mm) brick with XPS on one side
and cement plaster coat on both sides................................................................................................ 234
Table 34 : Walling technology and testing details for RCC Wall ........................................................... 235
Table 35: Walling technology and testing details for RCC Wall with EPS board on one side ............... 236
Table 36:Walling technology and testing details for RCC Wall with Styrofoam (EPS) on both sides ... 237
Table 37: Walling technology and testing details for RCC Wall with PVC boards on both sides .......... 238
Table 38 : Walling technology and testing details for RCC Wall with EPS insulation board on one side
and PVC boards on both sides ............................................................................................................. 240
ABBREVIATIONS
ASTM American Society for Testing and Materials
BIS Bureau of Indian Standards
BMTPC Building Materials and Technology Promotion Council
CARBSE Centre for Research in Building Science and Energy
CEPT Centre for Environmental Planning and Technology
CP Cement particles
CRDF CEPT Research and Development Foundation
EPS Expanded Polystyrene
GFRG Glass Fibre Reinforced Gypsum Panel
GHB Guarded Hot Box
GI Galvanised Iron
GKSPL Greentech Knowledge Solutions Pvt. Ltd
HVAC Heating Ventilation and Air-Conditioning
LGFSS Light Gauge Framed Steel Structure
120
MoHUA Ministry of Housing and Urban Affairs, Government of India
PACS Performance Appraisal Certification Scheme
PCM Phase Change Materials
PMAY Pradhan Mantri Awas Yojna
PPGI Pre-painted Galvanised Iron
RCC Reinforced Concrete Cement
SDC Swiss Agency for Development and Cooperation
TSM Technology Sub-Mission
XPS Extruded Polystyrene
RH Relative Humidity
U-Value Thermal transmittance value (W/m2 K)
121
Assessment of Research Lab Capacity and Capabilities
1. Introduction
The rising demand of affordable housing within urban cities in India is a constant challenge. As a result,
emerging construction systems and walling technologies are being developed to improve the cost and
speed dynamics involved in construction that uses conventional methods and materials. However,
considering climate change and associated events, the focus on thermal performance of all categories of
walling technologies is justified. This report submitted by CRDF, CEPT University aims to facilitate
knowledge regarding thermal performance evaluation of wall construction technologies through the
derivation of their U-values, using its state-of-the-art laboratory facilities. To validate their U-value test
results for a dependable reference in sustainable building practices, the research activity protocol has
been listed in Figure 1. This database has been envisaged to facilitate efficient and sustainable affordable
housing construction This research activity tests thirty-four wall assemblies that may fall in one of the
following categories:
122 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Assessment of Research Lab Capacity and Capabilities
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 123
Assessment of Research Lab Capacity and Capabilities
Figure 3: Photographs of the metering chamber attached to the specimen frame and the entire
assembly of GHB opened up and closed.
124 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Testing Procedure
3. Testing Procedure
This section introduces the standard testing procedure followed for the testing of masonry based walls
and BMTPC certified walls.
To determine the net energy flow through the specimen, a five sided metering box is placed with the
open side against the warm face of the test panel. Apparently, if there is no net energy exchange across
the walls other than that of the metering box, and only negligible flanking loss around the specimen, the
heat input from the fan and heaters, minus any cooling coil energy extraction from the metering box,
would be considered a measure of the energy flux through the metered area of the specimen.
Since it is not practically possible to have the condition mentioned above, the GHB apparatus is designed
to obtain an accurate measure of the net sample heat flow. Here, the net energy transfer through the
specimen is determined from net measured energy input to the metering chamber, rectifying the losses
through the chamber walls and flanking loss for the specimen at the perimeter of the metering area. The
heat loss rate through the metering chamber walls is curbed by using highly insulated walls and
controlling the surrounding ambient temperature, or by using a temperature controlled guard chamber.
That portion of the specimen outside the boundary of the metering area or the specimen frame, exposed
to the guarding space temperature, constitutes a passive guard to minimize the flanking heat flow in the
test panel near the perimeter of the metering area.
The basic hot box apparatus can be assembled in a wide variety of sizes, orientations, and designs. There
are two primary design configurations. The first is the guarded hot box used for the testing, that has a
controlled “guard” chamber surrounding the metering box. An example of this configuration is
presented in Figure 4 (ASTM, n.d.).
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 125
Testing Procedure
frame were further sealed using XPS insulation strips and finally sealed using a silicone sealant as seen
in Figure 5 and Figure 6.
Figure 5: Photographs showing thermal imaging (left) and testing of Rattrap bond wall assembly in
GHB
Figure 6: Photographs showing sealing procedure with XPS (left) and silicone sealant (right) to avoid
heat transfer through gaps
126 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Identification of Walling Technologies
Furthermore, the Annual Report 2017-2018 published by Ministry of housing and urban affairs, under
Pradhan Mantri Awas Yojana- Housing For All (Urban) also lists out the same 16 new technologies
certified under the 2nd edition of BMTPC Compendium. These technologies have been earmarked to
be adopted under the PMAY mission as on 31.11.2017, as seen in Figure 8 (MOHUA, 2017).
To cover the most trending technologies such as industrially manufactured and/or pre-fabricated walling
technologies in phase I, enabling possible interventions at the earliest, the following criteria was set:
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 127
Identification of Walling Technologies
Figure 8: Cover page of the latest Annual report by MoHUA (left) and the list of 16 technologies
assigned to be adopted for PMAY mission (right)
Source: (MOHUA, 2017)
128 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Identification of Walling Technologies
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 129
Identification of Walling Technologies
The traditional walling systems needed to be constructed in the prevalent vernacular way of
construction, employing skilled artisans with expert guidance for results that can be applied. Thus, the
execution services were rendered by MAT – Lab, a firm specialized in bamboo & earth construction,
construction innovations, artisan training and R&D (hereinafter referred to as Second Party). All the
traditional walling samples required regional craftsmen to construct the framework or make the masonry
units regionally using their nearest locally available materials. The same samples were constructed or
finished directly into the 980 mm x 980 mm specimen frame of GHB as explained in Annexure 1. The
in-situ finishing required cement or mud plastering, masonry of the masonry units, curing and drying.
Table 3 shows more information of the second party and its list of services for this project. Drawings
and details as seen in Annexure 1 and 2, necessary for this process were shared by the Thus, second
party. Correspondence was maintained until the sample was secured into the apparatus.
Table 2: List of walling technologies selected along with source region, manufacturer information,
and PAC number.
Sr Wall Technology/
Manufacturer Location PAC No
No. Masonry
1 Rattrap bond wall - Ahmedabad, Gujarat -
Light Gauge framed
M/s JB Fabinfra Bhikaji Cama Place,
2 steel structure with 1014-S/2014
Pvt. Ltd New Delhi
EPS
Light Gauge framed
M/s JB Fabinfra Bhikaji Cama Place,
3 steel structure with 1014-S/2014
Pvt. Ltd New Delhi
PPGI Sheet
M/s Jindal Steel
Reinforced EPS core
4 & Power Ltd Angul, Odisha 1020-S/2015
Panel system
Glass fibre reinforced M/s FACT – RCF
5 Gypsum Panel - Building Products Cochin, Kerala 1009-S/2012
Unfilled Ltd. (FRBL)
Glass fibre reinforced
M/s FACT – RCF
Gypsum Panel -with
6 Building Products Cochin, Kerala 1009-S/2012
RCC and non-
Ltd. (FRBL)
structural filling
130 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Identification of Walling Technologies
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 131
Identification of Walling Technologies
132 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Results
5. Results
Table 4 shows the U-values obtained for all twenty-four tested wall assemblies and Figure 9 shows
evaluation of the thermal performances of the same.
Phase- I
3 Light Gauge framed steel structure with PPGI Sheet 150 2.12
7 Glass fibre reinforced Gypsum Panel - with partial RCC filling 124 2.13
Phase- II
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 133
Results
20 AAC Block Wall with Cement Mortar and Cement Plaster 230 0.78
21 AAC Block Wall with Lime mortar and Lime Plaster 220 0.82
22 Burnt Clay Brick with Lime Mortar and Lime Plaster 250 2.31
Phase-III
25 Hollow Clay Brick (100mm thick) with Cement Plaster 130 2.71
26 Hollow Clay Brick (100mm thick) with Cement Plaster and XPS 158 0.89
28 Hollow Clay Brick (200mm thick) with Cement Plaster 230 1.83
29 Hollow Clay Brick (200mm thick) with Cement Plaster and XPS 258 0.75
34 RCC Wall with PVC panels on both side and EPS board 165 0.52
Note: The thermal conductivity of burnt clay brick used for the rat-trap bond wall was tested using the
Thermal Constants Analyser as 0.5187 W/mK and brick wall as 0.5286 W/mK.
134 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Results
0 1 2 3 4
U value (W/m2.K)
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 135
Annexure I
6. Annexures
Annexure I: Summary of the Selected Walling Technologies
This section is an elaboration on the types of wall samples procured and tested for thermal performance
using GHB.
The walls are typically 230 mm thick and the bricks are laid as shown in Figure 11 with different brick
faces (Shiners and Rowlocks) to form a cavity unlike conventional bricklaying (Stretchers and headers).
The Rat trap bond is an external walling technique and is recommended for load-bearing buildings up
to 3 storeys and as filler walls for buildings with concrete columns and beams (Swiss Agency for
Development and Cooperation SDC, n.d.).
For the purpose of this research, the 230 mm thick rat-trap bond wall was constructed within the
specimen frame of GHB using locally available burnt clay bricks from Ahmedabad as shown in Figure
12. The illustration in plan and elevation is available in Annexure 2.
Figure 10: Photograph of a housing project by Laurie Baker employing rat-trap bond wall assembly.
136 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Shiner
Burnt Clay Bricks (230 X 110
X 75 mm)
[IS 1077:1991]
12 mm thick
Rowlock Cement Mortar
(cement: sand in 1:1 ratio)
to lay the bricks
[IS 2250:1981]
Header
10 mm thick cement
Plaster coat on both
sides [IS 1661:1972]
Soldier Sailor
Figure 11: Different brick faces used in wall construction (left) and 3d illustration of a typical Rat-
trap bond Wall (right).
Figure 12: Photographs showing the construction of Rat-trap bond wall within the specimen frame of
GHB.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 137
Annexure I
This LGFSS wall type has a GI steel stud frame and layers of Gypsum board as its internal layers and
EPS board and shotcrete as its external layers, as illustrated in Figure 16 shows the test sample acquired
from the manufacturer mentioned in Table 2 and fixed into the GHB specimen frame. The illustration
in plan and elevation is available in Annexure 2.
This LGFSS wall type has a GI steel stud frame and layers of Gypsum board as its internal layer, vapor
barrier and pre-painted galvanized iron sheet (PPGI) as external layers. Figure 17 shows the test sample
acquired from the manufacturer mentioned in Table 2 and fixed into the GHB specimen frame. The
illustration in plan and elevation is available in Annexure 2.
Figure 13: Photograph showing walls and floor plates of LGFSS assembled at a site.
138 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 139
Annexure I
Figure 16: Photographs of LGFSS with EPS wall sample (left) & the sample wall installed within the
specimen frame of GHB (right).
Figure 17: Photographs of LGFSS with PPGL sheet wall sample (left) & the sample installed within
the specimen frame of GHB (right).
140 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
The sample panel was prepared as per established standards by the manufacturer. The sample wall panel
of size 980 mm x 980 mm was delivered to CARBSE and directly fixed for testing into the GHB
specimen frame as shown in Figure 20. The illustration in plan and elevation is available for reference
in Annexure 2.
Figure 18: Photograph of an affordable housing construction employing Reinforced EPS core panels.
Source: (BMTPC, 2017)
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 141
Annexure I
Figure 20: Example of on-siteshotcreting (left), Sample of EPS core panel received from the
manufacturer (middle) and EPS core panel fixed into the specimen frame of GHB (right).
Source: (left) (BMTPC, 2018a)
142 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
4. Glass Fibre Reinforced Gypsum Panel (GFRG) - Unfilled, partially filled and fully
filled
Glass Fibre Reinforced Gypsum (GFRG) Panel is a product made from calcined gypsum, plaster,
reinforced with glass fibres and is used for mass housing construction. Details of the same are as per
those mentioned in the Performance Appraisal Certificate (PAC) issued to manufacturers by BMTPC
(BMTPC, 2011). Class 1 of GFRG panel is mostly used for external wall applications. Each panel is
manufactured in 12m length, 3m height and consists of cavities separated by ribs as seen in Figure 23.
The panels may be used as unfilled, partially filled or fully-filled, with a concrete and non-structural
filling, based on structural applications as shown in Figure 22.
Three samples of GFRG panels were obtained from the manufacturer and were prepared as per standard
applications on-site as seen in Figure 24, Figure 25, and Figure 26. The sample of unfilled class 1 water-
resistant grade GFRG panel was tested with its hollow cavities and the partially filled panel was tested
after the middle cavity was reinforced with an 8mm diameter steel rod and M20 grade concrete. In case
of a fully filled panel, middle cavity was filled in the same manner as partially filled panel and all the
other cavities were filled with M10 grade concrete (non-structural core filling). Annexure 2 contains
illustrations for the same.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 143
Annexure I
Figure 21: Photograph of an affordable housing construction employing GFRG panel. Source:
(MoHUA, 2017)
Figure 22: 3D illustrations (top) and photographs of the GFRG Panel samples: Unfilled, partly filled
and fully filled (bottom).
144 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Figure 23: Components of a typical GFRG panel (left), on-site preparation of GFRG partly filled
panel (middle) and GFRG fully filled panel fixed into the GHB specimen frame (right).
Cavity in the
GFRG Panel
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 145
Annexure I
Figure 25: 3d illustration showing specifications of GFRG Panel with RCC and non-structural filling
Figure 26: 3d illustration showing specifications of GFRG Panel with partial RCC filling
146 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
5. Brick Wall
A conventional brick wall popularly adopted for housing construction in the country, as seen in Figure
27, was also tested as a base case for the purpose of this research. A standard 230 mm thick brick wall
with plaster was directly constructed within the specimen frame of GHB using locally available burnt
clay bricks from Ahmedabad city, following IS1077 : 1991 for bricks (BIS, 2005) and IS2250 : 1981
for cement mortar (BIS, 1993) as shown in Figure 28. After fully drying and being tested for moisture
via thermal imaging, the testing of wall sample was conducted.
Figure 28: Photographs showing brick wall constructed within the specimen frame of GHB.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 147
Annexure I
Since this wall sample assembly of size 980mm x 980mm, that has a concrete core and shotcrete plaster,
exceeded the weight that the GHB Box could bear, the sample tested here was trimmed to the size of
460mm x 460mm with no change in its assembly thickness or properties. The remaining area of the
specimen frame was covered with 30mm XPS sheets — a high insulating material as seen in Figure 30.
Any gaps between the sample and specimen frame were further sealed using XPS insulation strips and
finally sealed using silicone sealant. The illustration in plan and elevation is available in Annexure 2.
Figure 29: Photographs of the assembly of ‘Coffor’ panels without insulation (first) and filled with
concrete on-site(second).
Source: (Coffor Construction Company LLD, n.d.)
