112
112
SUBMITTED BY
ALI RAZA
222-1759-00656
ROLL. NO. 22CR112
Session Period
01-09-24 to 28-04-25
CIVIL DEPARTMENT
GOVERNMENT COLLEGE TECHNOLOGY
SAHIWAL.
2025
SUPERVISED CONSTRUCTION PROJECT REPORT
5 MARLA HOUSE OF ALI RAZA
SUBMITTED TO
SUBMITTED BY
Session Period
1-09-24 to 28-04-25
I hereby certified that I have completed the twelve weeks training in partial fulfillment
of the requirement for the award of DAE CIVIL TECHNOLOGY.
I did my training in CLASS WORK from 09-09-24 to 28-05-25 The matter is
represented in this report has not been submitted by me for the award of any other degree
elsewhere.
ALI RAZA
222-1759-00656
Examined by:
Mr. SHAFEEL MEHMOOD
In-charge/HOD
Mr. Saleem Anjum
DEDICATION
Thanks to ALLAH Almighty who strengthened us to carry out this project. This project
is dedicated our Beloved Parents and respected Teachers who devoted us to complete this thesis
Without their patience, understanding support and most of all love the competition of this
research work would not have been possible. The main role in this report making our respected
First and foremost, we would like to thank ALLAH Almighty the Most Gracious, The
Most Bountiful the Omnipotent and The Omnipresent, THE MASTER OF THE WORLD, for
giving us the strength ability for successful completion of our project. Respects are for the
beloved Holy Prophet MUHAMMAD (S.A.W) who enable us to recognize us our creator.
We would like to express our gratitude to all those who give the possibility to complete
this project. We are thankful to the CIVIL DEPARTMENT, for giving such a golden
opportunity to commence this project in the first instance. We have furthermore too thankful
to the lecture, Shafeel Mehmood we encouraged and guide us for our project. We also thankful
to the entire civil department at G.C.T Sahiwal for their stimulating support. We are Thankful
to Head of Department of Civil in G.C.t Sahiwal, for the way he trained us for future, his
constant help. Giddiness and attention though out the project. He was kind, understanding and
sympathetic towards us. Indeed, working with him, he was a blessing for us.
We wish to express our sincere for providing us with all the necessary facilities for
research.
Finally, our thanks go to all the people like who have support us to complete the project
work directly or indirectly.
At the end acknowledgements will remain incomplete, until the encouraging role of our
Parents, Brother and sister is not greatly recognized and ultimately appreciated
i
ABSTRACT
Field training and report submission is one of the main courses in DAE Civil. The purpose
of this course is to apply the theoretical knowledge into practical work. There was two main parts
and the second pat is office work.
The student can be trained as site engineer, it gives you the opportunity to supervise the
construction work closely, or as design engineer using software programs such as Primavera, Auto
CAD, MS office etc.
2
Table of Contents
ACKNOWLEDGMENT ...................................................................................................................................................... i
ABSTRACT ......................................................................................................................................................................2
INTRODUCTION .............................................................................................................................................................8
1 Project Overview and Objectives ...........................................................................................................................8
• 1.1 Project Title ...............................................................................................................................................8
• 1.2 Project Location .........................................................................................................................................8
• 1.3 Project Goal ...............................................................................................................................................8
• 1.4 Specific Objectives .....................................................................................................................................8
2 Background and Motivation ..................................................................................................................................8
• 2.1 Homeowner's Requirements and Vision ...................................................................................................8
• 2.2 Rationale for Construction ........................................................................................................................8
• 2.3 Site Analysis ...............................................................................................................................................9
o 2.3.1 Plot Dimensions and Orientation ......................................................................................................9
o 2.3.2 Soil Conditions ...................................................................................................................................9
3 Design and Planning Phase: ...................................................................................................................................9
• 3.1 Elaboration of Design and Planning ..........................................................................................................9
o 3.1.1 Architectural Design ..........................................................................................................................9
o 3.1.2 Structural Design ...............................................................................................................................9
o 3.1.3 MEP (Mechanical, Electrical, Plumbing) Design ................................................................................9
o 3.1.4 Interior Design ...................................................................................................................................9
o 3.1.5 Landscape Design ..............................................................................................................................9
• 3.2 Regulatory Approvals Phase ......................................................................................................................9
o 3.2.1 Submission of Drawings .....................................................................................................................9
o 3.2.2 Obtaining Building Permits ................................................................................................................9
• 3.3 Construction Phase....................................................................................................................................9
o 3.3.1 Site Preparation .................................................................................................................................9
o 3.3.2 Foundation Work ...............................................................................................................................9
o 3.3.3 Superstructure Construction .............................................................................................................9
o 3.3.4 Roofing...............................................................................................................................................9
o 3.3.5 MEP Installations ...............................................................................................................................9
o 3.3.7 Exterior Finishing ...............................................................................................................................9
• 3.4 Handover Phase: ....................................................................................................................................10
o 3.4.1 Final Inspections ..............................................................................................................................10
o 3.4.2 Snagging and Rectification...............................................................................................................10
3
o 3.4.3 Handover of Keys and Documents ..................................................................................................10
4 Regulatory and Legal Considerations (Sahiwal Specific)......................................................................................10
• 4.1 Sahiwal Development Authority (SDA) Regulations ................................................................................10
• 4.2 Building Permits and Approvals...............................................................................................................10
