BCPL-STT-GIFTCITY-Level-5- IST Test Script(1)

The IST Test Script for STT-DC-GIFT City in Ahmedabad outlines the methodology for integrated system tests for electrical, mechanical, fire, and ELV systems. It includes details on testing instruments, pre-test conditions, and a comprehensive list of test scenarios to be conducted. The document is prepared by Hitesh Gupta and Amit Navik, with a focus on ensuring safety and compliance during testing activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
15 views56 pages

BCPL-STT-GIFTCITY-Level-5- IST Test Script(1)

The IST Test Script for STT-DC-GIFT City in Ahmedabad outlines the methodology for integrated system tests for electrical, mechanical, fire, and ELV systems. It includes details on testing instruments, pre-test conditions, and a comprehensive list of test scenarios to be conducted. The document is prepared by Hitesh Gupta and Amit Navik, with a focus on ensuring safety and compliance during testing activities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 56

IST TEST SCRIPT

FOR STT-DC-GIFT CITY


AHMEDABAD

Prepared By
Hiesth Gupta & Amit Navik

Beratung Consultants Private Limited


IST TEST SCRIPT

Document Control

Project STT-DC-GIFT CITY, AHMEDABAD


Document IST Test Script

Revision Purpose of Issue Date Prepared By Checked by Amendments / Revised


Sections
0 For Review & 02-April-2025 Hitesh Gupta Ramesh Lakde
Approval & Amit Navik

Comment Response Sheet


Review
Sr. Document Document Status
Reviewer Comment Comment BCPL Response Remarks
No Revision date (Open/Close)
date

www.beratungconsultants.com
Page 2
IST TEST SCRIPT

ATTENDING PARTIES

Preamble
The signatures below of the team members confirm that the data in the following report is up to
date and in line with the testing & commissioning activities performed on the said equipment’s.

Client
Organization –
Print name –
Email ID –
Signature –

T&C Consultant
Organization –
Print name –
Email ID –
Signature –

PMC
Organization –
Print name –
Email ID –
Signature –

Design Consultant
Organization –
Print name –
Email ID –
Signature –

General Contractor
Organization –
Print name –
Email ID –
Signature –

www.beratungconsultants.com
Page 3
IST TEST SCRIPT

TABLE OF CONTENTS
ATTENDING PARTIES ................................................................................................................... 3
1. INTRODUCTION .................................................................................................................. 6
2. TESTING INSTRUMENTS REQUIRED ..................................................................................... 8
3. ABBREVIATIONS & DEFINITIONS ......................................................................................... 8
4. HEALTH & SAFETY ............................................................................................................... 8
5. PRE-TEST CONDITIONS .......................................................................................................10
6. LIST OF IST SCENARIOS .......................................................................................................11
7. PRE-IST CHECKS .................................................................................................................12
8. PRE-CHECKS AND LOAD MEASUREMENT ............................................................................13
9. ELECTRICAL IST SCENARIO’S ...............................................................................................15
TEST 01. POWER FAILURE & RESTORE AT 33 KV HT PANEL-1 / OUTPUT BREAKER FOR
TRANSFORMER-1 (SOURCE A) ....................................................................................................15
TEST 02. POWER FAILURE & RESTORE AT 33 KV HT PANEL-2 / OUTPUT BREAKER FOR
TRANSFORMER-3 (SOURCE B).....................................................................................................16
TEST 03. FAILURE OF POWER SUPPLY TO BOTH HT PANEL-1 & HT PANEL-2, LOAD TRANSFERS TO
DIESEL GENERATORS ..................................................................................................................17
TEST 04. RESTORATION OF POWER SUPPLY OF BOTH HT PANEL-1 AND HT PANEL-2 AND LOAD
TRANSFERS FROM DIESEL GENERATORS TO UTILITY POWER (UTILITY POWER RESTORE/GRID
RESTORATION) ...........................................................................................................................19
TEST 05. MAKE BEFORE BREAK TEST (MAINTENANCE BYPASS OPERATIONAL/ SKRU) @ 1000 KW IT
LOAD ON UPS O/P PANEL -1A WITH UTILITY POWER ..................................................................20
TEST 06. MAKE BEFORE BREAK TEST (MAINTENANCE BYPASS OPERATIONAL/ SKRU) @ 1000 KW IT
LOAD ON UPS O/P PANEL -1B WITH UTILITY POWER...................................................................22
TEST 07. MAKE BEFORE BREAK TEST (MAINTENANCE BYPASS OPERATIONAL/ SKRU) @ HVAC
LOAD ON HVAC UPS O/P PANEL -1A WITH UTILITY POWER .........................................................24
TEST 08. MAKE BEFORE BREAK TEST (MAINTENANCE BYPASS OPERATIONAL/ SKRU) @ HVAC
LOAD ON HVAC UPS O/P PANEL -1B WITH UTILITY POWER .........................................................26
TEST 09. FAILURE AND RESTORATION OF INCOMER OF UPS I/P PANEL-1A FROM MAIN LT PANEL-1
28
TEST 10. FAILURE AND RESTORATION OF INCOMER OF UPS I/P PANEL-1B FROM MAIN LT PANEL-3
29
TEST 11. FAILURE AND RESTORATION OF INCOMER OF 300 KVA UPS I/P PANEL-1 FROM CHILLER
PANEL-1A ...................................................................................................................................30
TEST 12. FAILURE AND RESTORATION OF INCOMER OF 300 KVA UPS I/P PANEL-1B FROM CHILLER
PANEL-1B ...................................................................................................................................31

www.beratungconsultants.com
Page 4
IST TEST SCRIPT

10. MECHANICAL IST SCENARIO’S ............................................................................................32


TEST-01. NO LOAD TEST AT 0% LOAD IN DC HALL ........................................................................32
TEST-02. LOAD TEST AT 25% LOAD IN DC HALL (250 KW) .............................................................33
TEST-03. LOAD TEST AT 50% LOAD IN DC HALL (500 KW) .............................................................33
TEST-04. LOAD TEST AT 75% LOAD IN DC HALL (750 KW) .............................................................34
TEST-05. HEAT LOAD TEST AT 100% LOAD IN DC HALL (1000 KW) ................................................35
TEST-06. DUTY PAHU UNIT FAILURE AT 100% IT LOAD (1000 KW) IN DC HALL .............................37
TEST-07. DUTY PAHU UNIT SUPPLY AIR TEMPERATURE SENSOR FAILURE AT 100% IT LOAD (1000
KW) IN DC HALL .........................................................................................................................38
TEST-08. PAHU UNITS PRIMARY SOURCE POWER FAILURE ..........................................................40
TEST-09. FAILURE SCENARIO CHILLED WATER HEADER (CIRCUIT-A) AT 2ND FLOOR FOR DC HALL ..42
TEST-10. FAILURE SCENARIO CHILLED WATER HEADER (CIRCUIT-B) AT 2ND FLOOR FOR DC HALL ..44
11. FIRE IST SCENARIO’S ..........................................................................................................46
TEST-01: SINGLE SMOKE DETECTOR ACTIVATION AT 2F DC HALL .................................................46
TEST-02: ACTIVATION OF ANY TWO DETECTOR IN 2F DC HALL ....................................................47
TEST-03: ACTIVATION OF MANUAL GAS RELEASE STATION FOR 2F DC HALL ................................47
TEST-04: SINGLE SMOKE DETECTOR ACTIVATION AT 2F UPS ROOM-A .........................................48
TEST-05: ACTIVATION OF ANY TWO DETECTOR IN 2F UPS ROOM-A.............................................49
TEST-06: ACTIVATION OF MANUAL GAS RELEASE STATION FOR 2F UPS ROOM-A ........................49
TEST-07: SINGLE SMOKE DETECTOR ACTIVATION AT 2F UPS ROOM-B .........................................50
TEST-08: ACTIVATION OF ANY TWO DETECTOR IN 2F UPS ROOM-B.............................................51
TEST-09: ACTIVATION OF MANUAL GAS RELEASE STATION FOR 2F UPS ROOM-B ........................51
12. BMS IST SCENARIO’S ..........................................................................................................52
TEST-01: FAILURE SCENARIO-BMS – NETWORK COMMUNICATION FAILURE................................52
TEST-02: FAILURE SCENARIO_BMS: SERVER / POWER FAILURE ...................................................53
13. DATA LOGGER LAYOUT AND ARRANGEMENT: ....................................................................54
14. PQM ARRANGEMENT: .......................................................................................................55

www.beratungconsultants.com
Page 5
IST TEST SCRIPT

1. INTRODUCTION

STT is developed a DC in on 2nd floor as an expansion to their existing data centre at Gift City
Ahmedabad.
This document defines methodology to be followed for integrated system tests to be conducted
for Electrical, Mechanical, Fire and ELV systems installed for the project.

a. Equipment Load and Service Level Agreement

IT load is as follows:

Rooms No of Per Rack kW Total IT Source 1 Source 2


Racks Load (kW) (kW) (kW)
Data Centre – Data Hall at
1000 KW 500 KW 500 KW
2nd Floor

Service Level Agreement (SLA) monitoring a verification for the purposes of Heat load/
Mechanical/ Electrical Tests shall be based on the following:

TFS Temperature Relative Humidity


SLA < STT Advise> < STT Advise >
(Cold Aisle Cold Aisle Temperature Range at the top of the Supply Air Relative Humidity
Rack:
Conditions) in the Cold Aisle: 20% to 80%
20°C to 24°C

SOQ Condition IEC 61000 CIS PR24


Server Power ITIC curve
Quality Frequency must be within +/- 5%
Harmonic Voltage Distortion < 5%
PF 0.95 lagging to 0.95 leading at full load

b. Resources (Participants, Team Location Matrix)

Manpower allocation shall follow as per drawing attached below. There is different planning
for mechanical, electrical, Fire & IBMS IST manpower allocation.