148 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Figure 30: 3D sectional illustration of insulated coffor panel sample used as the specimen for the test.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 149
Annexure I
For the purpose of this research, the bamboo grid and frame were constructed by local craftsmen in the
Maroli town, Navsari district, of Gujarat State in India, where this method of construction is still
practiced by its tribal population. This wall panel sample was constructed in a perpendicular lattice using
untreated hollow split bamboo of 4 to 6 mm thick as seen in Figure 33. For aesthetic outer finish, the
convex shape of the split bamboo is faced outside and the concave shape is faced inside the space. The
bamboo mesh was attached to a 25mm thick wooden frame of 980mm x 980 mm using iron nails on the
edges, to keep the sample sturdy. The bond between bamboo and concrete is much lesser than the bond
between steel and concrete. Thus, a sheet of steel chicken wire-mesh of 1/2 inch diameter grid, 22 gauge,
0.7mm thickness, was stretched flat on the aliquant bamboo grid and fixed in place by tying steel wires
at several grid intersections. The first layer of 10mm cement plastering 1:6 (Cement to Sand Ratio) was
applied on both the sides of the bamboo and steel-mesh assembly by the artisan. As soon as the first
layer dried off, the 10mm second layer of the same plaster was applied. This panel required curing for
3-4 days and 3-4 days for drying. This assembly was then transported to the lab and fixed inside the
GHB specimen frame as shown in Figure 33. All the edges of the sample were sealed off using silicone.
The illustration in plan and elevation is available in Annexure 2.
150 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Conductivity:1.335 W/m.k
Specific Heat: 916.87
J/Kg.K or 0.872 MJ/m3.K
Figure 33: Photographs showing the Bamboo crete wall sample without cement plaster constructed
regionally by the artisan (left) and Bamboo crete wall sample cement-plastered on both the sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 151
Annexure I
For the purpose of this research, the wattle and frame were constructed and an estimated quantity of
daub was prepared by the local craftsmen of Songadh Taluka, in the Dang district of Gujarat. A 930mm
x 930mm wattle was prepared using a couple of 20-25mm wide and only 2-3mm thick untreated bamboo
slats by intertwining them alternatively in perpendicular directions as shown in Figure 36. This wattle
was then attached to a 980mm x 980mm wooden frame with metal handles for sturdiness. A
homogenous daub was separately prepared there using the locally available red soil (64 kgs), cow dung
(16 kgs), grass husk (16 kgs) or jute fibres and water (12 litres) in 16:4:4:3 ratio respectively. The red
soil is made wet and kept in wet conditions for 3 days. On the 4th day, after pugging the wet red soil
using feet, the plaster is finished by mixing the natural stabilizers - cow dung and husk in it using hands.
These wattle and daub were transported to the lab to fix the wattle frame in the GHB specimen frame as
Figure 37. The daub is made suitable to plaster by the artisan by adding 5-6 litres of water and mixing
it well. The first layer of daub, thin enough to cover the exposed bamboo slats was then applied using
hands on both the sides of the panel as seen in Figure 36. The first layer is allowed to dry avoiding direct
sunlight, the second layer was applied to form a total thickness of 5-6mm on both the sides. After 24
hours of drying time, the third layer of daub of 8-10mm was applied to fill the cavities or cracks
developed after drying. The GHB specimen frame was kept exposed to the open environment to dry for
5 days but avoiding direct sunlight as seen in Figure 37. The sample edges were sealed with silicon to
avoid the heat transfer through gaps after drying. The illustration in plan and elevation is available in
Annexure 2.
152 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Bamboo frame
(Perpendicular Lattice using
untreated hollow split
bamboo of 2 to 3 mm thick)
15 mm thick Homogenous
Daub (Red Soil: Cowdung:
Grass husk/Jute fibres:Water in
16:4:4:3 ratio) on both sides of
the lattice
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 153
Annexure I
Figure 36: Photograph showing Wattle prepared by artisans fixed in a wooden frame (left) and Daub
prepared regionally and brought to the testing facility for plastering (right).
Figure 37 Application of daub on the wattle (left), GHB specimen frame exposed to outside conditions
to dry the walling assembly sample
154 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
For the purpose of this research, around 75 stabilized adobe blocks of 230 x 230 x 75 mm each and the
mud mortar mix were prepared by the local artisans in the North Gujarat region. For the stabilized adobe
blocks, a dry mix composed of soil, sand and cement was first prepared. Then water was added to this
mix, and pugging was done to attain a wet mixture. Later, husk was added as reinforcement to mixture
while pugging and adding water, as a binder material. The ratio of soil, sand, cement and husk being
9:3:1/2:4.5. The mixture was then poured in a wooden formwork, and kept for 15-20 mins. The blocks
were removed from the formwork and kept in a shaded place to dry. These blocks were cured for 10-15
days by sprinkling water on them rather than directly spraying on top of them. Mud mortar is a mixture
of clayey soil and sand which is used as a binder to hold the blocks. The ratio for the mud mortar used
in the sample was 1 sand: 5 soil. These materials were then transported to the lab to construct the
masonry directly into the GHB specimen frame. The cutting of blocks was done on site as per GHB
specimen frame size. The blocks are laid on the wet mortar to align and set easily to allow some
movement while construction of the wall as seen in Figure 39. After allowing the finished wall to dry
for 36 hours, the sample edges were sealed with silicon to avoid the heat transfer through gaps. The
illustration in plan and elevation is available in Annexure 2.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 155
Annexure I
Figure 39: Photographs of (a)Pugging of the mud mix for the adobe; (b) Pouring mud mix in the
mould; (c)Removing blocks from the mould; (d) Levelling of a course of the blocks; (e) Dried
stabilized adobe wall
156 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
The laterite clay is diffused in immense masses, without any appearance of stratification and is placed
over the granite that forms the basis of Malayala. It is full of cavities and pores, and contains a very
large quantity of iron in the form of yellow and red ochres. In the mass, while excluded from the air, it
is dug up in square masses with a pick-axe, and immediately cut into desired shape with a trowel. Soon
after, it becomes hard as brick, and resists the air and water much better than other clay bricks in India.
(Schellmann, n.d.) It is estimated that 2.83cum(100 cu-ft) of soil is excavated in each load. (Nasheed et
al., n.d.) The blocks shall be exposed preferably for a period of three months before being used in the
construction of masonry to ensure adequate stabilization. The standard laterite block sizes available in
India are 390 x 190 x 190mm, 490 x 190 x 190mm and 590 x 290 x 290mm. (BIS, 2003) Most common
weathering damages namely granular disintegration, bio-degradation and salt attack stem from presence
of moisture. Hence protection from dampness prolongs the life of laterite masonry. (Kasthurba et al.,
2006) Figure 41 shows a 3D illustration of the laterite block wall.
For the purpose of this research, laterite blocks of 355 x 205 x 92mm size were sourced from Ratnagiri
district of Maharashtra in India. Using locally sourced sand and soil from Ahmedabad city, mud mortar
of 1 sand: 5 soil ratio was used as a binder to hold the blocks. This masonry was directly constructed in
the GHB specimen frame requiring cutting of the blocks in-situ as seen in Figure 40. The finished wall
was left to dry for 48 hours before thermal imaging and testing as seen in Figure 42.
Figure 40: Photograph of the artisan cutting the laterite block to fit each course into the specimen
frame; Sideways photograph of the reduced laterite block (right)
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 157
Annexure I
Laterite Blocks
(355 X 205 X
92 mm)
15 mm thick
Mud mortar
(sand: soil in
1:5 ratio) to lay
the blocks
[IS 13077:1991]
Figure 42 Left-Right: Photograph of the artisan cutting the laterite block to fit each course into the
specimen frame; Sideways photograph of the reduced laterite block (right)
158 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
For the purpose of this research, around 75 unstabilized adobe blocks of 230 x 230 x 75 mm each and
the mud mortar mix were prepared by the local artisans in the North Gujarat region. For the unstabilized
adobe blocks, a dry mix composed of husk, sand and soil in 4.5:3:9 ratio was first prepared. Then water
was added to this mix, and pugging was done to attain a wet mixture. Later, husk was added as
reinforcement to mixture while pugging and adding water, as a binder material. The ratio of soil, sand,
cement and husk was 9: 3: 0.5: 4.5. The mixture was then poured in a wooden formwork, and kept for
15-20 mins. The blocks were removed from the formwork and kept in a shaded place to dry for at least
15-20 days. No curing was required due to absence of stabilizers. The ratio for the mud mortar used in
the sample was 1 sand: 5 soil. These materials were then transported to the lab to construct the masonry
directly into the GHB specimen frame. The assembly can be referred from Figure 43. The cutting of
blocks was done on site as per GHB specimen frame size. The blocks were laid on the wet mortar to
align and set easily to allow some movement while construction of the wall as seen in Figure 44. The
wall was left to dry for 36 hours. The illustration in plan and elevation is available in Annexure 2.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 159
Annexure I
Figure 44 Artisan laying the second course of the unstabilized adobe (left); Completed wall assembly
of the unstabilized adobe (right)
160 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
For the purpose of this research, around 75 stabilized adobe blocks of 230 x 230 x 75 mm each and the
mud mortar mix were prepared by the local artisans in the North Gujarat region. For the unstabilized
adobe blocks, a dry mix composed of husk, sand and soil in 4.5:3:9 ratio was first prepared. Then water
was added to this mix, and pugging was done to attain a wet mixture. Later, husk was added as
reinforcement to mixture while pugging and adding water, as a binder material. The ratio of soil, sand,
cement and husk being 9:3:1/2:4.5. The mixture was then poured in a wooden formwork, and kept for
15-20 mins. The blocks were removed from the formwork and kept in a shaded place to dry for at least
15-20 days. No curing was required as no stabilizers were added to the composition. The ratio for the
mud mortar used in the sample was 1 sand: 5 soil. These materials were then transported to the lab to
construct the masonry directly into the GHB specimen frame. The cutting of blocks was done on site as
per GHB specimen frame size. The blocks are laid on the wet mortar to align and set easily to allow
some movement while construction of the wall. The process can be seen in Figure 46. After allowing
the finished wall to dry for 36 hours, the sample edges were sealed with silicon to avoid the heat transfer
through gaps. The illustration in plan and elevation is available in Annexure 2.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 161
Annexure I
Figure 46 (a) Making of the CSEB mix; (b) Filling the mix in the mould of the press machine; (c)
Compressing the mix using a manual press machine; (d) Preparation of the mortar for assembly; (e)
Laying of the second course of the CSEB; (d)Finishing of the CSEB wall assembly in the GHB box.
162 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
For the purpose of this research, around 55 unstabilized compressed-earth-blocks of 230 x 230 x 105
mm each and the mud mortar mix were prepared by the local artisans in the North Gujarat region. For
the unstabilised CEB, first the dry mixture is prepared with sand soil in 1:3 ratio and mixed properly.
Lime water is added to the mixture, in such a way that it's not too much wet or dry. Lime water acts as
a stabilizer here. Wet enough to form a lump and dry enough to break when dropped from a height. The
mixture is then poured in a metal mould fixed in the block-compress-machine, properly filled till the top
and compressed to form the blocks. The blocks are removed from the mould and kept in a shaded place.
These blocks are cured for 10-15 days by sprinkling water on them rather than directly spraying on top
of them. The blocks are kept to dry in a shaded area for at least 15-20 days. The unstabilized CEB blocks
were covered with a wet jute cloth for 10 days before the sample assembly. This was done to avoid the
formation of cracks because of the reaction from the lime water. This chemical reaction can also form a
new material such as a pozzolana. After that it is kept to dry in a shaded area before using it for the
sample wall. The ratio for the mud mortar used in the sample was 1 sand: 5 soil.
These materials were then transported to the lab to construct the masonry directly into the GHB
specimen frame. The cutting of blocks was done on site as per GHB specimen frame size. This can be
seen in Figure 48. The blocks are laid on the wet mortar to align and set easily to allow some movement
while construction of the wall. After allowing the finished wall to dry for 36 hours, the sample edges
were sealed with silicon to avoid the heat transfer through gaps. The illustration in plan and elevation is
available in Annexure 2.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 163
Annexure I
15 mm thick Mud
mortar
(sand: soil in 1:5 ratio)
to lay the blocks
[IS 13077:1991]
Figure 48 Cutting the unstabilized CEB for the second course unit (left); Finished unstabilized CEB
wall assembly in the GHB box.
164 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
14. Autoclaved Aerated Concrete (AAC) Block Wall with Perlite-based cement plaster
Autoclaved aerated concrete (AAC) is a lightweight, precast, thermally insulating building
material used to produce concrete masonry unit (CMU) like blocks for building construction. AAC is
manufactured from fly ash, lime, gypsum, aluminium, cement, sand, and other raw materials. AAC
blocks are advantageous because they simultaneously provide structure, insulation, and fire- and mold-
resistance while being easy to construct with. Moreover, due to the bigger size of individual blocks, they
require less mortar than a clay brick wall of same size. Refer this walling technology in Figure 49.
In current traditional building practices, the AAC block wall is constructed, typically with regular
cement mortar and finished with plaster. For the purpose of the research, this walling technology was
constructed using Perlite-based cement as the plaster for finishing and regular cement mortar between
the AAC blocks. This type of plaster is thermally insulating and inhibits heat transfer from either side.
Both AAC blocks and perlite-based cement plater were procured from Ahmedabad, Gujarat. The readily
available AAC blocks of standard size in India, 600mm x 200mm x 100mm or 24” x 8” x 4” were used.
A 5mm thk layer of cement mortar was applied between AAC block. The plaster applied to both sides
of the wall was 20mm thick. The illustration in plan and elevation is available in Annexure 2.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 165
Annexure I
First, dry mixture was prepared with sand, soil, and aggregate in the 2:6:4 ratio. Next, lime water was
sprinkled on the mixture to prevent excessive wetting. The prepared mixture was wet enough to form
lumps in hand but dry enough to allow breakage when dropped from a height. This mixture was poured
into a wooden formwork up to a height of around 10 cm and then rammed. The process was repeated to
form consistent layers. A geo-grid wire mesh was used between the layers for reinforcement. After
compression, the density was checked using a penetrometer. After completion, the formwork was
carefully dismantled to avoid cracking on edges.
The materials were transported to the lab and then installed in the GHB specimen as seen in Figure 51.
The whole wall was divided into 4 parts for the ease of logistics. The blocks were chiseled for
accommodation within the sample holder. Next, cement mortar was applied to fix the blocks on the
sample holder frame. The blocks were then laid on the wet mud mortar to align and set easily by allowing
some movement during the construction. The sand to soil ratio used to prepare the mud mortar applied
between the blocks was 1:5. The finished wall was left to dry for 24-36 hours before thermal imaging
and testing began. The illustration in plan and elevation is available in Annexure 2.
166 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Figure 51: Unstabilized rammed earth block and wall sample preparation.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 167
Annexure I
First, dry mixture was prepared with cement, sand, soil, and aggregate in the 1:2:6:4 ratio. Next, lime
water was sprinkled on the mixture to prevent excessive wetting. The prepared mixture was wet enough
to form lumps in hand but dry enough to allow breakage when dropped from a height. This mixture was
poured into a wooden formwork up to a height of around 10 cm and then rammed. The process was
repeated to form consistent layers. A geo-grid wire mesh was used between the layers for reinforcement.
After compression, the density was checked using a penetrometer. After completion, the formwork was
carefully dismantled to avoid cracking on edges.
The materials were transported to the lab and then installed in the GHB specimen. The whole wall was
divided into 4 parts for the ease of logistics. The blocks were chiseled for accommodation within the
size of GHB sample holder. Next, cement mortar was applied to fix the blocks on the sample holder
frame. The blocks were then laid on the wet mud mortar to align and set easily by allowing some
movement during the construction. The sand to soil ratio used to prepare the mud mortar applied
between the blocks was 1:5. The finished wall was left to dry for 24-36 hours before thermal imaging
and testing began. The illustration in plan and elevation is available in Annexure 2.