• 4.3 Utility Connections ..................................................................................................................................10
• 4.4 Environmental Regulations .....................................................................................................................10
• 4.5 Labor Laws ...............................................................................................................................................10
5 Conclusion ...........................................................................................................................................................10
Construction Material and its used .............................................................................................................................11
6 Cementitious Materials .......................................................................................................................................11
• 7.1 Ordinary Portland Cement (OPC) ............................................................................................................11
• 7.2 Aggregate (Sand & Crushed Stone) .........................................................................................................13
o 7.2.1 Sand (Fine Aggregate) ......................................................................................................................13
o 7.2.2 Crushed Stone (Coarse Aggregate) ..................................................................................................15
• 7.3 Water .......................................................................................................................................................17
7 Masonry Materials ...............................................................................................................................................19
• 8.1 Clay Bricks ................................................................................................................................................19
• 8.2 Cement Mortar ........................................................................................................................................21
8 Reinforcement Steel (Rebar) ...............................................................................................................................23
9 Roofing Materials ................................................................................................................................................25
• 10.1 Reinforced Cement Concrete (RCC) Slab ...............................................................................................25
10 Finishing Materials ........................................................................................................................................27
• 11.1 Plaster ....................................................................................................................................................27
• 11.2 Doors and Windows ..............................................................................................................................29
• 11.3 Paints and Wall Finishes ........................................................................................................................31
Methodology of Preparing a House Load Bearing Wall ...............................................................................................33
Phase 1: Planning and Design ......................................................................................................................................33
1. Structural Design and Drawings ....................................................................................................................33
o Engage a Qualified Structural Engineer ....................................................................................................33
o Detailed Drawings.....................................................................................................................................33
o Material Specifications .............................................................................................................................33
2. Site Investigation and Preparation ................................................................................................................33
o Soil Testing (if necessary) .........................................................................................................................33
o Site Clearance ...........................................................................................................................................33
o Marking the Wall Layout ..........................................................................................................................33
3. Material Procurement and Storage ...............................................................................................................33
o Source Quality Materials ..........................................................................................................................33
4
o Proper Storage ..........................................................................................................................................33
Phase 2: Foundation Preparation ................................................................................................................................33
1. Clean the Foundation Surface ..................................................................................................................33
2. Dampen the Foundation ...........................................................................................................................33
Phase 3: Wall Construction ..........................................................................................................................................34
1. Laying the First Course (Setting Out) .............................................................................................................34
o Mortar Bed ...............................................................................................................................................34
o Positioning the Units ................................................................................................................................34
o Checking for Level and Plumb ..................................................................................................................34
2. Subsequent Courses ......................................................................................................................................34
o Staggering Joints .......................................................................................................................................34
o Maintaining Mortar Joints ........................................................................................................................34
o Checking Level and Plumb Regularly ........................................................................................................34
3. Incorporating Openings (Doors and Windows) .............................................................................................34
o Lintel Support ...........................................................................................................................................34
o Placing Lintels ...........................................................................................................................................34
o Continuing Construction Above Lintels ....................................................................................................34
4. Incorporating Reinforcement (if required) ....................................................................................................34
o Placement .................................................................................................................................................34
o Grouting (for concrete blocks)..................................................................................................................34
5. Wall Ties (for cavity walls, if applicable) .......................................................................................................34
6. Top of the Wall ..............................................................................................................................................34
o Levelling Course ........................................................................................................................................34
o Preparation for Superstructure ................................................................................................................35