A vendor support name list with scope of work and contact number(s) below:

www.beratungconsultants.com
Page 6
IST TEST SCRIPT

IST Team

Company Name Trade Person-in-Charge Contact Number


ST Telemedia (STT) GDC CxM
ST Telemedia (STT) Ops Lead
ST Telemedia (STT) PM
ST Telemedia (STT) T&C
Beratung Consultants Pvt Ltd (BCPL) CxA
Beratung Consultants Pvt Ltd (BCPL) CxA
Crescon PM
Schneider Electric GC
PDU
Genset
BMS/CPM
Chiller
Fuel
Mech
Elec
PAHU
Fire
MV
Tx

Typical Electrical IST manpower allocation

Station Area Allocated Person Floor Remarks


level
Command Center
BMS / EPMS /CPM
DC Hall
HV Switch room
MLTP
UPS
Chiller Plant
Generators

www.beratungconsultants.com
Page 7
IST TEST SCRIPT

2. TESTING INSTRUMENTS REQUIRED

Description Manufacturer Model no / Serial no. Calibration Remarks


Range due date

Multimeter
Clamp meter
3-phase analyzer
Modular load Quantity as per
DC hall load
banks/Server matrix and
Simulators Load bank Plan
Thermography
camera
Temperature & RH
data loggers

Note - All instruments shall be available at with valid calibration certificates.

3. ABBREVIATIONS & DEFINITIONS

• HVAC - Heating Ventilation and Air Conditioning


• PAC – Precision Air Conditioning Unit
• PAHU – Critical room Air Conditioning
• CFM- Cubic feet per minute
• L/s - Liter / sec
• GPM - Gallons per minute
• TR - Ton of Refrigeration
• BTU - British Thermal Unit
• DBT - Dry bulb temperature
• WBT - Wet Bulb temperature
• MFM Multifunctional Meter

4. HEALTH & SAFETY


In order to ensure safe conditions during testing the following rules have to be followed:
• Persons engaged with this commissioning are experienced and have received proper and
adequate training related to procedures and test equipment utilized for the particular
testing and commissioning activity.
• Test instruments and test leads should be maintained in a safe condition and the test
methods not to create danger either for the operator or for other persons.
• Detailed risk assessment has been undertaken & all possible hazards will be identified. This
risk assessment to be carried out as per the guidelines mentioned in the vendor EHS
assessment sheet and the same to be approved by the Project management team.

www.beratungconsultants.com
Page 8
IST TEST SCRIPT

The following Safety requirements will be followed as a minimum during all works –
• Safety will have first priority.
• Work will commence as per safety regulations laid in the contract specifications and project
safety plan.
• Persons engaged with this commissioning are experienced in the activities which they will
undertake.
• All personnel undertaking the works shall receive appropriate training and safety instruction
relating to the works being undertaken.
• All personnel will receive proper and adequate training related to the test equipment
utilized for the particular testing and commissioning activity.
• Test instruments and test leads should be maintained in a safe condition and the test
methods not to create danger either for the operator or for other persons.
• Personnel undertaking the works will be provided with appropriate guidelines and guidance
relating to the work.
• Proper safety harness to be used and secured if required.
• All personal protective equipment shall be used as appropriate according to the nature of
the job.
• Housekeeping shall be of good standard and debris shall be removed.
• Daily safety training will be done before the commencement of each shift and each new
task.
• PPE shall be issued to all personnel.
• The area under/around the work area of the equipment/system will be barricaded off to
prevent access during commissioning activities. Only personnel directly involved in the
commissioning will be permitted to enter the barricaded area.
• Signage as identified in the risk assessment will be erected.

www.beratungconsultants.com
Page 9
IST TEST SCRIPT

5. PRE-TEST CONDITIONS

Inspection of the electrical installation/connections should be made to verify the equipment is


correctly selected and not visibly damaged or defective. Inspections that need to be carried out
prior to the test include but not limited to.
Manufacturer's pre-start and start-up recommendations.

• The testing facility is clean & free from all hazards such as spilled water/oil, tipping, electrical
loose connections, safety w.r.t. equipment damage etc.
• Ensure all Level-2 to Level-4 tests completed, and all issues are closed.
• Ensure that chillers and chilled water pumps are operating as per design configuration.
• All Parameters are set in the CPM and Chiller Units as per design requirements.
• Ensure ventilation system is adequate and is in operation.
• Ensure Cooling in DC Hall, UPS Rooms are operational, and the HVAC units are operational in
working and design configuration.
• Ensure modular load banks are connected as per IT load Capacity.
• Load in the DC hall shall be equally distributed on both the Source-A and Source-B as per
Rack load layout.
• PAHU/PAC units in UPS room and electrical Room are operational and working as per design
configuration.
• Ensure that the temperature & RH data loggers are positioned in the DC hall as indicated in
section 12.
• Ensure that trend of UPS, BMS & EPMS sensors are getting logged in the respective system.
• Ensure all Level-4 Tests are completed, and test reports are available
• Ensure that trend of MFM Meters, PDUs, UPS, Battery Monitoring System and BMS sensors
is getting logged in the BMS and EPMS system.
• Ensure all Level-4 Tests are completed, and test reports are available
• BMS Control in AUTO mode
• No Alarms present in Fire Alarm Panel, Pre-action Cabinet, GRP Panels
• All doors locked and access control system is operational
• Capture initial screenshots of BMS and FAS Graphics.
• All defects and shortages fixed and completed found during Level-2, Level-3 and Level-4.
• All level of tagging in place for the equipments.
• Lockout Tagout in Place.

www.beratungconsultants.com
Page 10
IST TEST SCRIPT

6. LIST OF IST SCENARIOS

Test Duration
Test Scenarios Compliance
No
ELECTRICAL IST
Test-1
Power Failure & Restore at 33 kV HT Panel-1 / Output Breaker for  15 mins
Transformer-1
Test-2 Power Failure & Restore at 33 kV HT Panel-2 / Output Breaker for  15 mins
Transformer-3
Test-3 Total Power Failure at 33 kV HT Panel-1 and HT Panel-2 both Source  30 mins
Test-4 Restore Total Power at MVP-1 and MVP-2 both Source  15 mins
Test-5 Battery Charger Power Failure Scenario @ Source-1 (Failure of DC  15 mins
110V Source for the LT Panels)
Test-6 Failure and Restoration of Incomer of UPS I/P Panel-1A from Main LT  15 mins
Panel-1
Test-7
Failure and Restoration of Incomer of UPS I/P Panel-1B from Main LT  15 mins
Panel-3
Test-8
Failure and Restoration of Incomer of Chiller Panel-1A from Main LT  15 mins
Panel-1
Test-9
Failure and Restoration of Incomer of Chiller Panel-1B from Main LT  15 mins
Panel-3
Test-10
Make Before Break Test (Maintenance Bypass Operation) at UPS O/P  15 mins
Panel 1A @100% Load in DC Hall
Test-11
Make Before Break Test (Maintenance Bypass Operation) at UPS O/P  15 mins
Panel 1B @100% Load in DC Hall
Test-12
Make Before Break Test (Maintenance Bypass Operation) at HVAC  15 mins
UPS O/P Panel 1A @100% Load in DC Hall
Test-13
Make Before Break Test (Maintenance Bypass Operation) at HVAC  15 mins
UPS O/P Panel 1B @100% Load in DC Hall
Mechanical IST
Test-1 No Load test at 0% Load  15 mins
Test-2 Step/Part Load Test at 25% Load  15 mins
Test-3 Step/Part Load Test at 50% Load  15 mins
Test-4 Step/Part Load Test at 75% Load  15 mins
Test-5 Full Load Test at 100% Load  60 mins
Test-6 Duty PAHU Unit#1 Failure at 100% Load  30 mins
Test-7 Duty PAHU Unit#5 Failure at 100% Load  30 mins
Test-8 Supply/REturn Air Sensor Failure for Duty PAHU Unit at 100% Load  15 mins
Test-9 PAHU Unit Power supply failure Primary Source  15 mins
Test-10 Chilled Water Header Source-A Failure  30 mins
Test-11 Chilled Water Header Source-B Failure  30 mins
FIRE IST
Test-1 Single Smoke Detector Activation in 2F DC Hall  15 mins
Test-2 Two Smoke Detector Activation in 2F DC Hall  15 mins
Test-3 Manual Release Switch Activation in 2F DC Hall  15 mins

www.beratungconsultants.com
Page 11
IST TEST SCRIPT

Test-4 Single Smoke Detector Activation in 2F UPS Room & Panel Room-A  15 mins
Test-5 Two Smoke Detector Activation in 2F UPS Room & Panel Room-A  15 mins
Test-6 Manual Release Switch Activation in 2F UPS Room & Panel Room-A  15 mins
Test-7 Single Smoke Detector Activation in 2F UPS Room & Panel Room-B  15 mins
Test-8 Two Smoke Detector Activation in 2F UPS Room & Panel Room-B  15 mins
Test-9 Manual Release Switch Activation in 2F UPS Room & Panel Room-B  15 mins
BMS/EPMS/CPM SYSTEM
Test-1 Master BMS/EPMS/CPM Server Failure  15 mins
Test-2 BMS/EPMS/CPM Network Communication Failure  15 mins