168 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
Figure 53: Stabilized rammed earth block and wall sample preparation.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 169
Annexure I
17. AAC Block Wall with Cement Mortar and Cement Plaster
Autoclaved aerated concrete (AAC) is a lightweight, precast, thermally insulating building
material used to produce concrete masonry unit (CMU) like blocks for building construction. AAC is
manufactured from fly ash, lime, gypsum, aluminium, cement, sand, and other raw materials. AAC
blocks are advantageous because they simultaneously provide structure, insulation, and fire- and mold-
resistance while being easy to construct with. Moreover, due to the bigger size of individual blocks, they
require less mortar than a clay brick wall of same size. Refer this walling technology in Figure 54.
The materials were transported to the lab and the wall was constructed in the GHB specimen. Cement
mortar was applied to fix the blocks on the sample holder frame. The blocks were then laid on the wet
mortar to align and set easily by allowing some movement during the construction. The cement to sand
ratio used to prepare the cement mortar applied between the blocks was 1:4. The wall was left for 24
hours for the mortar to dry. Next, the cement plaster was prepared in mentioned ratio and applied to
finish the wall surface. The completed sample was left to dry for 10 days before thermal imaging and
testing began. The illustration in plan and elevation is available in Annexure 2.
Figure 54: 3D Illustration of AAC block wall with cement mortar and cement plaster
170 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
18. AAC Block Wall with Lime Mortar and Lime Plaster
Industrially manufactured, precast AAC blocks can be used to construct insulating walls with suitable
block-bedding and wall finishing materials. Apart from cement, lime mortar and lime plaster are suitable
materials in AAC block wall construction. Lime mortar used for above ground construction is called
non-hydraulic lime. Refer this walling technology in Figure 55.
In order to prepare lime mortar, quicklime was first slaked or hydrated for 3-4 days. Next, it was mixed
with sieved sand in the ratio 1:3. Similarly, lime plaster was prepared by combining lime and sand in
the ratio 1:4 after hydration of quick lime was complete.
The materials were transported to the lab and the wall was constructed in the GHB specimen as seen in
Figure 56. The wall was directly constructed in the sample holder. Lime mortar was applied to fix the
blocks on the sample holder frame. The blocks were then laid on the lime mortar to align and set easily
by allowing some movement during the construction. The sample was left for a day for the mortar to
dry. Lime plaster was applied on the next day for wall finishing. The completed wall was left to dry for
5-6 days before thermal imaging and testing began. The illustration in plan and elevation is available in
Annexure 2.
Figure 55: 3D Illustration of AAC block wall with lime mortar and lime plaster
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 171
Annexure I
Figure 56: Preparation of AAC block wall with lime mortar and lime plaster.
172 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
19. Burnt Clay Brick Wall with Lime Mortar and Lime Plaster
Burnt clay brick is one of the most common materials used in wall construction. Due to faster setting
time, brick walls are typically constructed with cement mortar. However, lime mortar is also commonly
used as an alternative to cement mortar. When quick lime is thoroughly mixed with enough water, it
forms a slurry which is used as mortar. This non-hydraulic lime slurry naturally turns back to calcium
carbonate by reacting with carbon dioxide in the air. This process is called the lime cycle.
In order to prepare lime mortar, quicklime was first slaked or hydrated for 3-4 days. Next, it was mixed
with sieved sand in the ratio 1:3. Similarly, lime plaster was prepared by combining lime and sand in
the ratio 1:4 after hydration of quick lime was complete.
The materials were transported to the lab and then installed in the GHB specimen as seen in Figure 58.
The wall was directly constructed in the sample holder. Lime mortar was applied to fix the blocks on
the sample holder frame. The blocks were then laid on the lime mortar to align and set easily by allowing
some movement during the construction. The sample was left for a day for the mortar to dry. Lime
plaster was applied on the next day for wall finishing. The completed wall was left to dry for 5-6 days
before thermal imaging and testing began. The illustration in plan and elevation is available in
Annexure 2.
Figure 57: 3D Illustration of burnt clay brick wall with lime mortar and lime plaster
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 173
Annexure I
Figure 58: Preparation of burnt clay brick wall with lime mortar and lime plaster.
174 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
For the purpose of this research limestone blocks of size 355 mm x 200mm x 140mm were sourced from
Junagadh. In order to prepare lime mortar, quicklime was first slaked or hydrated for 3-4 days. Next, it
was mixed with sieved sand in the ratio 1:3. Similarly, lime plaster was prepared by combining lime and
sand in the ratio 1:4 after hydration of quick lime was complete.
The materials were transported to the lab and then installed in the GHB specimen as seen in Figure 60.
The wall was directly constructed in the sample holder. Lime mortar was applied to fix the blocks on
the sample holder frame. The blocks were then laid on the lime mortar to align and set easily by allowing
some movement during the construction. The sample was left for a day for the mortar to dry. Lime
plaster was applied on the next day for wall finishing. The completed wall was left to dry for 5-6 days
before thermal imaging and testing began. The illustration in plan and elevation is available in
Annexure 2.
Figure 59: 3D Illustration of limestone wall with lime mortar and lime plaster
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 175
Annexure I
Figure 60: Preparation of limestone wall with lime mortar and lime plaster.
176 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
For the purpose of this research limestone blocks of size 355 mm x 200mm x 140mm were sourced from
Junagadh. The materials were transported to the lab and the wall was constructed in the GHB specimen
as seen in Figure 62. Cement mortar was applied to fix the blocks on the sample holder frame. The
blocks were then laid on the wet mortar to align and set easily by allowing some movement during the
construction. The cement to sand ratio used to prepare the cement mortar applied between the blocks
was 1:4. The wall was left for 24 hours for the mortar to dry. Next, the cement plaster was prepared in
the same ratio (1:4) and applied to finish the wall surface. The completed sample was left to dry for 10
days before thermal imaging and testing began. The illustration in plan and elevation is available in
Annexure 2.
Limestone Blocks
(355 X 200 X 140 mm)
[IS 2185 (Part 3):1984]
Conductivity: 0.969 W/m.K
Figure 61: 3D Illustration of limestone wall with cement mortar and cement plaster
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 177
Annexure I
Figure 62: Preparation of limestone wall with cement mortar and cement plaster
178 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
22. Hollow clay brick (100mm thick) wall with cement plaster
Hollow clay bricks contain designed air gaps which significantly reduce the construction material and
hence, the dead load. They are manufactured using natural additives such as coal ash, rice husk, and saw
dust along with clay sourced from dead water tanks. Hollow clay brick walls can be constructed using
either cement mortar (1:4 ratio for 100 mm thick walls) or a special kind of dry adhesive manufactured
especially for tightly fixing the hollow bricks in wall. These bricks can be be chiselled for fixing
electrical or plumbing conduits.
For this technology hollow clay bricks of full size- 400 mm x 200mm x 100mm and half size- 200 mm
x 200 mm x 100 mm were sourced from Bengaluru. The materials were transported to the lab and the
wall was constructed in the GHB specimen as seen in Figure 64. The blocks were laid with dry adhesive
applied using a dispenser. The same was used to fix the blocks on the sample holder frame. The cement
plaster was prepared in the 1:1 ratio and applied to finish the wall surface. The illustration in plan and
elevation is available in Annexure 2.
Figure 63: 3D Illustration of hollow clay brick wall (100 mm thick) with cement plaster on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 179
Annexure I
Figure 64: Preparation of hollow clay brick wall with cement plaster on both sides
180 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
23. Hollow clay brick (100mm thick) wall with XPS insulation
Extruded Polysterene insulation is manufactured through extrusion process, which allows the XPS sheet
or board to have a smooth finish on both top and bottom sides. Moreover, the extrusion process gives
the board a closed cell structure which may help in moisture resistance. XPS boards are available in
various thicknesses and compressive strengths.
For this technology hollow clay bricks of full size- 400 mm x 200mm x 100mm and half size- 200 mm
x 200 mm x 100 mm were sourced from Bengaluru. The materials were transported to the lab and the
wall was constructed in the GHB specimen as seen in Figure 66. The blocks were laid with dry adhesive
applied using a dispenser. The same was used to fix the blocks on the sample holder frame. The cement
plaster was prepared in the 1:1 ratio and applied to the wall surface. The XPS board was fixed on the
plaster coat using PVC film and finished with cement screed. The illustration in plan and elevation is
available in Annexure 2.
Figure 65: 3D Illustration of hollow clay brick wall (100 mm thick) with XPS insulation on one side
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 181
Annexure I
Figure 66: Preparation of hollow clay brick wall with cement plaster on both sides and XPS insulation
on one side
182 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
24. Hollow clay brick (200mm thick) wall with rockwool insulation infill
Hollow clay bricks contain designed air gaps which significantly reduce the construction material and
hence, the dead load. The air gaps can be used to infill rockwool insulation to increase thermal resistance
of the walling technology. Rockwool or mineral wool is manufactured from a mix of volcanic rock and
slag obtained as byproduct from steel manufacturing industry.
For this technology hollow clay bricks of full size- 400 mm x 200mm x 100mm and half size- 200 mm
x 200 mm x 100 mm were sourced from Bengaluru. The blocks were filled with rockwool insulation
sourced locally in Ahmedabad. The wall was constructed in the GHB specimen with rockwool-infilled
clay bricks as seen in Figure 68. The blocks were laid with dry adhesive applied using a dispenser. The
cement plaster was prepared in the 1:1 ratio and applied to finish the wall surface. The illustration in
plan and elevation is available in Annexure 2.
Figure 67 : 3D Illustration of hollow clay brick wall (200 mm thick) with rockwool insulation infill
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 183
Annexure I
Figure 68: Preparation of hollow clay brick wall with rockwool infill
184 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
25. Hollow clay brick (200mm thick) wall with cement plaster
Hollow clay bricks contain designed air gaps which significantly reduce the construction material and
hence, the dead load. They are manufactured using natural additives such as coal ash, rice husk, and saw
dust along with clay sourced from dead water tanks. Hollow clay brick walls can be constructed using
either cement mortar (1:4 ratio for 100 mm thick walls) or a special kind of dry adhesive manufactured
especially for tightly fixing the hollow bricks in wall. These bricks can be be chiselled for fixing
electrical or plumbing conduits.
For this technology hollow clay bricks of full size- 400 mm x 200mm x 200mm and half size- 200 mm
x 200 mm x 200 mm were sourced from Bengaluru. The materials were transported to the lab and the
wall was constructed in the GHB specimen as seen in Figure 70. The blocks were laid with dry adhesive
applied using a dispenser. The same was used to fix the blocks on the sample holder frame. The cement
plaster was prepared in the 1:1 ratio and applied to finish the wall surface. The illustration in plan and
elevation is available in Annexure 2.
Figure 69: 3D Illustration of hollow clay brick wall (200 mm thick) with cement plaster on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 185
Annexure I
Figure 70: Preparation of hollow clay brick wall with rockwool infill
186 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
26. Hollow clay brick (200mm thick) wall with XPS insulation
Extruded Polysterene insulation is manufactured through extrusion process, which allows the XPS sheet
or board to have a smooth finish on both top and bottom sides. Moreover, the extrusion process gives
the board a closed cell structure which may help in moisture resistance. XPS boards are available in
various thicknesses and compressive strengths.
For this technology hollow clay bricks of full size- 400 mm x 200mm x 200mm and half size- 200 mm
x 200 mm x 200 mm were sourced from Bengaluru. The materials were transported to the lab and the
wall was constructed in the GHB specimen as seen in Figure 72. The blocks were laid with dry adhesive
applied using a dispenser. The same was used to fix the blocks on the sample holder frame. The cement
plaster was prepared in the 1:1 ratio and applied to the wall surface. The XPS board was fixed on the
plaster coat using PVC film and finished with cement screed. The illustration in plan and elevation is
available in Annexure 2.
Figure 71: 3D Illustration of hollow clay brick walls (200 mm thick) with XPS insulation on one side
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 187
Annexure I
Figure 72: Preparation of hollow clay brick wall (200mm thick) with XPS insulation
188 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
• It allows for comparison between RCC-based technologies with varying insulating materials.
• It is representative of the walling technologies achieved through emerging construction
techniques such as tunnel formwork, precast concrete construction, etc which allow faster
construction. The constituents of concrete can be varied based on desired performance.
The RCC wall sample was constructed using RCC blocks with vertical and horizontal reinforcements
i.e. steel bars of 8 mm diameter placed 110 mm apart, outside the sample. The blocks were then installed
in the GHB sample holder as shown in Figure 74. The illustration in plan and elevation is available in
Annexure 2.
Concrete Wall
(980 X 980 X 100 mm)
[IS 456:2000]
Conductivity: 1.583 W/m.K
Specific Heat: 942.48 J/KgK or
1.689 MJ/m3K
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 189
Annexure I
190 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
The RCC wall sample was constructed using RCC blocks with vertical and horizontal reinforcements
i.e. steel bars of 8 mm diameter placed 110 mm apart, outside the sample. The blocks were then installed
in the GHB sample holder as shown in Figure 76. Further EPS board was fixed to one side of the wall.
Figure 76 shows the process of constructing RCC wall sample in the GHB samaple holder. The
illustration in plan and elevation is available in Annexure 2.
Concrete Wall
(980 X 980 X 100 mm)
[IS 456:2000]
Conductivity: 1.583 W/m.K
Specific Heat: 942.48 J/KgK or
1.689 MJ/m3K
Figure 75: 3D Illustration of RCC wall with EPS board on one side
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 191
Annexure I
Figure 76: Preparation of RCC wall with EPS board on one side
192 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
The RCC wall sample was constructed using RCC blocks with vertical and horizontal reinforcements
i.e. steel bars of 8 mm diameter placed 110 mm apart, outside the sample. The blocks were then installed
in the GHB sample holder as shown in Figure 78. Further Styrofoam (EPS) boards were fixed to both
sides of the wall. Figure 78 shows the process of constructing RCC wall sample in the GHB samaple
holder. The illustration in plan and elevation is available in Annexure 2.
Concrete Wall
(980 X 980 X 100 mm)
[IS 456:2000]
Conductivity: 1.583 W/m.K
Specific Heat: 942.48 J/KgK or 1.689 MJ/m3K
Figure 77: 3D Illustration of RCC wall with Styrofoam (EPS) board on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 193
Annexure I
Figure 78: Preparation of RCC wall with Styrofoam (EPS) board on both sides
194 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
The RCC wall sample was constructed using RCC blocks with vertical and horizontal reinforcements
i.e. steel bars of 8 mm diameter placed 110 mm apart, outside the sample. The blocks were then installed
in the GHB sample holder as shown in Figure 80. Further PVC panels were fixed to both sides of the
wall. Figure 80 shows the process of constructing RCC wall sample in the GHB samaple holder. The
illustration in plan and elevation is available in Annexure 2.
Concrete Wall
(980 X 980 X 100 mm)
[IS 456:2000]
Conductivity: 1.583 W/m.K
Specific Heat: 942.48 J/KgK or
1.689 MJ/m3K
Figure 79: 3D Illustration of RCC wall with PVC panels on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 195
Annexure I
Figure 80: Preparation of RCC wall with PVC panels on both sides
196 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure I
31. RCC Wall with EPS Board on one side and PVC panels on both sides
This walling technology is derived from pre-fabricated sandwich panel systems that consists of a core
material sandwiched between two face boards. The core material consists of RCC while the face boards
could be made of fibre-cement, PVC panels, or calcium silicate boards. Further, insulation can be added
to this assembly in the form of either EPS granule balls in the core material or as EPS board finished
with cement screed.