Phase 4: Quality Control and Curing ............................................................................................................................35
1. Regular Checks ..............................................................................................................................................35
o Dimensions ...............................................................................................................................................35
o Alignment .................................................................................................................................................35
o Mortar Joints ............................................................................................................................................35
o Material Quality ........................................................................................................................................35
o Reinforcement Placement ........................................................................................................................35
2. Curing ............................................................................................................................................................35
o Importance ...............................................................................................................................................35
o Method .....................................................................................................................................................35
Phase 5: Inspection ......................................................................................................................................................35
1. Intermediate Inspections ..............................................................................................................................35
2. Final Inspection .............................................................................................................................................35
5
• Safety ........................................................................................................................................................35
• Weather Conditions..................................................................................................................................35
• Skilled Labor .............................................................................................................................................35
• Adherence to Codes and Regulations .......................................................................................................35
ABSTRACT OF QUANTITY .............................................................................................................................................36
Bill of cost ....................................................................................................................................................................40
Material Statement .....................................................................................................................................................42
Labour Statement ........................................................................................................................................................43
ACTIVITY TABLE ............................................................................................................................................................44
GANT CHART ................................................................................................................................................................45
ACTIVITY NETWORK .....................................................................................................................................................46
WBS .............................................................................................................................................................................47
OBS ..............................................................................................................................................................................48
DRAWINGS ...................................................................................................................................................................49
CROSS SECTION: ......................................................................................................................................................49
MAP: ........................................................................................................................................................................50
6
Table of Figure
Figure 1 Ordinary Portland Cement (OPC)...................................................................................................................12
Figure 2 Sand (Fine Aggregate) ....................................................................................................................................14
Figure 3 Crushed Stone (Coarse Aggregate) ................................................................................................................16
Figure 4 Water .............................................................................................................................................................18
Figure 5 Clay Bricks ......................................................................................................................................................20
Figure 6 Cement Mortar ..............................................................................................................................................22
Figure 7 Reinforcement Steel (Rebar) .........................................................................................................................24
Figure 8 Reinforced Cement Concrete (RCC) Slab .......................................................................................................26
Figure 9 Plaster ............................................................................................................................................................28
Figure 10 Doors and Windows .....................................................................................................................................30
Figure 11 Paints and Wall Finishes ..............................................................................................................................32
TABLE OF TABLES
Table 1 BILL OF QUANTITIES ........................................................................................................................................39
Table 2 BILL OF COST ...................................................................................................................................................41
Table 3 MATERIAL STATEMENT ...................................................................................................................................42
Table 4 LABOUR SCHEDULE .........................................................................................................................................43
CHAPTER # 1
7
INTRODUCTION
8
dwelling to ensure greater privacy, autonomy, and the ability to establish their own
household routines and preferences.
• 2.3 Site Analysis:
o 2.3.1 Plot Dimensions and Orientation: 27 × 50 feet = 1350 square feet
o 2.3.2 Soil Conditions: Currently, the preliminary understanding of the plot's soil
conditions is based on the general knowledge of the area in Sahiwal. It is
assumed to be predominantly alluvial soil, common in this region, which
generally offers decent bearing capacity for residential construction
9
• 3.4 Handover Phase:
o 3.4.1 Final Inspections: Conducting thorough inspections to ensure quality and
compliance.
o 3.4.2 Snagging and Rectification: Identifying and rectifying any defects or
incomplete work.
o 3.4.3 Handover of Keys and Documents: Formal handover of the completed
house and relevant documents to the homeowner.
5 Conclusion
This detailed introduction provides a foundational understanding of the multifaceted process
involved in constructing a 5 Marla house in Sahiwal. By outlining the project objectives, scope
of work, management approach, and regulatory considerations, this document sets the stage
for a well-planned and efficiently executed construction project that will ultimately deliver a
comfortable and fulfilling living space for the homeowner. The subsequent phases of this
project will delve deeper into each of these aspects, providing specific details and action plans
for successful completion.