7. PRE-IST CHECKS
All the systems to be checked for the healthiness and the systems to be configured as follows:
1. All selector switch of VCB’s and ACB’s are in AUTO and Remote Mode
2. All DG’s are in synchronization mode.
3. BMS/CPM Control in AUTO mode
4. All Parameters are set in the CPM and Chiller Units as per design requirements.
5. Load banks are placed as per Rack layout and load bank plan.
6. Data loggers are placed as per the Load bank plan and Data Logger Placement and keep in
logging for 1 min
7. 1.0 MW load is connected to the sockets in the DC Hall as per Rack Layout equally distributed
on both the Source S1 and Source S2.
8. Chiller Plant is online on CPM System.
9. PAHU Units are in Operational in AUTO mode and Controlled by Group Controller
10. No alarm presents on the BMS, CPM & EPMS system.
11. Capture the Screen shots of Normal System from the BMS/CPM/EPMS
12. All Fire alarm panel is normal, and all detection devices are active.
13. Ensure trends are running on the BMS/CPM/EPMS
14. All CSU’s, AHU’s are operational as per design logic
15. PAHU Units in the DC hall are operational.
16. No Alarms or trouble present on the Fire Alarm Panel.
17. Fire Mimic Panel is online with no alarms
18. Confirm with Operation Team before proceeding with the Test for announcement on other
floors
19. Confirm that the Outgoing Valve of Pre-action system is Closed Manually (Main Sprinkler Pipe
isolated)
20. Confirm that Actuator Valve of Gas Suppression System is isolated and removed temporarily
from the Cylinders

www.beratungconsultants.com
Page 12
IST TEST SCRIPT

8. Pre-Checks and Load Measurement


START TIME: END TIME:
Record the Load in DC Hall Pass  Fail 
IT Load in DC Hall: ________kW

Record the Load on each UPS and PDU in Operation:

L1 L2 L3 Total (kW)
STT-GUJ-DC-2F- IT-I/P UPS-1A

STT-GUJ-DC-2F- IT-I/P UPS-1B

STT-GUJ-DC-2F-PDU-1A

STT-GUJ-DC-2F-PDU-2A

STT-GUJ-DC-2F-PDU-3A

STT-GUJ-DC-2F-PDU-4A

STT-GUJ-DC-2F-PDU-1B
1

STT-GUJ-DC-2F-PDU-2B

STT-GUJ-DC-2F-PDU-3B

STT-GUJ-DC-2F-PDU-4B

Record the Number of PAHU Units in Operation:


PAHU Tag ON / PAHU Tag ON /
OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

www.beratungconsultants.com
Page 13
IST TEST SCRIPT

Capture the screenshots of BMS with all PAC/PAHU parameters.

Record the Number of Chillers, pumps are in Operation:


Chiller Tag ON / OFF Auto / Manual
STT-GUJ-DC-TF-ACC-01

Primary pumps ON / OFF Auto / Manual


STT-GUJ-DC-TF-PP-01

Secondary pumps
STT-GUJ-DC-TF-SP-02

Capture the screenshots of CPM/BMS/EPM

Record the initial loads on Chiller Panels


L1 L2 L3 Total (kW)
STT-GUJ-DC-2F-Chiller Panel 1A

STT-GUJ-DC-2F-Chiller Panel 1B

2
Record the Loads on Main LT Panels in Electrical Rooms
L1 L2 L3 Total (kW)
Main LT Panel-1

Main LT Panel-3

3 Capture the Screenshots of BMS/CPM/EPMS Pass  Fail 


4 No Alarms present in the BMS/CPM/EPMS Pass  Fail 
Monitor the Temperature inside the DC hall and capture the screenshots for the Pass  Fail 
5
temperature profile
6 Ensure temperature and Rh Trends are running on the BMS, CPM & EPMS Pass  Fail 
Note: Keep this load condition till the End of Electrical IST.
Comments:

www.beratungconsultants.com
Page 14
IST TEST SCRIPT

9. ELECTRICAL IST SCENARIO’S

Test 01. Power Failure & Restore at 33 kV HT Panel-1 / Output Breaker for Transformer-1 (Source A)

START TIME: END TIME:


Ensure equal distribution of load on all UPS. Pass  Fail 
Capture the Screenshots of UPS, LV Panel MFM on EPMS along with trend.
1

Record the Load in DC hall: 1000 kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure captured the screenshots of CPM/BMS Pass  Fail 
4 Pass  Fail 
OPEN the VCB at HT PANEL-1 (Outgoing Breaker for Transformer1)
5 Pass  Fail 
Ensure IT UPS and Mech UPS went on Battery Mode till DG Comes in Operation
Pass  Fail 
Ensure DG-3 is Running and load transfers on DG and record the Load on DG
6
DG-3: __________kW
7 Ensure IT UPS 1125 kVA UPS-1A working in Normal condition Pass  Fail 
8 Ensure MECH UPS 300kVA UPS working in normal condition Pass  Fail 
9 Check the Chiller Panel-1A operational on DG Source
10 CLOSE the VCB at HT PANEL-1 (Outgoing Breaker for Transformer1)
11 Ensure Load Transfers from DG to Utility Pass  Fail 
12 Ensure IT UPS, Mech UPS and Chiller Panel-1A are on Utility Pass  Fail 
13 Ensure No Load Drops during the Transfer from Utility to DG and DG to Utility Pass  Fail 
14 Ensure the PQM Trends and running and recorded. Pass  Fail 
15 Ensure there is no Impact of Source B Panels and UPS Pass  Fail 
16 No Impact to BMS Pass  Fail 
17 No impact to PAHU units Pass  Fail 
18 No break in the Server Load in the DC hall Pass  Fail 
19 No Rise in temperature in the DC hall Pass  Fail 
Observations:

www.beratungconsultants.com
Page 15
IST TEST SCRIPT

Test 02. Power Failure & Restore at 33 kV HT Panel-2 / Output Breaker for Transformer-3 (Source B)

START TIME: END TIME:


Ensure equal distribution of load on all UPS. Pass  Fail 
Capture the Screenshots of UPS, LV Panel MFM on EPMS along with trend.
1

Record the Load in DC hall: 1000 kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure captured the screenshots of CPM/BMS Pass  Fail 
4 Pass  Fail 
OPEN the VCB at HT PANEL-2 (Outgoing Breaker for Transformer-3)
5 Pass  Fail 
Ensure IT UPS and Mech UPS went on Battery Mode till DG Comes in Operation
Pass  Fail 
Ensure DG-4 is Running and load transfers on DG and record the Load on DG
6
DG-4: __________kW
7 Ensure IT UPS 1125 kVA UPS-1B working in Normal condition Pass  Fail 
8 Ensure MECH UPS 300kVA UPS working in normal condition Pass  Fail 
9 Check the Chiller Panel-1B operational on DG Source
10 CLOSE the VCB at HT PANEL-2 (Outgoing Breaker for Transformer-3)
11 Ensure Load Transfers from DG to Utility Pass  Fail 
12 Ensure IT UPS, Mech UPS and Chiller Panel-1B are on Utility Pass  Fail 
13 Ensure No Load Drops during the Transfer from Utility to DG and DG to Utility Pass  Fail 
14 Ensure the PQM Trends and running and recorded. Pass  Fail 
15 Ensure there is no Impact of Source A Panels and UPS Pass  Fail 
16 No Impact to BMS Pass  Fail 
17 No impact to PAHU units Pass  Fail 
18 No break in the Server Load in the DC hall Pass  Fail 
19 No Rise in temperature in the DC hall Pass  Fail 
Observations:

www.beratungconsultants.com
Page 16
IST TEST SCRIPT

Test 03. Failure of Power supply to both HT Panel-1 & HT Panel-2, Load Transfers to Diesel Generators
(Utility or Grid Failure)
START TIME: END TIME:
Ensure equal distribution of load on all UPS. Pass  Fail 
Capture the Screenshots of UPS, LV Panel MFM on EPMS along with trend.
1

Record the Load in DC hall: 1000 kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure captured the screenshots of EPMS/CPM/BMS Pass  Fail 
4 Pass  Fail 
OPEN the Incomer VCB’s at HT PANEL-1 and 2
5 IT UPS and Mech UPS goes to Battery Mode Pass  Fail 
Changeover happens from Utility Power supply to DG Power supply Pass  Fail 
6
Changeover time: _______ Secs
8 PAHU units are OFF during the Changeover from Source Utility to DG source Pass  Fail 
9 No break in the Server Load in the DC hall Pass  Fail 
Rise in temperature in the DC hall happens during changeover from Source Utililty to Pass  Fail 
10
DG
Changeover happens from EB Power supply to DG Power supply Pass  Fail 
11
Changeover time: _______ Secs
12 Note DG are running in synchronization mode Pass  Fail 
Note Load on Each DG’s and its status Pass  Fail 
L1 L2 L3 Total (kW) ON/OFF
DG–1

DG-2
13

DG-3

DG-4

14 All IT UPS resumes operation in Inverter Mode after DG Power supply kicks In. Pass  Fail 
15 All MECH UPS of resume operation in Inverter Mode on DG Power supply kicks In. Pass  Fail 
16 PAHU units will be running normally in DG power supply Pass  Fail 
17 No break in the Server Load in the DC hall Pass  Fail 
Monitor the temperature in the DC hall which is not exceeding design temperature Pass  Fail 
18
limits (Supply Air 22 +/- 2)
19 Capture the screen shots of BMS, EPMS & CPM Pass  Fail 
20 Capture the temperature and humidity trend of the DC Hall Pass  Fail 
21 Capture the alarm logs on the BMS, EPMS & CPM Pass  Fail 

www.beratungconsultants.com
Page 17
IST TEST SCRIPT

Test 03. Failure of Power supply to both HT Panel-1 & HT Panel-2, Load Transfers to Diesel Generators
(Utility or Grid Failure)
START TIME: END TIME:
Ensure No-break or interruption in the Connected Load in the DC Hall during Pass  Fail 
22
changeover.
Record the parameters after Load Transfers completely and capture the Screenshots of Pass  Fail 
23
EPMS, BMS, CPM
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 18
IST TEST SCRIPT

Test 04. Restoration of Power Supply of Both HT Panel-1 and HT Panel-2 and load transfers from Diesel
Generators to Utility Power (Utility Power Restore/Grid Restoration)
Start Time: End Time:
Ensure equal distribution of load in each PDU and as per rack layout
Capture the Screenshots of PDU Load distribution in BMS
1

