The document outlines procedures for passing an IBSS at ON, including communication protocols and speed restrictions based on signal status. It also details train operations during single line working on double line in both Absolute and Automatic Block Systems, emphasizing the roles of the LP and necessary authorities. Additionally, it lists caution order circumstances with speed restrictions and shunting authorities in the Absolute Block system.

Uploaded by

ilayaraja6
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views6 pages

Short Answers

The document outlines procedures for passing an IBSS at ON, including communication protocols and speed restrictions based on signal status. It also details train operations during single line working on double line in both Absolute and Automatic Block Systems, emphasizing the roles of the LP and necessary authorities. Additionally, it lists caution order circumstances with speed restrictions and shunting authorities in the Absolute Block system.

Uploaded by

ilayaraja6
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Page |1

1.Explain the procedure to pass IBSS at ON.

1. If IBSS is at ON, LP shall stop his Train in rear of the Signal.


2. IF SPT IS PROVIDED:
a) LP shall contact SM of the Station in Rear over SPT.
b) If the IBSS is at ON due to occupation of preceding Train in the Block Section :
 SM shall inform the same and clear the IBSS after obtaining line clear.
c) If IBSS is at ON due to failure:
 SM shall obtain Line Clear from Station in advance.
 He shall then authorize LP to pass IBSS at ON by giving a Message + PN
through SPT and LP can pass the signal with normal speed.
3. IF SPT IS NOT PROVIDED or LP could not communicate the SM
through SPT:
a) LP shall wait for FIVE minutes.
b) He shall then proceed at a Cautious Speed & be prepared to
stop short of any obstruction.
c) The Speed shall not exceed
 15 Kmph, if the view ahead is clear.
 8 Kmph, if the view ahead is not clear.
4. The Speed Restriction shall be exercised till the Train reaches the FSS of
the Station in advance, even if the FSS and Intermediate GSS are in OFF.
5. If LP sees a preceding Train / obstruction in the Block Section in
advance, he shall maintain a safe Distance of 75m or one OHE span
between his Train and preceding Train/obstruction. In emergency it
may be reduced.
6. LP shall report the same to SM of the Station in advance.
7. On becoming aware that the IBSS is defective (due to failure of Block
Instrument or Track Circuit or Axle Counter or failure of Signal itself),
SM shall
a) Treat the entire Section (X-Y and Y-Z) as one Block Section.
b) Obtain Line Clear through Block Telephone or other approved Means.
c) Issue Paper Line Clear Ticket as ATP for entire Section (X-Z) with
T/369(3b) for passing the IBSS at ON. LP shall pass the IBSS at ON
at Normal Speed without stopping the Train.
Page |2

2 Explain working of trains during S/L working on D/L in Absolute Block System

1. On a Double line Section, Whenever one line is obstructed due to an accident / obstruction ,
temporary single line working on Double line may be introduced.

2. It shall be introduced between the two nearest Stations provided with cross over points .

3. If Any class ‘C’ Station available between the above two Stations, It shall treated as closed.
4. Authorities issued:
T/D 602 is issued as Authority to proceed.
Right direction
 For despatch-T/D 602.
 LSS shall not be cleared.
 If there is a IBSS T/369(3b) shall also to be issued.
 For reception- by taking ‘OFF’ Home signal.
Wrong direction
 For despatch-T/D 602 +T/511+ Piloting
 For reception- LP shall stop his train at the LSS of the same line or FSS of the
adjacent line whichever comes first.
written memo [as per SR.5.10 (i)] + caution order 15 KMPH + Piloting
5. Role of LP:
 Speed of first Train shall not exceed 25 KMPH.
 LP of the first train shall inform gateman and gang man enroute.
 LP of all wrong direction trains shall switch on flasher light.
 LP of all trains shall give frequent short whistles.
Page |3

3. Explain working of trains during S/L working on D/L in Automatic Block System

On a Double line section, If one line is obstructed due to Accident, failure or any other reason,
single line working on double line may be introduced .
Wrong direction trains:
Despatch:
 Each 1st train : PLCT + T/A 912 + T/511 + Caution order for 25 kmph
 Subsequent trains : PLCT + T/A 912 + T/511 + Caution order with information only.
Reception:
 Written memo as per SR 5.10 + Caution order + Piloting
Right direction trains:
Despatch:
 Each 1st Train : PLCT + Caution order for 25 kmph
 Subsequent trains : Automatic indication + Caution order with information only.
Reception:
 By taking off signals.
Role of LP:
 LP of first train shall inform Gangmen and Gateman enroute about the
introduction of single line working on double line.
 LP of all wrong direction trains shall switch on their Flasher light.
 LP of all trains shall give frequent short whistles.