The RCC wall sample was constructed using RCC blocks with vertical and horizontal reinforcements
i.e. steel bars of 8 mm diameter placed 110 mm apart, outside the sample. The blocks were then installed
in the GHB sample holder as shown in Figure 82. Further PVC panels were fixed to both sides of the
wall and EPS sheet to only one side. Figure 82 shows the process of constructing RCC wall sample in
the GHB samaple holder. The illustration in plan and elevation is available in Annexure 2.
Concrete Wall
(980 X 980 X 100 mm)
[IS 456:2000]
Conductivity: 1.583 W/m.K
Specific Heat: 942.48 J/KgK or 1.689 MJ/m3K
Figure 81: 3D Illustration of RCC wall with EPS board and PVC panels on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 197
Annexure I
Figure 82: Preparation of RCC wall with EPS board on one side and PVC panels on both sides
198 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
10 mm thick cement
Plaster on both sides
12 mm thick Cement
Mortar to lay bricks
Elevation Section
Plan
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 199
Annexure II
Elevation Section
Plan
Figure 84 : Schematic drawings of LGFSS wall sample: External wall type 1 with EPS as per
specifications and drawings found in BMTPC Performance appraisal certificate (PAC) no: 1014-
S/2014.
200 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Table 6 : Walling technology and testing details for LGFSS wall sample with EPS board
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
10 mm thick
Cement Plaster mix
(cement : sand in IS 9012:1978
for Guniting
1:1 ratio)
4 mm dia wire of
UTS 480 MPa of
spacing 150 x
Steel Chicken Wire
150 mm or 1.4 IS 3150:1982
mesh
mm dia of
spacing 40 x 40
mm.
Expanded ASTM C
Polysterene (EPS) 15 mm thick IS 4671:1984 1363
Board
Concrete mix
(for core wall 95 mm thick IS 456:2000
panel)
ASTM A
Steel C Section 653A,
(Nogging) 653/M:2013,
IS 277:1992
IS 2095
Gysum Board 15 mm thick
(Part-I): 2011
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 201
Annexure II
Elevation Section
Plan
Figure 85: Schematic drawings of LGFSS wall sample with PPGI sheet as per specifications and
drawings found in BMTPC Performance appraisal certificate (PAC) no:1014-S/2014.
Table 7 : Walling technology and testing details for LGFSS wall sample with PPGI sheet
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Pre- Painted
Galvanized
35 mm thick IS 14246:1995
Iron (PPGI)
sheet
Vapor
ASTM C
Barrier 5 mm thick ASTM E1745
1363
membrane
On a 610 mm ASTM A
Steel C
grid of 653A,
Section
Galvanized 653/M:2013,
(Nogging)
steel of IS 277:1992
202 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
specified
grade.
Gysum IS 2095 (Part-
15 mm thick
Board I): 2011
Elevation Section
Note: When used as in-fill wall
in famed RCC structure, the
frame structure shall be
designed in accordance with
Plan IS 456:2000 or IS 800:2007
Figure 86 : Schematic drawings of Reinforced EPS core panel wall sample as per specifications and
drawings found in the BMTPC Performance Appraisal Certificate (PAC) no: 1020-S/2015.
Table 8: Walling technology and testing details for Reinforced EPS core panel wall
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Shotcrete Mix
(for both 35 mm thick IS 9012:1978
ASTM C
sides)
1363
Galvanized IS : 432 (Part
3 mm dia
Steel members I)- 1982;
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 203
Annexure II
Elevation Section
Plan
Figure 87: Schematic drawings of Glass Fibre Reinforced Gypsum building Panel wall sample; Class-
1 unfilled panel, as per specifications and drawings found in BMTPC Performance Appraisal
Certificate (PAC) no: 1009-S/2012 and structural design manual.
204 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Table 9: Walling technology and testing details for GFRG Panel wall- unfilled
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Class 1 Glass
124 mm thick
Fibre ASTM
(15 mm thick
Reinforced C1355/ ASTM C
at both side
Gypsum Panel C1355M- 1363
with 94 mm
(Water 96 (2020)
cavity inside)
resistant)
d. With RCC and non-structural filling
Total wall thickness= 124 mm
U value of the assembly= 2.12 W/m2K
Elevation Section
Plan
Figure 88 : Schematic drawings of Glass Fibre Reinforced Gypsum building Panel wall sample;
Class-1 fully filled load-bearing panel as per specifications and drawings found in BMTPC
Performance Appraisal Certificate (PAC) no: 1009-S/2012 and structural design manu
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 205
Annexure II
Table 10 : Walling technology and testing details for GFRG Panel wall- fully filled
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Class 1 Glass
124 mm thick
Fibre ASTM
(15 mm thick
Reinforced C1355/
at both side
Gypsum Panel C1355M-
with 94 mm
(Water 96 (2020)
cavity inside)
resistant)
Cavity Filled
with non-
structural core ASTM C
filling 1363
206 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Elevation Section
Plan
Figure 89 : Schematic drawings of Glass Fibre Reinforced Gypsum building Panel wall sample;
Class-1 partially filled load-bearing panel with non-structural core filling as per specifications found
in BMTPC Performance Appraisal Certificate (PAC) no: 1009-S/2012
Table 11 : Walling technology and testing details for GFRG Panel wall- partially filled
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
124 mm thick
Class 1 Glass Fibre ASTM
(15 mm thick
Reinforced C1355/
at both side
Gypsum Panel C1355M-
with 94 mm
(Water resistant) 96 (2020)
cavity inside) ASTM C
Cavity (every 3rd 1363
or 4th) filled with
M20 concrete, IS 456:2000
reinforced with
8mm dia MS Bar
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 207
Annexure II
10 mm thick Cement
plaster on both sides
12 mm thick Cement
Mortar to lay the bricks
Elevation Section
Plan
208 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
30 mm thick Expanded
Polysterene (XPS-
insulation) Sheet
15 mm thick Cement
Plaster coat
3 mm thick Filtering
Grid made of 0.5 mm
rib mesh
50 mm thick Extruded
Polysterene (XPS) sheet
under the mesh
Vertical stiffner
C-Channel at 200 mm c/c
Horizontal Stiffners
Concrete Infill
Elevation Section
Plan
Figure 91 : Schematic drawing of Structural Stay-in-Place Formwork (Coffor) wall sample with
insulation as per specifications found in BMTPC Performance Appraisal Certificate (PAC) no:
1035-S/ 2018.
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 209
Annexure II
Table 13 : Walling technology and testing details for of Structural Stay-in-Place Formwork (Coffor)
wall sample with insulation
Extruded
ASTM
Polysterene 30 mm thick
C578-19
(EPS) Sheet
Cement Plaster IS
15 mm thick
(for both sides) 1661:1972
3 mm thick
Filtering Grid (with a grid
on both sides made of 0.5
mm rib mesh) ASTM C
1363
Extruded
polyseteren
ASTM
(XPS) sheet 50 mm thick
C578-19
attached to the
filtering grid
Concete (infill)
mix with the
150 mm thick IS 456:2000
steel
reinforcement
210 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
20 mm thick Cement
Plaster on both sides of the
steel wire mesh
Bamboo Frame
(Perpendicular Lattice using
untreated hollow split
bamboo of 4 to 6 mm thick)
Wooden Frame
Elevation Section
Plan
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 211
Annexure II
15 mm thick Homogenous
Daub on both sides of the
Lattice
Bamboo frame
(Perpendicular Lattice using
untreated hollow split
bamboo of 2 to 3 mm thick)
Wooden Frame
Elevation Section
Plan
212 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
15 mm thick Mud
Mortar to lay the
blocks
Stabilized Adobe
Blocks (230 X 230 X
75 mm)
Elevation Section
Plan
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 213
Annexure II
Elevation Section
Plan
214 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Unstabilized Adobe
Blocks (230 X 230 X
75 mm)
Elevation Section
Plan
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 215
Annexure II
Stabilized Compressed
Earth (CEB) Blocks
(230 X 230 X 75 mm)
Elevation Section
Plan
Figure 97: Schematic drawings of the Compressed Stabilized Earth Block (CSEB) Wall
Table 19: Walling technology and testing details for Compressed Stabilized Earth Block (CSEB) Wall
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
15 mm thick
Mud Mortar IS
(sand:soil in
mix 13077:1991
1:5 ratio)
ASTM C
230 x 230 x 75
Stabilized 1363
mm (soil:sand
Compressed IS
:cement:husk
Earth Blocks 1725:1982
in 9:3:0.5:4.5
(CEB)
ratio)
216 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
15 mm thick Mud
mortar to lay the blocks
Unstabilized Compressed
Earth (CEB) Blocks (230
X 230 X 75 mm)
Elevation Section
Plan
Figure 98 : Schematic drawings of the Unstabilized Compressed Earth Block (CEB) Wall
Table 20: Walling technology and testing details for Unstabilized Compressed Earth Block Wall
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
15 mm thick
Mud Mortar IS
(sand:soil in
mix 13077:1991
1:5 ratio)
230 x 230 x 75 ASTM C
Unstabilized 1363
mm (soil:sand
Compressed IS
:cement:husk
Earth Blocks 1725:1982
in 9:3:0.5:4.5
(CEB)
ratio)
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 217
Annexure II
14. Autoclaved Aerated Concrete (AAC) Block Wall with Perlite-based Cement
Plaster
Total wall thickness= 230 mm
U value of the assembly= 0.76 W/m2K
Mortar
15 mm thick Perlite-
based Plaster on both
5 mm thick Cement
Mortar to lay the
blocks
Autoclaved Aerated
Concrete(AAC) Blocks
(600 X 200 X 90 mm)
Elevation Section
Plan
Figure 99: Schematic drawings of the Autoclave Aerated Concrete Block Wall with Perlite-based
cement plaster
Table 21:Walling technology and testing details for AAC Block Wall with Perlite-based cement plaster
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Perlite-based
0.1144 0.01017
Plaster (for both 15 mm thick
W/m.K MJ/m3K
sides)
Cement Mortar IS 1.487 942.16
5 mm thick
mix 2250:1981 W/m.K J/Kg.K ISO ASTM C
0.6269 22007-2 1363
3
Autoclave IS: 2185 MJ/m K
600 X 200 X 0.1877
Aerated Concrete (Part 3)- or
90 mm W/m.K
(AAC) Block 1984 924.15
J/Kg.K
218 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
10 mm thick Mud
mortar to lay the blocks
Unstabilized Rammed
Earth Blocks
(480 X 480 X 230 mm)
Elevation Section
Plan
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 219
Annexure II
10 mm thick Mud
mortar to lay the blocks
stabilized Rammed
Earth Blocks
(480 X 480 X 230 mm)
Elevation Section
Plan
220 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
17. AAC Block Wall with Cement Mortar and Cement Plaster
Total wall thickness= 230 mm
U value of the assembly= 0.78 W/m2K
Mortar
15 mm thick Cement
Plaster coat on both sides
15 mm thick
Cement Mortar
to lay the blocks
AAC Blocks
(600 X 200 X 90 mm)
Elevation Section
Plan
Figure 102: Schematic drawings of AAC block wall with cement mortar and cement plaster
Table 24: Walling technology and testing details for AAC block wall with cement mortar and plaster
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Cement 916.07
Plaster mix IS 1.411 J/kg.K or
15 mm thick
(for both 1661:1972 W/m.K 1.050
sides) MJ/m3K
942.28
15 mm thick
Cement IS: 2250- 1.393 J/kg.K or ISO ASTM C
(cement:sand
Mortar mix 1981 W/m.K 0.8308 22007-2 1363
in 1:4 ratio)
MJ/m3K
Autoclave 893.77
IS: 2185
Aerated 600 X 200 X 0.1810 J/kg.K or
(Part 3)-
Concrete 90 mm W/m.K 0.5111
1984
(AAC) Block MJ/m3K
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 221
Annexure II
18. AAC Block Wall with Lime Mortar and Cement Plaster
Total wall thickness= 220 mm
U value of the assembly= 0.82 W/m2K
Mortar
10 mm thick
Lime Plaster coat
on both sides
15 mm thick
Lime Mortar to
lay the blocks
AAC Blocks
(600 X 200 X 90 mm)
Elevation Section
Plan
Figure 103 : Schematic drawings of AAC block wall with lime mortar and lime plaster
222 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Table 25: Walling technology and testing details for AAC block wall with lime mortar and lime
plaster
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 223
Annexure II
19. Burnt Clay Brick Wall with Lime Mortar and Lime Plaster
Total wall thickness= 250 mm
U value of the assembly= 2.31 W/m2K
Mortar
10 mm thick
Lime Plaster coat
on both sides
12 mm thick
Lime Mortar to lay
the blocks
Burnt Clay Bricks
(230 X 115 X 75 mm)
Elevation Section
Plan
Figure 104: Schematic Illustration of burnt clay brick wall with lime mortar and lime plaster
224 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Table 26: Walling technology and testing details for burnt clay brick wall with lime mortar and lime
plaster
Properties Testing Method
856.28
12 mm thick J/kg.K
Lime Mortar 0.9617 ISO ASTM C
(lime: sand in IS: 712-1984
mix W/m.K 22007-2 1363
1:3 ratio) 1.688
MJ/m3K
933.31
Brunt Clay 230 X 115 X IS 0.5069 J/kg.K
Brick 75 mm 1077:1992 W/m.K
0.7963
MJ/m3K
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 225
Annexure II
12 mm thick Lime
Plaster coat on both
sides
20 mm thick
Lime Mortar to lay
the blocks
Limestone Blocks
(355 X 200 X 140 mm)
Elevation Section
Plan
Figure 105: Schematic drawings of Limestone wall with lime mortar and lime plaster
Table 27 : Walling technology and testing details for Limestone wall with lime mortar and lime plaster
Properties Testing Method
226 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Elevation Section
Plan
Figure 106: Schematic drawings of Limestone wall with cement mortar and cement plaster
Table 28: Walling technology and testing details for Limestone wall with cement mortar and plaster
Properties Testing Method
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 227
Annexure II
22. Hollow Clay Brick (100 mm thk) Wall with Cement Plaster
Total wall thickness= 130 mm
U value of the assembly= 2.71 W/m2K
Elevation Section
Plan
Figure 107: Schematic drawings of hollow clay (100 mm )brick with cement plaster coat on both sides
Table 29: Walling technology and testing details for hollow clay (100 mm )brick with cement plaster
Properties Testing Method
228 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
23. Hollow Clay Brick (100 mm thk) Wall with XPS board on one side and Cement
Plaster
Total wall thickness= 158 mm
Elevation Section
Plan
Figure 108: Schematic drawings of hollow clay bricks (100 mm) wall with extruded polysterene board
on one side and cement plaster coat on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 229
Annexure II
Table 30 : Walling technology and testing details for hollow clay bricks (100 mm) wall with extruded
polysterene board on one side and cement plaster coat on both sides
Properties Testing Method
Extruded
ASTM 0.0316 Not ASTM C
Ploysterene 25 mm thick
C578-19 W/m.K Applicable 518
(XPS) Board
957.91 ASTM C
Cement 1363
15 mm thick J/kg.K
Plaster mix IS 1.389
(cement: sand
(for both 1661:1972 W/m.K 1.315
in 1:1 ratio)
sides)
MJ/m3K ISO
22007-2
872.96
J/kg.K
Hollow Clay 400 X 200 X IS: 3952- 0.635
Brick 100 mm 1988 W/m.K
1.215
MJ/m3K
230 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
24. Hollow Clay Brick (200 mm thk) Wall with Rockwool insulation infill and Cement
Plaster
Total wall thickness= 230 mm
U value of the assembly= 1.83 W/m2K
15 mm thick
Cement Plaster coat
on both sides
Elevation Section
Plan
Figure 109: Schematic drawings of hollow clay bricks (200 mm) wall with rockwool insulation infill
and cement plaster
Table 31: Walling technology and testing details for hollow clay bricks (200 mm) wall with rockwool
insulation infill and cement plaster
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
15 mm thick 957.91
Cement Plaster
(cement: IS 1.389 J/kg K ISO
mix (for both
sand in 1:1 1661:1972 W/m.K 1.315 22007-2
sides)
ratio) MJ/m3K ASTM C
IS 1363
Infill
Not 8183:1993; 0.039 Not ASTM C
Rockwool
Applicable BS EN W/m.K Applicable 518
(insulation)
13162:2012
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 231
Annexure II
15 mm thick
Cement Plaster coat
on both sides
Elevation Section
Plan
Figure 110 : Schematic drawings of hollow clay (100 mm) brick with cement plaster
Table 32 : Walling technology and testing details for hollow clay (100 mm) brick with cement plaster
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Cement 957.91
15 mm thick
Plaster mix IS 1.389 J/kg.K
(cement: sand
(for both 1661:1972 W/m.K 1.315
in 1:1 ratio)
sides) MJ/m3K ISO ASTM C
872.96 22007-2 1363
Hollow Clay 400 X 200 X IS: 3952- 0.635 J/kg.K
Brick 200 mm 1988 W/m.K 1.215
MJ/m3K
232 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
26. Hollow Clay Brick (200 mm thk) Wall with Extruded Polystyrene (XPS) on one
side and Cement Plaster
Total wall thickness= 258 mm
2 mm thick
Cement Screed layer
25 mm thick
Extruded
Polysterene
(XPS) Board
15 mm thick Cement
Plaster on both sides
Elevation Section
Plan
Figure 111 : Schematic drawings of hollow clay (200 mm) brick with XPS on one side and cement
plaster coat on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 233
Annexure II
Table 33:Walling technology and testing detaibls for hollow clay (200 mm) brick with XPS on one side
and cement plaster coat on both sides
Properties Testing Method
234 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
Concrete Wall
(980 X 980 X 100 mm)
Steel Reinforcement-
horizontal and vertical
members
(8 mm dia, at 110 mm c/c)
Elevation Section
Plan
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 235
Annexure II
28. RCC Wall (100 mm thk) with Expanded Polystyrene (EPS) board on one side
Total wall thickness= 153 mm
U value of the assembly= 0.58 W/m2K
2 mm thick
Cement Screed
Concrete Wall
(980 X 980 X 100 mm)
Steel Reinforcement-
horizontal and vertical
members
(8 mm dia, at 110 mm c/c)
Elevation Section
Plan
Figure 113 : Schematic drawings of 100 mm thick RCC Wall with EPS board on one side
Table 35: Walling technology and testing details for RCC Wall with EPS board on one side
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
Cement
2 mm thick
Screed
PVC Film 1 mm thick
Expanded
IS: 4671- 0.0365 Not ASTM C
Ploysterene 50 mm thick
1984 W/m.K Applicable 518
(EPS) Board ASTM C
Steel 8 mm dia, IS: 2062 1363
Reinforcement at 110 mm c/c (Grade A)
942.484
100 mm 1.5831 J/kg.K ISO
Concrete Mix IS: 456-2000
thick W/m.K 1.6891 22007-2
MJ/m3K
236 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
29. RCC Wall (100 mm thk) with Styrofoam (EPS) board on both sides
Total wall thickness= 154 mm
U value of t-he assembly= 0.65 W/m2K
24 mm thick Styrofoam
(insulation) on both sides
Concrete Wall
(980 X 980 X 100 mm)
Steel Reinforcement-
horizontal and vertical
(8 mm dia, at 110 mm c/c)
Elevation Section
Plan
Figure 114 : Schematic drawings of 100 mm thick RCC Wall with Styrofoam (EPS) on both sides