Record the Load in DC hall: 1000 kW


2 CLOSE the VCB at HT PANEL-1 & 2
3 IT UPS Which are connected goes to Battery Mode
4 MECH UPS goes on Battery Mode Pass  Fail 
6 PAHU units are OFF during the Changeover from DG source to EB Source Pass  Fail 
7 No break in the Server Load in the DC hall Pass  Fail 
Rise in temperature in the DC hall happens during changeover from DG to Utility Pass  Fail 
8
source
Changeovers happen from DG Power supply to Utility Power supply Pass  Fail 
9
Changeover time: _______ Secs
10 Monitor the temperature & humidity inside the DC Hall Pass  Fail 
11 Capture Alarm logs from the BMS/CPM/EPMS Pass  Fail 
12 Capture the screenshots from the BMS/CPM/EPMS Pass  Fail 
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 19
IST TEST SCRIPT

Test 05. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ 1000 kW IT Load on UPS O/P
Panel -1A with Utility Power

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS Pass  Fail 
Record the Load on the UPS-1A

STT-GUJ-DC-2F- IT-I/P UPS-1A


5 R Y B Total kW

6 Ensure Incoming feeders at UPS O/P Panel-1A from 1125 kVA UPS-1A is CLOSED Pass  Fail 
The incoming Feeder from UPS Input Panel (STT-GUJ-DC-2F- IT-I/P UPS-1A) is OPEN at Pass  Fail 
7
UPS O/P Panel-1A (Maintenance Bypass Breaker)
Pass  Fail 
Ensure Castle key A is at UPS O/P Panel UPS Incomer (I/C-1) & Castle key B is in the
8
SKRU Box.
9 Pass  Fail 
Initiate Make Before Break Test
10 Pass  Fail 
Put the 1125 kVA UPS 1A in Static Bypass from Display of the UPS
11 Pass  Fail 
Check the Key-B from SKRU box will be released
Pass  Fail 
12 Remove the key-B from SKRU box and insert in Wrap-around bypass feeder (I/C-2)
at UPS O/P Panel-1A
Pass  Fail 
Check the Voltage at Incomer of Wrap-around feeder (I/C-2) and UPS Incoming
13 feeder (I/C-1) at UPS O/P Panel-1A and Ensure difference voltage between phase-
R, Y, B to phase-R, Y, B shall be less than 5V
CLOSE the Wrap-Around bypass feeder (I/C-2) at UPS O/P Panel-1A and OPEN Pass  Fail 
14
Incomer-1
15 Remove the Key-A from Incomer-1 at UPS O/P Panel-1A and insert in SKRU Box Pass  Fail 
16 OPEN the Incoming feeders at UPS I/P Panel-1A for 1125 kVA UPS-1A Pass  Fail 
17 No impact on the connected load in the DC hall Pass  Fail 
18 1125 kVA UPS are isolated and in Maintenance mode Pass  Fail 
19 Initiate Restoration of UPS on Inverter from Maintenance Pass  Fail 

www.beratungconsultants.com
Page 20
IST TEST SCRIPT

Test 05. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ 1000 kW IT Load on UPS O/P
Panel -1A with Utility Power

START TIME: END TIME:


20 CLOSE the Incoming feeders at UPS I/P Panel-1A for 1125 kVA UPS-1A Pass  Fail 
21 Switch ON the 1125 kVA UPS-1A Pass  Fail 
22 Put the 1125 kVA UPS 1A in Static Bypass from Display of the UPS Pass  Fail 
23 Key-A from SKRU Box will get released Pass  Fail 
Remove the key and insert in Incomer-1 at UPS O/P Panel-1A and CLOSE the Incomer Pass  Fail 
24
breaker (I/C-1)
25 Load transfers on the Static bypass of UPS-1A Pass  Fail 
OPEN the Wrap-around bypass feeder and remove the key-B from Wrap-around Pass  Fail 
26
bypass feeder (I/C-2) and insert key-B into SKRU box
28 Load transfers on Inverter Mode from Static Bypass Pass  Fail 
Record the Load on the UPS-1A Pass  Fail 
STT-GUJ-DC-2F- IT-I/P UPS-1A
R Y B Total kW
29

30 Capture the Screen shots of EPMS Pass  Fail 


Observation:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 21
IST TEST SCRIPT

Test 06. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ 1000 kW IT Load on UPS O/P
Panel -1B with Utility Power

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS Pass  Fail 
Record the Load on the UPS-1B

STT-GUJ-DC-2F- IT-I/P UPS-1B


5 R Y B Total kW

6 Ensure Incoming feeders at UPS O/P Panel-1B from 1125 kVA UPS-1B is CLOSED Pass  Fail 
The incoming Feeder from UPS Input Panel (STT-GUJ-DC-2F- IT-I/P UPS-1B) is OPEN at Pass  Fail 
7
UPS O/P Panel-1B (Maintenance Bypass Breaker)
Pass  Fail 
Ensure Castle key A is at UPS O/P Panel UPS Incomer (I/C-1) & Castle key B is in the
8
SKRU Box.
9 Pass  Fail 
Initiate Make Before Break Test
10 Pass  Fail 
Put the 1125 kVA UPS 1B in Static Bypass from Display of the UPS
11 Pass  Fail 
Check the Key-B from SKRU box will be released
Pass  Fail 
12 Remove the key-B from SKRU box and insert in Wrap-around bypass feeder (I/C-2)
at UPS O/P Panel-1B
Pass  Fail 
Check the Voltage at Incomer of Wrap-around feeder (I/C-2) and UPS Incoming
13 feeder (I/C-1) at UPS O/P Panel-1B and Ensure difference voltage between phase-
R, Y, B to phase-R, Y, B shall be less than 5V
CLOSE the Wrap-Around bypass feeder (I/C-2) at UPS O/P Panel-1B and OPEN Pass  Fail 
14
Incomer-1
15 Remove the Key-A from Incomer-1 at UPS O/P Panel-1B and insert in SKRU Box Pass  Fail 
16 OPEN the Incoming feeders at UPS I/P Panel-1B for 1125 kVA UPS-1B Pass  Fail 
17 No impact on the connected load in the DC hall Pass  Fail 
18 1125 kVA UPS are isolated and in Maintenance mode Pass  Fail 
19 Initiate Restoration of UPS on Inverter from Maintenance Pass  Fail 

www.beratungconsultants.com
Page 22
IST TEST SCRIPT

Test 06. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ 1000 kW IT Load on UPS O/P
Panel -1B with Utility Power

START TIME: END TIME:


20 CLOSE the Incoming feeders at UPS I/P Panel-1B for 1125 kVA UPS-1B Pass  Fail 
21 Switch ON the 1125 kVA UPS-1B Pass  Fail 
22 Put the 1125 kVA UPS 1B in Static Bypass from Display of the UPS Pass  Fail 
23 Key-A from SKRU Box will get released Pass  Fail 
Remove the key and insert in Incomer-1 at UPS O/P Panel-1B and CLOSE the Incomer Pass  Fail 
24
breaker (I/C-1)
25 Load transfers on the Static bypass of UPS-1B Pass  Fail 
OPEN the Wrap-around bypass feeder and remove the key-B from Wrap-around Pass  Fail 
26
bypass feeder (I/C-2) and insert key-B into SKRU box
28 Load transfers on Inverter Mode from Static Bypass Pass  Fail 
Record the Load on the UPS-1B Pass  Fail 
STT-GUJ-DC-2F- IT-I/P UPS-1B
29 R Y B Total kW

30 Capture the Screen shots of EPMS Pass  Fail 


Observation:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 23
IST TEST SCRIPT

Test 07. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ HVAC Load on HVAC UPS O/P
Panel -1A with Utility Power

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS Pass  Fail 
Record the Load on the UPS-1A

STT-GUJ-DC-2F- HVAC UPS-1A


5 R Y B Total kW

6 Ensure Incoming feeders at HVAC UPS O/P Panel-1A from 1125 kVA UPS-1A is CLOSED Pass  Fail 
The incoming Feeder from UPS Input Panel (300 kVA UPS-1 I/P Panel) is OPEN at Pass  Fail 
7
HVAC UPS O/P Panel-1A (Maintenance Bypass Breaker)
Pass  Fail 
Ensure Castle key A is at HVAC UPS O/P Panel UPS Incomer (I/C-1) & Castle key B is
8
in the SKRU Box.
9 Pass  Fail 
Initiate Make Before Break Test
10 Pass  Fail 
Put the 300 kVA UPS 1A in Static Bypass from Display of the UPS
11 Pass  Fail 
Check the Key-B from SKRU box will be released
Pass  Fail 
12 Remove the key-B from SKRU box and insert in Wrap-around bypass feeder (I/C-2)
at HVAC UPS O/P Panel-1A
Pass  Fail 
Check the Voltage at Incomer of Wrap-around feeder (I/C-2) and UPS Incoming
13 feeder (I/C-1) at HVAC UPS O/P Panel-1A and Ensure difference voltage between
phase-R, Y, B to phase-R, Y, B shall be less than 5V
CLOSE the Wrap-Around bypass feeder (I/C-2) at HVAC UPS O/P Panel-1A and OPEN Pass  Fail 
14
Incomer-1
15 Remove the Key-A from Incomer-1 at HVAC UPS O/P Panel-1A and insert in SKRU Box Pass  Fail 
16 OPEN the Incoming feeders at 300kVA UPS I/P Panel-1A for 300 kVA UPS-1A Pass  Fail 
17 No impact on the connected load in the DC hall Pass  Fail 
18 300 kVA UPS are isolated and in Maintenance mode Pass  Fail 
19 Initiate Restoration of UPS on Inverter from Maintenance Pass  Fail 

www.beratungconsultants.com
Page 24
IST TEST SCRIPT

Test 07. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ HVAC Load on HVAC UPS O/P
Panel -1A with Utility Power

START TIME: END TIME:


20 CLOSE the Incoming feeders at 300 kVA UPS I/P Panel-1A for 300 kVA UPS-1A Pass  Fail 
21 Switch ON the 300 kVA UPS-1A Pass  Fail 
22 Put the 300 kVA UPS 1A in Static Bypass from Display of the UPS Pass  Fail 
23 Key-A from SKRU Box will get released Pass  Fail 
Remove the key and insert in Incomer-1 at HVAC UPS O/P Panel-1A and CLOSE the Pass  Fail 
24
Incomer breaker (I/C-1)
25 Load transfers on the Static bypass of UPS-1A Pass  Fail 
OPEN the Wrap-around bypass feeder and remove the key-B from Wrap-around Pass  Fail 
26
bypass feeder (I/C-2) and insert key-B into SKRU box
28 Load transfers on Inverter Mode from Static Bypass Pass  Fail 
Record the Load on the 300 kVA UPS-1A Pass  Fail 
STT-GUJ-DC-2F 300kVA UPS-1A
R Y B Total kW
29

30 Capture the Screen shots of EPMS Pass  Fail 


Observation:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 25
IST TEST SCRIPT

Test 08. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ HVAC Load on HVAC UPS O/P
Panel -1B with Utility Power

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS Pass  Fail 
Record the Load on the UPS-1B

STT-GUJ-DC-2F- HVAC UPS-1B


5 R Y B Total kW

6 Ensure Incoming feeders at HVAC UPS O/P Panel-1B from 1125 kVA UPS-1B is CLOSED Pass  Fail 
The incoming Feeder from UPS Input Panel (300 kVA UPS-1 I/P Panel) is OPEN at Pass  Fail 
7
HVAC UPS O/P Panel-1B (Maintenance Bypass Breaker)
Pass  Fail 
Ensure Castle key A is at HVAC UPS O/P Panel UPS Incomer (I/C-1) & Castle key B is
8
in the SKRU Box.
9 Pass  Fail 
Initiate Make Before Break Test
10 Pass  Fail 
Put the 300 kVA UPS 1B in Static Bypass from Display of the UPS
11 Pass  Fail 
Check the Key-B from SKRU box will be released
Pass  Fail 
12 Remove the key-B from SKRU box and insert in Wrap-around bypass feeder (I/C-2)
at HVAC UPS O/P Panel-1B
Pass  Fail 
Check the Voltage at Incomer of Wrap-around feeder (I/C-2) and UPS Incoming
13 feeder (I/C-1) at HVAC UPS O/P Panel-1B and Ensure difference voltage between
phase-R, Y, B to phase-R, Y, B shall be less than 5V
CLOSE the Wrap-Around bypass feeder (I/C-2) at HVAC UPS O/P Panel-1B and OPEN Pass  Fail 
14
Incomer-1
15 Remove the Key-A from Incomer-1 at HVAC UPS O/P Panel-1B and insert in SKRU Box Pass  Fail 
16 OPEN the Incoming feeders at 300kVA UPS I/P Panel-1B for 300 kVA UPS-1B Pass  Fail 
17 No impact on the connected load in the DC hall Pass  Fail 
18 300 kVA UPS are isolated and in Maintenance mode Pass  Fail 
19 Initiate Restoration of UPS on Inverter from Maintenance Pass  Fail 

www.beratungconsultants.com
Page 26
IST TEST SCRIPT

Test 08. Make Before Break Test (Maintenance Bypass Operational/ SKRU) @ HVAC Load on HVAC UPS O/P
Panel -1B with Utility Power

START TIME: END TIME:


20 CLOSE the Incoming feeders at 300 kVA UPS I/P Panel-1B for 300 kVA UPS-1B Pass  Fail 
21 Switch ON the 300 kVA UPS-1B Pass  Fail 
22 Put the 300 kVA UPS 1B in Static Bypass from Display of the UPS Pass  Fail 
23 Key-A from SKRU Box will get released Pass  Fail 
Remove the key and insert in Incomer-1 at HVAC UPS O/P Panel-1B and CLOSE the Pass  Fail 
24
Incomer breaker (I/C-1)
25 Load transfers on the Static bypass of UPS-1B Pass  Fail 
OPEN the Wrap-around bypass feeder and remove the key-B from Wrap-around Pass  Fail 
26
bypass feeder (I/C-2) and insert key-B into SKRU box
28 Load transfers on Inverter Mode from Static Bypass Pass  Fail 
Record the Load on the 300 kVA UPS-1B Pass  Fail 
STT-GUJ-DC-2F 300kVA UPS-1B
R Y B Total kW
29

30 Capture the Screen shots of EPMS Pass  Fail 


Observation:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 27
IST TEST SCRIPT

Test 09. Failure and Restoration of Incomer of UPS I/P Panel-1A from Main LT Panel-1

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS/BMS Pass  Fail 
Record the Load on the 1125 kVA IT UPS-1A
1125 kVA IT UPS-1A
R Y B Total kW
5

6 OPEN the incomer Breaker at UPS I/P Panel-1A which is coming from Main LT Panel-1 Pass  Fail 
7 Check IT UPS-1A goes on battery mode Pass  Fail 
8 Check the alarms in EPMS/BMS
9 Pass  Fail 
No impact on the IT UPS-1B
10 Pass  Fail 
No impact on the connected load in the DC hall
11 Pass  Fail 
Ensure there is no abnormalities found
Pass  Fail 
CLOSE the incomer Breaker at UPS I/P Panel-1A which is coming from Main LT
12
Panel-1
13 Pass  Fail 
Check IT UPS-1A goes on Utility Mode from Battery
Record the Load on the 1125 kVA IT UPS-1A Pass  Fail 
1125 kVA IT UPS-1A
14 R Y B Total kW

15 No drop on the connected load in the DC hall Pass  Fail 


16 Capture the Screen shots of EPMS/BMS Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations

www.beratungconsultants.com
Page 28
IST TEST SCRIPT

Test 10. Failure and Restoration of Incomer of UPS I/P Panel-1B from Main LT Panel-3

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS/BMS Pass  Fail 
Record the Load on the 1125 kVA IT UPS-1B
1125 kVA IT UPS-1B
R Y B Total kW
5

6 OPEN the incomer Breaker at UPS I/P Panel-1B which is coming from Main LT Panel-1 Pass  Fail 
7 Check IT UPS-1B goes on battery mode Pass  Fail 
8 Check the alarms in EPMS/BMS
9 Pass  Fail 
No impact on the IT UPS-1B
10 Pass  Fail 
No impact on the connected load in the DC hall
11 Pass  Fail 
Ensure there is no abnormalities found
Pass  Fail 
CLOSE the incomer Breaker at UPS I/P Panel-1B which is coming from Main LT
12
Panel-1
13 Pass  Fail 
Check IT UPS-1B goes on Utility Mode from Battery
Record the Load on the 1125 kVA IT UPS-1B Pass  Fail 
1125 kVA IT UPS-1B
14 R Y B Total kW

15 No drop on the connected load in the DC hall Pass  Fail 


16 Capture the Screen shots of EPMS/BMS Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations

www.beratungconsultants.com
Page 29
IST TEST SCRIPT

Test 11. Failure and Restoration of Incomer of 300 kVA UPS I/P Panel-1 from Chiller Panel-1A

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS/BMS Pass  Fail 
Record the Load on the 300 kVA HVAC UPS-1A
300 kVA HVAC UPS-1A
5 R Y B Total kW

OPEN the incomer Breaker at 300 kVA UPS I/P Panel-1A which is coming from Chiller Pass  Fail 
6
Panel-1A
7 Check 300 KVA HVAC UPS-1A goes on battery mode Pass  Fail 
8 Check the alarms in EPMS/BMS
9 Pass  Fail 
No impact on the 300 KVA HAVC UPS-1B
10 Pass  Fail 
No impact on the connected load in the DC hall and no impact on cooling
11 Pass  Fail 
Ensure there is no abnormalities found
Pass  Fail 
12 CLOSE the incomer Breaker at 300 kVA UPS I/P Panel-1A which is coming from
Chiller Panel-1A
13 Pass  Fail 
Check 300 kVA HVAC UPS-1A goes on Utility Mode from Battery
Record the Load on the 300 kVA UPS-1A Pass  Fail 
300 kVA HVAC UPS-1A
14 R Y B Total kW

15 No drop on the connected load in the DC hall Pass  Fail 


16 Capture the Screen shots of EPMS/BMS Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations

www.beratungconsultants.com
Page 30
IST TEST SCRIPT

Test 12. Failure and Restoration of Incomer of 300 kVA UPS I/P Panel-1B from Chiller Panel-1B

START TIME: END TIME:


Ensure equal distribution in each PDU and as per rack layout Pass  Fail 
Capture the Screenshots of PDU Load distribution in EPMS
1

Record the Load in DC hall: _________kW


2 Ensure all Selector switch of the Breakers in Auto Mode Pass  Fail 
3 Ensure PQA is in Trending Mode
4 Ensure captured the screenshots of EPMS/BMS Pass  Fail 
Record the Load on the 300 kVA HVAC UPS-1B
300 kVA HVAC UPS-1B
R Y B Total kW
5

OPEN the incomer Breaker at 300 kVA UPS I/P Panel-1B which is coming from Chiller Pass  Fail 
6
Panel-1B
7 Check 300 KVA HVAC UPS-1B goes on battery mode Pass  Fail 
8 Check the alarms in EPMS/BMS
9 Pass  Fail 
No impact on the 300 KVA HAVC UPS-1B
10 Pass  Fail 
No impact on the connected load in the DC hall and no impact on cooling
11 Pass  Fail 
Ensure there is no abnormalities found
Pass  Fail 
CLOSE the incomer Breaker at 300 kVA UPS I/P Panel-1B which is coming from
12
Chiller Panel-1B
13 Pass  Fail 
Check 300 kVA HVAC UPS-1B goes on Utility Mode from Battery
Record the Load on the 300 kVA UPS-1B Pass  Fail 
300 kVA HVAC UPS-1B
14 R Y B Total kW

15 No drop on the connected load in the DC hall Pass  Fail 


16 Capture the Screen shots of EPMS/BMS Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations

www.beratungconsultants.com
Page 31
IST TEST SCRIPT

10. MECHANICAL IST SCENARIO’S

TEST-01. No Load Test at 0% Load in DC Hall

START TIME: END TIME:


Record the Number of PAHU Units in Operation: Pass  Fail 
PAHU Tag ON / PAHU Tag ON /
OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the screenshots of BMS with all PAC/PAHU parameters captured.