 Speed of each first train in both right and wrong direction shall not exceed 25
kmph.
Page |4

4. Explain the procedures prescribed for passing defective HOME signal


Trains shall be received by using anyone of the following methods:
 Calling-on Signal.
 Message + PN through SPT. ( Not to be used for first train)
 T/369(3b) .
 T/369(1) .
CALLING-ON SIGNAL:
 Train shall be stopped at the FSS .
 After actuating the calling on track circuit and waiting for 60 sec, Calling on
signalshall show OFF aspect.
 LP shall Stop, draw ahead with caution and be prepared to stop
short ofobstruction.
 OFF aspect of calling on signal authorizes the LP to pass that signal only.
MESSAGE THROUGH SPT:
 Train shall be stopped at the FSS.
 SM shall issue a Message+PN through SPT to LP.
 It contains Message No,Train No, Signal No &Description, Road No,Speed & PN.
 LP shall record the Message in his Rough Journal Book .
 More than one reception signal can be mentioned in single message.
 Speed shall not exceed 15KMPH.
FORM T/369(3b):
 Train shall be stopped at the FSS.
 SM shall prepare Form T/369(3b) in Duplicate.
 It shall be delivered to LP through a Competent Railway Servant at the foot
of thedefective Signal.
 More than one reception signal can be mentioned in a single form.
 Speed shall not exceed 15 KMPH.
T/369(1):
 SM shall advise the Nominated Station in rear.
 It shall be Last Stopping Station as in WTT - for Mail/Express Trains or Station
in rear - for other Trains.
 SM at Nominated Station in rear shall issue Advance Authority T/369(1)
 Proceed Hand Signal (PHS) shall be shown at the foot of the defective Signal.
 If PHS is not shown, LP shall stop his Train.
Page |5

5 Explain any TEN(10) Caution order circumstances with speed restrictions

OCCASIONS SPEED NOT TO EXCEED


Engineering works or Repairs on the As advised by the Engineering official
Track
Whenever LP reports Slack/Rough First train LP to stop and Examine , If
running or Heavy Lurch safe to move then 10KMPH
Rail Fracture/ Weld Failure 20 KMPH- if certified by Keyman/
Trackman/ Engg GK
30KMPH - if certified by JE/P.Way
Unsafe condition of the Bunds of Tanks 15KMPH during Day, clear weather.
or Rivers. 10KMPH during Night/ View ahead is not
clear.
Water reaches the Danger Level Mark at 15KMPH during Day, clear weather.
Bridges. 10KMPH during Night/ View ahead is not
clear.
Engine Pushing 15KMPH- if Guard travels in leading
vehicle.
10KMPH-if Guard travels other than
leading vehicle.
When sabotage is suspected- To start 15KMPH- Day/Clear Weather.
LE/ Tower Wagon / TMM 10KMPH- Night/ View not clear.

During the period of overhauling of 15KMPH at the Station


interlocking lever frames
Whenever the Train is piloted into the 15KMPH or lesser Speed given in SWR
Station on a written authority to enter
Non-Signalled/ Non-Running line.

OHE break down on Double/ Multiple 20KMPH by Day


Line Sections ( for 1st Train on adjacent 10KMPH by Night
line)
Page |6

when Line Clear obtained through 25 kmph for First Train only.
Indirect Means on Twin single line
During Temporary Single Line Working 25KMPH for each first train in both right
on Double Line in Automatic Block and wrong direction.
System.
When a Patrolman does not report within i) 40KMPH- Day & Visibility Clear.
15mts of his scheduled arrival. ii) 15KMPH-Night/ Day, Visibility is Poor.
When Goods stock is attached to Passenger Not to exceed 75KMPH
Trains.

6 Explain Shunting authorities issued in Absolute Block system


S.No Area of Shunting Authority
SINGLE LINE – TOKENLESS
1. Beyond Starter to T/806+ Shunt Key
a) Advanced Starter/ SLB or
b) Opposing FSS
2. Beyond opposing FSS (BLOCK BACK) T/806+ Shunt Key+ PN
3. In the face of an approaching Train T/806+ HOME Key
(Upto Advanced Starter or SLB)

4. If Shunt key could not be extracted or T/806+ Endorsement+ PN


failure of Block Instrument

DOUBLE LINE- TOKENLESS


5. Within Station section T/806
6. Beyond LSS (BLOCK FORWARD) T/806+ LSS Key
7. In rear of (BLOCK BACK) T/806+ PN
a) Outermost Facing points or
b) BSLB
8. If LSS key could not be extracted or T/806+ Endorsement+ PN
failure of Block Instrument