10
CHAPTER # 2
Construction Material and its used
6 Cementitious Materials
• 7.1 Ordinary Portland Cement (OPC):
o Material: A fine grey powder consisting of a mixture of calcium silicates and other
compounds, manufactured by grinding clinker (produced by heating limestone and
clay).
o Use: The fundamental binding agent for concrete, mortar, and plaster. It reacts with
water (hydration) to form a hard, strong matrix.
o Applications in a 5 Marla House:
▪ Foundation: Used in PCC (Plain Cement Concrete) for the base and RCC
(Reinforced Cement Concrete) for footings, column stubs, and plinth
beams.
▪ Superstructure: Integral component of RCC for columns, beams, slabs
(floors and roof).
▪ Masonry: Used as the binder in cement mortar for laying bricks or
concrete blocks.
▪ Plastering: Forms the base of cement plaster for interior and exterior
wall finishes.
o Considerations in Sahiwal: Availability is generally good. Choose reputable brands to
ensure quality and strength. Consider the grade of cement (e.g., 43 grade, 53 grade)
based on structural requirements. Store in a dry place to prevent hardening.
11
Figure 1 Ordinary Portland Cement (OPC)
12
• 7.2 Aggregate (Sand & Crushed Stone):
▪ Material: Small, loose grains of eroded rock. River sand is commonly used
▪ Use: Provides bulk and workability to concrete and mortar, filling the
strength.
▪ Considerations in Sahiwal: Quality can vary. Ensure it's clean, free from
excessive silt, clay, and organic matter, which can weaken the concrete or
workability.
13
Figure 2 Sand (Fine Aggregate)
14
o 7.2.2 Crushed Stone (Coarse Aggregate):
requirements of the concrete mix design. Ensure it's clean and free from
brick aggregate.
15
Figure 3 Crushed Stone (Coarse Aggregate)
16
• 7.3 Water:
o Material: Clean, potable water free from harmful impurities, chemicals, and
excessive salts.
o Use: Essential for the hydration of cement, which is the chemical reaction that binds
o Considerations in Sahiwal: Use clean water. Impurities can negatively affect the
17
Figure 4 Water
18
7 Masonry Materials
o Material: Rectangular units made from clay, moulded, dried, and fired in a kiln.
o Use: Primarily used for constructing walls (load-bearing and partition walls).
bricks with uniform colour, sharp edges, and a metallic sound when struck
together. High water absorption can indicate poor quality. Consider the strength
19
Figure 5 Clay Bricks
20
• 8.2 Cement Mortar:
o Material: A mixture of cement, sand, and water. The ratio of cement to sand
o Considerations in Sahiwal: Use the correct mix ratio as per the load-bearing
requirements. Proper mixing and application are crucial for good bonding. Curing
the mortar joints with water for several days is essential for strength
development.
21
Figure 6 Cement Mortar
22
8 Reinforcement Steel (Rebar)
• Material: Steel bars with deformations (ribs or lugs) on their surface to improve bonding
with concrete. Available in various diameters and grades (e.g., Grade 40, Grade 60).
concrete (RCC) is essential for structural elements that experience bending or tension.
o Superstructure: Columns, beams, floor slabs, roof slab, lintels above openings.
grade and quality. Check for rust and damage. Proper cutting, bending, and placement
according to the structural drawings are critical for the structural integrity of the house.
Cover blocks are used to ensure proper concrete cover over the reinforcement for
23
Figure 7 Reinforcement Steel (Rebar)
24
9 Roofing Materials
o Use: A common and durable roofing solution providing structural stability and
weather protection.
leakage, insulation for thermal comfort during hot summers, and a well-designed
25
Figure 8 Reinforced Cement Concrete (RCC) Slab
26
10 Finishing Materials
o Use: Provides a smooth and even surface on walls and ceilings for painting or
other finishes.
cracks. Consider using gypsum plaster for interiors for a smoother finish.
27
Figure 9 Plaster
28
• 11.2 Doors and Windows:
doors).
their durability and lower maintenance compared to wood. Consider the quality
of frames, hinges, and locks for security. Proper sealing is important to prevent
29
Figure 10 Doors and Windows
30
• 11.3 Paints and Wall Finishes:
withstand the local climate. Good quality primer is essential for proper adhesion
and finish.