1
Record the Number of Chillers, pumps are in Operation:
Chiller Tag ON / OFF Auto / Manual
STT-GUJ-DC-TF-ACC-01

Primary pumps ON / OFF Auto / Manual


STT-GUJ-DC-TF-PP-01

Secondary pumps
STT-GUJ-DC-TF-SP-02

Capture the screenshots of CPM/BMS/EPM

Record the initial loads on Chiller Panels at Terrace


Record the initial loads on Chiller Panels

L1 L2 L3 Total (kW)
STT-GUJ-DC-2F-Chiller Panel 1A

2
STT-GUJ-DC-2F-Chiller Panel 1B

Record the Loads on Main LT Panels in Electrical Rooms


L1 L2 L3 Total (kW)

www.beratungconsultants.com
Page 32
IST TEST SCRIPT
Main LT Panel-1

Main LT Panel-3

3 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 


4 No Alarms present in the EPMS/BMS/CPM Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to 24 Pass  Fail 
5
Deg C

TEST-02. Load Test at 25% Load in DC Hall (250 kW)

START TIME: END TIME:


Increase the Load to 25% (250 kW), Pass  Fail 
Ensure equal distribution as per rack layout.
Capture the Screenshots of Load distribution in EPMS

Record the Load in DC hall: _______ kW

1 Record the Load on each UPS in Operation:


Record the Load on the UPS-1A and UPS-1B
STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

2 Capture the screenshots of CPM/BMS/EPMS


Adequate time of 15 mins to stabilize the load in DC Hall Pass  Fail 
3
Record the Time:
4 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
5 No Alarms present in the EPMS/BMS/CPM Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to 24 Pass  Fail 
6
Deg C

TEST-03. Load Test at 50% Load in DC Hall (500 kW)

START TIME: END TIME:


Increase the Load to 50% (500 kW), Pass  Fail 
Ensure equal distribution as per rack layout.
1 Capture the Screenshots of Load distribution in EPMS

Record the Load in DC hall: _______ kW

www.beratungconsultants.com
Page 33
IST TEST SCRIPT

Record the Load on each UPS in Operation:


Record the Load on the UPS-1A and UPS-1B
STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Adequate time of 15 mins to stabilize the load in DC Hall_ Pass  Fail 


2
Record the Time:
3 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
4 No Alarms present in the EPMS/BMS/CPM Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to 24 Pass  Fail 
5
Deg C
Record the average temperature and humidity readings from BMS Pass  Fail 

6 Temperature:

Humidity

TEST-04. Load Test at 75% Load in DC Hall (750 kW)

START TIME: END TIME:


Increase the Load to 75% (750 kW), Pass  Fail 
Ensure equal distribution as per rack layout.
Capture the Screenshots of Load distribution in EPMS

Record the Load in DC hall: ________ kW

1 Record the Load on each UPS in Operation:


STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Adequate time of 30 mins to stabilize the load in DC Hall_ Pass  Fail 


2
Record the Time:
3 Capture the Screenshots of PAHU Units
4 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
5 No Alarms present in the EPMS/BMS/CPM Pass  Fail 

www.beratungconsultants.com
Page 34
IST TEST SCRIPT

Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to 24 Pass  Fail 
6
Deg C
Record the average temperature and humidity readings from BMS Pass  Fail 

6
Temperature:
Humidity

Test-05. Heat Load Test at 100% Load in DC Hall (1000 kW)

START TIME: END TIME:

Increase the Load to 100% (1000 kW), Pass  Fail 


Ensure equal distribution as per rack layout.
Capture the Screenshots of Load distribution in EPMS

Record the Load in DC hall: ________ kW


Record the Load on each UPS in Operation:
STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Record the Number of PAHU Units in Operation:


1 PAHU Tag ON / PAHU Tag ON /
OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the Screenshots of CPM/BMS/EMPS


Adequate time of 15 mins to stabilize the load in DC Hall Pass  Fail 
2
Record the Time:
Keep the 100% Load for 1 hours in the DC hall and monitor the temperature inside the
3
DC Hall
Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
4

5 No Alarms present in the EPMS/BMS/CPM Pass  Fail 


Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to 24 Pass  Fail 
6
Deg C

www.beratungconsultants.com
Page 35
IST TEST SCRIPT

Record the average temperature and humidity readings from BMS Pass  Fail 

7 Temperature:

Humidity:
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 36
IST TEST SCRIPT

Test-06. Duty PAHU unit failure at 100% IT load (1000 kW) in DC Hall
START TIME: END TIME:
Record the Load in DC hall:__________ kW Pass  Fail 

Record load on 1125kVA UPS Output Panels-1A & 1B


STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Record the Number of PAHU Units in Operation:


PAHU Tag ON / PAHU Tag ON /
1 OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the Screenshots of CPM/BMS/EMPS


Fail the Duty PAHU unit (PAHU Tag: ___________________________) from the Pass  Fail 
2
Display of the PAHU unit
3 Alarm Displays on the BMS Pass  Fail 
4 Standby PAHU unit Starts after receiving signal from Group Controller Pass  Fail 
Keep the 100% Load for 30 mins in the DC hall and monitor the temperature inside Pass  Fail 
5
the DC Hall
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to Pass  Fail 
6
24 Deg C
7 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
8 No Alarms present in the EPMS/BMS/CPM Pass  Fail 
Record the average temperature and humidity readings from BMS Pass  Fail 

9 Temperature:

Humidity:
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 37
IST TEST SCRIPT

Test-07. Duty PAHU Unit supply Air Temperature Sensor Failure at 100% IT Load (1000 kW) in DC Hall

START TIME: END TIME:


Record the Load in DC hall: __________ kW Pass  Fail 

Record load on 1125kVA UPS Output Panels-1A & 1B


STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Record the Number of PAHU Units in Operation:


PAHU Tag ON / PAHU Tag ON /
1 OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the Screenshots of CPM/BMS/EMPS


Record the % opening of CHW valve and fan speed for the PAHU unit, for which Pass  Fail 
failing the Sensor
2 PAHU Unit Tag:
CHW Valve: _______________% Opening
Fan Speed: _______________%
Fail the supply air temperature sensor for the PAHU unit is in Operation by Pass  Fail 
3 disconnecting communication cable
Duty PAHU unit (PAHU Tag: ___________________________)
Alarm will generate on the PAHU unit and controller gives signal (Fail safe mode) to Pass  Fail 
4
CHW valves to Open 100% for that particular PAHU Unit
Record the % opening of CHW valve and fan speed for the PAHU unit: Pass  Fail 

5 PAHU Unit Tag:


CHW Valve: _______________% Opening
Fan Speed: _______________%
Monitor the temperature in the DC hall and capture the screenshots of Pass  Fail 
6
Temperature + Rh Sensors in BMS.
7 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
8 No Alarms present in the EPMS/BMS/CPM Pass  Fail 

www.beratungconsultants.com
Page 38
IST TEST SCRIPT

Test-07. Duty PAHU Unit supply Air Temperature Sensor Failure at 100% IT Load (1000 kW) in DC Hall

START TIME: END TIME:


Restore the communication cable of supply air temperature sensor for the PAHU Pass  Fail 
Unit

9
PAHU Unit Tag:
CHW Valve: _______________% Opening
Fan Speed: _______________%
10 Capture the Screenshots of EPMS/BMS/CPM Pass  Fail 
Record the average temperature and humidity readings from BMS Pass  Fail 

11 Temperature:

Humidity:
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 39
IST TEST SCRIPT

Test-08. PAHU Units Primary Source Power Failure

START TIME: END TIME:


Record the Load in DC hall:__________ kW Pass  Fail 

Record load on 1125kVA UPS Output Panels-1A & 1B


STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Record the Number of PAHU Units in Operation:


PAHU Tag ON / PAHU Tag ON /
1 OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the Screenshots of CPM/BMS/EMPS


Pass  Fail 
Fail the one source through the PAHU UPS by switching OFF the Main Incoming
2
Breaker

3 PAHU units go on to the Raw Power through inbuilt ATS in PAHU Units. Pass  Fail 
4 Adequate time of 30 mins shall be allowed to PAHU units to run on Raw power Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to Pass  Fail 
5
24 Deg C
6 Capture the Screen Shots of BMS, Temp +Rh Sensor Readings in BMS Pass  Fail 
Resume the Incoming Power PAHU UPS Panel by switching ON the Main Incoming Pass  Fail 
7
Breaker.
8 The PAHU units resumes on UPS power supply Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C to Pass  Fail 
9
24 Deg C
10 Capture the Screen Shots of BMS, Temp+Rh Sensor Readings in BMS Pass  Fail 
Capture the Trends of Temperature & humidity from T+Rh Sensor inside the DC hall- Pass  Fail 
11
1.
Capture the final screenshots of PAHU units and Temperature + Rh Sensors in the Pass  Fail 
12
BMS. Also capture the Screenshots of EPMS for the Load on each PDU

www.beratungconsultants.com
Page 40
IST TEST SCRIPT

Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 41
IST TEST SCRIPT

Test-09. Failure Scenario Chilled Water Header (Circuit-A) at 2nd floor for DC Hall

START TIME: END TIME:


Record the Load in DC hall:__________ kW Pass  Fail 

Record load on 1125kVA UPS Output Panels-1A & 1B


STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Record the Number of PAHU Units in Operation:


PAHU Tag ON / PAHU Tag ON /
1 OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the Screenshots of CPM/BMS/EMPS


Pass  Fail 
2 Ensure all isolation and motorized valves are open from Both the Sources A & B

Check the Opening % actuators of PAHU units and capture the screenshots from Pass  Fail 
3
BMS
Pass  Fail 
4 CLOSE the CHW Isolation Valve of CHW Header of Circuit-A manually