Table 36:Walling technology and testing details for RCC Wall with Styrofoam (EPS) on both sides
Properties Testing Method
Particulars Dimensions Specification Total
Specific
Conductivity Particulars Wall
heat
assembly
Cement
2 mm thick
Screed
PVC Film 1 mm thick
Styrofoam
IS: 4671- 0.0352 Not ASTM C
Board 24 mm thick
1984 W/m.K Applicable 518 ASTM C
(insulation)
Steel 8 mm dia, IS: 2062 1363
Reinforcement at 110 mm c/c (Grade A)
942.484
100 mm 1.5831 J/kg.K ISO
Concrete Mix IS: 456-2000
thick W/m.K 1.6891 22007-2
MJ/m3K
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 237
Annexure II
30. RCC Wall (100 mm thk) with Polyvinyl Chloride (PVC) boards on both sides
Total wall thickness= 112 mm
U value of the assembly= 2.62 W/m2K
Concrete Wall
(980 X 980 X 100 mm)
Elevation Section
Plan
Figure 115: Schematic drawings of 100 mm thick RCC Wall with PVC boards on both sides
Table 37: Walling technology and testing details for RCC Wall with PVC boards on both sides
Properties Testing Method
Total
Particulars Dimensions Specification Specific
Conductivity Particulars Wall
heat
assembly
PVC Board
0.084 0.3468
sealed with 6 mm thick
W/m.K MJ/m3K
silicone gel
8 mm dia,
Steel IS: 2062
ISO ASTM C
Reinforcement @ 110 mm (Grade A)
C/C 22007-2 1363
942.484
100 mm 1.5831 J/kg.K
Concrete Mix IS: 456-2000
thick W/m.K 1.6891
MJ/m3K
238 Centre for Advanced Research in Building Sciece & Energy, CEPT University
Annexure II
31. RCC Wall (100 mm thk) with Expanded Polystyrene (EPS) board on one side and
Polyvinyl Chloride (PVC) board on both sides
Total wall thickness= 165 mm
2 mm thick
Cement Screed
1 mm thick PVC Film
50 mm thick Expanded
Polysterene (EPS) Board
Elevation Section
Plan
Figure 116:Schematic drawings of 100 mm thick RCC Wall with EPS insulation board on one side
and PVC boards on both sides
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 239
Annexure II
Table 38 : Walling technology and testing details for RCC Wall with EPS insulation board on one side
and PVC boards on both sides
Properties Testing Method
Expanded
IS: 4671- 0.0365 Not ASTM C
Polysterene 24 mm thick
1984 W/m.K Applicable 518
(EPS) Board
0.084 0.3468
PVC Board 6 mm thick
W/m.K MJ/m2K
ASTM C
1363
8 mm dia,
Steel IS: 2062
@ 110 mm
Reinforcement (Grade A)
C/C
ISO
22007-2
942.484
J/kg.K
1.5831
Concrete Mix 100 mm thick IS: 456-2000
W/m.K
1.6891
MJ/m3K
240 Centre for Advanced Research in Building Sciece & Energy, CEPT University
References
7. References
1. ASTM. (n.d.). C 1363 – 97: Standard Test Method for the Thermal Performance of Building
Assemblies by Means of a Hot Box Apparatus 1. Retrieved March 25, 2020, from
http://arnisco.com/astm/PDF/C1363.PDF
2. BIS. (1993). IS 2250 - 1981: Code of Practice for Preparation and Use of Masonry Mortars.
3. BIS. (2005). IS 1077 - 1992: Common Burnt Clay Building Bricks -Specifications.
4. BMTPC. (n.d.-a). Retrieved August 18, 2019, from
http://www.bmtpc.org/newsdetails.aspx?mid=27
5. BMTPC. (n.d.-b). BMTPC - Already issued PACs. Retrieved March 5, 2020, from
http://bmtpc.org/topics.aspx?mid=47&Mid1=383
6. BMTPC. (2011). GFRG Panel PAC BMTPC.
http://www.bmtpc.org/DataFiles/CMS/file/PDF_Files/22_GFRG-Panel-RCF.pdf
7. BMTPC. (2014). LGFSS PAC BMTPC.
http://bmtpc.org/DataFiles/CMS/file/PDF_Files/28_PACS_ LGFSS.pdf
8. BMTPC. (2015). Reinforced EPS Core Panel System.
http://bmtpc.org/DataFiles/CMS/file/PDF_Files/34_PAC-EPS.pdf
9. BMTPC. (2017). BMTPC on Twitter: “Expanded polystyrene core panel system(EPS) is the
potential construction technology for mass housing.”
https://twitter.com/bmtpcdelhi/status/907828179225673728
10. BMTPC. (2018a). BMTPC EPS core panel - YouTube.
https://www.youtube.com/watch?v=4pvXDLAZzmo
11. BMTPC. (2018b). BMTPC light gauge steel structure system - YouTube.
https://www.youtube.com/watch?v=4pvXDLAZzmo
12. BMTPC. (2018c). Structural Stay-in-Place Formwork (Coffor) System PAC BMTPC.
http://bmtpc.org/DataFiles/CMS/file/PDF_Files/50_PAC_Coffor.pdf
13. CBERD. (2014). US-India Joint Centre for Building Energy Research and Development.
http://cberd.org
14. Coffor Construction Company LLD. (n.d.). Coffor Structural Formwork. Retrieved April 16,
2020, from https://www.coffor.com/en/
15. Jayasinghe, C. (2016). Comparative Performance of Masonry Bond Patterns. October 2008.
16. MoHUA. (2017). Housing For All- Public brochure. http://mhupa.gov.in
17. MOHUA. (2017). MINISTRY OF HOUSING AND URBAN AFFAIRS, Annual Report 2017-18.
http://moud.gov.in
18. Saurabh, T. (2015). Laurie Baker: A model for Sustainable Architectural Design.
https://www.researchgate.net/profile/Saurabh_Tewari2
19. Swiss Agency for Development and Cooperation SDC. (n.d.). Principles of rat trap bond.
20. Tam, V. W. Y. (2011). Cost Effectiveness of using Low Cost Housing Technologies in
Construction. Procedia Engineering, 14, 156–160.
https://doi.org/10.1016/j.proeng.2011.07.018
21. Varanashi, S. (2012). Masonry walls or concrete columns? - The Hindu.
https://www.thehindu.com/features/homes-and-gardens/Masonry-walls-or-concrete-
columns/article13383124.ece
Part II: Derivation of U-values for Wall Assemblies and Walling Technologies 241
References
242
Advancing Building Energy Efficiency in India
i
APRIL 2024
Supported by
Project By
Construction Agency
243
Advancing Building Energy Efficiency in India
April 2024
Thumbimpressions LLP
244
Authors
Dr. Rajan Rawal, CEPT Research and Development Foundation, CEPT University
Dr. Yash Shukla, CEPT Research and Development Foundation, CEPT University
Krishna Patel, CEPT Research and Development Foundation, CEPT University
Nikhil Bhesaniya, CEPT Research and Development Foundation, CEPT University
Documentation support
Milind Zaveri, Thumbimpressions Collaborative
Graphics by
Krishna Patel, CEPT Research and Development Foundation, CEPT University
Acknowledgments
We gratefully acknowledge all the roof assembly manufacturers for providing us with the necessary
study sample. We also acknowledge International Sustainable Energy Foundation and
Thumbimpressions Collaborative and the supporting artisans for expert execution of all the traditional
roofing assembly samples.
245
Disclaimer
CEPT Research and Development Foundation does not endorse any of the products or
technologies mentioned in this document.
246
CONTENTS
1. Introduction .............................................................................................................................. 252
247
LIST OF FIGURES
Figure 1: Project Outline and research activity protocol .................................................................... 252
Figure 2: Exploded View of the Guarded Hot Box Apparatus .......................................................... 253
Figure 3 Photographs of the metering chamber attached to the specimen frame and the entire ......... 254
Figure 4: 3D showing the specimen frame ......................................................................................... 255
Figure 5: Thatch Roofing Assembly in the GHB specimen frame apparatus ..................................... 255
Figure 6: Selected roofing assembly for testing.................................................................................. 257
Figure 7: Thermal performance evaluation of the selected roof assemblies, lower the U-value, better the
performance ........................................................................................................................................ 259
Figure 8: Project of a warehouse project constructed using Flat PPGI Sheet (Source:
https://www.indiamart.com/proddetail/factory-shed-22308673388.html ) ........................................ 260
Figure 9: Illustration of Flat PUF Insulated roof panel with PPGI sheet sample used as the specimen for
the test. ................................................................................................................................................ 261
Figure 10:Photographs showing Front (left) and the back (right) of the Flat PPGI sheet with PUF Sheet
insulation ............................................................................................................................................. 261
Figure 11:Project of an industrial shed constructed using curved PPGI Sheet ................................... 262
Figure 12: Illustration of Curved PUF Insulated roof panel with PPGI sheet sample used as the specimen
for the test. .......................................................................................................................................... 263
Figure 13: Photographs showing the Front (left) and the back (right) of Curved PPGI sheet with PUF
Insulation within the GHB apparatus .................................................................................................. 263
Figure 14: Project of an industrial shed constructed using TRIMDEK single skin PPGI sheet ......... 264
Figure 15: Illustration of TRIMDEK single skin PPGI sheet with PUF insulation and Aluminum sheet
vapor barrier sample used as the specimen for the test. ...................................................................... 265
Figure 16: Photographs showing the Front (left) and the back (right) of Curved PPGI sheet with PUF
insulation within the GHB apparatus. ................................................................................................. 265
Figure 17: : Project of a house in Bangalore by Good Earth using Timber structure with Mangalore tiles
roofing ................................................................................................................................................. 266
Figure 18: Illustration of Timber with Single sided Mangalore tile roofing sample used as the specimen
for the test ........................................................................................................................................... 267
Figure 19: Photographs showing Front (left) and the back (right) of the Timber with Single sided
Mangalore tile roofing within the GHB apparatus.............................................................................. 267
Figure 20: Roof construction using Timber structure with Double-sided Mangalore tiles roofing .... 268
Figure 21: Illustration of Timber with Double sided Mangalore tile roofing sample used as the specimen
for the test ........................................................................................................................................... 269
Figure 22: Photographs showing the Front (left) and the back (right) of Timber structure with Double
sided Mangalore tiles roofing within the GHB Apparatus.................................................................. 269
Figure 23: Roof construction using Bamboo structure with Clay tiles roofing .................................. 270
248
Figure 24: Illustration of Bamboo with Single sided Mangalore tile roofing sample used as the specimen
for the test ........................................................................................................................................... 271
Figure 25: Photographs showing Front (left) and the back (right) of the Bamboo with Single sided
Mangalore tile roofing within the GHB Apparatus............................................................................. 271
Figure 26: Roof consruction with double sided mangalore tiles roofing ............................................ 272
Figure 27: Photographs showing Front (left) and the back (right) of the Bamboo with double-sided
Mangalore tile roofing within the GHB Apparatus............................................................................. 273
Figure 28: Roof construction of a restaurant using Thatch roof ......................................................... 274
Figure 29: Illustration of Thatch roofing sample used as the specimen for the test ........................... 275
Figure 30: Photographs showing Front (left) and the back (right) of the Thatch roofing within the GHB
Apparatus ............................................................................................................................................ 275
Figure 31: Roof construction of mud house using thatch in Alwar, Rajasthan .................................. 276
Figure 32: Illustration of Thatch roofing with 75mm XPS sample used as the specimen for the test 277
Figure 33: Photographs showing Front (left) and the back (right) of the Thatch roofing within the GHB
Apparatus. ........................................................................................................................................... 277
Figure 34: Roof construction using timber with single sided mangalore tile roofing and cement sheet
............................................................................................................................................................ 278
Figure 35: Illustration of sample used as the specimen for the test .................................................... 279
Figure 36: Photographs showing Front (left) and the back (right) of the timber with single sided
mangalore tiles with cement board within the GHB Apparatus ......................................................... 279
Figure 37:Schematic drawings of Flat PPGI sheet with PUF insulation as per specifications ........... 280
Figure 38:Schematic drawings of Curved PPGI sheet with PUF insulation as per specifications ..... 281
Figure 39:Schematic drawings of TRIMDEK single skin steel with PUF insulation and Aluminium
sheet water proofing as per specifications .......................................................................................... 282
Figure 40: Schematic drawings of timber with single sided Mangalore tiles roof as per specifications
............................................................................................................................................................ 283
Figure 41:Schematic drawings of Timber with double sided Mangalore tiles roof as per specifications
............................................................................................................................................................ 284
Figure 42:Schematic drawings of Bamboo with single sided Mangalore tiles roof as per specifications
............................................................................................................................................................ 285
Figure 43:Schematic drawings of Bamboo with Double sided Mangalore tiles roof as per specifications
............................................................................................................................................................ 286
Figure 44:Schematic drawings of Thatch roof as per specifications .................................................. 287
Figure 45:Schematic drawings of Thatch roof with 75mm XPS insulation as per specifications ...... 288
Figure 46:Schematic drawings of Timber with single sided Mangalore tile roof and cement board roof
as per specifications ............................................................................................................................ 289
249
LIST OF TABLES
Table 1: Selected Roofing Assemblies for testing .............................................................................. 256
Table 2: List of Roofing technologies selected along with source region and manufacturer information
............................................................................................................................................................ 258
Table 3: Thermal transmittance value database of all selected roofing assemblies and technologies.259
Table 4: Roofing technology and testing details for Flat PPGI sheet with PUF Insulation roofing
assembly.............................................................................................................................................. 280
Table 5: Roofing technology and testing details for Curved PPGI sheet with PUF insulation roofing
assembly.............................................................................................................................................. 281
Table 6:Roofing technology and testing details for TRIMDEK single skin steel sheet with PUF
insulation and Aluminium sheet water proofing roofing assembly .................................................... 282
Table 7:Roofing technology and testing details for Timber with single sided Mangalore tiles roof
assembly.............................................................................................................................................. 283
Table 8:Roofing technology and testing details for Timber with double sided Mangalore tiles roof
assembly.............................................................................................................................................. 284
Table 9:Roofing technology and testing details for Bamboo with single sided Mangalore tiles roof
assembly.............................................................................................................................................. 285
Table 10:Roofing technology and testing details for Bamboo with Double sided Mangalore tiles roofing
assembly.............................................................................................................................................. 286
Table 11:Roofing technology and testing details for Thatch roof assembly....................................... 287
Table 12:Roofing technology and testing details for Bamboo with Double sided Mangalore tiles roofing
assembly.............................................................................................................................................. 288
Table 13: Roofing technology and testing details for Timber with single sided Mangalore tile roof and
cement board roof assembly .............................................................................................................. 289
251
Assessment of Research Instruments
1. Introduction
This report submitted by CRDF, CEPT University aims to facilitate knowledge regarding thermal
performance evaluation of roof construction technologies through the derivation of their U-values,
using its state-of-the-art laboratory facilities. To validate their U-value test results for a dependable
reference in sustainable building practices, the research activity protocol has been listed in Figure1.