31
Figure 11 Paints and Wall Finishes
32
CHAPTER # 3
Methodology of Preparing a House Load Bearing Wall
Preparing a load-bearing wall for construction is a critical process that requires careful planning and execution to
ensure structural integrity and safety. Here's a detailed methodology:
33
Phase 3: Wall Construction
1. Laying the First Course (Setting Out):
o Mortar Bed: Apply a uniform layer of mortar of the specified thickness on the foundation
along the marked layout of the wall.
o Positioning the Units: Carefully place the first course of bricks or blocks according to the
drawings, ensuring they are level and aligned. Use a spirit level and string line to maintain
horizontal and vertical alignment.
o Checking for Level and Plumb: Continuously check the level (horizontal) and plumb
(vertical) of the first course. This is crucial as it forms the base for the entire wall.
2. Subsequent Courses:
o Staggering Joints: Lay subsequent courses, ensuring that the vertical joints between the
units are staggered (lapped) to provide better strength and prevent continuous vertical cracks.
The overlap should typically be at least one-third the length of the unit.
o Maintaining Mortar Joints: Apply a consistent thickness of mortar between the units
(both horizontal bed joints and vertical head joints). The mortar should be workable and provide
good adhesion. Strike the joints neatly for both structural integrity and aesthetics.
o Checking Level and Plumb Regularly: Use a spirit level and plumb bob frequently as
the wall progresses to ensure it remains straight and vertical. Use a mason's line stretched taut
between corners or guide blocks to maintain alignment.
3. Incorporating Openings (Doors and Windows):
o Lintel Support: When reaching the level of door or window openings, ensure adequate
support for the lintel (a horizontal beam that spans the opening). This might involve using
temporary supports (props) while the lintel is being placed and the mortar sets.
o Placing Lintels: Carefully place the lintels (concrete, steel, or masonry) over the openings,
ensuring they are properly bedded in mortar and extend sufficiently beyond the sides of the
opening (bearing). The length of the bearing should be as specified in the structural drawings.
o Continuing Construction Above Lintels: Continue laying masonry units above the
lintels, maintaining the bond and alignment.
4. Incorporating Reinforcement (if required):
o Placement: If the design calls for reinforcement (e.g., in reinforced masonry walls or concrete
block walls), place the steel bars according to the structural drawings, ensuring proper cover
(distance between the steel and the outer surface of the masonry).
o Grouting (for concrete blocks): For reinforced concrete block walls, after placing the
reinforcement, the cores of the blocks containing the steel are filled with grout (a flowable
concrete mix) to bond the steel to the masonry.
5. Wall Ties (for cavity walls, if applicable): If the load-bearing wall is part of a cavity wall
system, ensure wall ties are installed at the specified intervals to connect the inner and outer leaves of
the wall.
6. Top of the Wall:
o Levelling Course: Finish the top of the wall with a level course of masonry units.
34
o Preparation for Superstructure: Prepare the top of the wall as specified in the drawings
for connection to the next structural element (e.g., floor slab, roof beam). This might involve
creating a level surface or embedding connection elements.
Phase 5: Inspection
1. Intermediate Inspections: It's good practice to have inspections at critical stages of
construction (e.g., after the first few courses, after lintel placement, upon completion of the wall) by the
structural engineer or a qualified supervisor to ensure compliance with the drawings and specifications.
2. Final Inspection: A final inspection should be carried out upon completion of the wall before any
further loads are applied.
Important Considerations:
• Safety: Implement appropriate safety measures on the construction site, including providing personal
protective equipment (PPE) for workers and ensuring safe working practices.
• Weather Conditions: Avoid constructing masonry walls during extreme weather conditions (e.g.,
heavy rain, freezing temperatures) as these can negatively impact the quality of the mortar.
• Skilled Labor: Employ experienced and skilled masons who understand the principles of load-bearing
wall construction and can work accurately according to the drawings.
• Adherence to Codes and Regulations: Ensure that the construction complies with all relevant
local building codes and regulations.