Check the opening % of PAHU units after Failing the Source-1 in PAHU Room-1, Pass  Fail 
5
both actuator valves get OPEN to cater the load inside the DC hall
6 Adequate time shall be allowed to Stabilize the Temperature inside the DC hall Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C Pass  Fail 
7
to 24 Deg C
8 Capture the Screen Shots of BMS, Temp +Rh Sensor Readings in BMS Pass  Fail 
9 Re-store / OPEN the CHW Isolation valve which were closed in step 4 Pass  Fail 
Check the Opening/Closing % of actuators of PAHU units and capture the Pass  Fail 
10
screenshots from BMS

www.beratungconsultants.com
Page 42
IST TEST SCRIPT

Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C Pass  Fail 
11
to 24 Deg C
12 Capture the Screen Shots of BMS, Temp +Rh Sensor Readings in BMS Pass  Fail 
Capture the Trends of Temperature & humidity from T+Rh Sensor inside the DC Pass  Fail 
13
hall.
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 43
IST TEST SCRIPT

Test-10. Failure Scenario Chilled Water Header (Circuit-B) at 2nd floor for DC Hall

START TIME: END TIME:


Record the Load in DC hall:__________ kW Pass  Fail 

Record load on 1125kVA UPS Output Panels-1A & 1B


STT-GUJ-DC-2F- IT-I/P UPS-1A STT-GUJ-DC-2F- IT-I/P UPS-1B
R Y B Total kW R Y B Total kW

Record the Number of PAHU Units in Operation:


PAHU Tag ON / PAHU Tag ON /
1 OFF OFF
DC Hall DC Hall
STT-GUJ-DC-2F-PAHU01 STT-GUJ-DC-2F-PAHU07
STT-GUJ-DC-2F-PAHU02 STT-GUJ-DC-2F-PAHU08
STT-GUJ-DC-2F-PAHU03 STT-GUJ-DC-2F-PAHU09
STT-GUJ-DC-2F-PAHU04 STT-GUJ-DC-2F-PAHU10
STT-GUJ-DC-2F-PAHU05 STT-GUJ-DC-2F-PAHU11
STT-GUJ-DC-2F-PAHU06

Capture the Screenshots of CPM/BMS/EMPS


Pass  Fail 
2 Ensure all isolation and motorized valves are open from Both the Sources A & B

Check the Opening % actuators of PAHU units and capture the screenshots from Pass  Fail 
3
BMS
Pass  Fail 
4 CLOSE the CHW Isolation Valve of CHW Header of Circuit-B manually

Check the opening % of PAHU units after Failing the Source-2 in PAHU Room-1, Pass  Fail 
5
both actuator valves get OPEN to cater the load inside the DC hall
6 Adequate time shall be allowed to Stabilize the Temperature inside the DC hall Pass  Fail 
Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C Pass  Fail 
7
to 24 Deg C
8 Capture the Screen Shots of BMS, Temp +Rh Sensor Readings in BMS Pass  Fail 
9 Re-store / OPEN the CHW Isolation valve which were closed in step 4 Pass  Fail 
Check the Opening/Closing % of actuators of PAHU units and capture the Pass  Fail 
10
screenshots from BMS

www.beratungconsultants.com
Page 44
IST TEST SCRIPT

Monitor the Temperature inside the DC hall and it is within the range of 20 Deg C Pass  Fail 
11
to 24 Deg C
12 Capture the Screen Shots of BMS, Temp +Rh Sensor Readings in BMS Pass  Fail 
Capture the Trends of Temperature & humidity from T+Rh Sensor inside the DC Pass  Fail 
13
hall.
Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 45
IST TEST SCRIPT

11. FIRE IST Scenario’s

REFER FIRE CAUSE & EFFECT MATRIXSS


Test-01: Single Smoke Detector activation at 2F DC Hall
If alarm
If alarm does not
Activation of Single Detector in DC acknowledge/alarm reset
acknowledge/reset in 2
Cause in the 2 mins seek and
mins seek and search delay
Result
Hall search delay time (False
time
Alarm)
EFFECT Expected Actual Expected Actual Pass / Fail

1 Alarm on fire alarm panels with beep. ✓ ✓ Pass  Fail 


Activation of Speaker Cum Strobe in BMS Pass  Fail 
2
Room/Security Hut  
All the devices and systems shall be reinstating Pass  Fail 
3
in normal condition.  
Alert Message on Particular floor after 2 mins Pass  Fail 
4
(Seek & Search time)  ✓
Alert Message on 1 below and 1 floor above in Pass  Fail 
5
common area  
6 Evacuation Message on Particular Floor.   Pass  Fail 
Hooter/ Speaker cum strobe activation Pass  Fail 
7
particular floor  ✓
Unlock Access Control Doors of Exit Path Doors Pass  Fail 
8
and the Doors where the Fire has occurred  ✓
Shut Off AHU/TFA and its fire dampers (No
9
CRAC machine shut OFF) of particular area.  ✓ Pass  Fail 

Activation of Staircase & Lift Lobby


10
pressurisation Fans  ✓ Pass  Fail 

Lift homing signal to Ground floor (only at the


11
activation of the devices closer to lifts lobby)  ✓ Pass  Fail 
Activation of Ventilation fan in basement
12 parking area if smoke gets detected at  ✓ Pass  Fail 
basement level (if applicable)
Indication Alarm on Gas Release Module (Area  
13 Pass  Fail 
wise)

14 Timer circuit to start 60 sec. Countdown   Pass  Fail 


15 De-activation of Gas Release process   Pass  Fail 
Activation of “EVACUATE GAS RELEASED" &
16
"DO NOT ENTER" Signage's.  ✓ Pass  Fail 

Signal to PILOT cylinder actuator on the floor.  


17 The Signal shall be routed through Pass  Fail 
AUTO/Manual operations
Alarm signal to campus/developer/common Pass  Fail 
30
area Fire Alarm Panel  ✓
31 Alarm signal to BMS ✓ ✓ Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations:

www.beratungconsultants.com
Page 46
IST TEST SCRIPT

Test-02: Activation of any two Detector in 2F DC Hall

Test-03: Activation of Manual Gas Release Station for 2F DC Hall


Activation of any two Activation of Manual Gas
Cause detectors Release Station
Result

EFFECT Expected Actual Expected Actual Pass / Fail

1 Alarm on fire alarm panels with beep. ✓ ✓ Pass  Fail 


Activation of Speaker Cum Strobe in BMS Room/Security Pass  Fail 
2
Hut
 
All the devices and systems shall be reinstating in Pass  Fail 
3
normal condition.  
Alert Message on Particular floor after 2 mins (Seek & Pass  Fail 
4
Search time)  
Alert Message on 1 below and 1 floor above in common Pass  Fail 
5
area ✓ ✓
6 Evacuation Message on Particular Floor. ✓ ✓ Pass  Fail 

7 Hooter/ Speaker cum strobe activation particular floor ✓ ✓ Pass  Fail 


Unlock Access Control Doors of Exit Path Doors and the Pass  Fail 
8
Doors where the Fire has occurred ✓ ✓
Shut Off AHU/TFA and its fire dampers (No CRAC
9
machine shut OFF) of particular area. ✓ ✓ Pass  Fail 

10 Activation of Staircase & Lift Lobby pressurisation Fans ✓ ✓ Pass  Fail 

Lift homing signal to Ground floor (only at the activation


11
of the devices closer to lifts lobby) ✓ ✓ Pass  Fail 
Activation of Ventilation fan in basement parking area if
12
smoke gets detected at basement level (if applicable) ✓ ✓ Pass  Fail 

13 Indication Alarm on Gas Release Module (Area wise) ✓ ✓ Pass  Fail 

14 Timer circuit to start 60 sec. Countdown ✓ ✓ Pass  Fail 


15 De-activation of Gas Release process   Pass  Fail 
Activation of “EVACUATE GAS RELEASED" & "DO NOT
16
ENTER" Signage's. ✓ ✓ Pass  Fail 

Signal to PILOT cylinder actuator on the floor. The Signal


17
shall be routed through AUTO/Manual operations ✓ ✓ Pass  Fail 
Alarm signal to campus/developer/common area Fire
30
Alarm Panel ✓ ✓ Pass  Fail 
31 Alarm signal to BMS ✓ ✓ Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations:

www.beratungconsultants.com
Page 47
IST TEST SCRIPT

Test-04: Single Smoke Detector activation at 2F UPS Room-A


If alarm
If alarm does not
Activation of Single Detector in DC acknowledge/alarm reset
acknowledge/reset in 2
Cause in the 2 mins seek and
mins seek and search delay
Result
Hall-2 search delay time (False
time
Alarm)
EFFECT Expected Actual Expected Actual Pass / Fail

1 Alarm on fire alarm panels with beep. ✓ ✓ Pass  Fail 


Activation of Speaker Cum Strobe in BMS Pass  Fail 
2
Room/Security Hut  
All the devices and systems shall be reinstating Pass  Fail 
3
in normal condition.  
Alert Message on Particular floor after 2 mins Pass  Fail 
4
(Seek & Search time)
 ✓
Alert Message on 1 below and 1 floor above in Pass  Fail 
5
common area  
6 Evacuation Message on Particular Floor.   Pass  Fail 
Hooter/ Speaker cum strobe activation Pass  Fail 
7
particular floor  ✓
Unlock Access Control Doors of Exit Path Doors Pass  Fail 
8
and the Doors where the Fire has occurred  ✓
Shut Off AHU/TFA and its fire dampers (No
9
CRAC machine shut OFF) of particular area.  ✓ Pass  Fail 

Activation of Staircase & Lift Lobby


10
pressurisation Fans  ✓ Pass  Fail 

Lift homing signal to Ground floor (only at the


11
activation of the devices closer to lifts lobby)  ✓ Pass  Fail 
Activation of Ventilation fan in basement
12 parking area if smoke gets detected at  ✓ Pass  Fail 
basement level (if applicable)
Indication Alarm on Gas Release Module (Area  
13 Pass  Fail 
wise)

14 Timer circuit to start 60 sec. Countdown   Pass  Fail 


15 De-activation of Gas Release process   Pass  Fail 
Activation of “EVACUATE GAS RELEASED" &
16
"DO NOT ENTER" Signage's.
 ✓ Pass  Fail 

Signal to PILOT cylinder actuator on the floor.  


