Demo Exam for Production & Logistics
Demo Exam for Production & Logistics
Which three of the following activities within the product life cycle are
categorised as product development?
o Production planning
o Marketing
o Disposal
o Distribution
o Design
o Calculation of working time
o ABC-Analysis
o Production
o Bill of materials breakdown
o Logistics
o Determination of requirements
o Product Planning
2. Which type of stock is calculated from warehouse stock, prebooked stock
and order stock (calculated stock)?
Select one:
o Order stock
o Workshop stock
o Warehouse stock
o Available stock
o Prebooked stock
Select one:
o Vendor parts
o Merchandise
o Operating materials
o Raw materials
o Input materials
o Auxiliary materials
4. Which type of requirement is the demand for individual parts, assemblies or
raw materials that can be determined using parts lists or where-used lists?
Select one:
o Additional requirements
o Net requirements
o Total gross requirements
o Secondary requirements
o Gross production requirements
o Tertiary requirements
o Primary requirements
5. Calculate the profit contribution of procurement if cost of materials are 60%
and the return on sales 14%. Use 3% as the value for the material cost
savings.
Result:
6. The following requirements or stocks are given. Please complete the table.
Week 35 Week 36
Additional requirements 23 7
Warehouse stock 55 11
Order stock 37 19
Available stock
Net requirements
A1 A2 B3 A4 D5
Part Quantity Part Quantity Part Quantity Part Quantity Part Quantity
A4 Answer
Parts A2 and D5 appear at different positions in the product breakdown. How should
these cases be treated? Does the the modular parts list from above contain all required
tables (answer a) or are separate tables needed for every occurence of a materials A2
and D5 (answer b)? Answer 1 Question 7 ab
8. You have the following product breakdown:
A1 A2 B3 A4 D5
Part Quantity Part Quantity Part Quantity Part Quantity Part Quantity
A4 Answer
9. The following weekly consumptions are given:
Period 34 35 36 37 38
Demand 76 56 88 29
Weight 89 17 37 36
10. The following data is given:
Period 35 36 37 38 39
Forcast 62 50 67 64 52
Consumption 50 55 67 53
• Using this MAD value, how many parts do you need to order in week 39 if you
want to achieve a service level of 84.15%? Answer
Trend calculation:
• The start value at the end of week 30 is 52 parts and the gradient is 7 parts
per week.
• How many parts do you have to order at the end of week 36 if you determine
this using trend calculation? Answer
11. The following demand data is provided:
Period 31 32 33 34 35 36
Cost information:
Using the Part Period method, determine the optimal order quantities, as well as the
order costs, inventory costs and total costs. Specify the results in the tables
below. Round to two decimal places.
Quantities:
31 Answer
32 Answer
33 Answer
34 Answer
35 Answer
36 Answer
Period 31 32 33 34 35 36
Cost information:
Using the Silver/Meal method, determine the optimal order quantities, as well as the
order costs, inventory costs and total costs. Specify the results in the tables
below. Round to two decimal places.
Quantities:
31 Answer
32 Answer
33 Answer
34 Answer
35 Answer
36 Answer
Select one:
o Chain conveyor
o Storage and retrieval system
o Roller conveyor
o Automated guided vehicle
o Belt conveyor
o Front forklift
o Tugger train
o Pallet truck
14. This manufacturing process applies material layer by layer to create three-
dimensional objects. It is often used in prototyping and spare parts supply.
Select one:
15. A design sketch is created on the basis of the performance specification and
the concept. The principle solutions are implemented.
Select one:
o Design
o Elaborate
o Plan / clarify
o Deliver
o Build
o Conceptualize
16. This time type contains the sum of the times of all process stages that can
occur in addition to the execution of scheduled work processes and
independently of orders. Examples of this time type are Searching for parts,
asking for information, going to the vending machine, personal tasks.
Select one:
o Order time
o Allowance time
o Occupancy time
o Time per piece
o Secondary time
o Additional time
o Process related activity interruption
o Activity time
o Interruption time
o Working time
o Resting time
o Planned time
o Setup time
o Main time
o Execution time
o Preparation time
o Recovery time
o Basic time
17. You are provided with the following data for processing an order:
Select one:
o SCM
o Conwip
o MRP3
o BOA
o FSZ
o MRP1
o Kanban
o MRP2
o ERP
o OPT
Select one:
o Series manufacturing
o Mass manufacturing
o Individual manufacturing
o Flow manufacturing
o Workshop manufacturing
o Group manufacturing
20. The decisive factors for this type of assembly structure can be the use of
special machines, the separation due to different environmental
requirements and occupational health and safety regulations.
Select one:
Select one:
o Air
o Pipeline
o Road
o Rail
o Sea
Select one:
o Depony
o Recyling (changed products)
o Re-use (changed purpose)
o Recyling (same products)
o Thermal recycling
o Re-use (same purpose)