35
ABSTRACT OF QUANTITY
36
WALL G 1 9.25 1.5 0.5 6.9375
WALL H 1 16.25 1.5 0.5 12.1875
WALL I 1 5.25 1.5 0.5 3.9375
2ND STEP
WALLA 2 50.375 1.125 0.5 56.671875
WALL B 4 28.125 1.125 0.5 63.28125
WALL C 2 5.125 1.125 0.5 5.765625
WALL D 2 12 1.125 0.5 13.5
WALL E 1 19.125 1.125 0.5 10.7578125
WALL F 1 11.625 1.125 0.5 6.5390625
WALL G 1 9.625 1.125 0.5 5.4140625
WALL H 1 16.625 1.125 0.5 9.3515625
WALL I 1 5.625 1.125 0.5 3.1640625
STEP 3
WALLA 2 50 0.75 2.5 187.5
WALL B 4 28.5 0.75 2.5 213.75
WALL C 2 5.5 0.75 2.5 20.625
WALL D 2 12 0.75 2.5 45
WALL E 1 19.5 0.75 2.5 36.5625
WALL F 1 12 0.75 2.5 22.5
WALL G 1 10 0.75 2.5 18.75
WALL H 1 17 0.75 2.5 31.875
37
WALL C 2 5.5 0.75 12 99
WALL D 2 12 0.75 12 216
WALL E 1 19.5 0.75 12 175.5
WALL F 1 12 0.75 12 108
WALL G 1 10 0.75 12 90
WALL H 1 17 0.75 12 153
WALL I 1 6 0.75 12 54
2821.5
10 FINISHING
PLASTER 0
WALLA 2 50 - 12 1200
WALL B 4 28.5 - 12 1368
WALL C 2 5.5 - 12 132
WALL D 2 12 - 12 288
WALL E 1 19.5 - 12 234
WALL F 1 12 - 12 144
WALL G 1 10 - 12 120
WALL H 1 17 - 12 204
WALL I 1 6 - 12 72
3762
11 POINTING 0
WALLA 2 50 - 12 1200
WALL B 4 28.5 - 12 1368
WALL C 2 5.5 - 12 132
WALL D 2 12 - 12 288
WALL E 1 19.5 - 12 234
WALL F 1 12 - 12 144
WALL G 1 10 - 12 120
WALL H 1 17 - 12 204
WALL I 1 6 - 12 72
3762
12 PAINT 0
WALLA 2 50 - 12 1200
WALL B 4 28.5 - 12 1368
WALL C 2 5.5 - 12 132
WALL D 2 12 - 12 288
WALL E 1 19.5 - 12 234
WALL F 1 12 - 12 144
WALL G 1 10 - 12 120
WALL H 1 17 - 12 204
WALL I 1 6 - 12 72
38
3762
13 DISTEMPER 0
WALLA 2 50 - 12 1200
WALL B 4 28.5 - 12 1368
WALL C 2 5.5 - 12 132
WALL D 2 12 - 12 288
WALL E 1 19.5 - 12 234
WALL F 1 12 - 12 144
WALL G 1 10 - 12 120
WALL H 1 17 - 12 204
WALL I 1 6 - 12 72
3762
14 FLOORING 1 50 30 1500
15 ROOFING 1 50 30 0.5 750
16 DEDUCTION DOOR - 0
BED ROOM 2 4 0.75 7 42
BOTH 3 3 0.75 7 47.25
KITCHEN 1 4 0.75 7 21
LUNCH 1 4 0.75 7 21
BATHAK 2 4 0.75 7 42
173.25
17 WINDOWS 0
BED ROOM 2 4 0.75 4 24
BOTH 3 4 0.75 4 36
KITCHEN 1 2 0.75 2 3
LUNCH 1 4 0.75 2 6
BATHAK 2 4 0.75 4 24
SATIRE 1 4 0.75 4 12
81
18 LINTEL DOOR 0
BED ROOM 2 5 0.5 0
BOTH 3 3 0.75 0.5 3.375
KITCHEN 1 5 0.75 0.5 1.875
LUNCH 1 5 0.75 0.5 1.875
BATHAK 1 5 0.75 0.5 1.875
9
19 DEDUCTION WINDOW 0
BAD ROOM 2 5 0.75 0.5 3.75
BATH 3 5 0.75 0.5 5.625
39
Bill of cost
SR
SCHEDULE UNI REMAR
. DESCRIPTION QTY RATE AMOUNT
REFERENCE T KS
#
SITE PREPRATION
0.1
LAND CLEARANCE 1500 10533.6 % 15800.4
GRADING AND
LEVELLING(Dressing and
levelling of earhtwork to
Ch# 3-26-18- designed section OF 0.1
(b) Ordinary or hard soil ) 1500 940.9 % 1411.35
FOUNDATION WORKS