This database has been envisaged to facilitate efficient and sustainable affordable housing construction
This research activity tests ten roofing assemblies that may fall in one of the following categories:
GHB is used to test the thermal performance of non-homogenous specimens, such as complex wall
assemblies, cavity walls, ventilated shaded wall assembly or walls with phase change materials (PCM).
It determines the amount of heat transfer through a given material or assembly of various materials.
This is done by controlling the temperature on both sides of the material and minimizing the extraneous
heat transfers that takes place through material other than the given one; which can be used to determine
the thermal transmittance of a homogeneous as well as a non-homogenous specimen and can test a
specimen with a maximum thickness of 350mm.
The metering chamber is cooled using a chiller and the guard chamber is maintained at the same
temperature using an HVAC system. The climatic chamber is maintained at higher temperatures using
electric coils. Surface, water and air temperature sensors are placed for temperature control along with
relative humidity (RH), pressure, and air velocity sensors placed at equal distances. The GHB used for
testing is custom made as per ASTM C1363. The range of measurement is 0.1 to 5 W/m2k and the
specimen size must have a maximum width of 980 mm, length of 980 mm and thickness up to 350 mm
(CBERD, 2014). Figure 2 is a photograph showing the assembly of GHB at CARBSE. The testing
procedure is further elaborated in Section 3 of this report
3. Testing Procedure
3.1. General Procedure
The GHB apparatus is traditionally recognized as the only absolute method for thermal conductivity
measurement in a steady state for homogeneous and non-homogeneous materials. To determine the net
energy flow through the specimen, a five sided metering box is placed with the open side against the
warm face of the test panel. Apparently, if there is no net energy exchange across the walls other than
that of the metering box, and only negligible flanking loss around the specimen, the heat input from the
fan and heaters, minus any cooling coil energy extraction from the metering box, would be considered
a measure of the energy flux through the metered area of the specimen. Since it is not practically
possible to have the condition mentioned above, the GHB apparatus is designed to obtain an accurate
measure of the net sample heat flow. Here, the net energy transfer through the specimen is determined
from net measured energy input to the metering chamber, rectifying the losses through the chamber
walls and flanking loss for the specimen at the perimeter of the metering area. The heat loss rate through
the metering chamber walls is curbed by using highly insulated walls and controlling the surrounding
ambient temperature, or by using a temperature controlled guard chamber. That portion of the specimen
outside the boundary of the metering area or the specimen frame, exposed to the guarding space
temperature, constitutes a passive guard to minimize the flanking heat flow in the test panel near the
perimeter of the metering area. The basic hot box apparatus can be assembled in a wide variety of sizes,
orientations, and designs. There are two primary design configurations. The first is the guarded hot box
used for the testing, that has a controlled “guard” chamber surrounding the metering box. An example
of this configuration is presented in Figure 4 (ASTM, n.d.).
Figure 3 Photographs of the metering chamber attached to the specimen frame and the entire
255 Centre for Advanced Research in Building Science & Energy, CEPT University
Testing Procedure
1. Availability from Manufacturers: Samples were sourced from manufacturers who had the product
readily available for procurement.
2. Manufacturers: Preference was given to manufacturers who were willing to provide roofing samples
of the specified dimensions (980mm x 980mm) to accommodate the GHB instrument’s specimen frame
for testing purposes.
3. Inclusion of Traditional Techniques: Samples were chosen from materials and techniques that
reflect traditional roofing practices currently utilized in both vernacular and contemporary green
building methodologies in India.
4. Feasibility for Testing Apparatus: The selection of technology and materials was contingent upon
their feasibility to be constructed into samples that seamlessly fit within the testing apparatus frame. It
was crucial that such construction did not necessitate alterations to the inherent properties of the
materials or deviate from the regional construction methodologies.
8 Thatch roof
257 Centre for Advanced Research in Building Science & Energy, CEPT University
Testing Procedure
Table 2: List of Roofing technologies selected along with source region and manufacturer information
5. Results
Table 3 shows the Thermal Transmittance values obtained for all 10 assemblies and Figure 5 shows
evaluation of the thermal performances of the same.
Table 3: Thermal transmittance value database of all selected roofing assemblies and technologies.
Figure 7: Thermal performance evaluation of the selected roof assemblies, lower the U-value, better the performance
6. Annexures
Annexure I: Summary of the Selected Roofing Technologies
This section is an elaboration on the types of roof samples procured and tested for thermal performance
using GHB.
1. Flat PUF-insulated roof panels with PPGI sheet (Pre-painted galvanized iron)
Flat PPGI (Pre-Painted Galvanized Iron) sheet with PUF (Polyurethane Foam) insulated roof panels
refers to a type of roofing material that combines insulation and a protective outer layer for buildings.
PUF is a type of insulation material that is commonly used in construction. It is formed by combining
two liquid components to create a foam, which is then used to insulate various building elements. PPGI
is a type of steel sheet that has been coated with a layer of zinc to protect it from corrosion, and then
further coated with a layer of paint for aesthetic purposes.
Use: These panels are primarily used as roofing material for various types of buildings, including
commercial, industrial, and residential structures. Some of the advantages include ease of installation,
durability, and corrosion resistance.
Figure 8: Project of a warehouse project constructed using Flat PPGI Sheet (Source:
https://www.indiamart.com/proddetail/factory-shed-22308673388.html )
Figure 9: Illustration of Flat PUF Insulated roof panel with PPGI sheet sample used as the specimen for the test.
Figure 10:Photographs showing Front (left) and the back (right) of the Flat PPGI sheet with PUF Sheet insulation
261 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
2. Curved PUF-insulated roof panels with PPGI sheet (Pre-painted galvanized iron).
The Curved PPGI sheet with PUF insulated roof panels is similar to the Flat PPGI assembly but with
ribbed roofing and wall cladding profile with subtle fluting in the pans to provide strength and long-
spanning capabilities.
Use: These panels are primarily used as roofing material for various types of buildings, including
commercial, industrial, and residential structures.
Source: https://www.indiamart.com/proddetail/badminton-court-roofing-sheds-shuttle-court-constructions-in-chennai-tamil-
nadu-india-14464440797.html?pos=10&pla=n
Figure 12: Illustration of Curved PUF Insulated roof panel with PPGI sheet sample used as the specimen for the test.
Figure 13: Photographs showing the Front (left) and the back (right) of Curved PPGI sheet with PUF Insulation within the
GHB apparatus
263 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
3. TRIMDEK single skin Steel sheet with PUF insulation and Aluminium sheet vapour barrier
LYSAGHT TRIMDEK 1015 is a versatile, trapezoidal ribbed roofing and wall cladding profile with
subtle fluting in the pans to provide strength and long spanning capabilities. It is ideal for industrial and
commercial applications. It is manufactured from high strength steel and provides excellent spanning
capability resulting in better design freedom. TRIMDEK is manufactured from Al-Zn alloy coated steel
that offers excellent corrosion resistance and lasts up-to four times more than ordinary Zinc coated steel
profiles. TRIMDEK profile comes with Solar Reflectance Technology that lowers surface temperature
by absorbing lesser heat from the sun. It keeps both roofs & buildings cooler at reduced energy costs.
Use: These panels are primarily used as roofing material for various types of buildings, including
commercial, industrial, and residential structures.
Figure 14: Project of an industrial shed constructed using TRIMDEK single skin PPGI sheet
Source: https://tatabluescopesteel.com/products-solutions/durashine/purlin/
Figure 15: Illustration of TRIMDEK single skin PPGI sheet with PUF insulation and Aluminum sheet vapor barrier sample
used as the specimen for the test.
Figure 16: Photographs showing the Front (left) and the back (right) of Curved PPGI sheet with PUF insulation
within the GHB apparatus.
265 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
The single-sided Mangalore tile roofing stands out as a foundational and widely embraced roofing style
in India. Crafted from baked clay, Mangalore tiles exhibit remarkable qualities, inherently resisting
moisture absorption and heat retention, making them both waterproof and heat-resistant. Beyond their
durability, the design of these tiles ensures effective rainwater drainage, making them especially suited
for regions with heavy rainfall. Their versatility and reliability position them as a preferred choice,
offering a sturdy and weather-resistant solution for a range of architectural applications.
An additional advantage lies in the ease of maintenance, as these tiles can be replaced individually when
broken, eliminating the need for replacing the entire roof. The straightforward installation process
further contributes to its widespread adoption as a roofing material across the country.
Use: Mangalore tiles have garnered widespread popularity for residential roofing, particularly in
tropical or coastal climates.
Figure 17: : Project of a house in Bangalore by Good Earth using Timber structure with Mangalore tiles roofing
Source: https://goodearth.org.in/connect/materials/benefits-of-clay-roof-tiles/
Figure 18: Illustration of Timber with Single sided Mangalore tile roofing sample used as the specimen for the test
Figure 19: Photographs showing Front (left) and the back (right) of the Timber with Single sided Mangalore tile roofing
within the GHB apparatus
267 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
This roofing assembly features a unique design, incorporating two layers of Mangalore tiles. Unlike
conventional assemblies, this design includes one layer positioned conventionally on the top, while an
additional layer is installed beneath, serving a dual purpose as both a structural component and a false
ceiling. The crucial element of this innovative design lies in the air gap between the two layers of
Mangalore tiles, creating an effective insulating barrier. This dual-layered system not only enhances the
structural integrity of the roof but also contributes to improved thermal insulation, making it a
sophisticated and efficient solution for roofing applications.
Use: This assembly is commonly seen in residences, schools, churches in the hot and humid regions
of the country
Figure 20: Roof construction using Timber structure with Double-sided Mangalore tiles roofing
Source: https://m.youtube.com/watch?v=so-bvHB9rSk
Figure 21: Illustration of Timber with Double sided Mangalore tile roofing sample used as the specimen for the test
Figure 22: Photographs showing the Front (left) and the back (right) of Timber structure with Double sided Mangalore tiles
roofing within the GHB Apparatus
269 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
The assembly typically composed of timber and Mangalore tiles can seamlessly incorporate bamboo as
a substitute for timber, offering a practical alternative, especially in regions where acquiring timber
poses challenges. Bamboo proves to be a fitting replacement due to its ready availability in comparable
section sizes and its impressive combination of durability, tensile strength, and compressive strength,
allowing it to bear substantial loads.
Use: This particular assembly is also used in the construction of roofs of houses in regions where timber
is difficult to get.
Figure 23: Roof construction using Bamboo structure with Clay tiles roofing
Source: https://bamboou.com/how-to-install-a-clay-tile-roof/0-cover-how-to-install-a-clay-tile-roof-for-a-bamboo-building/
Figure 24: Illustration of Bamboo with Single sided Mangalore tile roofing sample used as the specimen for the test
Figure 25: Photographs showing Front (left) and the back (right) of the Bamboo with Single sided Mangalore tile roofing
within the GHB Apparatus
271 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
Similar to the timber with double-sided Mangalore tiles roofing, this assembly simply replaces the
timber with bamboo counterparts. In areas where timber scarcity is a concern, the easy adaptability of
bamboo becomes a significant advantage. Its robust structural properties make it a reliable choice for
maintaining the integrity of the assembly. This substitution not only addresses the issue of timber
availability but also aligns with sustainable and eco-friendly construction practices, given bamboo’s
renewable and fast-growing nature. Consequently, this adaptable and resource-efficient modification
ensures the continued feasibility and resilience of the timber and Mangalore tile assembly.
Use: Similar to the previous assembly, this roofing assembly is used for the constuction of houses in
the regions where timber is difficult to get.
Figure 26: Roof consruction with double sided mangalore tiles roofing
Source: https://m.youtube.com/watch?v=so-bvHB9rSk
Figure 27: Photographs showing Front (left) and the back (right) of the Bamboo with double-sided Mangalore tile roofing
within the GHB Apparatus
273 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
8. Thatch roofing
Thatch roofing, a prevalent choice for rural dwellings in India, is crafted from dried hay sourced from
maize or millet crops after the harvest season. This eco-friendly roofing material, known for its
exceptional insulating qualities, is not only readily available but also contributes to sustainable
construction practices.