17 The Signal shall be routed through Pass  Fail 
AUTO/Manual operations
Alarm signal to campus/developer/common Pass  Fail 
30
area Fire Alarm Panel  ✓
31 Alarm signal to BMS ✓ ✓ Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations:

www.beratungconsultants.com
Page 48
IST TEST SCRIPT

Test-05: Activation of any two Detector in 2F UPS Room-A

Test-06: Activation of Manual Gas Release Station for 2F UPS Room-A


Activation of any two Activation of Manual Gas
Cause detectors Release Station
Result

EFFECT Expected Actual Expected Actual Pass / Fail

1 Alarm on fire alarm panels with beep. ✓ ✓ Pass  Fail 


Activation of Speaker Cum Strobe in BMS Room/Security Pass  Fail 
2
Hut  
All the devices and systems shall be reinstating in Pass  Fail 
3
normal condition.  
Alert Message on Particular floor after 2 mins (Seek & Pass  Fail 
4
Search time)  
Alert Message on 1 below and 1 floor above in common Pass  Fail 
5
area ✓ ✓
6 Evacuation Message on Particular Floor. ✓ ✓ Pass  Fail 

7 Hooter/ Speaker cum strobe activation particular floor ✓ ✓ Pass  Fail 


Unlock Access Control Doors of Exit Path Doors and the Pass  Fail 
8
Doors where the Fire has occurred ✓ ✓
Shut Off AHU/TFA and its fire dampers (No CRAC
9
machine shut OFF) of particular area. ✓ ✓ Pass  Fail 

10 Activation of Staircase & Lift Lobby pressurisation Fans ✓ ✓ Pass  Fail 

Lift homing signal to Ground floor (only at the activation


11
of the devices closer to lifts lobby) ✓ ✓ Pass  Fail 
Activation of Ventilation fan in basement parking area if
12
smoke gets detected at basement level (if applicable) ✓ ✓ Pass  Fail 

13 Indication Alarm on Gas Release Module (Area wise) ✓ ✓ Pass  Fail 

14 Timer circuit to start 60 sec. Countdown ✓ ✓ Pass  Fail 


15 De-activation of Gas Release process   Pass  Fail 
Activation of “EVACUATE GAS RELEASED" & "DO NOT
16
ENTER" Signage's. ✓ ✓ Pass  Fail 

Signal to PILOT cylinder actuator on the floor. The Signal


17
shall be routed through AUTO/Manual operations ✓ ✓ Pass  Fail 
Alarm signal to campus/developer/common area Fire
30
Alarm Panel ✓ ✓ Pass  Fail 
31 Alarm signal to BMS ✓ ✓ Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations:

www.beratungconsultants.com
Page 49
IST TEST SCRIPT

Test-07: Single Smoke Detector activation at 2F UPS Room-B


If alarm
If alarm does not
Activation of Single Detector in DC acknowledge/alarm reset
acknowledge/reset in 2
Cause in the 2 mins seek and
mins seek and search delay
Result
Hall-2 search delay time (False
time
Alarm)
EFFECT Expected Actual Expected Actual Pass / Fail

1 Alarm on fire alarm panels with beep. ✓ ✓ Pass  Fail 


Activation of Speaker Cum Strobe in BMS Pass  Fail 
2
Room/Security Hut  
All the devices and systems shall be reinstating Pass  Fail 
3
in normal condition.  
Alert Message on Particular floor after 2 mins Pass  Fail 
4
(Seek & Search time)
 ✓
Alert Message on 1 below and 1 floor above in Pass  Fail 
5
common area  
6 Evacuation Message on Particular Floor.   Pass  Fail 
Hooter/ Speaker cum strobe activation Pass  Fail 
7
particular floor  ✓
Unlock Access Control Doors of Exit Path Doors Pass  Fail 
8
and the Doors where the Fire has occurred  ✓
Shut Off AHU/TFA and its fire dampers (No
9
CRAC machine shut OFF) of particular area.  ✓ Pass  Fail 

Activation of Staircase & Lift Lobby


10
pressurisation Fans  ✓ Pass  Fail 

Lift homing signal to Ground floor (only at the


11
activation of the devices closer to lifts lobby)  ✓ Pass  Fail 
Activation of Ventilation fan in basement
12 parking area if smoke gets detected at  ✓ Pass  Fail 
basement level (if applicable)
Indication Alarm on Gas Release Module (Area  
13 Pass  Fail 
wise)

14 Timer circuit to start 60 sec. Countdown   Pass  Fail 


15 De-activation of Gas Release process   Pass  Fail 
Activation of “EVACUATE GAS RELEASED" &
16
"DO NOT ENTER" Signage's.
 ✓ Pass  Fail 

Signal to PILOT cylinder actuator on the floor.  


17 The Signal shall be routed through Pass  Fail 
AUTO/Manual operations
Alarm signal to campus/developer/common Pass  Fail 
30
area Fire Alarm Panel  ✓
31 Alarm signal to BMS ✓ ✓ Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations:

www.beratungconsultants.com
Page 50
IST TEST SCRIPT

Test-08: Activation of any two Detector in 2F UPS Room-B

Test-09: Activation of Manual Gas Release Station for 2F UPS Room-B


Activation of any two Activation of Manual Gas
Cause detectors Release Station
Result

EFFECT Expected Actual Expected Actual Pass / Fail

1 Alarm on fire alarm panels with beep. ✓ ✓ Pass  Fail 


Activation of Speaker Cum Strobe in BMS Room/Security Pass  Fail 
2
Hut
 
All the devices and systems shall be reinstating in Pass  Fail 
3
normal condition.  
Alert Message on Particular floor after 2 mins (Seek & Pass  Fail 
4
Search time)  
Alert Message on 1 below and 1 floor above in common Pass  Fail 
5
area ✓ ✓
6 Evacuation Message on Particular Floor. ✓ ✓ Pass  Fail 

7 Hooter/ Speaker cum strobe activation particular floor ✓ ✓ Pass  Fail 


Unlock Access Control Doors of Exit Path Doors and the Pass  Fail 
8
Doors where the Fire has occurred ✓ ✓
Shut Off AHU/TFA and its fire dampers (No CRAC
9
machine shut OFF) of particular area. ✓ ✓ Pass  Fail 

10 Activation of Staircase & Lift Lobby pressurisation Fans ✓ ✓ Pass  Fail 

Lift homing signal to Ground floor (only at the activation


11
of the devices closer to lifts lobby) ✓ ✓ Pass  Fail 
Activation of Ventilation fan in basement parking area if
12
smoke gets detected at basement level (if applicable) ✓ ✓ Pass  Fail 

13 Indication Alarm on Gas Release Module (Area wise) ✓ ✓ Pass  Fail 

14 Timer circuit to start 60 sec. Countdown ✓ ✓ Pass  Fail 


15 De-activation of Gas Release process   Pass  Fail 
Activation of “EVACUATE GAS RELEASED" & "DO NOT
16
ENTER" Signage's. ✓ ✓ Pass  Fail 

Signal to PILOT cylinder actuator on the floor. The Signal


17
shall be routed through AUTO/Manual operations ✓ ✓ Pass  Fail 
Alarm signal to campus/developer/common area Fire
30
Alarm Panel ✓ ✓ Pass  Fail 
31 Alarm signal to BMS ✓ ✓ Pass  Fail 
OVERALL RESULT: Pass  Fail 
Observations:

www.beratungconsultants.com
Page 51
IST TEST SCRIPT

12. BMS IST Scenario’s

Test-01: Failure Scenario-BMS – Network Communication Failure

START TIME:
Remove the LAN cable Connected to the main server from (DDC Panel) and ensure
1 that there is no Communication Issue in BMS
Pass  Fail 
2 Ensure no impact on BMS System.
3 Ensure Mechanical System Monitoring System running on Standby BMS server Pass  Fail 

4 Ensure no impact to BMS Data Logging. Pass  Fail 


To verify no impact on any System integrated with BMS because of failure of BMS Pass  Fail 
5
Master Server (Simulated by removing the LAN Cable)
Restore to Normal Mode inserting the LAN cable in DDC panel and check the status in
6 Pass  Fail 
server and take the snap with normal condition on both server
7 Capture screenshots of BMS Alarm log Pass  Fail 

8 No interruption to critical system Pass  Fail 

Record the below status:

DDC Panel Status during Normal and Main Server Failure:

Master Server Status during Normal condition:

10

Master Server Status during LAN Cable removed from Master server.

Note the status and ensure all the data in BMS are in line without any Interruption and
BMS snap captured.
Pass  Fail 
OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 52
IST TEST SCRIPT

Test-02: Failure Scenario_BMS: Server / Power Failure

Power Failure to BMS Master PLC

START TIME:
1 Master PLC CPU power supply to be turned OFF. Pass  Fail 
2 Redundant PLC indication for ready to pickup to be noted and Fail the Master PLC Pass  Fail 
3 Ensure no impact on BMS System communication during Master PLC failure Pass  Fail 

4 Ensure BMS System running on Redundant BMS PLC Pass  Fail 

5 Ensure no impact to BMS Data Logging. Pass  Fail 

6 Restore to Normal Mode by resuming Power supply Pass  Fail 

7 Capture the screenshots of BMS Alarm Log during Master PLC failure Pass  Fail 

8 No interruption to critical system Pass  Fail 


Observations:

OVERALL RESULT: Pass  Fail 

www.beratungconsultants.com
Page 53
IST Test Script

13. Data Logger Layout and arrangement:

www.beratungconsultants.com
Page 54
IST TEST SCRIPT

14. PQM ARRANGEMENT:

1. IT Line Up

www.beratungconsultants.com
Page 55
IST TEST SCRIPT

2. Mechanical Line Up

www.beratungconsultants.com
Page 56