EXCAVATION (Earthwork
excavation undressed 1860.9
lead upto a single throw 3
of Kassi, phaorah or
Ch# 3-24-1- shove In ordinary soil) 5,643.0 0.1 10501.227
(b) 0 % 99
P.C.C (Cement concrete
plain including placing
compacting, finishing
and curing
complete (including
372.19
screening and
washing of stone
aggregate)
Ratio 1: 4: 8 37,631. 140062.16
90 1% 86
BRICK WORK IN
FOUNDATION (Pacca
1097.6
brick work in mud
9
Ch# 7-48-1- mortar in buildings in 26,449. 290331.32
(1) foundation and plinth) 30 1% 12
47303.128
587.81
D.P.C 8047.35 1% 04
FILLING AND 0.1
1500
COMPACTION 7547.75 % 11321.625
SUPER STRUCTURE WORK
40
B/WORK IN SUPER
STRUCTER (Pacca brick
2821.0
work in mud mortar in
5
buildings in foundation 1077217.9
and plinth) 38185 1% 43
RCC WORK
100
20.43
LINTEL 769.3 % 15716.799
100
ROOF SLAB 750
52.55 % 39412.5
STEEL 1500 31757.4 1% 476361
FINISHING WORKS
FLOORING 1350 11180.2 1% 150932.7
100 739115.12
DOOR (INSTALLATION) 206.5 3579.25 % 5
WINDOW 100
(INSTALLATION) 76 1310 % 99560
MAIN GATE 100
84
(INSTALLATION) 1648.35 % 138461.4
174075.26
3762
PLASTER 4627.2 1% 4
160315.74
3762
POINTING 4261.45 1% 9
DISTEMPER 3762 1518.2 1% 57114.684
PAINTING 672 1853.35 1% 12454.512
3657468.8
TOTAL COST 96
41
Material Statement
SR.N Quantiti
o Description es Material
Cement(Ba Sand Crush Brick Steel Stone
gs) (cft) (cft) No (kg) Chips
1 P.C.C 307.5 35 175 350 - - -
B/W in
2 Foundation 1047.09 55 346 - 14136 - -
3 D.P.C 192.37 102 256 513 - - -
4 B/W in S/S 2308.5 170 854 - 37847 - -
5 Lintel 20.43 2 5 11 - 36 -
6 Plaster 3078 31 158 - - - -
7 Pointing 3078 - - - -
8 Flooring 1350 91 457 - - - 231
9 Roofing 675 131 328 657 - 1501 -
617 2579 1531 51983 1537 231
42
Labour Statement
SR.N Quantitie
o Description s Labour Labour
Maso Bahisht DA Maso Bahisht
n Cooli i Y n Cooli i
11.1
1 P.C.C 372.19 3.72 22.32 2 2 1.86 6 1
B/W in
2 Foundation 1097.69 21.95 35.67 8 8 2.74 4.45 1
11.7
3 D.P.C 587.81 6 35.26 3 3 2 5 1
4 B/W in S/S 2821.05 70 136 21.15 15 4.67 9.06 1.41
5 Lintel 50.43 0.2 1.22 0.1 1 0.2 1.22 0.1
6 Plaster 3762 28.21 37.62 9.4 6 4.7 6.27 1.57
7 Pointing 3762 28.21 37.62 9.4 6 4.7 6.27 1.57
8 Distemper 3762 9.4 9.4 3 3.13 3.13 -
9 Flooring 1350 13.5 10.12 2.7 2 6.75 5.06 1.35
10 Roofing 750 7.5 22.5 7.5 1 7.5 22.5 7.5
188.6 347.7 80.8
18315.17 9 3 63.25 47 38.25 7 16.5 0
43
5 MARLA HOUSE BY ALI RAZA Classic Schedule Layout 17-Apr-25 17:41
Activity ID Activity Name Original Duration BL Project Total Start Finish Total Float
Cost
ACTIVITY TABLE
44
GANT CHART
45
ACTIVITY NETWORK
46
WBS
47
OBS
48
DRAWINGS
CROSS SECTION:
49
MAP:
50