The construction of a thatch roof typically involves layering and securing bundles of dried hay in an
overlapping fashion. A sturdy framework, often made from bamboo or timber, supports the thatch
bundles. The layers of hay create a dense and effective barrier against external elements while allowing
for optimal ventilation. Additionally, a well-constructed thatch roof can withstand varying weather
conditions, providing reliable shelter to occupants.
Use: Thatch roof is majorly used as a DIY material to construct houses in the rural regions. Some
moderns buildings have also used thatch roof like the example shown below.
Source: https://www.archdaily.com/900248/bamboo-long-house-restaurant-bambubuild/5b73f291f197ccf52700026e-
bamboo-long-house-restaurant-bambubuild-photo
Figure 29: Illustration of Thatch roofing sample used as the specimen for the test
Figure 30: Photographs showing Front (left) and the back (right) of the Thatch roofing within the GHB Apparatus
275 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
Thatch roof construction, a traditional technique, combines natural aesthetics with modern insulation
like XPS (Extruded Polystyrene). Typically, thatch comprises dried hay layered on a timber, bamboo
or metal roof frame. Integrating XPS insulation enhances energy efficiency by offering thermal
resistance, minimizing heat transfer and maintaining interior comfort. The XPS insulation also provides
durability, resisting moisture and mold growth, prolonging the roof’s lifespan offering sustainable and
comfortable shelter solutions.
Figure 31: Roof construction of mud house using thatch in Alwar, Rajasthan
Source: https://www.archdaily.com/989711/mud-house-sketch-design-studio/63344dc44dba6e02cc399a6a-mud-house-
sketch-design-studio-photo
Figure 32: Illustration of Thatch roofing with 75mm XPS sample used as the specimen for the test
Figure 33: Photographs showing Front (left) and the back (right) of the Thatch roofing within the GHB Apparatus.
277 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure I
10. Timber + Single sided Mangalore tile roofing with Cement Fiber Board
Timber with single sided mangalore tile roofing can be constructed with a several variations like cement
fiber board, insulations, etc. We chose this particular variation since its use is widespread and it is easy
to construct. This variation involves using cement fiber boards as an underlayment beneath the
Mangalore tiles. CFB provides a solid and durable surface for the tiles to rest upon. It enhances the
structural integrity of the roof, improves weather resistance, and helps prevent water seepage.
Additionally, CFB is resistant to fire, pests, and rot, further increasing the longevity of the roof.
Figure 34: Roof construction using timber with single sided mangalore tile roofing and cement sheet
Source: https://www.ecopro.co.in/fibre-cement-roofs-a-growing-trend-in-india/
Figure 35: Illustration of sample used as the specimen for the test
Figure 36: Photographs showing Front (left) and the back (right) of the timber with single sided mangalore tiles with cement
board within the GHB Apparatus
279 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure II
ELEVATION SECTION
PLAN
Figure 37:Schematic drawings of Flat PPGI sheet with PUF insulation as per specifications
Table 4: Roofing technology and testing details for Flat PPGI sheet with PUF Insulation roofing assembly
Properties
IS 3069:1994
PUF
IS : 12436 - 120 ASTM C518 0.02901 - 0.0413
Insulation
1988
ELEVATION SECTION
PLAN
Figure 38:Schematic drawings of Curved PPGI sheet with PUF insulation as per specifications
Table 5: Roofing technology and testing details for Curved PPGI sheet with PUF insulation roofing assembly
Properties
IS 3069:1994
PUF
IS : 12436 - 80-120 ASTM C518 0.02901 - 0.0413
Insulation
1988
281 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure II
3. TRIMDEK single skin steel sheet with PUF insulation and Aluminium sheet water proofing
ELEVATION SECTION
PLAN
Figure 39:Schematic drawings of TRIMDEK single skin steel with PUF insulation and Aluminium sheet water proofing as
per specifications
Table 6:Roofing technology and testing details for TRIMDEK single skin steel sheet with PUF insulation and Aluminium
sheet water proofing roofing assembly
Properties
PUF IS 3069:1994
50-75 ASTM C518 0.02901 - 0.0413
Insulation IS : 12436 - 1988
ELEVATION SECTION
PLAN
Figure 40: Schematic drawings of timber with single sided Mangalore tiles roof as per specifications
Table 7:Roofing technology and testing details for Timber with single sided Mangalore tiles roof assembly
Properties
283 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure II
ELEVATION SECTION
PLAN
Figure 41:Schematic drawings of Timber with double sided Mangalore tiles roof as per specifications
Table 8:Roofing technology and testing details for Timber with double sided Mangalore tiles roof assembly
Properties
ELEVATION SECTION
PLAN
Figure 42:Schematic drawings of Bamboo with single sided Mangalore tiles roof as per specifications
Table 9:Roofing technology and testing details for Bamboo with single sided Mangalore tiles roof assembly
Properties
285 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure II
ELEVATION SECTION
PLAN
Figure 43:Schematic drawings of Bamboo with Double sided Mangalore tiles roof as per specifications
Table 10:Roofing technology and testing details for Bamboo with Double sided Mangalore tiles roofing assembly
Properties
8. Thatch roof
ELEVATION SECTION
PLAN
Table 11:Roofing technology and testing details for Thatch roof assembly
Properties
287 Centre for Advanced Research in Building Science & Energy, CEPT University
Annexure II
ELEVATION SECTION
PLAN
Figure 45:Schematic drawings of Thatch roof with 75mm XPS insulation as per specifications
Table 12:Roofing technology and testing details for Bamboo with Double sided Mangalore tiles roofing assembly
Properties
10. Timber with single sided Mangalore tile roof and cement Board
ELEVATION SECTION
PLAN
Figure 46:Schematic drawings of Timber with single sided Mangalore tile roof and cement board roof as per specifications
Table 13: Roofing technology and testing details for Timber with single sided Mangalore tile roof and cement board roof
assembly
Properties
Cement
IS 14862 : 2000 12 0.5128 - 1.1073
Fiber Board
289 Centre for Advanced Research in Building Science & Energy, CEPT University
References
ASTM. (n.d.). C 1363 – 97: Standard Test Method for the Thermal Performance of Building Assemblies
by Means of a Hot Box Apparatus 1. Retrieved March 25, 2020, from
http://arnisco.com/astm/PDF/C1363.PDF
ISO 22007-2 : Plastics — Determination of thermal conductivity and thermal diffusivity —Part 2 :
Transient plane heat source (hot disc) method. Edition 2022-06
C518 − 21 Standard Test Method for Steady-State Thermal Transmission Properties by Means of the
Heat Flow Meter Apparatus, Published September 2021. DOI: 10.1520/C0518-21
Project by:
Thermo-Physical Properties
of
Construction Materials
Annexure -009_March 2014
U.S.-India Joint Center for Building Energy Research and Development (CBERD)
Thermal Specific
Density
Name Form Conductivity Heat Image Description
kg/m³
W/(mK) MJ/m³K
Acrylic Sheet Board 1145 0.2174 1.5839 Acrylic sheet has unique physical characteristics. It is much clear, more impact resistant and weighs half
as compared to finest optical glass. It doesn’t turn yellow after a while, has 92 % light transmittance and is
an excellent insulator. It is available in number of translucent as well as transparent colours.
Armor Insulation 270 0.0678 0.1578 Armor is a class – A building product made up of very high quality natural cotton fibres. It is eco-friendly
and carries high resistance values in case of smoke, fungi, fire and corrosiveness.
Asbestos Cement Board 1404 0.4709 0.7218 Asbestos cement board contains high proportion of asbestos sheet which are bonded together with Portland
Board cement. It is a dense rigid board which is resistant to flame, weathering and fire and doesn’t allow easy heat
flow. It is mostly used in board form in buildings.
Asbestos Sheet Board 1377 0.5128 1.2043 Asbestos sheet is made up of very high quality of asbestos fibres. It is very durable, fire resistant and very
-Shera efficient insulating material. It is used in form of sheet. Asbestos cause’s health risks therefore the use of
it nowadays has gone minimal.
Autodaved Aerated Block 642 0.1839 0.7940 AAC is a porous, lightweight, resource efficient concrete used as precast building material providing
Concrete Block structure, insulation, and fire and mould resistance. Its improved thermal efficiency helps in reducing
(AAC) building heating and cooling load. AAC is manufactured by mixing a silica rich material such as fine
ground sand or fly ash, cement, a sulphate source such as gypsum, quicklime, a rising agent and water.
Workability allows accurate cutting and easy installation thus minimizing generation of solid waste. AAC
products include blocks, wall panels, floor and roof panels, and lintels.
Bamboo Wood 913 0.1959 0.6351 Bamboo is type of plant with hard hollow stem. It is woody in nature and has an extremely hard surface.
Before application it needs to be chemically treated. It is considered as one of the best renewable
resources available on earth. Apart from its other structural non-structural uses it is also used as
reinforcement these days.
Brass Metal 8500 106.4800 11.1164 Brass has muted yellow colour and higher malleability in comparison to bronze and zinc. The relatively
low melting point of brass and its flow characteristics makes it a relatively easy material to cast. Its
cost effectiveness, low manufacturing, corrosion resistance and machinability allow manufacturers to
produce vast range of products. It is mostly used in Commercial plumbing and OEM applications also its
antibacterial properties make it useful for doorknobs especially in hospitals.
Calcium Silicate Board 1016 0.2810 0.8637 Calcium silicate board is considered much safer and better option than asbestos cement board for
Board providing insulation. It is used in construction industry as insulation and can also be used for equipment
insulation.
Cement Board Board 1340 0.4384 0.8113 A cement board is made up of cement and reinforcing fibres which are then formed into various sizes of
board. It is mainly used as a backing board which adds strength and impact resistance to wall and is better
in comparison to gypsum boards. Thin cement board sheets allows bending in case of curved surfaces.
Cement Bonded Board 1251 0.3275 1.1948 Cement Bonded Particle Board (CBPB) is dimensionally stable having superior structural integrity and
Particle Board does not delaminate in water. CBPB can be sanded, routed, drilled, sawn, planed, nailed and screwed
with standard carpentry tools. The board is easy to maintain as it is highly scratch resistant and resistive
towards pest. Available in various sizes and is applicable for False Ceiling, Wall Cladding, kitchen cabinets,
Cupboards, Cabins, Partitions and Door panels.
Ceramic Fiber Insulation 128 0.0491 0.1093 Ceramic fibre blanket is manufactured from high strength spun ceramic fibres. It is lightweight, thermally
Blanket efficient, have excellent thermal stability, low shrinkage at elevated temperature, low heat storage, good
cold strength, excellent hot strength, thermal shock resistance and excellent resistance to most chemicals.
It is used as insulation in construction industry.
Cement Fiber Board 1276 0.3880 0.8973 Cement fibre Board Panel is made up of cement, sand and recycled wood waste available at economic
Board pricing. Fibre cement board is more durable and less toxic then vinyl and have less maintenance than
wood. It is resistant to fire, insects, rot and general decay. Waterproof, fire resistant polymer texture coating
is applied on exterior panels. It is used for roof panels, wall panels, false ceiling, door, window etc.
Cement Plaster 278 1.2080 0.9719 Cement plaster is mixture of suitable sand, portland cement and water which is normally applied to
masonry interiors and exteriors to achieve a smooth surface.
Cement Powder Powder 1070 0.1137 0.7943 Cement power is made by heating limestone and then grinding it to form fine powder. This powder when
mixed with stone, sand and aggregate forms concrete. It is widely used in construction.
Ceramic Blue Tile Tile 2707 1.3720 1.2082 Ceramic tile is made up of materials like porcelain and earthenware. It is extremely durable, has great
strength. Cooling and heating systems can be installed underneath it. This particular tile is blue in colour
and is available in many colours and sizes. It can be used in wide range of application like flooring, shower
area, roofing, countertops and walls.
Ceramic Tile - Tile 2549 0.8018 1.6168 Ceramic bathroom tile has great strength, is extremely durable and easy to maintain and is preferred for
Bathroom use at places where hygiene is a prime concern like bathroom. It is also anti-water absorption and easy to
clean.
Ceramic Tile Tile 2700 1.5996 1.1438 Ceramic tile is made up of materials like porcelain and earthenware. It is extremely durable, has great
strength. Cooling and heating systems can be installed underneath it. It can be used in wide range of
application like flooring, shower area, roofing, countertops and walls.
Chile Wood Wood 362 0.1422 0.4102 Chile is a white or pale yellow soft wood mostly found in northern hemisphere. It is light in weight and
straight grained. It is resistant to shrinking and swelling and is mostly used in packing materials.
Chitodio Stone 3209 3.7512 2.1223 Chitodio stone is available in different design and colours and is mainly used as flooring of super market,
shopping mall, warehouse flooring, etc.
Clay Tile Tile 2531 0.6323 1.4253 Clay tile is made of rich earth which is known for its plasticity. It is used for number of application like
roofing, flooring, wall cladding etc. and adds pleasing natural look to the place.
Float Glass/ Glass 2477 1.0522 1.9654 Float glass is manufactured from common glass making raw materials where some additional refining
Clear Glass agents are added to it to improve its properties. It can be tempered, bent, laminated and can also be
decorated.
Concrete Block Block 2427 1.3957 0.4751 Concrete Block 25/50 also called concrete masonry unit (CMU) is a precast concrete block. Most
25/50 concrete block have one or more hollow cavities, and their sides may be cast smooth or with a design. It is
widely used in construction industry for making walls.
Corian Board 1750 1.0120 2.0921 Corian is a solid, homogeneous, non-porous surfacing material composed of natural minerals and acrylic
resin. It can be thermoformed by heating, allowing unique shapes to be created. It is very durable,
hygienic, repairable, non-toxic, translucent, colourful, creates inconspicuous joints and is workable like
hardwood. Corian solid surfaces deliver high performance and outstanding aesthetics. It can be used for
wall cladding, kitchen countertops and bathroom vanity tops.
Crystal White Tile Tile 2390 1.5094 1.9427 Crystal white tile is a man-made material having crystal, sparkly finish known for its strength and
durability. Crystal tile is available in wide variety of colours, finished and sizes. Workability is easy but
has to be laid with great precision. It can be customised as per client’s requirement and adds different
dimension to space when teamed with mosaics, border tiles, wood furnishing etc. It is widely used for
bathrooms, kitchens, hallways flooring.
Dholpuri Stone Stone 2262 3.0840 1.5830 Dholpur stone is a type of sandstone having good mechanical strength, low water absorption, saline water
resistance, weather resistance and superior performance. It is available in various colours and sizes. It is
used for interior as well as exterior application such as landscaping, stonewalls, roofing, flooring, cladding,
pillars etc.
Distilled Water Water 1000 0.6134 3.8165 Distilled water is composition of hydrogen and oxygen molecules and is widely used in construction
projects.
Engineered Wood Tile 571 0.2527 1.4230 Engineered wood floor is composed of multiple layers of wood in form of plank that are cross layered, glues
Floor Tiles and pressed together. It is more resistant to higher moisture levels as compared to slid wood flooring thus
are widely used in regions having higher relative humidity levels. Engineered wood is much more stable
making it a universal product that can be installed over all types of subfloors.
Extruded Insulation 30 0.0321 0.0374 Extruded polystyrene (XPS) foam plastic insulation has a closed cell structure and lacks voids which
Polystyrene XPS make XPS very strong and durable material. It has low thermal conductivity and diffusivity. Its closed
cell structure helps resist moisture penetration without even using a facer. It is available in variable
compressive strength and is used for insulation in wall, roof, ceiling and building foundation.
Fiber Reinforced Board 1183 0.2252 1.6930 Fibre reinforced plastic is made by reinforcing fibres like carbon fibre, glass fibre etc. It is light weight, is
Plastic (FRP ) resistant to corrosion and has good mechanical properties thus offering environmental benefits.
Floor Board Board 954 0.2654 1.1423 Engineered wood flooring is made up of number of wood layers. It possesses great strength and stability
which is achieved by running each layer of wood at a 90° angle to the layer above. It is widely used across
the globe and can be installed over all types of subfloors.
Foam Cement Block 581 0.1588 0.5359 Form cement block is a light weight block which is used in construction of non-structural walls in order to
Block reduce the amount of structural concrete and steelwork. Its use leads to significant cost saving and also
provides thermal insulation.
Ghana Teak Wood Wood 529 0.2062 0.5769 Ghana teak wood has high strength, excellent durability and can withstand extreme weather conditions. It
is also known for its aesthetic appearance. It is mostly used in flooring, furniture, wall cladding, window &
door frames.
Glasswool Insulation 49 0.0351 0.0339 Glass wool or fibre glass insulation is made up of fibre glasses which are arranged into a texture similar
to wool. It is thermal and acoustical efficient and is available in form of sheets and rolls. It is inorganic in
nature and is non-corrosive, non-combustible and doesn’t absorb moisture.
Black Fine Granite Stone 3535 2.4351 2.2511 Granite is a type of igneous rock consisting of mica, quartz and feldspar. It is granular and crystalline in
texture. It has been used as flooring for decades now. It can be pink to grey in colour.
Black Coarse Stone 3473 2.5433 2.1996 Granite is a type of igneous rock consisting of mica, quartz and feldspar. It is granular and crystalline in
Granite texture. It has been used as flooring for decades now. Black Coarse granite as the name defines is coarse
in nature.
Green Marble Stone 2650 2.3720 2.5275 Marble is a metamorphic rock composed of recrystallized carbonate minerals mostly calcite. It has been in
use for more than 450 years now.
Gypsum Board Board 623 0.2527 0.6033 Gypsum board is also known as wallboard or drywall. It is made of plaster of paris and componenet of
cement. It is used as sheathing for interior walls and ceiling and provides a smooth surface finish. The
board is available in different thickness like 6mm, 12mm and 18mm.
Gypsum Powder Powder 588 0.2020 1.1918 Gypsum powder is formed form gypsum stone by heating the stone. The powder is known for adding
strength and viscosity to the material. It is used for plaster, paint and drywall.
Gypsum Powder Powder 542 0.1033 0.6260 Gypsum powder from board is formed form gypsum board. The powder is known for adding strength and
from Board viscosity to the material. It is used for plaster, paint and drywall.
Italian Black Stone 2911 2.3636 2.2349 Granite is a type of igneous rock consisting of mica, quartz and feldspar. It is granular and crystalline in
Granite texture. It has been used as flooring for decades now. It is used in bathrooms, kitchens etc.
Italian Marble Stone 2630 2.7752 2.1869 Marble is a metamorphic rock composed of recrystallized carbonate minerals mostly calcite. It has been in
use for more than 450 years now. It is mainly used as flooring and wall cladding in construction industry.
Jaisalmer Yellow Stone 3006 2.7447 2.0954 Jaisalmer Yellow is a type of limestone and is very fine grained as compared to other limestone. It has
Stone been used in monumental buildings and is used as flooring and cladding nowadays.
Jalore Stone 2982 3.4412 1.9617 Granite is a type if igneous rock consisting of mica, quartz and feldspar. It is granular and crystalline in
texture. It has been used as flooring for decades now. It is used in bathrooms, kitchens etc.
Laminated Board 656 0.1841 1.2621 Particle board is made up of saw dust and other wood waste. It is an inexpensive material used in place of
Particle Board wood panelling or boards. It is used only for interior projects and is not much durable. It can be machined
as per the customer need.
Lime Powder Powder 607 0.1286 0.7078 Lime powder in an inorganic compound also called slaked lime. It is either white or colourless crystal. It is
extensively used in construction industry.
Mangalore Roof Tile - Roof 2531 0.6051 1.2809 Mangalore tiles are red coloured tiles prepared from laterite clay. It is eco-friendly, cheap, durable and
Tile is available in different size and shapes as per users need. Due to vast availability of sizes and shapes
they are easy to handle and install but precaution is needed as these are delicate and are vulnerable to
breakage. These tiles can be used in many creative ways but their maintenance is an issue.
Ambaji Marble Stone 3128 2.8108 2.1943 Marble is a metamorphic rock composed of recrystallized carbonate minerals mostly calcite. It has
been in use for more than 450 years now. It is mainly used as flooring and wall cladding in construction
industry.
Medium Density Board 133 0.2045 0.9610 Medium density fibreboard is a type of hardwood made from wood fibres forming panels by applying high
Fiberboard (MDF) pressure and temperature. It is stronger and denser than plywood, is flat and has no knots. Workability
includes easy cutting, drilling, machining and filing without damaging the surface. It can also be painted to
produce smooth surface. It is used for making wall panels, display cabinets and storage units.
Melamine Board 807 0.2459 0.6509 Melamine Fibre board is used in the auto industry to create free-form shapes such as dashboards, rear
Fiberboard parcel shelves, and inner door shells.
Mild Steel (MS) Metal 7823 44.1170 4.1896 Mild Steel is one of the least expensive steel and most common metal used and is founded in almost every
product created from metal. It is relatively hard, very durable and can be easily welded and annealed. It
has poor resistance to corrosion and has to be protected. Its structural strength doesn’t allow MS to be
used for beams and girders.
Mineral Fiber - Board 773 0.2739 0.6427 Mineral fibre plain board is fire proof, mould proof, ensures better sound absorption and is a thermal
Plain insulator. It is eco-friendly and is ideally suited for places where high privacy levels are required.
Oak Laminated Tile 949 0.2652 1.3389 Oak laminated floor tile is extremely durable, is resistant to damage and easier to keep clean. It is very
Floor Tiles easy to install and is much more affordable than wood flooring.
Concrete Paver Tile 2210 1.7248 1.3413 Concrete paver tile is precast concrete form used widely as a tile. TIt is known for its strength, durability
Tiles and east application. Workability includes laying of interlocking tiles without using grout, instead sand
particles are spread over the pavers and tamped down thus they can be easily removed and reinstalled in
case some service needs to be provided. They are available in various textures and colours and are mostly
used in exterior pavement applications.
Paver Tile Tile 2612 1.4763 1.2737 Paver tile looks like brick but just half as thick as brick. It is durable and frost-proof and come in all the
colours that a brick comes into. They are used for flooring.
Plain & Board 902 0.2710 0.9740 Plain & pre laminated particle board is manufactured using plantation species of timber known for
Prelaminated superior finish, high durability, excellent machinability and resistance to termite, water and moisture. It is
Particle Board eco-friendly wood based panel board which is cost effective and extremely versatile. It is used for making
panel doors, flush doors, flooring, partitioning, false ceiling, wall panelling etc.
Plaster of Paris Powder 1000 0.1353 0.9526 Plaster of Paris is made by heating gypsum. It can be moulded in varies shapes and sizes after adding
(POP) Powder water to the powder. Its setting time is very less and is used in art, architecture, fireproofing, and medical
applications.
Plywood Board 697 0.2210 0.7258 Plywood is flexible, workable and re-usable. It is also resistant to cracking, splitting, shrinkage and twisting
and has good strength. It is widely used in building and furniture industry.
Polymer Plastic 1743 0.5027 1.6968 A polymer is created through the process called polymerisation. It is used as wall panels, sealing, coating,
(Anisotropic) roofing material and for piping system.
Polyurethane Insulation 40 0.0372 0.0704 Flexible polyurethane foam is used for thermal insulation and is most often used in bedding and
Foam (PUF) upholstery. Flexible polyurethane can be cut into various shapes. In construction rigid polyurethane is
commonly used.
POP Board Board 1080 0.4994 1.2167 POP is made by heating gypsum powder. POP board is a layer of plaster sandwiched between two sheets
of card board. Plaster board puts very little pressure on the environment. The product is non-toxic and
unwanted by-products from the process are minimal.
Porcelain Tile Tile 2827 1.5331 1.6259 Porcelain tile is ceramic tile. It has very less water absorption rate and can be glazed or kept unglazed. It
is used for flooring as well as wall cladding.
Pumice Square - Tile 2327 0.9907 0.4382 Bronze tiles is made of ceramic and various metal mixtures. It is engineered in a way that it look like
Bronze Tile bronze surface. It can be painted but surface needs to be conditioned before applying paint.
Quartz Stone 2359 3.7603 1.8277 Natural Quartz is the hardest non- precious crystal stone mined directly from the earth. Quartz surfaces
are created from pure natural Quartz. Its good looks and everlasting finish can be easily maintained by
simple and routine care and can be used in areas prone to footfalls and weathering. It is mostly used as
flooring material for commercial and residential projects.
Rajnagar Marble Stone 3332 5.6405 2.7770 Marble is a metamorphic rock composed of recrystallized carbonate minerals mostly calcite. It has been in
use for more than 450 years now. It is mainly used as flooring and wall cladding in construction industry.
Rigid Polyurethane Insulation 25 0.0384 0.0763 Rigid polyurethane foam is a very versatile material having great combination of physical strength and
(25 Kg/m3) mechanical properties. It can be used at places where insulation needs to be combined with load bearing.
It is impact resistant, known for its longevity, space saving and has low maintenance.
Rockwool Insulation 64 0.0461 0.0904 Rockwool insulation is made of actual rocks and minerals. It is also called stone wool insulation or
mineral wool insulation. It is known for its thermal resistance and sound absorptivity. It is commonly used
in building construction, industrial plants, and in automotive applications.
Rubber - Foam Insulation 89 0.0561 0.1486 Foam rubber is manufactured by forming gas bubbles in a plastic mixture with the help of blowing agent.
Foam rubber contains roughly 85 percent air and 15 percent rubber. Workability allows easy cutting and
fixing. It is used as insulation, expansion joint filler in masonry and concrete work and filler support sealant
in traffic bearing joints.
Rubber Wood Wood 472 0.1679 0.5034 Rubberwood has a dense grain character with little tendency to wrap or crack. It is eco friendly as it
is only harvested when it can no longer be used for its latex producing sap. Rubberwood has very less
shrinkage and is one of the more stable construction materials. It is extensively used in furniture industry
and for making kitchen accessories. Outdoor usage of the products is not recommended. Rubberwood
latex is also used for rubber based products.
Saag Wood Wood 959 0.2886 1.0258 Saag (Teak) is a yellowish brown timber having high oil content, high tensile strength and tight grain
making it a suitable option for outdoor furniture applications. Easy workability but presence of silica in
the wood causes severe blunting on edged tools. It is resistant to termite attacks and over time matures
to silvery grey finish. Used for manufacturing of articles where weather resistance is required and also for
indoor furnishing such as flooring, countertops, furniture, doors and window frames.
Sand Powder 1600 0.3075 1.1343 Sand is composed of rock and mineral particles and is a granular material. Its composition highly
depends on type of rock and mineral availability. In is widely used in building construction and
landscaping.
Sandstone Stone 2530 3.0097 1.5957 Sandstone is a sedimentary rock available in various colours. It is a valuable aquifer as it allows
percolation of water and stores large quantities. It is also helpful to filter out pollutants from the surface
and is a commonly used building material.
Soft Board Board 274 0.0943 0.2753 Soft Board is a light coloured sheet made up of bagasse. It is soft and resilient and is known for its sound
absorbing properties. It is available in variable thickness. It is used in wall and ceiling lining as acoustic
boards.
Soft Board-High Board 353 0.0983 0.2621 Soft Board is a light coloured sheet made up of bagasse. It is soft and resilient and is known for its sound
Density absorbing properties. It is available in variable thickness. It is used in wall and ceiling lining as acoustic
boards.
Stainless Steel Metal 7950 13.5633 3.6351 Stainless steel is an ideal material as it requires low maintenance, is resistant to corrosion. It differs
(SS) from the carbon steel by the mount of chromium present. The carbon steel rusts easily when exposed to
moisture whereas stainless steel doesn’t corrode, rust or stain but it is not fully stain proof. It is used in
buildings for practical as well as aesthetic reasons.
Steam Beech Wood 241 0.2331 0.5512 Beech is pale coloured, medium to heavy weight, hard and tough wood having good strength and high
Wood abrasion resistance. Workability is easy despite of its hardness. It can be cut, drilled, planed and milled.
Surface finishing of Beech is very straight forward as it can be stained, painted and polished. Beech can
shrink considerable and is subject to movement as compared to other woods. It is used for furniture,
interior furnishing, household equipment and plywood.
Straw Board Board 760 0.2237 0.7098 Strawboard is made of 100% straw and is strong, lightweight and impact resistant. It can be used as an
alternative to plasterboard. Workability includes easy cutting, machining, shaping and fixing. Strawboard
when incorporated into partitions can achieve half an hour fire and impact resistance. It is recyclable and
biodegradable and useful for preparing high quality building interior.
Teak Wood Wood 665 0.2369 0.8412 Teak is a yellowish brown timber having high oil content, high tensile strength and tight grain making it
a suitable option for outdoor furniture applications. Easy workability but presence of silica in the wood
causes severe blunting on edged tools. It is resistant to termite attacks and over time matures to silvery
grey finish. Used for manufacturing of articles where weather resistance is required and also for indoor
furnishing such as flooring, countertops, furniture, doors and window frames.
Tempered Glass Glass 2500 1.0493 1.9227 Tempered or toughened glass is one of the safety glass used at places where strength, safety and thermal
resistance are important considerations. It is stronger, harder and brittle than standard glass and shatters
into oval pebbles when broken. It is used in buildings for frameless assemblies, structurally loaded
applications and any other application that would become dangerous in the event of human impact.
Udaipur Brown Stone 3197 2.9210 2.2184 Marble is a metamorphic rock composed of recrystallized carbonate minerals mostly calcite. It has been in
Marble use for more than 450 years now.
V-Board Board 1191 0.2977 0.8245 V-Board is a particle board considered as an inexpensive alternative to solid wood boards. It is
produced by combining saw dust and other waste wood, provides a good insulation and has low thermal
conductivity. It can be easily cut into sheets with the help of customised saws. V-Board is highly effective
in maintaining a balanced temperature in air-conditioned spaces thus saving energy.
Veneered Particle Board 788 0.2363 0.7075 Natural wood veneer is denser and very smooth. It is generally applied to particle board to provide high
Board degree of finish. It is regarded as premium decorative finish and is widely used in office furniture, wall
lining, false ceiling etc.
Vitrified Tile Tile 2719 1.4786 1.8049 Vitrified tile has a low porosity and water absorption which makes it very strong and stain resistant. It
has better mechanical strength, is scratch and stain resistant and is not affected by acids, alkalis and
chemicals in comparison to marble and granites. It is mainly used for flooring purpose.
Resource Efficient Brick 1520 0.6314 0.9951 Resource Efficient Brick is a hollow brick with low water absorptivity, better finish, improved crushing
Bricks (REB) strength. It helps in resource saving due to its design and manufacturing. It helps in cutting down cost of
the construction.
Wood Wood 802 0.2652 0.8715 Wood is a hard, fibrous tissue found around the world. It is an organic material, a natural composite of
cellulose fibres (which are strong in tension) embedded in a matrix of lignin which resists compression. It
has been used for thousands of years for as a construction material.
Wood Pattern Stone 3126 3.4258 2.2852 Chitodio stones are available in different design and colours and is mainly used as flooring of super
Chitodio market, shopping mall, warehouse flooring, etc.